CN208213748U - Rubble cleaning system - Google Patents

Rubble cleaning system Download PDF

Info

Publication number
CN208213748U
CN208213748U CN201721895340.0U CN201721895340U CN208213748U CN 208213748 U CN208213748 U CN 208213748U CN 201721895340 U CN201721895340 U CN 201721895340U CN 208213748 U CN208213748 U CN 208213748U
Authority
CN
China
Prior art keywords
roller
rubble
support portion
cleaning system
column group
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721895340.0U
Other languages
Chinese (zh)
Inventor
于冰涛
辛国顺
吴杰
马化涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction Group Co Ltd
Original Assignee
Shanghai Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction Group Co Ltd filed Critical Shanghai Construction Group Co Ltd
Priority to CN201721895340.0U priority Critical patent/CN208213748U/en
Application granted granted Critical
Publication of CN208213748U publication Critical patent/CN208213748U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

The utility model relates to a kind of rubble cleaning systems.The rubble cleaning system includes support portion, feed hopper, roller, driving portion, water inlet pipe, Drainage Division and delivery section, feed hopper is set on support portion and connect with support portion, roller is set to the setting of the length direction on support portion and along support portion, feed hopper is connected to roller, roller is equipped with multiple apopores, driving portion is set on support portion and roller is driven to rotate, Drainage Division includes rhone and discharge outlet, rhone is set to below roller and is arranged along the length direction of roller, discharge outlet is connected to rhone, delivery site is below roller, the outlet end of the beginning access roller of delivery section.Using centrifugal principle, by the rotation of roller, phase mutual friction, improves cleaning efficiency between rubble and barrel, rubble and rubble.

Description

Rubble cleaning system
Technical field
The utility model relates to road construction fields, more particularly to rubble cleaning system.
Background technique
In pavement of road construction field, to the cleaning process of rubble, it appears particularly important.Generally, to the clear of metaling The helical rotation for mainly using more shafts is washed, and is cleaned by way of high-pressure flush.However, due to rubble shape Irregular, above-mentioned cleaning way is easy to cause rubble to be stuck between two shafts, so that cleaning equipment breaks down.Therefore, Above-mentioned cleaning method cleaning efficiency is not high.
Utility model content
Based on this, it is necessary to for the not high problem of above-mentioned cleaning method cleaning efficiency, it is high to provide a kind of cleaning efficiency Rubble cleaning system.
A kind of rubble cleaning system, comprising:
Support portion;
Feed hopper is set on the support portion and connect with the support portion;
Roller, be set on the support portion and along the length direction of the support portion be arranged, the feed hopper with it is described Roller connection, the roller are equipped with multiple apopores;
Driving portion is set on the support portion and the roller is driven to rotate;
Water inlet pipe is arranged along the feed hopper and protrudes into the roller;
Drainage Division, including rhone and discharge outlet, the rhone are set to below the roller and along the roller Length direction setting, the discharge outlet are connected to the rhone;
Delivery section is located at below the roller, and the beginning of the delivery section accesses the outlet end of the roller.
In one embodiment, the support portion includes bottom bracket, column group and crossbeam group, the column group include according to Secondary the first column group being arranged in parallel on the bottom bracket, the second column group and third column group, the roller are located at institute It states between the second column group and the third column group, the crossbeam group includes first crossbeam and second cross beam, and described first is horizontal Beam is set in the second column group, and the second cross beam is set in the third column group, the height of the first crossbeam Degree is greater than the height of the second cross beam.
In one embodiment, the third column group is equipped with mounting platform, and the driving part is flat in the installation On platform.
In one embodiment, the roller is equipped with rotary shaft, and the rotary shaft is connected to first cross by bearing On beam and the second cross beam.
In one embodiment, the driving portion includes main motor and reduction gear box, the main motor and the deceleration Gear-box connection, the reduction gear box and the rotation axis connection.
In one embodiment, the water inlet pipe is aperture water pipe, the water inlet pipe along the part that the feed hopper is arranged End be equipped with fountain head.
It in one embodiment, further include muddy water sedimentation basin, the muddy water sedimentation basin is connect with the discharge outlet.
It in one embodiment, further include clear water reserviors, the muddy water sedimentation basin is connect by water pump with the clear water reserviors, institute Water inlet pipe is stated to connect with the clear water reserviors.
It in one embodiment, further include automatic feeding machine, the feed hopper is accessed in the end of the automatic feeding machine.
Above-mentioned rubble cleaning system when in use, starts driving portion, and driving roller rotates, and water inlet tube of intaking is stable Afterwards, building stones are sent into through feed hopper, rubble enters roller, cleans by the rotation and water inlet pipe water flow of roller to rubble.Through Rubble after over cleaning enters delivery section through the outlet end of roller, is transported by delivery section collection;It rinses the muddy water generated and passes through rolling Apopore on cylinder falls into the rhone below roller, then is discharged through discharge outlet.Above-mentioned rubble cleaning equipment is remote using centrifugation From by the rotation of roller, rolling around the rubble in roller, phase mutual friction, mentions between rubble and barrel, rubble and rubble High cleaning efficiency, cleaning more thoroughly.
Detailed description of the invention
Fig. 1 is the schematic perspective view of the rubble cleaning system of an embodiment;
Fig. 2 is the perspective elevation of rubble cleaning system shown in FIG. 1;
Fig. 3 is the side view of rubble cleaning system shown in FIG. 1;
Fig. 4 is that the rubble of the rubble cleaning system of an embodiment cleans schematic diagram;
Fig. 5 is the rubble cleaning process perspective view of the rubble cleaning system of an embodiment;
Fig. 6 is the structural schematic diagram of the support portion of the rubble cleaning system of an embodiment;
Fig. 7 is the flow chart of the application construction method of the rubble cleaning system of an embodiment.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work All other embodiment obtained, fall within the protection scope of the utility model.
As shown in Figure 1-3, the rubble cleaning system 1 of an embodiment includes support portion 10, feed hopper 20, roller 30, driving Portion 40, water inlet pipe 50, Drainage Division 60 and delivery section 70, feed hopper 20 are set on support portion 10 and connect with support portion 10, rolling Cylinder 30 is set on support portion 10 and is arranged along the length direction of support portion 10, and feed hopper 20 is connected to roller 30, on roller 30 Equipped with multiple apopores 300, driving portion 40 is set on support portion 10 and roller 30 is driven to rotate, and Drainage Division 60 includes rhone 600 and discharge outlet 610, rhone 600 is set to 30 lower section of roller and is arranged along the length direction of roller 30, discharge outlet 610 with Rhone 600 is connected to, and delivery section 70 is located at 30 lower section of roller, the outlet end 310 of the beginning access roller 30 of delivery section 70.
As shown in Figure 4 and Figure 5, in figure direction shown in arrow be rubble moving direction.Above-mentioned rubble cleaning system 1 makes Used time starts driving portion 40, and driving roller 30 rotates, and water inlet pipe 50 is intake, and after stable, is sent into building stones through feed hopper 20, Rubble enters roller 30, is cleaned by the rotation of roller 30 and the water flow of water inlet pipe 50 to rubble.It is broken after over cleaning Stone enters delivery section 70 through the outlet end 310 of roller 30, is transported by the collection of delivery section 70;It rinses the muddy water generated and passes through roller 30 On apopore 300 fall into the rhone 600 of the lower section of roller 30, then be discharged through discharge outlet 610.Direction shown in arrow a in Fig. 4 For muddy water flow direction.Above-mentioned rubble cleaning system 1 is made broken in roller 30 using centrifugal principle by the rotation of roller 30 Stone rolls around, and phase mutual friction between rubble and barrel, rubble and rubble accelerates the speed that sludge falls off from rubble, improves Cleaning efficiency, cleans more thorough.
Referring to Fig. 6, in the present embodiment, support portion 10 includes bottom bracket 12, column group 14 and crossbeam group, column group 14 include the first column group 140, the second column group 142 and the third column group 144 being successively arranged in parallel on bottom bracket 12, For roller 30 between the second column group 142 and third column group 144, crossbeam group includes first crossbeam 160 and second cross beam 162, first crossbeam 160 is set in the second column group 142, and second cross beam 162 is set in third column group 144, and first is horizontal The height of beam 160 is greater than the height of second cross beam 162.Wherein, the height of first crossbeam 160 and the height of second cross beam 162 are Refer to the height of first crossbeam 160 and second cross beam 162 apart from same level (for example, ground).Support portion 10 is rubble cleaning System 1 provides support, wherein bottom bracket 12 is in " day " font, is welded by I-steel.First column group 140, second is vertical Column group 142 and third column group 144 are successively arranged in parallel on bottom bracket 12.First column group 140, the second column group 142 It is made of with third column group 144 two root posts.The both ends of first crossbeam 160 are connected to the two of the second column group 142 On root post, the both ends of second cross beam 162 are connected in the two root posts of third column group 144.Feed hopper 20 is located at the Between one column group 140 and the second column group 142, two of the two root posts of the first column group 140 and the second column group 142 are vertical Feed hopper 20 is fixed on support portion 10 by column.In the present embodiment, feed hopper 20 and the first column group 140 and the second column group 142 be welded connecting.
In the present embodiment, the lower section of bottom bracket 12 is additionally provided with concrete foundation 120, provides support for support portion 10. In the top pre-embedded steel slab of concrete foundation 120, bottom bracket 12 is welded in concrete foundation 120 by pre-embedded steel slab.? In the present embodiment, there are six concrete foundations 120, is arranged on the load position of six roots of sensation column, and length and width are respectively 0.3m, high For 0.4m, the size of pre-embedded steel slab is 5*200*200mm.
In the present embodiment, support portion 10 is steel construction, stability and flexing resistance with higher.Wherein, the first column Column in group 140 is 10# channel steel, is highly 1.27m.Column in second column group 142 is 20# I-steel, is highly 2.3m.Column in third column group 144 is 10# channel steel, is highly 1.35m.First crossbeam 160 is 10# I-steel, and length is 1.08m.Second cross beam 162 is 20# channel steel, length 1.08m.
More progressively, cant beam 18, the both ends of cant beam 18 are additionally provided between the second column group 142 and third column group 144 It is connect respectively with the column in the second column group 142 and third column group 144.Two root posts, the third of second column group 142 are vertical Two root posts, first crossbeam 160, second cross beam 162 and two cant beams 18 and bottom bracket 12 of column group 144 are formed together one Roller 30 is limited in the frame by cuboid framework, improves the safety in cleaning process.
The both ends of roller 30 are located between first crossbeam 160 and second cross beam 162.The height of first crossbeam 160 is big The outlet end 310 of roller 30 can be made to be angled slightly downward in the height of second cross beam 162, when rubble enters through feed hopper 20 After the completion of roller 30 and cleaning, it can be moved under gravity along roller 30 to outlet end 310, facilitate the defeated of rubble Out.Further, as depicted in figs. 1 and 2, in the present embodiment, roller 30 is equipped with rotary shaft 32, and rotary shaft 32 passes through bearing It is connected on first crossbeam 160 and second cross beam 162.Rotary shaft 32 is through roller 30 and roller 30, rotary shaft are stretched out in both ends 32 both ends pass through bearing respectively and are connected on first crossbeam 160 and second cross beam 162.When rotary shaft 32 rotates, roller 30 Also it rotates with it.
In the present embodiment, driving portion 40 includes main motor 400 and reduction gear box 410, main motor 400 and reduction gearing Case 410 connects, and reduction gear box 410 is connect with rotary shaft 32.Main motor 400 is that reduction gear box 410 provides electric power, and then drives Dynamic rotary shaft 32 rotates.Reduction gear box 410 can control the revolving speed of rotary shaft 32, and then be selected according to different rubbles Select different revolving speeds.In the present embodiment, as shown in fig. 6, third column group 144 is equipped with mounting platform 146, driving portion 40 is located at On the mounting platform 146.In the present embodiment, main motor 400 is the three-phase motor of 7.5kw, the input of reduction gear box 410 End connection main motor 400, output end connect rotary shaft 32.
Roller 30 is made of punching steel plate, wherein it is apopore 300 that punching, which is formed by hole,.As shown in Figure 2 and Figure 4, In roller 30 radially inside every a piece reinforced bar support 302 of 60 ° of settings, one group of six roots of sensation, totally five groups, every group of reinforced bar support 302 along roller 30 length direction interval 0.4m.In the present embodiment, 30 diameter of roller is 0.98m, length 2.3m.Cleaning The muddy water that rubble generates falls into Drainage Division 60 through apopore hole 300.In the present embodiment, it is 10mm's that apopore 300, which is aperture, Circular hole.
Please refer to Fig. 1 and Fig. 2, water inlet pipe 50 is arranged along feed hopper 20 and protrudes into roller 30, wherein water inlet pipe 50 be the perimeter setting being open along feed hopper 20.In the present embodiment, water inlet pipe 50 is to open along the part that feed hopper 20 is arranged The end of hole water pipe, water inlet pipe 50 is equipped with fountain head.Being set to the water inlet pipe 50 at feed hopper 20 can be set multiple spray heads, Rubble can tentatively be cleaned at feed hopper 20, after entering roller 30, can be accelerated under the injection of fountain head broken The cleaning of stone.In the present embodiment, water inlet pipe 50 provides high pressure water by the high-pressure hydraulic pump of 2.2kw, and water inlet pipe 50 protrudes into roller 30 End be equipped with flat fountain head, and then the pressure that increased water flow ejects improves cleaning effect and cleaning efficiency.In this implementation In example, water inlet pipe 50 is additionally provided with valve 500, controls being turned on and off for water inlet pipe 50 by valve 50, and then according to cleaning feelings The water delivery state of condition selection water inlet pipe 50.As shown in Figure 1, in the present embodiment, there are two valves 500.
In the present embodiment, rubble cleaning system 1 further includes muddy water sedimentation basin, and muddy water sedimentation basin is connect with discharge outlet 610. Rhone 600 is located at the lower section of roller 30 and is arranged along the rotary shaft of roller 30 32, cleans in the rotation of roller 30 to rubble During, the muddy water of generation is discharged into rhone 600 under the action of gravity and centrifugal force through apopore 300, rhone 600 In muddy water again through discharge outlet 610 enter muddy water sedimentation basin.It closer, in the present embodiment, further include clear water reserviors, muddy water Sedimentation basin is connect by water pump with clear water reserviors, and water inlet pipe 50 is connect with clear water reserviors.For muddy water after muddy water sedimentation basin precipitating, sludge is heavy Enter bottom of pond, is layered with the clear water on upper layer.Clear water reserviors are pumped into after the water in muddy water sedimentation basin is limpid, then with water pump, then again will Water in clear water reserviors is pumped into water inlet pipe 50, to recycle, saves water, reduces the pollution to environment.In the present embodiment, mud Water sedimentation pond is equipped with loading machine entrance, and loading machine is facilitated to carry out dredging operation, clears up the sludge in muddy water sedimentation basin.
Please refer to Fig. 1 and Fig. 4, the rubble after cleaning enters delivery section 70 through the outlet end 310 of roller 30, through conveying Portion 70 is transported to corresponding place.In the present embodiment, delivery section 70 is belt conveyor, and the beginning of belt conveyor accesses roller At 30 outlet end 310, the rubble after cleaning falls into belt conveyor, as the movement of belt is transported and is collected.
In the present embodiment, rubble cleaning equipment further includes automatic feeding machine, and feed hopper is accessed in the end of automatic feeding machine 20, it realizes the automation of charging, improves cleaning efficiency.
Referring again to Fig. 1 and Fig. 6, in the present embodiment, rubble cleaning system 1 further includes operating platform 80, is located at support In portion 10.Operating platform 80 is that the platform of inspection and maintenance is provided for staff.In the present embodiment, operating platform 80 is The steel plate of 0.5*2m is welded on bottom bracket 12 positioned at the side of main motor 400.
Above-mentioned rubble cleaning system 1 when in use, opens main motor 400, and reduction gear box 410 starts, and drives roller 30 Rotation opens the valve 500 of water inlet pipe 50, is supplied water from high-pressure hydraulic pump to water inlet pipe 50, after stable equipment operation, using automatic Rubble is sent into feed hopper 20 by charger, and rubble enters roller 30, rotation and water inlet pipe by roller 30 through feed hopper 20 Rubble is cleaned in the injection of 50 fountain heads, since first crossbeam 160 is higher than second cross beam 162, so that roller 30 slightly inclines Tiltedly, the rubble after cleaning moves along roller 30 under gravity and falls into belt conveyor, is collected and is transported by belt conveyor It walks, the muddy water for cleaning generation falls into rhone 600 through apopore 300, then enters muddy water sedimentation basin through discharge outlet 610, to mud After water in water sedimentation pond is limpid, it is pumped into clear water reserviors through water pump, is then pumped into water inlet pipe 50 and recycles again.Above-mentioned rubble Cleaning system 1 rolls around the rubble in roller 30 by being pivoted for roller 30 using centrifugal principle, rubble and cylinder Phase mutual friction between wall, rubble and rubble accelerates the speed that sludge falls off from rubble, improves cleaning efficiency, cleans more It is thorough.Muddy water drainage after cleaning imports muddy water sedimentation basin, recycles after precipitation, has saved water resource, reduces pair The pollution of environment.Above-mentioned rubble cleaning system 1 is building stones 10-13 cubic metres capable of washing per hour average in abundant operating, with biography The cleaning method of system is compared, and in the case where reaching same cleaning effect, cleaning efficiency improves a lot, save water 50% with On.In addition, above-mentioned rubble cleaning system 1 takes up little area, stable working performance, be easily installed maintenance and it is simple and reliable for structure.
The application construction method of above-mentioned rubble cleaning system 1 is introduced below.
As shown in Fig. 1-Fig. 7, the application construction method of the rubble cleaning system 1 of an embodiment, comprising the following steps:
Step S700 starts driving portion 40, and driving roller 30 rotates, and water inlet pipe 50 is intake.It works in rubble cleaning system 1 Before, it first allows roller 30 to rotate, and allows 50 water flowing of water inlet pipe, fed again after operating and stablizing, to ensure before cleaning 1 operational excellence of rubble cleaning system.
Step S710 is sent into building stones through feed hopper 20 after stable, and rubble enters roller 30 through feed hopper 20, leads to The water that the rotation and water inlet pipe 50 for crossing roller 30 convey cleans the rubble in roller 30.Feed hopper 20 and roller 30 connect Logical, rubble is entered under gravity in the roller 30 of rotation.In this embodiment, water inlet pipe 50 is arranged along feed hopper 20 Part is aperture water pipe, and the end that water inlet pipe 50 protrudes into roller 30 is equipped with fountain head.Rubble is at feed hopper 20 through aperture water pipe Tentatively cleaned, into roller 30 after the water that is ejected through fountain head clean again.Meanwhile the friction of rubble and barrel and Friction between rubble and rubble reduces adhesive force of the sludge on rubble, accelerates the speed that sludge falls off.
Step S720, the muddy water for rinsing generation is fallen into rhone 600 through the apopore 300 on roller 30, through discharge outlet 610 discharges.Muddy water is fallen into rhone 600 under the action of gravity and centrifugal force through apopore 300, in the present embodiment, also Equipped with muddy water sedimentation basin and clear water reserviors.Muddy water is discharged into muddy water sedimentation basin through discharge outlet 610, and the water in pond to be precipitated becomes limpid Afterwards, it is pumped into clear water reserviors using water pump to recycle.
Step S730, the rubble after cleaning enter delivery section 70 through the outlet end 310 of roller 30, are collected and transported by delivery section 70 It walks, completes the cleaning of rubble.The outlet end 310 of the beginning access roller 30 of delivery section 70, in the present embodiment, roller 30 is slightly It tilts down.Rubble after cleaning is fallen into delivery section 70 along roller 30 under gravity, is then collected and is transported, in case after Continuous construction usage.
The application construction method step of above-mentioned rubble cleaning system 1 is simple and convenient to operate, and can meet different constructions well Rubble cleaning under site condition.
Each technical characteristic of embodiment described above can be combined arbitrarily, for simplicity of description, not to above-mentioned reality It applies all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, all should be considered as described in this specification.
Above-described embodiments merely represent several embodiments of the utility model, the description thereof is more specific and detailed, But it cannot be understood as the limitations to utility model patent range.It should be pointed out that for the common skill of this field For art personnel, without departing from the concept of the premise utility, various modifications and improvements can be made, these are belonged to The protection scope of the utility model.Therefore, the scope of protection shall be subject to the appended claims for the utility model patent.

Claims (9)

1. a kind of rubble cleaning system characterized by comprising
Support portion;
Feed hopper is set on the support portion and connect with the support portion;
Roller is set on the support portion and is arranged along the length direction of the support portion, the feed hopper and the roller Connection, the roller are equipped with multiple apopores;
Driving portion is set on the support portion and the roller is driven to rotate;
Water inlet pipe is arranged along the feed hopper and protrudes into the roller;
Drainage Division, including rhone and discharge outlet, the rhone are set to below the roller and along the length of the roller Direction setting, the discharge outlet are connected to the rhone;
Delivery section is located at below the roller, and the beginning of the delivery section accesses the outlet end of the roller.
2. rubble cleaning system according to claim 1, which is characterized in that the support portion includes bottom bracket, column Group and crossbeam group, the column group includes the first column group being successively arranged in parallel on the bottom bracket, the second column group With third column group, for the roller between the second column group and the third column group, the crossbeam group includes the One crossbeam and second cross beam, the first crossbeam are set in the second column group, and the second cross beam is set to described In three column groups, the height of the first crossbeam is greater than the height of the second cross beam.
3. rubble cleaning system according to claim 2, which is characterized in that it is flat that the third column group is equipped with installation Platform, the driving part is on the mounting platform.
4. rubble cleaning system according to claim 2, which is characterized in that the roller is equipped with rotary shaft, the rotation Axis is connected on the first crossbeam and the second cross beam by bearing.
5. rubble cleaning system according to claim 4, which is characterized in that the driving portion includes main motor and reducing gear Roller box, the main motor are connect with the reduction gear box, the reduction gear box and the rotation axis connection.
6. rubble cleaning system according to claim 1, which is characterized in that the water inlet pipe is arranged along the feed hopper Part is aperture water pipe, and the end of the water inlet pipe is equipped with fountain head.
7. rubble cleaning system according to claim 1, which is characterized in that further include muddy water sedimentation basin, the muddy water is heavy Shallow lake pond is connect with the discharge outlet.
8. rubble cleaning system according to claim 7, which is characterized in that it further include clear water reserviors, the muddy water sedimentation basin It is connect by water pump with the clear water reserviors, the water inlet pipe is connect with the clear water reserviors.
9. rubble cleaning system according to claim 1, which is characterized in that further include automatic feeding machine, it is described automatically into The feed hopper is accessed in the end of material machine.
CN201721895340.0U 2017-12-29 2017-12-29 Rubble cleaning system Active CN208213748U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721895340.0U CN208213748U (en) 2017-12-29 2017-12-29 Rubble cleaning system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721895340.0U CN208213748U (en) 2017-12-29 2017-12-29 Rubble cleaning system

Publications (1)

Publication Number Publication Date
CN208213748U true CN208213748U (en) 2018-12-11

Family

ID=64532934

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721895340.0U Active CN208213748U (en) 2017-12-29 2017-12-29 Rubble cleaning system

Country Status (1)

Country Link
CN (1) CN208213748U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108246691A (en) * 2017-12-29 2018-07-06 上海建工集团股份有限公司 Rubble cleaning system and its application construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108246691A (en) * 2017-12-29 2018-07-06 上海建工集团股份有限公司 Rubble cleaning system and its application construction method

Similar Documents

Publication Publication Date Title
CN202283486U (en) Spiral sand washer
CN111533428B (en) Construction method for curing building slurry
CN110372161A (en) A kind of urban ecology river bottom mud pretreatment system and its processing method
CN106040362B (en) A kind of building waste pulverizer
CN205797424U (en) Synchronous Transmission crushing system for building waste pulverizer
CN208213748U (en) Rubble cleaning system
CN205797465U (en) Automatic spray dust falling system for building waste pulverizer
CN208798376U (en) One seed melon inner-rind digging device seed flesh separator
CN108246691A (en) Rubble cleaning system and its application construction method
CN111346726A (en) Movable sand washing station
CN114405151A (en) Gravity rotary type sewage treatment device and sewage treatment method
CN207276352U (en) Sewage collecting processing unit and system
CN205851040U (en) Depositing dust reducing mechanism for building waste disintegrating mechanism
CN111825289A (en) Hydraulic engineering synthesizes silt processing apparatus
CN217121028U (en) Highway engineering road bed road surface construction is with novel stone desilt device
CN202130431U (en) Automatic washer for engineering vehicle
CN202098387U (en) Automatic engineering vehicle flushing machine
CN212554410U (en) Concrete mixing device for construction
CN211524813U (en) Automatic sand discharging device for shield machine
KR100498119B1 (en) Apparatus for washing regenerated sand
CN207012675U (en) A kind of mixed mud tailstock material recovery system
CN205868412U (en) A adjustable rack construction for building rubbish rubbing crusher
CN202098390U (en) Automatic washer for engineering vehicles
CN211969388U (en) Efficient water-saving mining spraying device
CN218813439U (en) Air suction dredge for bridge construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant