CN208235959U - A kind of building construction temporary drainage structure - Google Patents
A kind of building construction temporary drainage structure Download PDFInfo
- Publication number
- CN208235959U CN208235959U CN201820494254.7U CN201820494254U CN208235959U CN 208235959 U CN208235959 U CN 208235959U CN 201820494254 U CN201820494254 U CN 201820494254U CN 208235959 U CN208235959 U CN 208235959U
- Authority
- CN
- China
- Prior art keywords
- drain bar
- gutter
- drainage hole
- connector
- drain
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Sink And Installation For Waste Water (AREA)
Abstract
The utility model discloses a kind of building construction temporary drainage structures, including the first drain bar, the second drain bar is connected on the right side of first drain bar, its the second drain bar end is provided with drain bar connector, and drain bar connector side wall is equipped with drain bar connector slot, the drain bar connector slot right end is connected with third drain bar, its third drain bar end is connected with the 4th drain bar, and the 4th drain bar end side wall be connected with gutter, the gutter leading portion side wall is provided with diversion trough connection, and gutter connector end is provided with gutter connector slot, second draining board bottom portion is provided with drainage hole, its drainage hole bottom is connected with drainage hole adapter, and drainage hole adapter end is provided with drainpipe.The building construction temporary drainage structure use package assembly, can Reusability, low cost save the cost, it is convenient to remove after construction, building waste will not be generated and cause environmental pollution, convenient for operator carry and assemble.
Description
Technical field
The utility model relates to water conservancy drainage equipment technical field, specially a kind of building construction temporary drainage structure.
Background technique
Once there is a large amount of precipitation during building construction, entire basis will be impregnated, and after long period of soaking, foundation settlement can
It can be able to be more than that specification prescribed requirement is faced then whole building will have great security risk so doing construction site well
When drainage works it is just particularly important, for science carry out flood season drainage works, reduce economic loss to the maximum extent, it is ensured that construction peace
Entirely, according to on-site actual situations, effective drainage measure is specially formulated.
Mostly use the way of temporary drain in conventional house construction project greatly, mainly with mortar laid stone lining, use coagulation
The modes such as molding paving geomembrane are directly excavated in soil casting, and stone masonry or concrete gutter waste material, and work progress is numerous
Trivial, the construction time is long, and cost is high, and it is larger that difficulty is removed after construction, and can generate new building waste after removing and pollute ring
Border;And soil property gutter is serious by directly washing away for water flow, easily causes blocking or collapses.
Utility model content
The purpose of this utility model is to provide a kind of building construction temporary drainage structures, to solve in above-mentioned background technique
The general room proposed builds discharge structure and mainly uses stone masonry or concrete gutter, wastes material, work progress is cumbersome, applies
Long between working hour, cost is high, and it is larger that difficulty is removed after construction, and can generate new building waste after removing and pollute environment;And
The problem of soil property gutter is serious by directly washing away for water flow, easily causes blocking or collapses.
To achieve the above object, the utility model provides the following technical solutions: a kind of building construction temporary drainage structure, packet
The first drain bar is included, is connected with the second drain bar on the right side of first drain bar, the second drain bar end is provided with drain bar
Connector, and drain bar connector side wall is equipped with drain bar connector slot, the drain bar connector slot right end is connected with third row
Water plate, third drain bar end is connected with the 4th drain bar, and the 4th drain bar end side wall is connected with gutter, described to draw
Sink leading portion side wall is provided with diversion trough connection, and gutter connector end is provided with gutter connector slot, second draining
Board bottom portion is provided with drainage hole, and drainage hole bottom is connected with drainage hole adapter, and drainage hole adapter end is provided with row
Water pipe.
Preferably, first drain bar, the second drain bar, third drain bar and the 4th drain bar pass through drain bar connector
It is connected with each other with drain bar connector slot, and the first drain bar, the second drain bar, third drain bar and the 4th drain bar are wavy
Structure.
Preferably, the volume equal shape size of the drain bar connector and drain bar connector slot is mutually coincide.
Preferably, the drainage hole is set to the first drain bar, the second drain bar, third drain bar and the 4th draining board group
At the trough of wave structure, and the connection type between drainage hole and the drainage hole adapter of lower section is to be threadedly coupled.
Preferably, the gutter is "u"-shaped, and the diversion trough connection of diversion front of the slot and the gutter of end connect
Head sump volume equal shape size is mutually coincide.
Compared with prior art, the utility model has the beneficial effects that the building construction temporary drainage structure is using assembling
Structure, can Reusability, low cost, it is convenient to remove after construction, will not generate building waste pollution environment.First draining
Plate, the second drain bar, third drain bar and the 4th drain bar are connected with each other by drain bar connector and drain bar connector slot, and the
One drain bar, the second drain bar, third drain bar and the 4th wavy structure of drain bar, wavy shaped configuration are conducive to rainwater stream
Enter trough to be discharged finally by drainage hole, so that ponding can not be assembled, the volume of drain bar connector and drain bar connector slot is equal
Shape size mutually coincide, and using the seamless interfacing of drain bar connector and drain bar connector slot, construction personnel is facilitated to organize installation and dismantling
It unloads, while waterproof performance is also preferable, drainage hole is set to the first drain bar, the second drain bar, third drain bar and the 4th draining
Board group at the trough of wave structure at, and the connection type between drainage hole and the drainage hole adapter of lower section be threadedly coupled,
Trough, which can drain rainwater, to be entered drainage hole and be discharged finally by drainpipe, and asking for ponding in building construction is preferably resolved
Topic, while dismountable drainage hole adapter is easy to carry, gutter is "u"-shaped, and the gutter of diversion front of the slot connects
The gutter connector sump volume equal shape size of head and end is mutually coincide, and drain bar edge is drained using gutter, is improved
Drainage effect, same dismountable gutter are carried and are assembled convenient for operator, are convenient for device Reusability, save the cost.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is the utility model overlooking structure diagram;
Fig. 3 is the utility model diversion slot structure schematic diagram;
Fig. 4 is the utility model gutter joint structure schematic diagram;
Fig. 5 is the utility model drainage hole structure schematic diagram;
Fig. 6 is A enlarged structure schematic diagram in the utility model Fig. 1.
In figure: 1, the first drain bar, the 2, second drain bar, 3, drain bar connector, 4, drain bar connector slot, 5, third draining
Plate, the 6, the 4th drain bar, 7, drainage hole, 8, drainage hole adapter, 9, drainpipe, 10, gutter, 11, diversion trough connection, 12,
Gutter connector slot.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-6 is please referred to, the utility model provides a kind of technical solution: a kind of building construction temporary drainage structure, including
First drain bar 1 is connected with the second drain bar 2 on the right side of first drain bar 1, and 2 end of the second drain bar is provided with drain bar and connects
First 3, and 3 side wall of drain bar connector is equipped with drain bar connector slot 4, the first drain bar 1, the second drain bar 2, third drain bar 5
It is connected with each other with the 4th drain bar 6 by drain bar connector 3 and drain bar connector slot 4, and the first drain bar 1, the second drain bar
2, third drain bar 5 and the wavy structure of the 4th drain bar 6, wavy shaped configuration are conducive to rainwater and flow into trough finally by row
Water hole 7 is discharged, so that ponding can not be assembled, 4 right end of drain bar connector slot is connected with third drain bar 5, third draining
5 end of plate is connected with the 4th drain bar 6, and 6 end side wall of the 4th drain bar is connected with gutter 10, drain bar connector 3 and row
The volume equal shape size of water plate connector slot 4 is mutually coincide, and the seamless right of drain bar connector 3 and drain bar connector slot 4 is utilized
It connects, facilitates construction personnel's assembly and disassembly, while waterproof performance is also preferable, 10 leading portion side wall of gutter is provided with diversion trough connection
11, and 11 end of diversion trough connection is provided with gutter connector slot 12, gutter 10 is "u"-shaped, and 10 front end of gutter
Diversion trough connection 11 and the 12 volume equal shape size of gutter connector slot of end mutually coincide, drain bar edge is using drawing
Sink 10 drains, and improves drainage effect, same dismountable gutter 10 is carried and assembled convenient for operator, so that device can
With Reusability, save the cost, 2 bottom of the second drain bar is provided with drainage hole 7, and 7 bottom of drainage hole is connected with drainage hole and turns
Connector 8, and 8 end of drainage hole adapter is provided with drainpipe 9, drainage hole 7 be set to the first drain bar 1, the second drain bar 2,
At the trough of third drain bar 5 and the 4th drain bar 6 composition wave structure, and the drainage hole adapter 8 of drainage hole 7 and lower section it
Between connection type be to be threadedly coupled, trough, which can drain rainwater, to be entered drainage hole 7 and be discharged finally by drainpipe 9, preferably
Solve the problems, such as ponding in building construction, while dismountable drainage hole adapter 8 is convenient for carrying and assembles.
Working principle: when using the building construction temporary drainage structure, drainage hole 7,8 and of drainage hole adapter are first checked
In drainpipe 9 whether clean foreign, to cleaning inside drainage hole 7, drainage hole adapter 8 and drainpipe 9, cleaning is finished
Afterwards, drain bar connector 3 and drain bar connector slot 4 are docked, so that the first drain bar 1, the second drain bar 2, third drain
It is connected with each other between plate 5 and the 4th drain bar 6, it is after assembling, drainage hole 7, drainage hole adapter 8 and drainpipe 9 is mutual
Connection forms drainage system, after assembling, will pass through the diversion trough connection 11 and diversion trough connection of head and the tail between gutter 10
Slot 12 is interconnected and fixed, and device is placed in the surface for needing drainage after fixed, prevents rain water-harvesting, draining finishes
Afterwards, it will dismantle between each part, drainage hole 7, drainage hole adapter 8 and drainpipe 9 carried out again after disassembly
Cleaning, so that next time continues to use, here it is the courses of work of the building construction temporary drainage structure.
Although the utility model is described in detail with reference to the foregoing embodiments, come for those skilled in the art
Say, it is still possible to modify the technical solutions described in the foregoing embodiments, or to part of technical characteristic into
Row equivalent replacement, within the spirit and principle of the utility model, any modification, equivalent replacement, improvement and so on should all
It is included within the scope of protection of this utility model.
Claims (5)
1. a kind of building construction temporary drainage structure, including the first drain bar (1), it is characterised in that: first drain bar (1)
Right side is connected with the second drain bar (2), and the second drain bar (2) end is provided with drain bar connector (3), and drain bar connector
(3) side wall is equipped with drain bar connector slot (4), and drain bar connector slot (4) right end is connected with third drain bar (5),
Its third drain bar (5) end is connected with the 4th drain bar (6), and the 4th drain bar (6) end side wall is connected with gutter
(10), gutter (10) the leading portion side wall is provided with diversion trough connection (11), and diversion trough connection (11) end is provided with and draws
Trough joint slot (12), the second drain bar (2) bottom are provided with drainage hole (7), and drainage hole (7) bottom is connected with draining
Hole adapter (8), and drainage hole adapter (8) end is provided with drainpipe (9).
2. a kind of building construction temporary drainage structure according to claim 1, it is characterised in that: first drain bar
(1), the second drain bar (2), third drain bar (5) and the 4th drain bar (6) pass through drain bar connector (3) and drain bar connector slot
(4) it is connected with each other, and the first drain bar (1), the second drain bar (2), third drain bar (5) and the 4th drain bar (6) are in wave
Shape structure.
3. a kind of building construction temporary drainage structure according to claim 1, it is characterised in that: the drain bar connector
(3) it mutually coincide with the volume equal shape size of drain bar connector slot (4).
4. a kind of building construction temporary drainage structure according to claim 1, it is characterised in that: the drainage hole (7) sets
It is placed in the wave of the first drain bar (1), the second drain bar (2), third drain bar (5) and the 4th drain bar (6) composition wave structure
At paddy, and the connection type between drainage hole (7) and the drainage hole adapter (8) of lower section is to be threadedly coupled.
5. a kind of building construction temporary drainage structure according to claim 1, it is characterised in that: the gutter (10) is
"u"-shaped, and the equal shape of gutter connector slot (12) volume of the diversion trough connection (11) of gutter (10) front end and end
Shape size is mutually coincide.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820494254.7U CN208235959U (en) | 2018-04-09 | 2018-04-09 | A kind of building construction temporary drainage structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820494254.7U CN208235959U (en) | 2018-04-09 | 2018-04-09 | A kind of building construction temporary drainage structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208235959U true CN208235959U (en) | 2018-12-14 |
Family
ID=64586986
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820494254.7U Expired - Fee Related CN208235959U (en) | 2018-04-09 | 2018-04-09 | A kind of building construction temporary drainage structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208235959U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117127701A (en) * | 2023-10-27 | 2023-11-28 | 中启胶建集团有限公司 | Temporary drainage structure for building engineering construction |
-
2018
- 2018-04-09 CN CN201820494254.7U patent/CN208235959U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117127701A (en) * | 2023-10-27 | 2023-11-28 | 中启胶建集团有限公司 | Temporary drainage structure for building engineering construction |
CN117127701B (en) * | 2023-10-27 | 2024-01-30 | 中启胶建集团有限公司 | Temporary drainage structure for building engineering construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111305566B (en) | High-rise residential full-professional alternate construction floor water interception method | |
CN201459905U (en) | Urban rainwater drainage system | |
CN211646629U (en) | Energy dissipation type flower bed suitable for drainage of sponge city high-rise building | |
CN208235959U (en) | A kind of building construction temporary drainage structure | |
CN213015043U (en) | Waterproof eaves structure for building | |
CN213358881U (en) | Secondary drainage device for ground of sinking type toilet | |
CN110106957A (en) | A kind of sponge type Rain Garden overflow mechanism | |
CN215976672U (en) | Assembly type prestressed construction waste recycled aggregate road | |
CN212771825U (en) | Garden road surface stone material laying structure | |
CN212896706U (en) | Temporary drainage structure for house construction | |
CN212956838U (en) | Super high-rise construction floor water interception structure | |
CN209457026U (en) | Geotechnical engineering side slope drainage structure | |
CN208009242U (en) | A kind of architectural engineering bridge drain pipeline structure | |
CN111058467B (en) | Basement backwater surface waterproof drainage structure and construction method | |
CN210459806U (en) | Building integrated building wall structure of photovoltaic | |
CN203684293U (en) | Antiseep structure of underground diaphragm wall | |
CN210288620U (en) | Prefabricated resin concrete escape canal | |
CN206090450U (en) | Sponge basin penetrant unit | |
CN206917112U (en) | The house roof guiding device that a kind of rainwater-proof with arc cornice structure splashes | |
CN205296349U (en) | Can assemble dismountable escape canal of having enough to meet need use | |
CN213741489U (en) | Double-layer rotatable embedded floor drain | |
CN219219291U (en) | Novel environment-friendly gully structure with combined grate cover | |
CN103696489B (en) | Quick detachable dewatering installation and mounting method thereof | |
CN218116802U (en) | Rain-proof, prevent pounding, easily pass through covering device of post-cast strip subsides | |
CN207062965U (en) | A kind of drainage of foundation pit system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181214 Termination date: 20200409 |