- Publication number
- CN208152486U CN208152486U CN201820008493.7U CN201820008493U CN208152486U CN 208152486 U CN208152486 U CN 208152486U CN 201820008493 U CN201820008493 U CN 201820008493U CN 208152486 U CN208152486 U CN 208152486U
- Authority
- CN
- China
- Prior art keywords
- floor
- fistulae
- pipeline
- fixed
- floor pipeline
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Refuse Collection And Transfer (AREA)
Abstract
The utility model discloses multi-rise building refuse collection pipe-line systems, including floor concrete framework, first floor pipeline and the second floor pipeline and the floor refuse hopper being arranged on the first floor pipeline and the second floor pipe rod wall, first floor pipeline and the second floor pipeline pass through fixed plate and are fixedly connected with floor concrete mechanism, floor refuse hopper includes the first fistulae and the second fistulae for being inclined at the first fistulae lower end, second fistulae is fixed with third fistulae far from one end of the first fistulae, and the tube wall of third fistulae is fixed with screw thread, third fistulae is connect by the first threaded hole with the first floor pipeline thread.The utility model is easy to operate, can between rubbish is poured into floor refuse hopper, reduce the manpower and material resources of floor rubbish cleaning, construction cost be greatly saved, while the first floor pipeline and the second floor pipe are easy to disassemble, and a layer spreading can be added with progress.
Description
Technical field
The utility model relates to technical field of buildings more particularly to multi-rise building refuse collection pipe-line systems.
Background technique
Architecture construction process is more, and the duration is long, and various processes can generate a large amount of building waste in different periods, respectively
Grade management file requires that every procedure accomplishes that the complete field of work is clear, construction site requires periodic cleaning.
Normal practice is all to be packed into trolley after being cleaned by worker, will fill rubbish by material elevator or building hoist
Trolley be hoisted to first layer ground, then rubbish is drawn to specified stacking point by the worker of first layer ground and is toppled over, then by artificial
Entrucking outward transport, this mode not only wasting manpower and material resources, but also waste a large amount of time.Therefore, the utility model devises more
Skyscraper refuse collection pipe-line system.
Utility model content
Time-consuming and laborious problem is cleared purpose of the utility model is to solve building waste, and the more high levels proposed are built
Building refuse clears pipe-line system.
To achieve the goals above, the utility model uses following technical solution:
Multi-rise building refuse collection pipe-line system, including floor concrete mechanism, the first floor pipeline and the second floor
Pipeline and the floor refuse hopper being arranged on the first floor pipeline and the second floor pipe rod wall, the first floor pipeline and
Second floor pipeline passes through fixed plate and is fixedly connected with floor concrete mechanism, the floor refuse hopper include the first fistulae with
And it is inclined at the second fistulae of the first fistulae lower end, second fistulae is fixed with third far from one end of the first fistulae
Fistulae, and the tube wall of the third fistulae is fixed with screw thread, the third fistulae passes through the first threaded hole and the first floor pipe
Road is threadedly coupled, and the first floor pipeline and the second floor pipeline are fastenedly connected by pipe sleeve, in the upper and lower side of the pipe sleeve
Wall offers annular groove, and the inside of the annular groove, which is equipped with, clamps ring plate, and the both ends outer wall for clamping ring plate is fixed with
Determine block, the side wall of the annular groove offers through-hole, and two fixed blocks both pass through through-hole, and the side wall of fixed block passes through
Two threaded holes are threaded with the same bolt, and the lower end of the second floor pipeline is equipped with garbage removing cart.
Preferably, the side wall of first fistulae opens up fluted, the inside of the groove be equipped with the upper end of groove and
The shaft that lower end is fixedly connected, the inside of the groove are equipped with the circular baffle plate with shaft pivot bush unit, the circular baffle plate
Side wall is fixed with convex block.
Preferably, the floor refuse hopper uses DN200 steel pipe.
Preferably, the fixed plate uses 5# angle steel.
Preferably, the clamping ring plate is elastic ring plate.
Preferably, the surface of the circular baffle plate is equipped with wearing layer.
Compared with prior art, the utility model provides multi-rise building refuse collection pipe-line system, and having following has
Beneficial effect:
1, the multi-rise building refuse collection pipe-line system is convenient for building by the way that the floor refuse hopper of each floor is arranged in
Layer worker is shipped to refuse hopper with trolley by after refuse sweeping, directly pours into floor refuse hopper, reduces the cleaning of floor rubbish
Manpower and material resources, construction cost is greatly saved, by the convex block being arranged on the first fistulae, circular baffle plate can be opened and closed,
And then can be avoided upper floor and pour into the dust of rubbish and flowed out from the opening of the first fistulae, the pollution of dust is reduced, by setting
The screw thread on third fistulae is set, convenient for separating floor refuse hopper with the first floor pipeline, and then is convenient for staff
Installation and removal, can add a layer spreading with progress.
2, the multi-rise building refuse collection pipe-line system is being added by the clamping ring plate and setting that are arranged in pipe sleeve
Fixed block and bolt in tight ring plate, the first floor pipeline and the second floor pipeline are nested into pipe sleeve, turning bolt can
It drives and clamps ring plate and contacted with the outer wall of the first floor pipeline and the second floor pipeline, and then can be by the first floor pipeline and the
Two floor pipelines are fastenedly connected, and are mounted and dismounted convenient for staff.
3, multi-rise building refuse collection pipe-line system, by the refuse collection that the second floor lower end of duct is arranged in
Vehicle can will stay the direct entrucking of rubbish flowed down in the first floor pipeline and the second floor pipeline, can reduce the pollution of dust.
It is not directed to part in the device to be the same as those in the prior art or can be realized by using the prior art, the utility model
It is easy to operate, can between rubbish is poured into floor refuse hopper, reduce the manpower and material resources of floor rubbish cleaning, greatly save
Construction cost, while the first floor pipeline and the second floor pipe are easy to disassemble, a layer spreading can be added with progress.
Detailed description of the invention
Fig. 1 be the utility model proposes multi-rise building refuse collection pipe-line system structural schematic diagram;
Fig. 2 be the utility model proposes multi-rise building refuse collection pipe-line system floor refuse hopper structural representation
Figure;
Fig. 3 be the utility model proposes multi-rise building refuse collection pipe-line system pipe sleeve structural schematic diagram.
In figure:1 first floor pipeline, 2 second floor pipelines, 3 floor concrete mechanisms, 4 fixed plates, 5 floor rubbish
Bucket, 6 pipe sleeves, 7 garbage removing carts, 8 first fistulaes, 9 second fistulaes, 10 third fistulaes, 11 bolts, 12 grooves, 13 circular baffle plates,
14 shafts, 15 convex blocks, 16 screw threads, 17 annular grooves, 18 clamp ring plate, 19 through-holes, 20 fixed blocks.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.
In the description of the present invention, it should be understood that term " on ", "lower", "front", "rear", "left", "right",
The orientation or positional relationship of the instructions such as "top", "bottom", "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings, and is only
For ease of description the utility model and simplify description, rather than the device or element of indication or suggestion meaning must have it is specific
Orientation, be constructed and operated in a specific orientation, therefore should not be understood as limiting the present invention.
Referring to Fig.1-3, multi-rise building refuse collection pipe-line system, including floor concrete mechanism 3, the first floor pipeline
1 and second floor pipeline 2 and the floor refuse hopper 5 that is arranged on 2 bar wall of the first floor pipeline 1 and the second floor pipeline,
One floor pipeline 1 and the second floor pipeline 2 are fixedly connected by fixed plate 4 with floor concrete mechanism 3, floor refuse hopper 5
Including the first fistulae 8 and it is inclined at the second fistulae 9 of 8 lower end of the first fistulae, the second fistulae 9 is far from the first fistulae 8
One end is fixed with third fistulae 10, and the tube wall of third fistulae 10 is fixed with screw thread 16, and third fistulae 10 passes through the first spiral shell
Pit is threadedly coupled with the first floor pipeline 1, and the first floor pipeline 1 and the second floor pipeline 2 are fastenedly connected by pipe sleeve 6, is managed
The upper and lower side inner wall of set 6 offers annular groove 17, and the inside of annular groove 17, which is equipped with, clamps ring plate 18, clamps the both ends outer wall of ring plate 18
It is fixed with fixed block 20, the side wall of annular groove 17 offers through-hole 19, and two fixed blocks 20 both pass through through-hole 19, and fixed
The side wall of block 20 passes through the second threaded hole and is threaded with the same bolt 11, and the lower end of the second floor pipeline 2 is equipped with rubbish
Rubbish clearing and transporting vehicle 7.
The side wall of first fistulae 8 opens up fluted 12, and the inside of groove 12 is equipped with to be fixed with the top and bottom of groove 12
The shaft 14 of connection, the inside of groove 12 are equipped with the circular baffle plate 13 with 14 pivot bush unit of shaft, can be by floor refuse hopper 5
Opening seals, and avoids dust pollution, and the side wall of circular baffle plate 13 is fixed with convex block 15, convenient for 13 shape of circular baffle plate is recessed
It being taken out in slot 12, floor refuse hopper 5 uses DN200 steel pipe, and fixed plate 4 uses 5# angle steel, and clamping ring plate 18 is elastic ring plate,
When bolt 11 loosens, clamping ring plate 18 can automatically reset, and the surface of circular baffle plate 13 is equipped with wearing layer, can keep off to circle
Plate 13 is protected, and avoiding circular baffle plate 13 from sliding for a long time influences its service life.
In the utility model, in use, being convenient for floor worker by rubbish by the floor refuse hopper 5 that each floor is arranged in
It after rubbish cleans, is shipped with trolley to refuse hopper, directly pours into floor refuse hopper 5, reduce the manpower object of floor rubbish cleaning
Construction cost is greatly saved in power, can be by round 13 baffles folding, in turn by the convex block 15 being arranged on the first fistulae 8
It can be avoided upper floor and pour into the dust of rubbish and flowed out from the opening of the first fistulae 8, reduce the pollution of dust, existed by setting
Screw thread 16 on third fistulae 10 convenient for separating floor refuse hopper 5 with the first floor pipeline 1, and then is convenient for work people
Member's installation and removal, can add a layer spreading with progress, step up ring plate by the clamping ring plate 18 and setting that are arranged in pipe sleeve 6
Fixed block 20 and bolt 11 on 18, the first floor pipeline 1 and the second floor pipeline 2 are nested into pipe sleeve 6, bolt 11 is turned
It is able to drive clamping ring plate 18 to contact with the outer wall of the first floor pipeline 1 and the second floor pipeline 2, and then can be by the first floor
Pipeline 1 and the second floor pipeline 2 are fastenedly connected, and are mounted and dismounted convenient for staff, by being arranged in the second floor pipe
The garbage removing cart 7 of 2 lower end of road can will stay the rubbish flowed down directly to fill in the first floor pipeline 1 and the second floor pipeline 2
Vehicle can reduce the pollution of dust.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not
It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this
Novel technical solution and its utility model design are subject to equivalent substitution or change, should all cover the protection model in the utility model
Within enclosing.
Claims (6)
1. multi-rise building refuse collection pipe-line system, including floor concrete mechanism (3), the first floor pipeline (1) and second
Floor pipeline (2) and the floor refuse hopper (5) being arranged on the first floor pipeline (1) and second floor pipeline (2) bar wall,
It is characterized in that, the first floor pipeline (1) and the second floor pipeline (2) pass through fixed plate (4) and floor concrete mechanism
(3) it is fixedly connected, the floor refuse hopper (5) includes the first fistulae (8) and is inclined at the of the first fistulae (8) lower end
Two fistulaes (9), second fistulae (9) is fixed with third fistulae (10) far from the one end of the first fistulae (8), and the third
The tube wall of fistulae (10) is fixed with screw thread (16), and the third fistulae (10) passes through the first threaded hole and the first floor pipeline
(1) it is threadedly coupled, the first floor pipeline (1) and the second floor pipeline (2) are fastenedly connected by pipe sleeve (6), the pipe sleeve
(6) upper and lower side inner wall offers annular groove (17), and the inside of the annular groove (17), which is equipped with, clamps ring plate (18), the clamping ring
The both ends outer wall of piece (18) is fixed with fixed block (20), and the side wall of the annular groove (17) offers through-hole (19), two institutes
Fixed block (20) is stated to both pass through through-hole (19), and the side wall of fixed block (20) pass through the second threaded hole be threaded with it is same
The lower end of bolt (11), the second floor pipeline (2) is equipped with garbage removing cart (7).
2. multi-rise building refuse collection pipe-line system according to claim 1, which is characterized in that first fistulae
(8) side wall opens up fluted (12), and the inside of the groove (12) is equipped with to be fixedly connected with the top and bottom of groove (12)
Shaft (14), the inside of the groove (12) is equipped with the circular baffle plate (13) with shaft (14) pivot bush unit, the round gear
The side wall of plate (13) is fixed with convex block (15).
3. multi-rise building refuse collection pipe-line system according to claim 1, which is characterized in that the floor refuse hopper
(5) DN200 steel pipe is used.
4. multi-rise building refuse collection pipe-line system according to claim 1, which is characterized in that the fixed plate (4)
Using 5# angle steel.
5. multi-rise building refuse collection pipe-line system according to claim 1, which is characterized in that the clamping ring plate
It (18) is elastic ring plate.
6. multi-rise building refuse collection pipe-line system according to claim 2, which is characterized in that the circular baffle plate
(13) surface is equipped with wearing layer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820008493.7U CN208152486U (en) | 2018-01-03 | 2018-01-03 | Multi-rise building refuse collection pipe-line system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820008493.7U CN208152486U (en) | 2018-01-03 | 2018-01-03 | Multi-rise building refuse collection pipe-line system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208152486U true CN208152486U (en) | 2018-11-27 |
Family
ID=64414797
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820008493.7U Active CN208152486U (en) | 2018-01-03 | 2018-01-03 | Multi-rise building refuse collection pipe-line system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208152486U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112012430A (en) * | 2020-08-31 | 2020-12-01 | 祝红星 | Interlayer building construction building rubbish clearance system |
-
2018
- 2018-01-03 CN CN201820008493.7U patent/CN208152486U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112012430A (en) * | 2020-08-31 | 2020-12-01 | 祝红星 | Interlayer building construction building rubbish clearance system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208152486U (en) | Multi-rise building refuse collection pipe-line system | |
CN211143291U (en) | Sewage pipe network dredging device for city | |
CN109837978A (en) | A kind of climb type pipeline cleaning machine people from bottom to top | |
CN206827417U (en) | Can have enough to meet need formula garbage collection device | |
CN210593589U (en) | Town road clearance rubbish transfer device | |
CN204662883U (en) | A kind of building waste passage | |
CN208202459U (en) | A kind of building sets up construction waste discharge and clears special facilities | |
CN210356203U (en) | Pit-shaped sewage cleaning device for building | |
CN209144981U (en) | A kind of water supply and sewerage pipeline dredging maintenance device | |
CN208668874U (en) | A kind of novel building vertical garbage transportation system | |
CN208009489U (en) | A kind of lattice composite material detection well lid | |
CN207192053U (en) | A kind of environmental sanitation clean type sanitation cart | |
CN207048001U (en) | A kind of plumbing antifouling type drainage pipeline | |
CN202427238U (en) | Drum type bar screen machine | |
CN206408575U (en) | A kind of electric sanitation truck equipped with air cleaning unit | |
CN215165765U (en) | Concrete pouring prefabricating tool | |
CN203477756U (en) | Robot for clearing pipeline blocking matter | |
CN206721767U (en) | A kind of road sweeper plate | |
CN112169889A (en) | Recovery unit is smashed to building rubbish | |
CN219992986U (en) | Can have enough to meet need assembled floor rubbish passageway and wash pump waste fitting discharging concurrently | |
CN208455785U (en) | Sewer Environment Protection and Drainage of Pulled Water pipe | |
CN213994994U (en) | A drainage device for municipal works | |
CN204528268U (en) | A kind of novel garbage can | |
CN112012430A (en) | Interlayer building construction building rubbish clearance system | |
CN218374341U (en) | Municipal drainage device convenient to maintain |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |