CN208201667U - Pier stud high-altitude operation platform and high-altitude construction system - Google Patents
Pier stud high-altitude operation platform and high-altitude construction system Download PDFInfo
- Publication number
- CN208201667U CN208201667U CN201721226873.XU CN201721226873U CN208201667U CN 208201667 U CN208201667 U CN 208201667U CN 201721226873 U CN201721226873 U CN 201721226873U CN 208201667 U CN208201667 U CN 208201667U
- Authority
- CN
- China
- Prior art keywords
- pier stud
- workbench
- column
- fence
- altitude
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Pier stud high-altitude provided by the utility model operation platform and high-altitude construction system are related to high-altitude construction safety technical field, which includes: workbench, high fence and low fence;The workbench is sheathed on outside pier stud, and the high fence is set to the outside of the workbench, and the low fence is set to the inside of the workbench;Correspond to the low fence on the workbench and be provided with column, the workbench is fixed on the pier stud by column.Workbench is set on pier stud by column in the operation platform of pier stud high-altitude provided by the utility model, it is easy to use, the high fence can guarantee the safety of personnel, entire platform can guarantee safety, save the cost for repeating to build, can reuse, with high security with it is at low cost the advantages that.
Description
Technical field
The utility model relates to high-altitude construction safety technical fields, more particularly, to a kind of pier stud high-altitude operation platform and height
Empty construction system.
Background technique
For a long time, in the construction of high-speed rail, expressway, always all without good safety protection facility, especially
Outstanding to be, in the construction of high-level bridge pier column, greatly all in reliable safety devices are lacked, having part is also with simple and crude
It is nonstandard, or by construction team with reinforcing bar weld all around column shelves once, the shelves that enclose construct, i.e., it is dangerous reliable, and expense of taking a lot of work
When, and be once finished and cut off, next time welds again, wastes a lot of manpower and material resources, and simultaneously unsightly, be not durable, security risk
More, Lessons are more.
The general state of the art is: after the template standing of pier stud comes, just welding several angle steel supports on the top of template
Once, several blocks of plates are then taken.It is once just gathered together with reinforcing bar weld all around on periphery.Safe altitude is inadequate, and the welding is not firm, security risk
Very much, the accident of falling at high altitude often occurs.
In construction site throughout the country, since these are lack of standardization, actually and unsafe simply the reason of building,
Caused by all kinds of falling from high altitude death by accident of hurting sb.'s feelings it is commonplace.
Status makes people worried: since the background technique of this respect is very poor, the technical of science is not sayed, serious non-compliance
National security specification, is substantially scrub, disposably, seriously lacks safety reliability and science, generally deposits
In accident potential, therefore status is badly in need of solving, and technology is suddenly to be modified.
It is of the existing technology the disadvantage is that: 1, by technical specification design, production, installation and use.2, it to weigh every time
It builds, cannot repeatedly utilize again.Material and artificial all in waste repeatedly.3, build process is dangerous, and construction efficiency is very low.4,
Structural instability, it is unreliable to weld, and is unable to undergo the dependence and collision of construction personnel, easily collapses and fall apart, and junk is caused to hurt sb.'s feelings or high
Empty landing accident.
In conclusion existing constructing device needs to repeat to build, cannot reuse and the problem of structural instability.
Utility model content
One of the utility model is designed to provide a kind of pier stud high-altitude operation platform, to solve existing constructing device
It needs to repeat to build, cannot reuse and the technical issues of structural instability.
Another of the utility model is designed to provide a kind of high-altitude construction system, the pier stud high-altitude including above-mentioned offer
Operation platform.
In order to solve the above technical problems, the utility model uses following technical scheme;The utility model first aspect mentions
The pier stud high-altitude operation platform of confession, wherein include: workbench, high fence and low fence;
The workbench is sheathed on outside pier stud, and the high fence is set to the outside of the workbench, described low to enclose
Column is set to the inside of the workbench;
Correspond to the low fence on the workbench and be provided with column, the workbench is fixed on institute by column
It states on pier stud.
Workbench is set on pier stud by column in the operation platform of pier stud high-altitude provided by the utility model, user
Just, the high fence can guarantee the safety of personnel, entire platform can guarantee safety, save the cost for repeating to build, can
Reuse, with high security with it is at low cost the advantages that.
In any of the above-described technical solution, further, it is provided with suspender on the column top, the column passes through
Suspender is set to outside the pier stud.
In any of the above-described technical solution, further, on the suspender corresponds to the pier stud and is provided with adjustable plate,
Adjusting bolt is provided on the adjustable plate, described one end for adjusting bolt is arranged in the inside of the adjustable plate Yu the pier stud
Connection.
In order to protect the steel form of pier stud, prevent adjusting bolt from causing to scratch to its inner surface, in any of the above-described technical side
In case, further, cushion block is provided between the adjusting bolt and the pier stud.
In any of the above-described technical solution, further, it is provided on the column for fixing the column bottom
Lead screw on the pier stud, one end of the lead screw are arranged in the column and connect with the outside of the pier stud.
In order to protect the steel form of pier stud, prevent adjusting bolt from causing to scratch to its outer surface, in any of the above-described technical side
In case, further, cushion block is provided between the lead screw and the pier stud.
It further include the exit passageway being connect with the high fence further in any of the above-described technical solution.
In any of the above-described technical solution, further, the exit passageway includes by platform and guardrail, the guardrail
It is rotatablely arranged on the platform.
In any of the above-described technical solution, further, manhole is offered on the high fence or workbench, is also wrapped
Include the rotation door for corresponding to the upper manhole setting.
The utility model additionally provides a kind of high-altitude construction system, wherein flat including pier stud high-altitude as described above construction
Platform.
By adopting the above technical scheme, the utility model has the following beneficial effects:
High fence described in the operation platform of pier stud high-altitude provided by the utility model and low fence are rotatably arranged in respectively
On the workbench, open fence construct, do not need using when fold pack up.It can guarantee safety, save repetition
The cost built can be reused, with high security with it is at low cost the advantages that.
Further, it is provided with suspender on the column top, the column is set to the pier stud by suspender
Outside.
Further, the pier stud is corresponded on the suspender and is provided with adjustable plate, tune is provided on the adjustable plate
Bolt is saved, described one end for adjusting bolt is arranged in the adjustable plate and connect with the inside of the pier stud.
Further, the lead screw for being fixed on the column bottom on the pier stud, institute are provided on the column
The one end for stating lead screw is arranged in the column and connect with the outside of the pier stud.
The additional aspect and advantage of the utility model will become obviously in following description section, or practical new by this
The practice of type is recognized.
Detailed description of the invention
It below will be right in order to illustrate more clearly of specific embodiment of the present invention or technical solution in the prior art
Specific embodiment or attached drawing needed to be used in the description of the prior art are briefly described, it should be apparent that, it is described below
In attached drawing be that some embodiments of the utility model are not paying creativeness for those of ordinary skill in the art
Under the premise of labour, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is the top view for the pier stud high-altitude operation platform that the utility model embodiment one provides;
Fig. 2 is the top view that the pier stud high-altitude operation platform that the utility model embodiment one provides removes pedal;
Fig. 3 is the structural schematic diagram of pier stud high-altitude operation platform and pier stud that the utility model embodiment one provides;
Fig. 4 is the structural schematic diagram for the pier stud high-altitude operation platform that the utility model embodiment one provides;Fig. 5 is that this is practical
The structural schematic diagram of exit passageway in the pier stud high-altitude operation platform that new embodiment one provides.
Appended drawing reference:
1: pier stud;2: pedal;3: high fence;
4: low fence;5: steel form;6: dodge gate;
7: column;8: suspender;9: adjustable plate;
10: lead screw;11: cushion block;12: adjusting bolt;
13: exit passageway;14: workbench.
Specific embodiment
The technical solution of the utility model is clearly and completely described below in conjunction with attached drawing, it is clear that described
Embodiment is the utility model a part of the embodiment, instead of all the embodiments.Based on the embodiments of the present invention, originally
Field those of ordinary skill every other embodiment obtained without making creative work belongs to practical
Novel protected range.It should be noted that in the absence of conflict, the feature in embodiments herein and embodiment can
To be combined with each other.
It is in the description of the present invention, it should be noted that term " center ", "upper", "lower", "left", "right", " perpendicular
Directly ", the orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings, and is only
For ease of description the utility model and simplify description, rather than the device or element of indication or suggestion meaning must have it is specific
Orientation, be constructed and operated in a specific orientation, therefore should not be understood as limiting the present invention.In addition, term " the
One ", " second ", " third " are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " is pacified
Dress ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integrally
Connection;It can be mechanical connection, be also possible to be electrically connected;Can be directly connected, can also indirectly connected through an intermediary,
It can be the connection inside two elements.For the ordinary skill in the art, above-mentioned art can be understood with concrete condition
The concrete meaning of language in the present invention.
Explanation is further explained to the utility model below with reference to specific embodiment.
As shown in Figures 1 to 5, the pier stud high-altitude operation platform that the embodiment of the utility model first aspect provides, comprising:
Workbench 14, high fence 3 and low fence 4;
The workbench 14 is sheathed on outside pier stud 1, and the high fence 3 is set to the outside of the workbench 14, institute
State the inside that low fence 4 is set to the workbench 14;
Correspond to the low fence 4 on the workbench 14 and be provided with column 7, the workbench 14 passes through column 7
It is fixed on the pier stud 1.
Workbench 14 is set on pier stud 1 by column 7 in 1 high-altitude operation platform of pier stud provided by the utility model,
Easy to use, the high fence 3 can guarantee the safety of personnel, entire platform can guarantee safety, save repeat to build at
This, can reuse, with high security with it is at low cost the advantages that.
Workbench 14 can be round or rectangular, rectangle etc., and concrete shape size is depending on the section of pier stud 1.Periphery
The safe altitude that column is 1.2 meters, inside fence is 200 millimeters of skirting board height for convenience of constructing operation.Pier stud 1 is applied in centre
Work, surrounding are surrounded with 80 centimetres of width of workbench 14, are high fences 3 on the outside of platform, fall to prevent personnel, platform it is interior
Side is low fence 4, is made a misstep to prevent personnel.Pedal 2 is equipped on workbench 14, workbench 14 is steel material, is set on pedal 2
Decorative pattern is equipped with anti-skidding.Construction personnel's activity is steady and sure, spacious, firm, safe on security platform.
Column 7 is close to the low fence 4 of inside, column 7 be it is multiple, multiple columns 7 are uniformly distributed along the circumferential direction of workbench 14, hang
Pendant 8 is arranged on symmetrical 4 columns 7 in inside, (each respectively setting one of column 7).Its primary structure is hanging down in column 7
Histogram makes its cross-arm in the top Flange Plane of 7 upper steel template 5 of column, makes whole workbench to one component of each weldering
14 are firmly suspended on the top of pier stud 1.
Whole device can be easily installed with dimidiation or muti-piece, can be attached between each other with fastener.
In any of the above-described technical solution, further, suspender 8, the column 7 are provided on 7 top of column
It is set to outside the pier stud 1 by suspender 8.
In any of the above-described technical solution, further, on the suspender 8 corresponds to the pier stud 1 and be provided with adjusting
Plate 9 is provided on the adjustable plate 9 and adjusts bolt 12, described one end for adjusting bolt 12 be arranged in the adjustable plate 9 with it is described
The inside of pier stud 1 connects.
By adjusting bolt 12 is adjusted for will be fixed on outside the pier stud 1 at the top of the column 7, it may be set to be
As long as his structure, which is able to achieve, to be fixed on the scheme outside the pier stud 1 at the top of column 7, as adjustable plate 9 can be along suspender 8
It is mobile, column 7 is fixed on the steel form 5 of pier stud 1.To adjust the opposite position of 5 inner wall of steel form Yu overall work platform 14
It sets, and reduces the opposite shaking of the platform, increase stability.
Suspender 8 is vertically installed in the top of pier stud 1, and the axis of adjustable plate 9 is parallel with the axis of column 7.
In order to protect the steel form 5 of pier stud 1, prevent adjusting bolt 12 from causing to scratch to its inner surface, in any of the above-described skill
In art scheme, further, cushion block 11 is provided between the adjusting bolt 12 and the pier stud 1.The material of cushion block 11 is wood
Material or other materials can prevent from causing to damage to 5 inner surface of steel form.
In order to enable the entire fixation of workbench 14 is more stable, in any of the above-described technical solution, further, institute
State the lead screw 10 being provided on column 7 for being fixed on 7 bottom of column on the pier stud 1, one end of the lead screw 10
The column 7 is arranged in connect with the outside of the pier stud 1.Column 7 can also can be consolidated using bolt 12 or other is adjusted
It is scheduled on the structure in 1 outside of pier stud.
In order to protect the steel form 5 of pier stud 1, prevent adjusting bolt 12 from causing to scratch to its outer surface, in any of the above-described skill
In art scheme, further, cushion block 11 is provided between the lead screw 10 and the pier stud 1.The material of cushion block 11 is wooden.
At the middle part or bottom of low 4 symmetrically arranged 4 columns 7 of fence, it is respectively provided with and holds out against lead screw 10, it is whole to make
Body platform and 1 steel form 5 of pier stud further hold out against and (to add wooden unit to fill gap at lead screw 10), make safe construction platform more
It is reliable and stable, and the table top that can adjust the workbench 14 is in horizontality, in order to which personnel construct and walk.
It further include the exit passageway 13 being connect with the high fence 3 further in any of the above-described technical solution.When
When workbench 14 has multiple, each workbench 14 is sheathed on respectively on pier stud 1, is symmetrical arranged on adjacent workbench 14
There is dodge gate 6, is connected with exit passageway 13 between adjacent dodge gate 6.
In the outside, certain antimere of high fence 3 opens up two dodge gates 6, to facilitate bigeminy, three, multi-joint pier stud
1, when more pier studs 1 under same bent cap are constructed simultaneously, a few pier bridging connection with the personnel for facilitating while constructing walk about in the air with
The exchange of goods and materials equipment.
In any of the above-described technical solution, further, the exit passageway 13 includes by platform and guardrail, the shield
Column is rotatablely arranged on the platform.
In the bigeminy, three, the construction of multi-joint pier stud 1, each pier stud 1 is fitted with the safe fence, two
The exit passageway 13 of mutual connection is provided between connection, three.The platform two sides of the exit passageway 13 are equipped with guardrail, exit passageway
13 both ends are connected with 1 fence of pier stud, and guardrails of both sides is movable or folds, and are rotatablely arranged at the platform by shaft
On.The fixed block for nonfloating rail can be set between guardrail and platform.
The both ends adjustable in length of exit passageway 13, guardrail and platform are settable multiple, and the platform of elongated portion can be rolled over
It is folded to be set to primary platform bottom, or the same elongated channel is provided on the inside of exit passageway 13, the guardrail of elongated channel and
Platform can be moved along the guardrail in outside, by modes such as guide rails, to increase the length of guardrail.To adapt to different engineering designs
Size needs.
The exit passageway 13 ensures construction safety, it is ensured that the mutual circulation between aerial construction personnel, technology, object
Money, the exchange of work equipment greatly facilitate construction, further improve work efficiency.
In any of the above-described technical solution, further, manhole is offered on the high fence 3 or workbench 14,
It further include the rotation door corresponding to the upper manhole setting.High 3 a part of fence in the outside is provided with rotation door or sets
It sets and opens up upper manhole on the floor of workbench, and set rotation door, two schemes are depending on the circumstances, to facilitate construction personnel
Disengaging.
The utility model additionally provides a kind of high-altitude construction system, wherein flat including pier stud high-altitude as described above construction
Platform.
A kind of high-altitude construction method, wherein apply 1 high-altitude operation platform of pier stud as described above, specific steps are as follows:
S1, workbench 14 is set on pier stud 1 by column 7, low fence 4 is arranged close to pier stud 1, and high fence 3 is remote
It is arranged from pier stud 1;
S2, the top of column 7 is fixed on pier stud 1 using adjustable plate 9, and is consolidated the bottom of column 7 using lead screw 10
It is scheduled on pier stud 1, fixes entire column 7;
Exit passageway 13 can be set between S3, multiple workbenches 14.
Column 7 provided by the utility model is set to the top of pier stud 1 by top suspender 8, and suspender 8 passes through adjusting
Position of the bolt 12 for 7 top and pier stud 1 of vertical columns, the position of vertical columns 7 bottom and pier stud 1 is used for by lead screw 10
It sets, walks about on workbench 14 convenient for personnel.It is connected between multiple workbenches 14 with exit passageway 13.The utility model
It is for 1 class of pier stud, 1 high-altitude operation platform purpose of pier stud provided by the utility model are as follows: to solve the personnel in site operation
Safety problem;Make the civilized construction in building site, safe construction rises to a new level;In addition to guaranteeing safe construction, also for
Construction cost has been saved in building site, is avoided the waste of manpower, financial resources caused by repetition is built, material resources, is in addition also ad save the time,
It is advanced by the duration, embodies and carries out production strictly in line with rules and regulations for building site, is kept the safety in production.
1 high-altitude operation platform of pier stud provided by the utility model solves the various difficult safety in the presence of site construction
Technical problem, and can be repeated several times use, waste of manpower, material resources is not repeated, has substantially saved construction cost, it is ensured that applies
Work is safe and efficient, quick.
In conclusion high fence described in the operation platform of pier stud high-altitude provided by the utility model and low fence rotate respectively
Ground is set on the workbench, open fence construct, do not need using when fold pack up.Can guarantee safety,
Save repeat build cost, can reuse, with high security with it is at low cost the advantages that.
Finally, it should be noted that the above various embodiments is only to illustrate the technical solution of the utility model, rather than it is limited
System;Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should
Understand: it is still possible to modify the technical solutions described in the foregoing embodiments, or to some or all of
Technical characteristic is equivalently replaced;And these are modified or replaceed, it does not separate the essence of the corresponding technical solution, and this is practical new
The range of each embodiment technical solution of type.In addition, it will be appreciated by those of skill in the art that although some implementations described herein
Example includes certain features included in other embodiments rather than other feature, but the group of the feature of different embodiments is desirable
Taste within the scope of the utility model and form different embodiments.For example, in claims above, institute
Claimed embodiment it is one of any can in any combination mode come using.
Claims (9)
1. a kind of pier stud high-altitude operation platform characterized by comprising workbench, high fence and low fence;
The workbench is sheathed on outside pier stud, and the high fence is set to the outside of the workbench, and the low fence is set
It is placed in the inside of the workbench;
Correspond to the low fence on the workbench and be provided with column, the workbench is fixed on the pier by column
On column;It is provided with suspender at the top of the column, the column is set to outside the pier stud by suspender.
2. pier stud high-altitude according to claim 1 operation platform, which is characterized in that correspond to the pier on the suspender
Column is provided with adjustable plate, and adjusting bolt is provided on the adjustable plate, and described one end for adjusting bolt is arranged in the adjustable plate
It is connect with the inside of the pier stud.
3. pier stud high-altitude according to claim 2 operation platform, which is characterized in that the adjusting bolt and the pier stud it
Between be provided with cushion block.
4. pier stud high-altitude according to claim 2 operation platform, which is characterized in that be provided on the column for by institute
The lead screw that column bottom is fixed on the pier stud is stated, one end of the lead screw is arranged in the outside of the column Yu the pier stud
Connection.
5. pier stud high-altitude according to claim 4 operation platform, which is characterized in that set between the lead screw and the pier stud
It is equipped with cushion block.
6. pier stud high-altitude according to claim 1 operation platform, which is characterized in that further include being connect with the high fence
Exit passageway.
7. pier stud high-altitude according to claim 6 operation platform, which is characterized in that the exit passageway includes passing through platform
And guardrail, the guardrail are rotatablely arranged on the platform.
8. pier stud high-altitude according to claim 1 operation platform, which is characterized in that opened on the high fence or workbench
It further include the rotation door corresponding to the upper manhole setting equipped with upper manhole.
9. a kind of high-altitude construction system, which is characterized in that including the pier stud high-altitude construction as described in claim 1-8 any one
Platform.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721226873.XU CN208201667U (en) | 2017-09-22 | 2017-09-22 | Pier stud high-altitude operation platform and high-altitude construction system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721226873.XU CN208201667U (en) | 2017-09-22 | 2017-09-22 | Pier stud high-altitude operation platform and high-altitude construction system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208201667U true CN208201667U (en) | 2018-12-07 |
Family
ID=64490017
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721226873.XU Expired - Fee Related CN208201667U (en) | 2017-09-22 | 2017-09-22 | Pier stud high-altitude operation platform and high-altitude construction system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208201667U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107642048A (en) * | 2017-09-22 | 2018-01-30 | 宁夏桥多美路桥钢模板科技有限公司 | Pier stud high-altitude construction platform and high-altitude construction method |
-
2017
- 2017-09-22 CN CN201721226873.XU patent/CN208201667U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107642048A (en) * | 2017-09-22 | 2018-01-30 | 宁夏桥多美路桥钢模板科技有限公司 | Pier stud high-altitude construction platform and high-altitude construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205025072U (en) | A construction platform device for high altitude construction | |
CN202054588U (en) | Hydraulic lift-type platform for overhaul and maintenance of GW-6 disconnecting links | |
CN104577876B (en) | Plug-in hanging basket for live working of helicopter | |
CN208201667U (en) | Pier stud high-altitude operation platform and high-altitude construction system | |
CN205206282U (en) | Concertina type work platform | |
CN205822747U (en) | Architectural engineering scaffold | |
US9243425B2 (en) | Safety barrier system | |
CN204752026U (en) | Tower crane escape way | |
CN207277192U (en) | Portable overhanging lifting platform for crash barrier template construction | |
CN206048160U (en) | A kind of height-adjustable split heads | |
CN107642048A (en) | Pier stud high-altitude construction platform and high-altitude construction method | |
CN205369866U (en) | Assembled steel ladder | |
CN205474792U (en) | Movable type cable ditch escape way bridge | |
CN208055875U (en) | Foldable high-altitude operation platform and high-altitude construction system | |
CN208650506U (en) | A kind of slip-framed reverse mould constructing device | |
CN207131172U (en) | Windproof fence rack | |
CN202913679U (en) | Double-function construction operation protection derrick in elevator shaft way | |
CN208517819U (en) | Pier stud high-altitude operation platform and high-altitude construction system | |
CN212052563U (en) | Scaffold for water conservancy construction | |
CN107587708A (en) | Foldable high-altitude construction platform and high-altitude construction method | |
CN206928697U (en) | A kind of safe ladder cage of new bananas type for building trade | |
CN208668277U (en) | Foldable high-altitude operation platform and high-altitude construction system | |
CN207863501U (en) | Heavy icing area reinforcement type shaft tower climbs cross-arm securing plate falling proof device | |
CN105836683A (en) | Aerial pile extension lifting basket of steel pipe piles | |
CN207686256U (en) | A kind of scaffold of the safety and stability municipal administration with lifting platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181207 Termination date: 20210922 |