CN208151872U - Scaffold formula Wavelike steel webplate hanging apparatus - Google Patents

Scaffold formula Wavelike steel webplate hanging apparatus Download PDF

Info

Publication number
CN208151872U
CN208151872U CN201820651725.0U CN201820651725U CN208151872U CN 208151872 U CN208151872 U CN 208151872U CN 201820651725 U CN201820651725 U CN 201820651725U CN 208151872 U CN208151872 U CN 208151872U
Authority
CN
China
Prior art keywords
scaffold
hanging
hanging basket
wavelike steel
steel webplate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820651725.0U
Other languages
Chinese (zh)
Inventor
王伟
林金彪
韦性前
马旭
顾少林
宿万东
侯晓龙
王奇志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningxia highway and Bridge Construction Co., Ltd
Original Assignee
Ningxia Road & Bridge Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningxia Road & Bridge Engineering Co ltd filed Critical Ningxia Road & Bridge Engineering Co ltd
Priority to CN201820651725.0U priority Critical patent/CN208151872U/en
Application granted granted Critical
Publication of CN208151872U publication Critical patent/CN208151872U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of scaffold formula Wavelike steel webplate hanging apparatus, including suspention Hanging Basket system, running gear, template system and tackling system, the suspention Hanging Basket system includes main couple, is connected by preceding upper beam with connection beam between main couple, and by rear anchor system and has poured beam section anchoring;The tackling system includes the scaffold set on main couple top, and the walking track of electric block is fixed on the downside of scaffold, and walking track is equipped with electric block.When use, it first passes through automobile loop wheel machine the steel web transported to bank is lifted on ship, ship transports steel web immediately below Hanging Basket, installs in horizontal transport to installation site hand fit after vertically being played steel web in place using Hanging Basket electric block tackling system.This structure suitable for water, korneforos, the ships P Passable such as marine Wavelike steel webplate bridge construction.The device structure is simple, practical, safe and reliable, at low cost, high-efficient, and the pier cantilever cradle construction stage makes smooth advances in guarantee water.

Description

Scaffold formula Wavelike steel webplate hanging apparatus
Technical field
The utility model patent is related in water steel web hanging device in Hanging Basket cantilever construction, more particularly, to one kind about And application method scaffold formula Wavelike steel webplate hanging apparatus.
Background technique
Box girder with corrugated steel webs is a kind of economic, efficient, easy construction novel steel-concrete composite structure form, this Kind structure thoroughly solves the crack problem of traditional prestressed concrete box girder web, for realizing bridge lightness, beautification Bridge Landscape realizes that bridge construction is energy-saving and sustainable development has important practical significance.
Currently, the lifting of highway bridge steel web is divided into two kinds of lifting methods land and waterborne.Land steel web passes through wooden handcart It behind transport to construction site, is lifted by crane by tower crane or truck crane, hand fit installs.But crane and tower crane in water Construction needs are unable to satisfy, steel web in water is carried out according to tower crane and installs, one is reached for main span across footpath and steel web weight It defines the level other project, needs middle TC7035B-16 tower crane that can just be installed in place, tower crane installation period is long, costly.
Domestic same bridges Wavelike steel webplate lifting is transported by molded block top surface to Hanging Basket, then passes through electricity Dynamic cucurbit tackling system lifting, such method require to be laid with steel web conveying track is longer, Hanging Basket height is higher, Hanging Basket compared with Weight, is unsatisfactory for the Hanging Basket weight of design document requirement.
Summary of the invention
For the above-mentioned prior art, the technical problem to be solved by the present invention is to provide a kind of scaffold formula waveform steel abdomens Plate hanging apparatus, to solve the problems, such as in water that crane and tower crane are unable to satisfy that construction needs, installation period is long, costly, and Pass through the problem that Hanging Basket load-bearing in molded block top surface means of transportation work progress is excessive.
In order to solve the above technical problems, the utility model provides a kind of scaffold formula Wavelike steel webplate hanging apparatus, including Suspention Hanging Basket system, running gear, template system and tackling system, the suspention Hanging Basket system front end are equipped with preceding suspender belt vertically, Running gear is set to suspention Hanging Basket system lower end by preceding suspender belt and walking hanging ring, and template system is set by preceding suspender belt and rear hanging In running gear lower end, the tackling system is set to the front end on suspention Hanging Basket system top;
The suspention Hanging Basket system includes main couple, is connected by preceding upper beam with connection beam between main couple, and pass through Anchor system is anchored with beam section has been poured afterwards;
The tackling system includes the scaffold set on main couple top, and the walking of electric block is fixed on the downside of scaffold Track, walking track are equipped with electric block.
Preferably, the vertical structure of the scaffold is herringbone structure or trapezium structure, both ends and the scaffold people of track of walking The both ends of the under shed of word structure or trapezium structure connect, and are fixedly connected by reinforcing rod.
Preferably, the running gear includes that traveling wheel, outer nose girder and walking hanging ring, the traveling wheel are set under connection beam Side, outer nose girder are set to and have poured beam section two sides, and front end is connect with preceding suspender belt, and rear end is connect by hanging ring of walking with connection beam, row The one end for walking hanging ring is connect with connection beam, and the other end is connect with outer nose girder.
Preferably, the template system includes preceding lower beam, rear lower beam and is vertical at bottom girder between the two, preceding Lower beam front end is equipped with preceding operating platform, and rear lower beam rear end is equipped with rear operating platform;Preceding lower beam is connect with preceding suspender belt, under rear After crossbeam passes through hanging with poured beam section and connect.
Preferably, the preceding suspender belt is set on preceding upper beam.
Preferably, railing is equipped on the upside of the main couple.
The scaffold formula Wavelike steel webplate hanging apparatus of the utility model, solves crane and tower crane in water and is unable to satisfy construction It needs, installation period length, costly problem, and is held by Hanging Basket in molded block top surface means of transportation work progress The excessive problem of weight, the lifting of Wavelike steel webplate in water is carried out by the scaffold formula tackling system on Hanging Basket, smoothly solves water Middle Wavelike steel webplate lifts problem, achieves satisfied achievement.
In conclusion will be transported using the scaffold formula Wavelike steel webplate hanging apparatus of the utility model by automobile loop wheel machine Steel web to bank is lifted on ship, and ship transports steel web immediately below Hanging Basket, is lifted by crane using Hanging Basket electric block System is installed in horizontal transport to installation site hand fit after vertically playing steel web in place.This structure is suitable for water In, korneforos, the ships P Passable such as marine Wavelike steel webplate bridge construction.The device structure is simple, practical, safe and reliable, At low cost, high-efficient, the pier cantilever cradle construction stage makes smooth advances in guarantee water.
Detailed description of the invention
Fig. 1 is the scaffold formula Wavelike steel webplate hanging apparatus structural schematic diagram of the utility model.
In figure:1- suspends Hanging Basket system in midair, 11- main couple, upper beam before 12-, 13- connection beam, anchor system after 14-, 15- Railing, 2- running gear, 21- traveling wheel, the outer nose girder of 22-, 23- walk hanging ring, 3- template system, lower beam before 31-, after 32- Lower beam, 33- bottom girder, operating platform before 34-, operating platform after 35- are hung after 36-, 4- tackling system, 41- scaffold, 42- It walks track, 43- electric block, 44- reinforcing rod, suspender belt before 5-, 6- Wavelike steel webplate
Specific embodiment
Specific embodiment of the present utility model is described in detail with reference to the accompanying drawing:
As shown in Figure 1, the scaffold formula Wavelike steel webplate hanging apparatus of the utility model, including suspention Hanging Basket system 1, walking System 2, template system 3 and tackling system 4,1 front end of suspention Hanging Basket system are equipped with preceding suspender belt 5 vertically, and running gear 2 passes through Preceding suspender belt 5 and walking hanging ring 23 are set to suspention 1 lower end of Hanging Basket system, and template system 3 is set to row by preceding suspender belt 5 and rear hanging 36 2 lower end of walking system, the tackling system 4 are set to the front end on suspention 1 top of Hanging Basket system;
The suspention Hanging Basket system 1 includes main couple 11, is connected between main couple 11 by preceding upper beam 12 and connection beam 13 It connects, and is anchored by rear anchor system 14 with beam section has been poured;
The tackling system 4 includes the scaffold 41 set on 11 top of main couple, and electronic calabash is fixed on the downside of scaffold 41 The walking track 42 of reed 43, walking track 42 are equipped with electric block 43.
The vertical structure of the scaffold 41 be herringbone structure or trapezium structure, walk track 42 both ends and 41 herringbone of scaffold The both ends of the under shed of structure or trapezium structure connect, and are fixedly connected by reinforcing rod 44.
The running gear 2 includes that traveling wheel 21, outer nose girder 22 and walking hanging ring 23, the traveling wheel 21 are set to connection beam 13 downsides, outer nose girder 22 are set to and have poured beam section two sides, and front end is connect with preceding suspender belt 5, and rear end passes through walking hanging ring 23 and contacts Beam 13 connects, and one end of walking hanging ring 23 is connect with connection beam 13, and the other end is connect with outer nose girder 22.
The template system 3 includes preceding lower beam 31, rear lower beam 32 and is vertical at bottom girder 33 between the two, preceding 31 front end of lower beam is equipped with preceding operating platform 34, and rear 32 rear end of lower beam is equipped with rear operating platform 35;Preceding lower beam 31 with before hang Band 5 connects, and hanging 36 is connect with beam section has been poured after rear lower beam 32 passes through.
The preceding suspender belt 5 is set on preceding upper beam 12.
Railing 15 is equipped on the upside of the main couple 11.
The working principle of the utility model is:Electric block row is welded with I-steel and channel steel on the main couple 11 of Hanging Basket Track 42, installation and debugging electric block 43 are walked, so that steel web can run to designated position after slinging.It will by automobile loop wheel machine The steel web transported to bank is lifted on ship, and ship transports steel web immediately below Hanging Basket, utilizes Hanging Basket electric block Tackling system 4 by 6 vertical lifting of steel web in place after again horizontal transport installed to installation site by hand fit.Steel abdomen Plate 6 is installed to be welded in place, is then adjusted hanging basket formwork absolute altitude, carries out reinforcement installation, concreting, tensioning and pressure Slurry process.
Above-mentioned combination attached drawing is explained in detail the embodiments of the present invention, but the utility model is not limited to Above embodiment can also make many variations to it within the knowledge of one of ordinary skill in the art.

Claims (6)

1. a kind of scaffold formula Wavelike steel webplate hanging apparatus, which is characterized in that including suspending Hanging Basket system (1), running gear in midair (2), template system (3) and tackling system (4), suspention Hanging Basket system (1) front end are equipped with preceding suspender belt (5), Running System vertically System (2) is set to suspention Hanging Basket system (1) lower end by preceding suspender belt (5) and walking hanging ring (23), and template system (3) passes through preceding suspender belt (5) and rear hanging (36) is set to running gear (2) lower end, before the tackling system (4) is set to suspention Hanging Basket system (1) top End;
The suspention Hanging Basket system (1) includes main couple (11), passes through preceding upper beam (12) and connection beam between main couple (11) (13) it connects, and by rear anchor system (14) and has poured beam section anchoring;
The tackling system (4) includes the scaffold (41) set on main couple (11) top, is fixed with electricity on the downside of scaffold (41) The walking track (42) of dynamic cucurbit (43), walking track (42) are equipped with electric block (43).
2. scaffold formula Wavelike steel webplate hanging apparatus according to claim 1, which is characterized in that the scaffold (41) is indulged It is herringbone structure or trapezium structure to structure, walks under the both ends and scaffold (41) herringbone structure or trapezium structure of track (42) The both ends of opening connect, and are fixedly connected by reinforcing rod (44).
3. scaffold formula Wavelike steel webplate hanging apparatus according to claim 1, which is characterized in that the running gear (2) Including traveling wheel (21), outer nose girder (22) and walking hanging ring (23), the traveling wheel (21) is set on the downside of connection beam (13), leads outside Beam (22) is set to and has poured beam section two sides, and front end is connect with preceding suspender belt (5), and rear end passes through walking hanging ring (23) and connection beam (13) One end of connection, walking hanging ring (23) is connect with connection beam (13), and the other end is connect with outer nose girder (22).
4. scaffold formula Wavelike steel webplate hanging apparatus according to claim 1, which is characterized in that the template system (3) Including preceding lower beam (31), rear lower beam (32) and it is vertical at bottom girder (33) between the two, preceding lower beam (31) front end Equipped with preceding operating platform (34), rear lower beam (32) rear end is equipped with rear operating platform (35);Preceding lower beam (31) and preceding suspender belt (5) Connection, after rear lower beam (32) passes through hanging (36) with poured beam section and connect.
5. scaffold formula Wavelike steel webplate hanging apparatus according to claim 1, which is characterized in that the preceding suspender belt (5) sets In on preceding upper beam (12).
6. scaffold formula Wavelike steel webplate hanging apparatus according to claim 1, which is characterized in that on the main couple (11) Side is equipped with railing (15).
CN201820651725.0U 2018-05-03 2018-05-03 Scaffold formula Wavelike steel webplate hanging apparatus Active CN208151872U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820651725.0U CN208151872U (en) 2018-05-03 2018-05-03 Scaffold formula Wavelike steel webplate hanging apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820651725.0U CN208151872U (en) 2018-05-03 2018-05-03 Scaffold formula Wavelike steel webplate hanging apparatus

Publications (1)

Publication Number Publication Date
CN208151872U true CN208151872U (en) 2018-11-27

Family

ID=64377462

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820651725.0U Active CN208151872U (en) 2018-05-03 2018-05-03 Scaffold formula Wavelike steel webplate hanging apparatus

Country Status (1)

Country Link
CN (1) CN208151872U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111483925A (en) * 2020-04-20 2020-08-04 浙江交工金筑交通建设有限公司 Asynchronous basket of hanging of wave form steel web bridge

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111483925A (en) * 2020-04-20 2020-08-04 浙江交工金筑交通建设有限公司 Asynchronous basket of hanging of wave form steel web bridge
CN111483925B (en) * 2020-04-20 2022-01-25 浙江交工集团股份有限公司 Asynchronous basket of hanging of wave form steel web bridge

Similar Documents

Publication Publication Date Title
CN106677211B (en) Wall tears assembled piping lane aluminum dipping form trolley system and its construction method open with the top plate whole morning poured
CN101476294B (en) Mounting method for underbeam segment of large-stride steel box girder stayed-cable bridge
CN101476291B (en) Segment-assembling simply supported box girder movable falsework construction method
CN101586330B (en) Receding construction method of cradle of continuous girder bridge made of prestressing concrete
CN101781879B (en) Construction method of single-pylon cable-stayed bridge without dorsal cables
CN102877418B (en) Stentless urban bridge anti-collision guardrail construction method and cradle vehicle and gun carrier thereof
CN104631333B (en) Arch bridge needle beam, stringer and floorings cast-in-place construction travelling bridge and method
CN205025086U (en) Strength nature skeleton concrete beam construction suspend template in midair
CN101781878B (en) Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof
CN103161126A (en) Road bridge variable section hollow high pier slip-form construction method
CN104790295A (en) Construction method of tire type gantry crane frame beam
CN101126223A (en) Mobile integral construction platform, construction method thereof and special sling for the same
CN110374008A (en) A method of the erection of cable-stayed bridge steel truss is carried out in marine environment
CN107905114A (en) A kind of construction method of large span Successive interference cancellation
CN104727227A (en) Whole-section erecting method for open lattice type steel beam of half-through steel box tied-arch bridge
CN208934425U (en) Self-propelled multifunctional material distributing machine
CN105239510A (en) Dismounting beam support used for high pier small-radius curve cast-in-situ box beam and construction method
CN103498425A (en) Full-dismounting combination type multifunctional bracket supporting structure and construction method thereof
CN108457243A (en) A kind of construction method of assembly concrete wave wall
CN110468743B (en) Movable hanging bracket for transformation of old bridge pier cap and construction method
CN208151872U (en) Scaffold formula Wavelike steel webplate hanging apparatus
CN207032062U (en) Tower with suspended cable available for Large-span Steel Box Beam construction
CN206800165U (en) A kind of highway bridge
CN206538685U (en) Twin shaft pier and middle binder truss move integrally system
CN105019357A (en) Method for mounting specially-shaped precast bridge decks on open lattice steel beams of arched bridge

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200820

Address after: 750001 room 1217, 12 / F, building 1, Fortune Center, Qingchun building, Xingqing District, Yinchuan City, Ningxia Hui Autonomous Region

Patentee after: Ningxia Zhongda Highway Construction Co.,Ltd.

Address before: 750001 Jinfeng District, the Ningxia Hui Autonomous Region, Wanshou Road, No. 142, Yinchuan

Patentee before: NINGXIA ROAD & BRIDGE ENGINEERING Co.,Ltd.

CP03 "change of name, title or address"
CP03 "change of name, title or address"

Address after: Office building 2, Luqiao building, 142 Wanshou Road, Jinfeng District, Yinchuan City, Ningxia Hui Autonomous Region, 750004

Patentee after: Ningxia highway and Bridge Construction Co., Ltd

Address before: 750001 room 1217, 12 / F, building 1, Fortune Center, Qingchun building, Xingqing District, Yinchuan City, Ningxia Hui Autonomous Region

Patentee before: Ningxia Zhongda Highway Construction Co.,Ltd.