Prior art keywords
fence
altitude construction
workbench
foldable
low
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710867761.0A
Other languages
Chinese (zh)
Other versions
CN107587708B (en
Inventor
祁文源
柳志宏
柳涓
钟旭新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changji Urban Construction Municipal Engineering Construction Co ltd
Original Assignee
Ningxia Bridge Luqiao Steel Template Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningxia Bridge Luqiao Steel Template Technology Co Ltd filed Critical Ningxia Bridge Luqiao Steel Template Technology Co Ltd
Priority to CN201710867761.0A priority Critical patent/CN107587708B/en
Publication of CN107587708A publication Critical patent/CN107587708A/en
Application granted granted Critical
Publication of CN107587708B publication Critical patent/CN107587708B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

Foldable high-altitude construction platform and high-altitude construction method provided by the invention, are related to high-altitude construction safety technical field, and the foldable high-altitude construction platform includes workbench, high fence and low fence;Workbench is arranged on joist, and the high fence and low fence are rotatably arranged on the workbench respectively.High fence and low fence are rotatably arranged on the workbench respectively described in foldable high-altitude construction platform provided by the invention, are opened fence and are constructed, fold and pack up when that need not use.Safety can be ensured, the cost for repeating to build is saved, can reuse, there are safe and low cost and other advantages.

Description

Foldable high-altitude construction platform and high-altitude construction method
Technical field
The present invention relates to high-altitude construction safety technical field, more particularly, to a kind of foldable high-altitude construction platform and high-altitude Construction method.
Background technology
For a long time, in the construction of high ferro, expressway, all there is no good safety protection facility always, especially Prominent, high-level bent cap, in the construction of crossbeam, greatly all in lacking security protection, or the building site civilian worker that leaves arbitrarily takes If temporary facility, and its handrail, railing and workbench are all very simple and crude, are constantly in and lack minimum safety and reliability The present situation to make people worried.
The in general state of the art is:Blocked with shelf pipe, or a guardrail is arbitrarily welded with reinforcing bar, impaled with the screen cloth of green Come just.This beam, which has finished, just to be sliced off, and next beam is built again again, and random very big, security reliability is worse, and And it is time-consuming take material, efficiency is very low, and can not repeatedly utilize, therefore also results in the serious waste of human, financial, and material resources.
In job site throughout the country, because these are lack of standardization, actually and the reason for unsafe guardrail fence, Caused by all kinds of falling from high altitude death by accident of hurting sb.'s feelings it is of common occurrence.
Present situation makes people worried:Because the background technology of this respect is very poor, technical without science is sayed, serious non-compliance National security specification, is substantially scrub, disposably, seriously lacks security reliability and science, generally deposits In accident potential, therefore present situation is badly in need of solving, and technology is suddenly to be modified.
Prior art has the drawback that:1. to repeat to set up every time, it is impossible to reuse, waste of material is serious.2. Cost of labor is very high, and repetition is built and efficiency of construction is very low.3. structural instability, insecure, accident and hidden is welded and connected Suffer from a lot.4. construction site seems disorderly and unsystematic, untidy specification.It is only an appearance 5. some safeguard structures are excessively thin Engineering, be unable to undergo workmen's collision unintentionally, by and long-term reuse, it is easy to collapse, produce dangerous or produce Deform and scrap.
The content of the invention
It is every to solve existing constructing device it is an object of the present invention to provide a kind of foldable high-altitude construction platform It is secondary to repeat to set up, it is impossible to reuse, and the technical problem that structure is thin.
It is another object of the present invention to provide a kind of high-altitude construction method, is applied using the foldable high-altitude of above-mentioned offer Work platform.
In order to solve the above technical problems, present invention employs following technical scheme;What first aspect present invention provided rolls over Folded high-altitude construction platform, wherein, including workbench, high fence and low fence;Workbench is arranged on joist, and the height encloses Column and low fence are rotatably arranged on the workbench respectively.
In any of the above-described technical scheme, further, the high fence and low fence can be rotated by rotating shaft respectively Ground is arranged on the workbench.
In any of the above-described technical scheme, further, in addition to be arranged at the high fence and the workbench it Between wedge, be also equipped with the wedge between the workbench and the low fence.
In any of the above-described technical scheme, further, in addition to for fixing the hook plate of the workbench and joist.
In any of the above-described technical scheme, further, described hook plate one end is fixed on the workbench, the other end It is provided with the hook groove matched with the joist.
In any of the above-described technical scheme, further, the through hole matched with the wedge is provided with the hook plate.
In any of the above-described technical scheme, further, population is offered on the high fence.
In any of the above-described technical scheme, further, the upper population is provided with door-plate on the high fence, The door-plate can be rotatably arranged on the high fence.
Present invention also offers a kind of high-altitude construction method, wherein, using foldable high-altitude construction platform as described above, Concretely comprise the following steps:
S1, workbench being arranged on joist, low fence is set close to building girder, and high fence is set away from building girder, Low fence and high fence are finally fixed using wedge;
S2, it is provided with baffle plate between the high fence and the low fence.
In any of the above-described technical scheme, further, in step S1 use and hook plate by the workbench and the support Beam connects.
Using above-mentioned technical proposal, the present invention has the advantages that:
High fence and low fence are rotatably arranged in institute respectively described in foldable high-altitude construction platform provided by the invention State on workbench, open fence and constructed, fold and pack up when that need not use.It can ensure that safety, saving repeat to take It the cost built, can reuse, there are safe and low cost and other advantages.
Further, in addition to the wedge that is arranged between the high fence and the workbench, the workbench The wedge is also equipped between the low fence.
Further, in addition to for fixing the hook plate of the workbench and joist.
The additional aspect and advantage of the present invention will become obvious in following description section, or the practice by the present invention Recognize.
Brief description of the drawings
Below will be to specific in order to illustrate more clearly of the specific embodiment of the invention or technical scheme of the prior art The required accompanying drawing used is briefly described in embodiment or description of the prior art, it should be apparent that, in describing below Accompanying drawing is some embodiments of the present invention, for those of ordinary skill in the art, before creative work is not paid Put, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is the positive structure schematic for the foldable high-altitude construction platform that the embodiment of the present invention one provides;
Fig. 2 is the top view for the foldable high-altitude construction platform that the embodiment of the present invention one provides;
Fig. 3 is the side view for the foldable high-altitude construction platform that the embodiment of the present invention one provides;
Fig. 4 is the structural representation for the foldable high-altitude construction platform folded state that the embodiment of the present invention one provides;
Fig. 5 is the structural representation for the bridge Coping Construction that the embodiment of the present invention one provides;
Fig. 6 is the arrangement signal of foldable high-altitude construction platform in the bridge Coping Construction that the embodiment of the present invention one provides Figure.
Reference:
100:Standard knot;102:Workbench;103:High fence;
104:Low fence;105:Wedge;106:Hook plate;
107:Rotating shaft;200:Adjustment section;201:The band special section of door;
300:Joist;301:Building girder;302:Baffle plate.
Embodiment
Technical scheme is clearly and completely described below in conjunction with accompanying drawing, it is clear that described implementation Example is part of the embodiment of the present invention, rather than whole embodiments.Based on the embodiment in the present invention, ordinary skill The every other embodiment that personnel are obtained under the premise of creative work is not made, belongs to the scope of protection of the invention. It should be noted that in the case where not conflicting, the feature in embodiments herein and embodiment can be mutually combined.
In the description of the invention, it is necessary to explanation, term " " center ", " on ", " under ", "left", "right", " vertical ", The orientation or position relationship of the instruction such as " level ", " interior ", " outer " be based on orientation shown in the drawings or position relationship, merely to Be easy to the description present invention and simplify description, rather than instruction or imply signified device or element must have specific orientation, With specific azimuth configuration and operation, therefore it is not considered as limiting the invention.In addition, term " first ", " second ", " the 3rd " is only used for describing purpose, and it is not intended that instruction or hint relative importance.
In the description of the invention, it is necessary to illustrate, unless otherwise clearly defined and limited, term " installation ", " phase Even ", " connection " should be interpreted broadly, for example, it may be being fixedly connected or being detachably connected, or be integrally connected;Can To be mechanical connection or electrical connection;Can be joined directly together, can also be indirectly connected by intermediary, Ke Yishi The connection of two element internals.For the ordinary skill in the art, with concrete condition above-mentioned term can be understood at this Concrete meaning in invention.
With reference to specific embodiment the present invention will be further explained explanation.
As shown in Figures 1 to 4, the foldable high-altitude construction platform that the embodiment of first aspect present invention provides, including work Make platform 102, high fence 103 and low fence 104;Workbench 102 is arranged on joist 300, the high fence 103 and low is enclosed Column 104 is rotatably arranged on the workbench 102 respectively.
In any of the above-described technical scheme, further, the high fence 103 and low fence 104 pass through rotating shaft 107 respectively It can be rotatably arranged on the workbench 102.
As shown in fig. 6, size can be designed according to the size of building girder 301 in foldable high-altitude construction platform, can So that various sizes of foldable high-altitude construction platform is laid out into combination according to the size of building girder 301.Foldable high-altitude construction is flat Platform includes standard knot 100 and adjustment section 200, and the length×width×height of standard knot 100 is 2m × 1m × 1.2m.Adjustment section 200 size can be designed according to demand, and multiple standard knots 100 are laid out along the surrounding of building girder 301 and start to be laid out, middle Space is using adjustment section 200.
The both sides of workbench 102 are high fence 103 and low fence 104, are connected as one with workbench 102.High fence 103 in outside, is highly 1200mm, low fence 104 is 200mm in inside height, and the low side of fence 104 is need of work, no Influence work.The safe altitude of the high side of fence 103 to ensure personal security, and its intensity, rigidity can resist completely personnel, The dependence or collision of object, will not collapse and damage, to prevent and avoid the generation of the accident of falling at high altitude.
Using rotating shaft 107 low skirt column can be made first to be folded on workbench 102, under then flash fence is folded again Come, form one with workbench 102, so as to reduce volume, in order to the lifting of foldable high-altitude construction platform, transport, Storage and keeping.Standard knot 100 after folding is highly only that (the wide x of the long x of the specification of standard knot 100 after folding are high by 200mm For:2000mm×1263mm×200mm).5 layers of only 1 meter of height are such as piled up when storage and transhipment, by that analogy.Greatly facilitate Hoisting transportation, storage and the keeping in building site.
In any of the above-described technical scheme, further, in addition to the high fence 103 and the workbench are arranged at Wedge 105 between 102, the wedge 105 is also equipped between the workbench 102 and the low fence 104.Wedge is set Plate 105 is easy to high fence 103 and low fence 104 to be perpendicularly fixed on workbench 102.
Wedge is locked by the high fence 103 of both sides and low fence 104, make this state high fence 103 and low fence 104 not It is foldable, wedge just foldable fence is only beaten when needing and removing.This ensure that construction safety.
In any of the above-described technical scheme, further, in addition to for fixing the workbench 102 and joist 300 Hook plate 106.Standard knot 100 is connected with the joist 300 of bottom using plate 106 is hooked.
In any of the above-described technical scheme, further, described hook plate 106 one end is fixed on the workbench 102, The other end is provided with the hook groove matched with the joist 300.
In any of the above-described technical scheme, further, it is provided with what is matched with the wedge 105 on the hook plate 106 Through hole.Gap insertion of the plate 106 from workbench is hooked, upper part carries the through hole matched with wedge 105, inserted for wedge, Lower part is connected by hooking groove with joist 300.
Standard knot 100 is connected with joist 300 using plate 106 is hooked, and is set on the hook plate 106 being arranged on workbench 102 There is through hole, wedge 105 is squeezed into by through hole in the through hole for hooking plate 106, for fixing fence.Foldable high-altitude construction platform can roll over Stacked design novel and unique, non-bolted joint, only with hook plate 106 plus wedge quickly connect, quick fixed and fast assembling-disassembling.
Pass in and out for the ease of people, in any of the above-described technical scheme, further, offered on the high fence 103 Population.The standard knot for offering population is the special section 201 of band door.
In any of the above-described technical scheme, further, the upper population is provided with door on the high fence 103 Plate, the door-plate can be rotatably arranged on the high fence 103.
In any of the above-described technical scheme, further, the high fence 103 and low fence 104 weld by multiple tubing Connect and form.
Workbench 102 is welded skeleton by light-duty tubing, and surface is that 3mm thickness checkered steel plate is with the weldering of following skeleton One.Workmen walks spacious firm, anti-skidding, safety, steady and sure nothing on the workbench that width is 1m and rocked relatively.
Present invention also offers a kind of high-altitude construction system, wherein, including foldable high-altitude construction platform as described above, Also include the baffle plate 302 being arranged between the high fence 103 and the low fence 104.
As shown in figure 5, being provided with multiple joists 300 on bent cap or crossbeam in building girder 301, foldable high-altitude is constructed Platform is arranged on joist 300.
Present invention also offers a kind of high-altitude construction method, wherein, using foldable high-altitude construction platform as described above, Concretely comprise the following steps:
S1, workbench 102 is arranged on joist 300, low fence 104 is set close to building girder 301, high fence 103 Set away from building girder 301, low fence 104 and high fence 103 are finally fixed using wedge 105;
S2, in order to ensure the safety of workmen, be provided with gear between the high fence 103 and the low fence 104 Plate 302.
Specifically it is installed as:When building site bent cap or construction of beam, on the anchor ear of pier stud, all made using two large-scale I-steel For bottom girder, some small shaped steel are laterally laid on two big bottom girder, small shaped steel is generally channel-section steel or I-steel, the interval of small shaped steel Generally 50cm-60cm, small shaped steel length are generally 6m.With this basis, the foldable high-altitude construction platform be just mounted in by On the platform of these small shaped steel layings.
The thickness of both sides steel form and the distance for width requirement of constructing separately is added to place standard knot according to bent cap or other crossbeams 100 should consider the length, width and height size requirement of construction beam with adjustment section 200, position, after arranging that particular location is proper on request, Caught on the joist 300 below hook plate and platform and wedging, wedge 105 are located at four angles of each standard knot 100.Due to The length, width and height size of every kind of construction concrete beam is not quite similar, it is therefore desirable to has adjustment section 200 to be made up, the standard knot 100 in outside Carry out fill up the gap provided with baffle plate 302.Installation is simple, reliable, rapid, improves efficiency of construction.It can also use according to demand The special section 201 of band door replaces a section or more standard section 100, is easy to the discrepancy of workmen.
In any of the above-described technical scheme, further, in step S1 using hook plate 106 by the workbench 102 with The joist 300 connects.
Foldable high-altitude construction platform provided by the invention solves the various safe skills of difficulty in the presence of site construction Art problem, and use is can be repeated several times, waste of manpower, material resources are not repeated, have significantly saved construction cost, it is ensured that construction It is safe efficient, quick.
Reasonable in design, firm welding, process, factorial praluction, materials ensure, can stand slight rush Hit, it is not easy to collapse, deform, can reuse for a long time.Especially connect the smart design of non-bolt.Bolt will not be produced to lose Lose, without supplementing new bolt every time.Even if make high fence with hooking plate 106 and catching on the following standard knot 100 of joist 300 and fix and reach 103 and low fence 104 it is fixed.As long as wedge is beaten during dismounting can remove standard knot 100, fence self-locking is also beaten simultaneously Open, you can fold transhipment.Whole installation, demolition process do not have to bolt, without spanner, only need one iron chains head can be completed, significantly Simplify work progress.
In summary, high fence 103 and low fence 104 are distinguished described in foldable high-altitude construction platform provided by the invention It is rotatably arranged on the workbench 102, opens fence and constructed, fold and pack up when that need not use.It can protect Card safety, save the cost for repeating to build, can reuse, there are safe and low cost and other advantages.
Finally it should be noted that:Various embodiments above is merely illustrative of the technical solution of the present invention, rather than its limitations;To the greatest extent The present invention is described in detail with reference to foregoing embodiments for pipe, it will be understood by those within the art that:Its according to The technical scheme described in foregoing embodiments can so be modified, either which part or all technical characteristic are entered Row equivalent substitution;And these modifications or replacement, the essence of appropriate technical solution is departed from various embodiments of the present invention technology The scope of scheme.In addition, it will be appreciated by those of skill in the art that although some embodiments described herein include other implementations Included some features rather than further feature in example, but the combination of the feature of different embodiments means in the present invention Within the scope of and form different embodiments.For example, in superincumbent claims, embodiment claimed It is one of any mode to use in any combination.

Claims (10)

1. a kind of foldable high-altitude construction platform, it is characterised in that including workbench, high fence and low fence;Workbench It is arranged on joist, the high fence and low fence are rotatably arranged on the workbench respectively.
2. foldable high-altitude construction platform according to claim 1, it is characterised in that the high fence and low fence difference It can be rotatably arranged on the workbench by rotating shaft.
3. foldable high-altitude construction platform according to claim 1, it is characterised in that also include being arranged at the high fence With the wedge between the workbench, the wedge is also equipped between the workbench and the low fence.
4. foldable high-altitude construction platform according to claim 3, it is characterised in that also include being used to fix the work The hook plate of platform and joist.
5. foldable high-altitude construction platform according to claim 4, it is characterised in that described hook plate one end is fixed on described On workbench, the other end is provided with the hook groove matched with the joist.
6. foldable high-altitude construction platform according to claim 4, it is characterised in that it is described hook plate on be provided with it is described The through hole of wedge matching.
7. foldable high-altitude construction platform according to claim 1, it is characterised in that offer people on the high fence Mouthful.
8. foldable high-altitude construction platform according to claim 7, it is characterised in that correspond on the high fence described Upper population is provided with door-plate, and the door-plate can be rotatably arranged on the high fence.
9. a kind of high-altitude construction method, it is characterised in that apply in foldable high-altitude of the application as described in claim 1-8 any one Work platform, is concretely comprised the following steps:
S1, workbench is arranged on joist, low fence is set close to building girder, and high fence is set away from building girder, finally Low fence and high fence are fixed using wedge;
S2, it is provided with baffle plate between the high fence and the low fence.
10. high-altitude construction method according to claim 9, it is characterised in that used in step S1 and hook plate by the work Platform is connected with the joist.
CN201710867761.0A 2017-09-22 2017-09-22 Foldable high-altitude construction platform and high-altitude construction method Active CN107587708B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710867761.0A CN107587708B (en) 2017-09-22 2017-09-22 Foldable high-altitude construction platform and high-altitude construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710867761.0A CN107587708B (en) 2017-09-22 2017-09-22 Foldable high-altitude construction platform and high-altitude construction method

Publications (2)

Publication Number Publication Date
CN107587708A true CN107587708A (en) 2018-01-16
CN107587708B CN107587708B (en) 2023-12-22

Family

ID=61048800

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710867761.0A Active CN107587708B (en) 2017-09-22 2017-09-22 Foldable high-altitude construction platform and high-altitude construction method

Country Status (1)

Country Link
CN (1) CN107587708B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589533A (en) * 2018-04-02 2018-09-28 广西路桥工程集团有限公司 A kind of application method of arch rib high-altitude folding type operational platform
CN112982960A (en) * 2021-05-14 2021-06-18 河南省第二建设集团有限公司 Interactive lifting formwork device and construction method

Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2675183A1 (en) * 1991-04-11 1992-10-16 Quillery Ste Nale Construction Guard rail support, in particular for a shuttering panel
EP1867806A1 (en) * 2006-06-14 2007-12-19 Eugenio Del Castillo Cabello Removable protection for intermediate stages of scaffolding
JP2009084966A (en) * 2007-10-03 2009-04-23 Shinwa Kk Guide for leading handrail
CN202627477U (en) * 2012-05-30 2012-12-26 苏州飞华铝制工业有限公司 Safety barrier for construction scaffold
CN103011033A (en) * 2012-12-21 2013-04-03 中联重科股份有限公司 High-altitude platform system and engineering machine comprising same
CN203475804U (en) * 2013-08-06 2014-03-12 湖南星邦重工有限公司 Foldable working platform
EP2712981A1 (en) * 2012-09-27 2014-04-02 Merle SAS Asymmetric railing for building site
JP2014101642A (en) * 2012-11-16 2014-06-05 Jfe Engineering Corp Installation method of safety balustrade for working
CN104295077A (en) * 2013-07-17 2015-01-21 五冶集团上海有限公司 Annular hanging platform for mounting stove shell of hot-blast stove, and mounting and dismounting method thereof
CN204676864U (en) * 2015-03-24 2015-09-30 河北盛卓建筑设备制造有限公司 A kind of attaching lifting discharging platform monolith platform underframe and detachable lateral guardrail
CN205046462U (en) * 2015-09-23 2016-02-24 中铁三局集团有限公司 Foldable pier shaft template joins externally platform
CN205189396U (en) * 2015-10-29 2016-04-27 卓然(靖江)设备制造有限公司 Industrial furnace is with standardized platform railing
CN105672636A (en) * 2015-11-19 2016-06-15 中建七局第二建筑有限公司 Elevating device for indoor construction
CN205637553U (en) * 2016-05-20 2016-10-12 国家电网公司 Insulating collapsible barrier of high strength platform
CN205646579U (en) * 2016-05-12 2016-10-12 国家电网公司 Large -scale spiral case in high altitude overhauls platform
CN106320183A (en) * 2016-09-28 2017-01-11 中交第航务工程局有限公司 Assembly type bent cap formwork system
CN106522567A (en) * 2016-12-14 2017-03-22 绍兴明煌建材科技有限公司 Assembled folded discharging platform and construction mode thereof
CN206418760U (en) * 2017-01-18 2017-08-18 吉林省水利水电勘测设计研究院地质勘察岩土工程院 River lake harnessing project prospecting sampling work platform
CN208055875U (en) * 2017-09-22 2018-11-06 宁夏路桥工程股份有限公司 Foldable high-altitude operation platform and high-altitude construction system
CN208668277U (en) * 2017-09-22 2019-03-29 宁夏桥多美路桥钢模板科技有限公司 Foldable high-altitude operation platform and high-altitude construction system
CH714893A2 (en) * 2018-04-12 2019-10-15 Quick Bauprodukte Ges Mit Beschraenkter Haftung Mobile scaffolding.

Patent Citations (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2675183A1 (en) * 1991-04-11 1992-10-16 Quillery Ste Nale Construction Guard rail support, in particular for a shuttering panel
EP1867806A1 (en) * 2006-06-14 2007-12-19 Eugenio Del Castillo Cabello Removable protection for intermediate stages of scaffolding
JP2009084966A (en) * 2007-10-03 2009-04-23 Shinwa Kk Guide for leading handrail
CN202627477U (en) * 2012-05-30 2012-12-26 苏州飞华铝制工业有限公司 Safety barrier for construction scaffold
EP2712981A1 (en) * 2012-09-27 2014-04-02 Merle SAS Asymmetric railing for building site
JP2014101642A (en) * 2012-11-16 2014-06-05 Jfe Engineering Corp Installation method of safety balustrade for working
CN103011033A (en) * 2012-12-21 2013-04-03 中联重科股份有限公司 High-altitude platform system and engineering machine comprising same
CN104295077A (en) * 2013-07-17 2015-01-21 五冶集团上海有限公司 Annular hanging platform for mounting stove shell of hot-blast stove, and mounting and dismounting method thereof
CN203475804U (en) * 2013-08-06 2014-03-12 湖南星邦重工有限公司 Foldable working platform
CN204676864U (en) * 2015-03-24 2015-09-30 河北盛卓建筑设备制造有限公司 A kind of attaching lifting discharging platform monolith platform underframe and detachable lateral guardrail
CN205046462U (en) * 2015-09-23 2016-02-24 中铁三局集团有限公司 Foldable pier shaft template joins externally platform
CN205189396U (en) * 2015-10-29 2016-04-27 卓然(靖江)设备制造有限公司 Industrial furnace is with standardized platform railing
CN105672636A (en) * 2015-11-19 2016-06-15 中建七局第二建筑有限公司 Elevating device for indoor construction
CN205646579U (en) * 2016-05-12 2016-10-12 国家电网公司 Large -scale spiral case in high altitude overhauls platform
CN205637553U (en) * 2016-05-20 2016-10-12 国家电网公司 Insulating collapsible barrier of high strength platform
CN106320183A (en) * 2016-09-28 2017-01-11 中交第航务工程局有限公司 Assembly type bent cap formwork system
CN106522567A (en) * 2016-12-14 2017-03-22 绍兴明煌建材科技有限公司 Assembled folded discharging platform and construction mode thereof
CN206418760U (en) * 2017-01-18 2017-08-18 吉林省水利水电勘测设计研究院地质勘察岩土工程院 River lake harnessing project prospecting sampling work platform
CN208055875U (en) * 2017-09-22 2018-11-06 宁夏路桥工程股份有限公司 Foldable high-altitude operation platform and high-altitude construction system
CN208668277U (en) * 2017-09-22 2019-03-29 宁夏桥多美路桥钢模板科技有限公司 Foldable high-altitude operation platform and high-altitude construction system
CH714893A2 (en) * 2018-04-12 2019-10-15 Quick Bauprodukte Ges Mit Beschraenkter Haftung Mobile scaffolding.

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589533A (en) * 2018-04-02 2018-09-28 广西路桥工程集团有限公司 A kind of application method of arch rib high-altitude folding type operational platform
CN108589533B (en) * 2018-04-02 2019-12-31 广西路桥工程集团有限公司 Application method of arch rib high-altitude folding type operation platform
CN112982960A (en) * 2021-05-14 2021-06-18 河南省第二建设集团有限公司 Interactive lifting formwork device and construction method

Also Published As

Publication number Publication date
CN107587708B (en) 2023-12-22

Similar Documents

Publication Publication Date Title
CN202227476U (en) High-altitude large-span overhung corridor-type reinforced concrete structure
CN105971274A (en) Cantilever support frame formwork system and construction method thereof
CN102535845A (en) Construction method of bearing frame of corridor structure
CN107524284A (en) A kind of regularization pylon protection system and installation method
CN205025072U (en) A construction platform device for high altitude construction
CN107165281A (en) A kind of high-altitude long-span overhung steel platform mould bases construction
CN108625485A (en) A kind of steel bar girder plate end connecting joint structure and construction method
CN107587708A (en) Foldable high-altitude construction platform and high-altitude construction method
CN103774838B (en) A kind of construction of lift well assembling safe operation platform and using method
CN103114754A (en) Alternative hoisting method for conjoined coal bunker top truss girder pre-placing
CN208668277U (en) Foldable high-altitude operation platform and high-altitude construction system
CN106760465A (en) A kind of steel-structure factory building installs auxiliary steel frame construction
CN109371846A (en) A kind of assembled Multifunction side is across cast-in-place support and its construction method
CN106400668B (en) A kind of combined Wavelike steel webplate bottom plate Shear connection key and construction method
CN105544402B (en) A kind of hanging gang form support frame and construction method for pier capping beam high
CN107587638A (en) Steel bar truss floor support plate and combined type floor support plate
CN211949510U (en) Annular cantilever platform construction supporting system
CN111648229A (en) Assembled hoop platform for bent cap construction and mounting method thereof
CN207685676U (en) Variable space operation platform of wet seam diaphragm of precast beam
CN204185146U (en) Construction of Steel Structure overhang crane between skyscraper two tall buildings
CN208055875U (en) Foldable high-altitude operation platform and high-altitude construction system
CN206513003U (en) A kind of steel-structure factory building installs auxiliary steel frame construction
CN206289988U (en) Overhanging unloading platform and material transfer device
CN212533700U (en) Pin-connected panel staple bolt platform of bent cap construction usefulness
CN206220547U (en) A kind of operating platform for steel structure column installation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20231128

Address after: Room 2029, 20th Floor, Jinchen International, No. 699 Huanghe Road, Changji City, Changji Hui Autonomous Prefecture, Xinjiang Uygur Autonomous Region, 831100 (Building 4, Hill 2, Zone 137)

Applicant after: Changji Urban Construction Municipal Engineering Construction Co.,Ltd.

Address before: Room 8-2020, Sijiyuan Community, Beijing West Road, Xixia District, Yinchuan City, Ningxia Hui Autonomous Region, 750000

Applicant before: NINGXIA QIAODUOMEI ROAD BRIDGE STEEL FORMWORK TECHNOLOGY CO.,LTD.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant