CN208122811U - A kind of oil well back-up sand equipment - Google Patents
A kind of oil well back-up sand equipment Download PDFInfo
- Publication number
- CN208122811U CN208122811U CN201820484572.5U CN201820484572U CN208122811U CN 208122811 U CN208122811 U CN 208122811U CN 201820484572 U CN201820484572 U CN 201820484572U CN 208122811 U CN208122811 U CN 208122811U
- Authority
- CN
- China
- Prior art keywords
- sand
- bucket
- water
- gaza
- water pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
The utility model belongs to field of petroleum exploitation, oil well plugging back-up sand equipment specially in petroleum secondary recovery, it is characterised in that:It is made of sand-filling apparatus (1) and priming apparatus (2) two parts, wherein sand-filling apparatus (1) upper end is back-up sand bucket (1.1), back-up sand bucket lower end connects water pipe (1.2) and water sand tube (1.3), water pipe (1.2) is above water sand tube (1.3), sand-filling apparatus (1) passes through hook (1.5) and priming apparatus (2) connection, control panel (1.4) are installed below back-up sand bucket (1.1), the desired effect that the utility model can achieve is:With the mixed husky ratio of baffle controls, the rate of gaza can be effectively controlled;Fill out hourglass bucket height it is artificial control, reduce working strength, propose effect;It encounters emergency case while can immediately treat, sand such as occur and block up, stop gaza immediately, cementing truck suppresses de-plugging;It establishes circulation conveniently, avoids filling out the risk for manually blocking gaza mouthful generation before sand to establish circulation.
Description
Technical field
The utility model belongs to field of petroleum exploitation, oil well plugging back-up sand equipment specially in petroleum secondary recovery.
Background technique
With the growth of Jiangsu oilfield, oily area most of at present enters the secondary recovery phase, oil-water well over time,
Pit shaft aging corrosion gradually increases.And the measure construction of secondary recovery phase is ordinary, working procedure gradually complicates, part aging
Pit shaft or seriously corroded or casing deformation cannot bear high pressure and tripping in packer.Certain penetrated can temporarily be blocked by filling out husky construction
Well section reaches measure construction purpose.Husky construction well is filled out at present gradually increase, and fill out husky device still many years ago, always not
It improves, there is numerous drawbacks.With the needs of social development, higher and higher, original behaviour for filling out husky device is required to operation field HSE
The practice does not meet HSE requirement, and there is an urgent need to improve to filling out husky technique and device improves.
It is the grains of sand to be transported in well by oil pipe, using carrying power of the water when pit shaft is just flowed through after a period of time
It is deposited in pit shaft, to achieve the purpose that oil-separating layer.Back-up sand protects target zone as oil-separating layer temporary in oil field development
A construction technology, be widely applied in construction, its great advantage is that polluted reservoir, negative pressure well can not established and be followed
It can not carry out playing plug in the case where ring, select back-up sand, simple to operation, construction investment is small.
It fills out hourglass bucket to connect on well head, since gaza's leak is unlimited, first manually that gaza mouthful is clogging, cementing truck is slow
The grains of sand after direct circulation is established, from manual control gaza of gaza mouthful, are transported to shaft bottom using the carrying capacity of water by shelves direct circulation.
Due to the nearly 2Mpa of the frictional resistance of pit shaft, take husky liquid pit shaft it is built-in attention recycle when, manually to block gaza mouthful has
Certain risk takes husky liquid and is not easy to establish direct circulation, does not meet the HSE requirement of job execution.
Drawback 2:Gaza mouthful is open type, and the rate of gaza wants manual control.
Drawback 3:When during filling out sand just in case causing blockages processing to be suppressed, it is necessary to connect cementing truck pipeline from new.
Drawback 4:Part well head is very high, and along with the height for filling out hourglass bucket, the labor of construction is increased when adding sand
Fatigue resistance, personnel's operation are relatively difficult.
Drawback 5:Because well site condition limits, need the sand added that cannot be transported to well head with vehicle, but manual handling leads to labor
Fatigue resistance is big.
Therefore a kind of can establish is needed to recycle gaza and manageable new device.
Summary of the invention
The utility model is mainly solving the technical problems that the bad control of speed, water sand easily cause spray during artificial plus few
Slurry.
The utility model is such solution above-mentioned technical problem:It is made of sand-filling apparatus and priming apparatus two parts,
Middle sand-filling apparatus upper end is back-up sand bucket, and back-up sand bucket lower end connects water pipe and water sand tube, and water pipe is above water sand tube, back-up sand dress
It sets and is connected by linking up with priming apparatus, control panel is installed below back-up sand bucket.
Water pipe and water sand tube opening upwards.
Back-up sand bucket upper end opening is greater than lower ending opening.
The utility model is attainable to be had the beneficial effect that:Device design is simple, facilitates installation, easy to operate, Ji Nengman
Sufficient field operation, and can guarantee construction quality;With the mixed husky ratio of baffle controls, the rate of gaza can be effectively controlled;Fill out hourglass bucket
Highly artificial controls, and reduces working strength, proposes effect;It encounters emergency case while can immediately treat, sand such as occur and block up,
Stop gaza immediately, cementing truck suppresses de-plugging;It is convenient to establish circulation, avoids filling out and manually blocks gaza before sand to establish circulation
The risk that mouth generates.
Detailed description of the invention
Attached drawing 1 is the utility model primary structure schematic diagram.
Specific embodiment
Parts title representated by each label is as follows in attached drawing:
Sand-filling apparatus 1 (back-up sand bucket 1.1, water pipe 1.2, water sand tube 1.3, control panel 1.4, hook 1.5), priming apparatus 2.
Embodiment 1:
It is made of sand-filling apparatus 1 and 2 two parts of priming apparatus, wherein 1 upper end of sand-filling apparatus is back-up sand bucket 1.1, back-up sand bucket
Lower end connects water pipe 1.2 and water sand tube 1.3, and for water pipe 1.2 above water sand tube 1.3, sand-filling apparatus 1 passes through 1.5 Hes of hook
Priming apparatus 2 connects, and is equipped with control panel 1.4 below back-up sand bucket 1.1.
Embodiment 2:
It is made of sand-filling apparatus 1 and 2 two parts of priming apparatus, wherein 1 upper end of sand-filling apparatus is back-up sand bucket 1.1, back-up sand bucket
Lower end connects water pipe 1.2 and water sand tube 1.3, and for water pipe 1.2 above water sand tube 1.3, sand-filling apparatus 1 passes through 1.5 Hes of hook
Priming apparatus 2 connects, and is equipped with control panel 1.4 below back-up sand bucket 1.1.
1.3 opening upwards of water pipe 1.2 and water sand tube.
Embodiment 3:
It is made of sand-filling apparatus 1 and 2 two parts of priming apparatus, wherein 1 upper end of sand-filling apparatus is back-up sand bucket 1.1, back-up sand bucket
Lower end connects water pipe 1.2 and water sand tube 1.3, and for water pipe 1.2 above water sand tube 1.3, sand-filling apparatus 1 passes through 1.5 Hes of hook
Priming apparatus 2 connects, and is equipped with control panel 1.4 below back-up sand bucket 1.1.
1.1 upper end opening of back-up sand bucket is greater than lower ending opening.
Embodiment 4:
It is made of sand-filling apparatus 1 and 2 two parts of priming apparatus, wherein 1 upper end of sand-filling apparatus is back-up sand bucket 1.1, back-up sand bucket
Lower end connects water pipe 1.2 and water sand tube 1.3, and for water pipe 1.2 above water sand tube 1.3, sand-filling apparatus 1 passes through 1.5 Hes of hook
Priming apparatus 2 connects, and is equipped with control panel 1.4 below back-up sand bucket 1.1.
1.3 opening upwards of water pipe 1.2 and water sand tube.
1.1 upper end opening of back-up sand bucket is greater than lower ending opening.
Husky device will be filled out to be placed in ground tanks, a clean water tank supplies water in the priming apparatus of ground, guarantees the water in tank
Position is higher than the water pipe of sand-filling apparatus, and the import of cementing truck connects the bottom water sand tube of sand-filling apparatus, and the outlet of cementing truck connects well
On port strobe.After cementing truck opens pump, water squeezes into oil pipe through cementing truck from the water pipe of sand-filling apparatus, establishes direct circulation.Take sand
Liquid compares after recycling normally from the baffle below gaza mouthful plus sand, back-up sand bucket to control to add, and water, sand pass through cementing truck toward well after mixing
Interior pumping, achievees the purpose that back-up sand.
After the utility model is developed, promoted first in Jiangsu oilfield side Min oil field 11#, effect is as follows:
1, side Min 11 is husky serious because stratum goes out, and oil recovery factory requires sand control measure operation, and low-temperature coating sand need to be squeezed into stratum
6000Kg.My team using it is improved fill out husky device and construct 6 hours fulfil assignment.
2, be calculated construction well be averaged gaza measure:
Side Min 11# fills out sand per hour:6000/6=1000 kilograms
It is improved efficiency after improvement:1000/426.18=2.35 times of practical increase rate:235%
Husky 2.35 times of the raising of device speed of application are filled out using improved.More than the target of expected raising 50%.
Claims (3)
1. a kind of oil well back-up sand equipment, it is characterised in that:It is made of sand-filling apparatus (1) and priming apparatus (2) two parts, wherein filling out
Sand device (1) upper end is back-up sand bucket (1.1), and back-up sand bucket lower end connects water pipe (1.2) and water sand tube (1.3), water pipe (1.2)
Above water sand tube (1.3), sand-filling apparatus (1) passes through hook (1.5) and priming apparatus (2) connection, back-up sand bucket (1.1) lower section peace
Equipped with control panel (1.4).
2. a kind of oil well back-up sand equipment according to claim 1, it is characterised in that:Water pipe (1.2) and water sand tube (1.3)
Opening upwards.
3. a kind of oil well back-up sand equipment according to claim 1 or 2, it is characterised in that:Back-up sand bucket (1.1) upper end opening is big
In lower ending opening.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820484572.5U CN208122811U (en) | 2018-04-08 | 2018-04-08 | A kind of oil well back-up sand equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820484572.5U CN208122811U (en) | 2018-04-08 | 2018-04-08 | A kind of oil well back-up sand equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208122811U true CN208122811U (en) | 2018-11-20 |
Family
ID=64194009
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820484572.5U Expired - Fee Related CN208122811U (en) | 2018-04-08 | 2018-04-08 | A kind of oil well back-up sand equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208122811U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111804391A (en) * | 2020-06-24 | 2020-10-23 | 程雅雯 | Special gravel manufacturing device for sand prevention and thin production of heavy oil well |
-
2018
- 2018-04-08 CN CN201820484572.5U patent/CN208122811U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111804391A (en) * | 2020-06-24 | 2020-10-23 | 程雅雯 | Special gravel manufacturing device for sand prevention and thin production of heavy oil well |
CN111804391B (en) * | 2020-06-24 | 2021-10-12 | 南京伟业机械有限公司 | Special gravel manufacturing device for sand prevention and thin production of heavy oil well |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101775977B (en) | Dual-tube injection well safety production string | |
CN208168933U (en) | A kind of buried Underwater Traffic Tunnel wastewater disposal basin dischargeable capacity optimization structure of Mining Method | |
CN209212206U (en) | A kind of packer for annular space pipeline | |
CN208122811U (en) | A kind of oil well back-up sand equipment | |
CN201416430Y (en) | Hydraulic controlled type concentric dual-pipe separate injection pipe string | |
CN106753299A (en) | Selective water plugging agent for thin oil well and preparation method and application thereof | |
CN104989319A (en) | Cementing method based on continuous cementing mode in petroleum exploration | |
CN203412535U (en) | Drilling fluid shunt device for starting or stopping pump through multiple steps | |
CN107676051A (en) | Coal bed gas well annular pressurizing coal powder fishing device and method | |
CN201443382U (en) | Downhole dosing device | |
CN205475234U (en) | Bootstrapping formula steel protects a pull -out device | |
CN201209423Y (en) | Oilfield workover treatment cement squeeze device | |
CN114718502A (en) | Abandoned well plugging method | |
CN209378507U (en) | A kind of overflow mechanism and the skimmer tank comprising it | |
CN106746021A (en) | A kind of acid oil-containing sewage treatment system for ocean platform | |
CN209603919U (en) | Not termination of pumping negative pressure sand washing auto Isolator Well Head | |
CN203175465U (en) | Packer for exploiting and fracturing of shale gas reservoir | |
CN206769892U (en) | Self-excitation pressure pulse is layered deblocking tool | |
CN216767345U (en) | Automatic filling device for pressure-control drilling plugging material | |
CN201835785U (en) | Oil-water well device capable of automatically controlling pressure relief and liquid discharge as well as pumping discharged liquid to production pipeline | |
RU2645695C1 (en) | Method of cementing of the additional column of pipes in the injection well | |
CN202348185U (en) | Self-supporting local circulation system | |
CN204609856U (en) | The online acidizing device of portable water injection well | |
CN207177842U (en) | Recovery device and oil well with same | |
CN105089567B (en) | Deep-well is adjustable low density flow quick fluid-discharge formation testing device and its operational method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181120 Termination date: 20190408 |
|