CN208202327U - A kind of double linked network protective layer insulation construction integrated wallboards - Google Patents

A kind of double linked network protective layer insulation construction integrated wallboards Download PDF

Info

Publication number
CN208202327U
CN208202327U CN201820753396.0U CN201820753396U CN208202327U CN 208202327 U CN208202327 U CN 208202327U CN 201820753396 U CN201820753396 U CN 201820753396U CN 208202327 U CN208202327 U CN 208202327U
Authority
CN
China
Prior art keywords
layer
protective layer
baffle
insulation construction
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820753396.0U
Other languages
Chinese (zh)
Inventor
祁帮增
赵东良
赵猛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Zhibo Insulation Materials Manufacturing Co Ltd
Original Assignee
Hebei Zhibo Insulation Materials Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Zhibo Insulation Materials Manufacturing Co Ltd filed Critical Hebei Zhibo Insulation Materials Manufacturing Co Ltd
Priority to CN201820753396.0U priority Critical patent/CN208202327U/en
Application granted granted Critical
Publication of CN208202327U publication Critical patent/CN208202327U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Building Environments (AREA)

Abstract

The utility model relates to a kind of double linked network protective layer insulation construction integrated wallboards, building wall board technical field is followed successively by protective layer, sandwich heat preservation layer and concrete from outside to inside;The protective layer is made of double layer bar and concrete;The size of mesh opening of the steel mesh of inside is twice of the size of mesh opening of the steel mesh in outside;It is connected between the protective layer, sandwich heat preservation layer and concrete by the high-strength connector of built-in reinforcing bar.The edge joint position of insulation construction integrated wallboard described in muti-piece is provided with fixed piece connector, the fixed piece connector includes the resin layer of built-in reinforcing bar and outsourcing, the resin layer of reinforcing bar one end stretching outsourcing, and it is provided with upward hook, first baffle, second baffle, third baffle, fourth gear plate and bottom plate are disposed on the resin layer from left to right.

Description

A kind of double linked network protective layer insulation construction integrated wallboards
Technical field
The utility model relates to a kind of wallboard more particularly to a kind of double linked network protective layer insulation construction integrated wallboards, belong to In building wall board technical field.
Background technique
EPS (molded polystyrene) in the prior art or XPS (molded polystyrene) building block or wallboard, are by hindering Combustion type polystyrene foam plastics module is as template and heat insulation layer, core casting concrete surface layer, plastering or radiant panel Material and a kind of novel composite wall formed.Which solve in terms of insulating layer of external wall of building hollowing, crack, fall off and inner wall surface The common fault got damp, tremble with fear, condense thoroughly etc. in terms of construction qualities.Greatly improve the durability and heat preservation energy-saving of insulating layer of external wall Performance is more excellent.Whole energy is built up to 75% or more standard, and can realize insulating layer and structure wall same service life.Ps is through adding After heat foamable, the manufactured EPS materials for wall module by special equipment, mold heating pressurization.This material can be in building block system Grafting forms various walls, and geometric dimension is accurate, and quality is stablized.Production and processing and construction site " zero " loss are realized, is realized China's industrial building energy-saving system zero is broken through.EPS building block shortens compared to traditional architecture construction period.EPS module is mixed Solidifying soil shear wall is exterior wall non-dismantling formwork before pouring, and is external wall insulating layer after concrete formation.To eliminate a side form Plate realizes structure load-bearing, wall thermal insulating one instead of the composite wall body structure of the secondary sticking heat-preservation plate of external thermal insulation system The completion of secondary property, accelerates construction speed, reduces constuction budget cost.EPS module application face is very wide, can be widely used for civilian Residential architecture, public building, cities and towns and farm dwelling transformation and industrial heat-insulation workshop and agriculture greenhouse, high-rise and low layer are high Shelves villa etc..In addition, EPS building block has good thermal insulation property and heat-proof quality, suitable for the cold north and sweltering heat South.Make to build cool in summer and warm in winter, greatly reduces the expense for adjusting such as " refrigeration or heat up " energy consumption for temperature. EPS module building construction in can free removal template, exempt from cutting etc. techniques, substantially reduce construction period and reduce working hour at This advantages that.
But existing EPS building block mostly uses traditional single net protective layer structure, needs to pour self-compacting concrete, and And monofilament net is pressed from both sides among 50mm concrete shield, it is easy to appear the uncompacted phenomenon of concreting.Meanwhile existing connection Part, intensity is different, especially the connector at wall plate piecing, and poor sealing effect, heat waste is big, and heat insulation effect is bad, is easy to lead Cause cold bridge phenomenon.
Utility model content
Therefore, in view of the above problems in the prior art, the utility model provides a kind of double linked network protective layer insulation constructions Integrated wallboard, to solve the uncompacted phenomenon of traditional single net protective layer concreting and edge joint position heat waste is big asks Topic.
To realize above-mentioned utility model, the technical scheme that the utility model is provided is as follows:
A kind of double linked network protective layer insulation construction integrated wallboards, the wallboard is that sandwich structure is sandwich structure, It is followed successively by protective layer, sandwich heat preservation layer and concrete from outside to inside;The protective layer is by double layer bar and mixes Solidifying soil is constituted, and every layer of steel mesh includes horizontal bar and vertical muscle, forms node, two layers of steel at horizontal bar and vertical muscle interconnection Connected between the corresponding node of muscle net by dowel, in every layer of steel mesh, vertical muscle in inside, horizontal bar on the outside, with Facilitate the flowing of concrete;Spacing head is provided on the outside of the steel mesh in outside;The size of mesh opening of the steel mesh of inside It is twice of the size of mesh opening of the steel mesh in outside;Between the protective layer, sandwich heat preservation layer and concrete It is connected by the high-strength connector of built-in reinforcing bar.
The edge joint position of insulation construction integrated wallboard described in muti-piece is provided with fixed piece connector, and the fixed piece connects Fitting includes the resin layer of built-in reinforcing bar and outsourcing, and the resin layer of outsourcing is stretched out in reinforcing bar one end, and is provided with upward card It hooks, is disposed with first baffle, second baffle, third baffle, fourth gear plate and bottom plate from left to right on the resin layer; Wherein, the reinforcing bar between hook and first baffle is used for fixed protection layer and its interior steel mesh, and sandwich heat preservation layer grips Between first baffle and fourth gear plate, and second baffle, third baffle are embedded in sandwich heat preservation layer, the concrete structure Layer is arranged between fourth gear plate and bottom plate;The spacing head is arranged on the outside of the hook.
Further, the overcoat thickness is 50mm.
Further, the insulation construction integrated wallboard is rectangular or rectangle.
Further, the node is using welding or binding connection.
Further, the length of the dowel is 10-50mm.
Further, the sandwich heat preservation layer is the insulating layers such as EPS, XPS.
Compared with the existing technology, the utility model has the following technical effect that
Double linked network protective layer insulation construction integrated wallboards of the utility model, horizontal bar on the outside, including vertical muscle Side facilitates concrete to flow, and outside steel mesh has spacing head, plays the role of providing silk screen protective layer, while inside reinforcing bar Net and outside steel mesh collective effect also serve as the effect of bearing sandwich heat preservation layer.Using the high-strength connector of built-in reinforcing bar, a side The fixed double-deck silk screen is played the role of in face, on the other hand plays the purpose of each layer of fixed wallboard.It is wrapped up outside fixed piece connector On the one hand resin material can be reduced connector and penetrate insulating layer bring " cold bridge ", another party is avoided high-strength by resin package Connector corrodes.Double linked network protective layer insulation construction integrated wallboards of the utility model keep the temperature mould using the tall and big plate of flood Block, it is easy for construction, reduce piece bring heat waste.Equally also have a standardized adjustment module, respectively 200mm, 300mm or Other nonstandard sizes.Non-standard big template die number is coped with, number of molds is reduced.
Detailed description of the invention
Fig. 1 is a kind of double linked network protective layer insulation construction integrated wallboard structural schematic diagrams of the utility model;
Fig. 2 is double layer bar structural schematic diagram;
Fig. 3 is fixed piece connector overall structure diagram;
Specific embodiment
The specific embodiment of 1-3 is described in further detail the utility model with reference to the accompanying drawing.
As shown in Figs. 1-2, a kind of double linked network protective layer insulation construction integrated wallboards, be sandwich structure, by outside to Inside it is followed successively by 50mm thick protection layers 1, sandwich heat preservation layer 2 and concrete 3.Protective layer 1 is by double layer bar 4 and coagulation Soil is constituted, and every layer of steel mesh 4 includes horizontal bar 5 and vertical muscle 6, and node, section are formed at 6 interconnection of horizontal bar 5 and vertical muscle Point is connected using welding or binding, is connected between two layers of corresponding node of steel mesh 4 by dowel 7, the length of dowel 7 is 20mm.In every layer of steel mesh 4, vertical muscle 6 in inside, horizontal bar 5 on the outside, to facilitate the flowing of concrete.The steel in outside Spacing head 9 is provided on the outside of muscle net 4.The size of mesh opening of the steel mesh 4 of inside is the two of the size of mesh opening of the steel mesh 4 in outside Times.It is connected between protective layer 1, sandwich heat preservation layer 2 and concrete 3 by the high-strength connector 8 of built-in reinforcing bar.Its In, as shown in figure 3, the edge joint position of insulation construction integrated wallboard described in muti-piece is provided with fixed piece connector 22, it is described solid Determine the resin layer 24 that piece connector 22 includes built-in reinforcing bar 23 and outsourcing, the resin layer of outsourcing is stretched out in 23 one end of reinforcing bar 24, and it is provided with upward hook 25, it is disposed with first baffle 26, second baffle from left to right on the resin layer 24 27, third baffle 28, fourth gear plate 29 and bottom plate 30;Wherein, the reinforcing bar 23 between hook 25 and first baffle 26 is for solid Determine protective layer 1 and its interior steel mesh 4, sandwich heat preservation layer 2 are clamped between first baffle 26 and fourth gear plate 29, and the Two baffles 27, third baffle 28 are embedded in sandwich heat preservation layer 2, the concrete 3 setting in fourth gear plate 29 and Between bottom plate 30;The setting of spacing head 9 is in 25 outside of hook.Sandwich heat preservation layer 2 is the insulating layers such as EPS, XPS.
Above-described embodiment, which is intended merely to become apparent from, illustrates that the technical solution of the utility model made enumerates, not to this reality With novel restriction, those skilled in the art according to the common knowledge of this field to technical scheme it is flexible also Within the application protection scope, in short, above-described embodiment is only to enumerate, the protection scope of the application is with appended claims Subject to book range.

Claims (6)

1. a kind of double linked network protective layer insulation construction integrated wallboards, it is characterised in that: the wallboard is sandwich structure, by Protective layer (1), sandwich heat preservation layer (2) and concrete (3) are followed successively by outside;The protective layer (1) is by clad steel Muscle net (4) and concrete are constituted, and every layer of steel mesh (4) includes horizontal bar (5) and vertical muscle (6), horizontal bar (5) and vertical muscle (6) node is formed at interconnection, is connected between the corresponding node of two layers of steel mesh (4) by dowel (7), every layer of reinforcing bar In net (4), vertical muscle (6) in inside, horizontal bar (5) on the outside, to facilitate the flowing of concrete;The steel mesh in outside (4) outside is provided with spacing head (9);The size of mesh opening of the steel mesh (4) of inside is the net of the steel mesh (4) in outside Twice of lattice size;Pass through built-in reinforcing bar between the protective layer (1), sandwich heat preservation layer (2) and concrete (3) High-strength connector (8) connection;
The edge joint position of insulation construction integrated wallboard described in muti-piece is provided with fixed piece connector (22), and the fixed piece connects Fitting (22) includes the resin layer (24) of built-in reinforcing bar (23) and outsourcing, and the resin layer of outsourcing is stretched out in reinforcing bar (23) one end (24), it and is provided with upward hook (25), is disposed with first baffle (26), on the resin layer (24) from left to right Two baffles (27), third baffle (28), fourth gear plate (29) and bottom plate (30);Wherein, hook (25) and first baffle (26) Between reinforcing bar (23) be used for fixed protection layer (1) and its interior steel mesh (4), sandwich heat preservation layer (2) is clamped to first Between baffle (26) and fourth gear plate (29), and second baffle (27), third baffle (28) are embedded in sandwich heat preservation layer (2), The concrete (3) is arranged between fourth gear plate (29) and bottom plate (30);The spacing head (9) is arranged described On the outside of hook (25).
2. a kind of double linked network protective layer insulation construction integrated wallboards according to claim 1, it is characterised in that: described anti- Sheath (1) with a thickness of 50mm.
3. a kind of double linked network protective layer insulation construction integrated wallboards according to claim 1, it is characterised in that: the guarantor The structure-integrated wallboard of temperature is rectangle or rectangular.
4. a kind of double linked network protective layer insulation construction integrated wallboards according to claim 1, it is characterised in that: the section Point is using welding or binding connection.
5. a kind of double linked network protective layer insulation construction integrated wallboards according to claim 1, it is characterised in that: the company The length for connecing muscle (7) is 10-50mm.
6. a kind of double linked network protective layer insulation construction integrated wallboards according to claim 1, it is characterised in that: the folder Heart insulating layer (2) is EPS, XPS sandwich insulating layer.
CN201820753396.0U 2018-05-21 2018-05-21 A kind of double linked network protective layer insulation construction integrated wallboards Active CN208202327U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820753396.0U CN208202327U (en) 2018-05-21 2018-05-21 A kind of double linked network protective layer insulation construction integrated wallboards

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820753396.0U CN208202327U (en) 2018-05-21 2018-05-21 A kind of double linked network protective layer insulation construction integrated wallboards

Publications (1)

Publication Number Publication Date
CN208202327U true CN208202327U (en) 2018-12-07

Family

ID=64517632

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820753396.0U Active CN208202327U (en) 2018-05-21 2018-05-21 A kind of double linked network protective layer insulation construction integrated wallboards

Country Status (1)

Country Link
CN (1) CN208202327U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112549672A (en) * 2020-12-02 2021-03-26 湖南大学 Protection and heat preservation integrated composite wallboard and manufacturing method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112549672A (en) * 2020-12-02 2021-03-26 湖南大学 Protection and heat preservation integrated composite wallboard and manufacturing method thereof

Similar Documents

Publication Publication Date Title
CN110093997A (en) A kind of prefabricated sandwich heat preservation overlapping concrete shear force wall and its preparation method and application
CN208202216U (en) A kind of insulation construction integrated wallboard
CN206128430U (en) Prefabricated heat preservation wallboard structure of integration and wallboard bolted connection subassembly
CN109866315A (en) A kind of Assembled self-insulating single side overlapped shear wall plate and its casting method
CN106088463A (en) A kind of precast concrete external wall panel and preparation method thereof
CN101481934A (en) Heat preserving system and construction process for construction exterior wall
CN201695515U (en) Light-steel light-concrete structural system
CN104478354B (en) Cement foamed heat insulation core material, inorganic compound heat insulation plate, manufacturing method and mold
WO2014094343A1 (en) Flow-guide-type foamed structure and prefab composite wall panel, and preparation method thereof
CN115126148A (en) Bolt connection precast concrete composite sandwich thermal insulation wallboard and preparation method thereof
CN107778025A (en) A kind of preparation method of high shock resistance cement polyphenyl formwork concrete wall
CN208202327U (en) A kind of double linked network protective layer insulation construction integrated wallboards
CN100365230C (en) Fiber reinforcement battened composite porous light partition plate and production process thereof
CN202000540U (en) Thermal insulation building block
CN205875449U (en) Outer insulation construction integration panel of building outer wall
CN209293242U (en) A kind of compound internal partition wall of precast light
CN208858025U (en) A kind of precast floor slab and precast floor slab mold
CN217811906U (en) Bolt connection precast concrete composite sandwich heat preservation wallboard
CN208202217U (en) A kind of double sandwich thermal insulated modules of linked network protective layer
CN207296087U (en) A kind of Prefabricated outer wall non-load bearing wall standard component
CN108558315A (en) Novel precast construction load bearing heat preserving, sound isolating decorative wall and steel fiber reinforced concrete
CN206477479U (en) A kind of compound heat preservation die plate wall body structure
CN102383501B (en) Embedded type aerated concrete composite outer wall heat insulation board
CN201258553Y (en) Composite thermal insulation building block forming male pin connection by casting
CN210917815U (en) Low-energy-consumption assembled heat-insulation wallboard

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: An integrated wall panel with double mesh protective layer insulation structure

Effective date of registration: 20221227

Granted publication date: 20181207

Pledgee: Bank of Baoding Limited by Share Ltd. Xushui branch

Pledgor: HEBEI ZHIBO INSULATION MATERIAL MANUFACTURING Co.,Ltd.

Registration number: Y2022980029210

PE01 Entry into force of the registration of the contract for pledge of patent right