CN208108828U - Smelting furnace tap hole blocking device - Google Patents

Smelting furnace tap hole blocking device Download PDF

Info

Publication number
CN208108828U
CN208108828U CN201820559176.4U CN201820559176U CN208108828U CN 208108828 U CN208108828 U CN 208108828U CN 201820559176 U CN201820559176 U CN 201820559176U CN 208108828 U CN208108828 U CN 208108828U
Authority
CN
China
Prior art keywords
drill steel
connecting rod
tap hole
smelting furnace
plug
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820559176.4U
Other languages
Chinese (zh)
Inventor
龙在华
陈精智
周毅
苏木阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei New Jinyang Resources Co ltd
Original Assignee
Hubei Jinyang Resources Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Jinyang Resources Co Ltd filed Critical Hubei Jinyang Resources Co Ltd
Priority to CN201820559176.4U priority Critical patent/CN208108828U/en
Application granted granted Critical
Publication of CN208108828U publication Critical patent/CN208108828U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Vertical, Hearth, Or Arc Furnaces (AREA)

Abstract

The utility model relates to apparatus for melting metal technical fields, more particularly to a kind of smelting furnace tap hole blocking device, including connecting rod and drill steel, described drill steel one end is fixedly connected with the connection boom end, the other end is fixedly connected with plug, the connecting rod and melting furnace outer wall are hinged, angle between the connecting rod and the drill steel is less than 120 °, the melting furnace outer wall is provided with several cross bars that connecting rod and drill steel are pulled to the smelting furnace, the crossbar end is axially disposed several buckles, the drill steel is provided with the link for hanging the buckle.Bending structure is formed by connecting rod and drill steel, plug gets lodged in tap hole, and bending structure is pressed to smelting furnace by cross bar, so that plug is pressed on tap hole, is prevented from generating gap between plug and tap hole, is led to leakage.The utility model is designed reasonably, operating method reduce the security risk in molten metal fusion-casting process.

Description

Smelting furnace tap hole blocking device
Technical field
The utility model relates to apparatus for melting metal technical fields, block and fill more particularly to a kind of smelting furnace tap hole It sets.
Background technique
In aluminum alloy melt casting production process, smelting furnace be melt molten aluminum key equipment, when molten aluminum in smelting furnace at Divide after adjusting, need to banish molten aluminum into lower furnace and handled in furnace, whether leakage is to guarantee aluminium to the tap hole of smelting furnace The key of alloy casting production process safety.
The existing device for blocking smelting furnace tap hole is made of conical a plug and holding rod, circular cone The plug of shape is welded on holding rod, and conical plug blocks tap hole, is putting plug by man-hour manually hand-held holding rod Liquid mouth blocks consolidation.The existing device for blocking smelting furnace tap hole not only increases labor intensity of workers, but also with molten The increase of furnace inner melt, molten aluminum are washed open the pressure increase of plug, plug by molten aluminum, and seam is generated between plug and tap hole Gap, so that molten aluminum flows out in furnace.
In addition, in the prior art, the tap hole of smelting furnace stream is built into cement, with will appear damage long afterwards, thus Occurs gap between plug and tap hole, the phenomenon of leakage happens occasionally.Due to the molten aluminium alloy temperature of leakage be up to 600 DEG C with On, if worker not only causes the waste of molten aluminium alloy, increase is produced into without the phenomenon of leakage of discovery tap hole in time This, and the high temperature aluminium alloys melt leaked out encounters cooling water and will explode, and causes serious accident.
Utility model content
The purpose of this utility model is that in view of the deficiencies of the prior art, and a kind of smelting furnace tap hole blocking dress is provided It sets, tap hole can be blocked into consolidation, melt is avoided to leak out from tap hole, reduce production cost and production safety hidden danger.
Technical solution adopted by the utility model to solve its technical problems is:A kind of smelting furnace tap hole blocking device, Including connecting rod and drill steel, described drill steel one end is fixedly connected with the connection boom end, and the other end is fixedly connected with plug, institute It states connecting rod the other end and melting furnace outer wall is hinged, the angle between the connecting rod and the drill steel is described less than 120 ° Melting furnace outer wall is provided with several cross bars that connecting rod and drill steel are pulled to the smelting furnace, and the crossbar end is along axis To several buckles are provided with, the drill steel is provided with the link for hanging the buckle.
Further, the angle between the connecting rod and the drill steel is 45 ° ~ 90 °.
Further, the connecting rod, the drill steel and the cross bar are in the same plane.
Further, the cross bar is 2, and 2 cross bars are symmetrical arranged by center line of the drill steel.
Further, the plug is cone.
Further, the connecting rod and the drill steel are integrally formed.
Further, the plug is made of heat-resisting material.
The utility model has the beneficial effects that:A kind of smelting furnace tap hole blocking device, including connecting rod and drill steel, it is described Drill steel one end is fixedly connected with the connection boom end, and the other end is fixedly connected with plug, the connecting rod and melting furnace outer wall Hingedly, for the angle between the connecting rod and the drill steel less than 120 °, the melting furnace outer wall is provided with several will be described Connecting rod and drill steel pull to the cross bar of the smelting furnace, and the crossbar end is axially disposed several buckles, the drill steel It is provided with the link for hanging the buckle.Bending structure is formed by connecting rod and drill steel, plug gets lodged in tap hole, cross bar Bending structure is pulled into smelting furnace with buckle, buckle catches on link and locks, so that plug is pressed on tap hole, prevents plug Gap is generated between tap hole, leads to leakage.The utility model is designed reasonably, operating method reduce molten metal founding Security risk in journey.
Detailed description of the invention
Fig. 1 is the smelting furnace tap hole blocking device structural schematic diagram of the utility model.
Fig. 2 is the partial enlarged view in the region Figure 1A.
Description of symbols:
1 --- connecting rod, 2 --- drill steel, 21 --- link, 3 --- plug, 4 --- smelting furnace, 41 --- tap hole, 5 --- cross bar.
Specific embodiment
The utility model is described in further detail in the following with reference to the drawings and specific embodiments, is not that this is practical Novel practical range limited to this.
As depicted in figs. 1 and 2, the smelting furnace tap hole blocking device of the present embodiment, including connecting rod 1 and drill steel 2, it is described 2 one end of drill steel is fixedly connected with 1 end of connecting rod, and the other end is fixedly connected with plug 3, the connecting rod 1 and smelting furnace 4 Outer wall is hinged, and for the angle between the connecting rod 1 and the drill steel 2 less than 120 °, the melting furnace outer wall is provided with several The connecting rod 1 and drill steel 2 are pulled to the cross bar 5 of the smelting furnace 4,5 end of cross bar is axially disposed there are several cards Button 51, the drill steel 2 are provided with the link 21 for hanging the buckle 51.In use, being plugged being put on plug 3, will block up First 3 are placed on tap hole 41 together with plugging, the central axis of plug 3 and the centerline axis parallel of tap hole, the buckle of cross bar 5 51 catch on and fasten on link 21, connecting rod 1 and drill steel 2 are compressed to close to 4 direction of smelting furnace, to make plug 3 that will melt 4 tap hole 41 of furnace blocks consolidation.Several buckles are set in 5 end of cross bar, which buckle 51 can according to circumstances be selected to detain It tightly on link 21, has the gap when between 4 tap hole 41 of smelting furnace and plug 3, when there is leakage, may be selected closer to smelting furnace Buckle 51 be clamped on link 21, thus make plug 3 by tap hole 41 block consolidation.
Angle between the connecting rod 1 and the drill steel 2 is 45 ° ~ 90 °, convenient for cross bar 5 by connecting rod 1 and drill steel 2 to When 4 direction of smelting furnace compresses, pressing force of the enhancing plug 3 to tap hole 41.
The connecting rod 1, the drill steel 2 and the cross bar 5 in the same plane, are convenient for cross bar 5 by connecting rod 1 and drill steel 2 compress to 4 direction of smelting furnace.
The cross bar is 2, and 2 cross bars 5 are symmetrical arranged with the drill steel 2 for center line, enhances drill steel 2 and connection The stability of bar 1 and pulling force to 4 direction of smelting furnace.
The plug 3 is cone, and tap hole 41 is blocked consolidation convenient for plug 3.
The connecting rod 1 and the drill steel 2 are integrally formed, and are conducive to cross bar 5 for connecting rod and drill steel to smelting furnace direction Clamping force passes to plug 3, and tap hole 41 is blocked consolidation.
The plug 3 is made of heat-resisting material, and plug 3 is prevented to be deformed because long-time contacts high temperature solution.
Finally it should be noted that above embodiments are only to illustrate the technical solution of the utility model, rather than to this reality With the limitation of novel protected range, although being explained in detail referring to preferred embodiment to the utility model, this field it is general Lead to it will be appreciated by the skilled person that can be with the technical solution of the present invention is modified or equivalently replaced, without departing from this The spirit and scope of utility model technical solution.

Claims (7)

1. smelting furnace tap hole blocking device, it is characterised in that:Including connecting rod(1)And drill steel(2), the drill steel(2)One end With the connecting rod(1)End is fixedly connected, and the other end is fixedly connected with plug(3), the connecting rod(1)The other end and molten Furnace(4)Outer wall is hinged, the connecting rod(1)With the drill steel(2)Between angle less than 120 °, the smelting furnace(4)Outside Wall is provided with several for the connecting rod(1)And drill steel(2)Pull to the smelting furnace(4)Cross bar(5), the cross bar(5) End is axially disposed several buckles(51), the drill steel(2)It is provided with the link for hanging the buckle(21).
2. smelting furnace tap hole blocking device according to claim 1, it is characterised in that:The connecting rod(1)With it is described Drill steel(2)Between angle be 45 ° ~ 90 °.
3. smelting furnace tap hole blocking device according to claim 1, it is characterised in that:The connecting rod(1), the pricker Bar(2)With the cross bar(5)In the same plane.
4. smelting furnace tap hole blocking device according to claim 1, it is characterised in that:The cross bar(5)It is 2,2 The cross bar(5)With the drill steel(2)It is symmetrical arranged for center line.
5. smelting furnace tap hole blocking device according to claim 1, it is characterised in that:The plug(3)For cone.
6. smelting furnace tap hole blocking device according to claim 1, it is characterised in that:The connecting rod(1)With it is described Drill steel(2)It is integrally formed.
7. smelting furnace tap hole blocking device according to claim 1, it is characterised in that:The plug(3)By high temperature resistant Material is made.
CN201820559176.4U 2018-04-19 2018-04-19 Smelting furnace tap hole blocking device Expired - Fee Related CN208108828U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820559176.4U CN208108828U (en) 2018-04-19 2018-04-19 Smelting furnace tap hole blocking device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820559176.4U CN208108828U (en) 2018-04-19 2018-04-19 Smelting furnace tap hole blocking device

Publications (1)

Publication Number Publication Date
CN208108828U true CN208108828U (en) 2018-11-16

Family

ID=64119171

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820559176.4U Expired - Fee Related CN208108828U (en) 2018-04-19 2018-04-19 Smelting furnace tap hole blocking device

Country Status (1)

Country Link
CN (1) CN208108828U (en)

Similar Documents

Publication Publication Date Title
CN208108828U (en) Smelting furnace tap hole blocking device
CN103567664B (en) Titanium-pipe line steel composite plate welding Ti-Ni welding wire and preparation method thereof
CN105420432B (en) A kind of replacing options of blast furnace cooling stave
CN202717879U (en) Novel polysilicon ingot casting furnace overflow protection device
CN208234968U (en) A kind of aluminium alloy smelting suction iron device
CN107363252A (en) The flow control device and method of Cleanliness of Molten Steel in a kind of raising casting process
CN204108309U (en) The cold steel extractor of steel ladle opening improved
CN109550928A (en) For removing the device of ladle upper nozzle
CN116397076A (en) Ladle externally-mounted bottom blowing brick leakage-proof structure
CN206916252U (en) A kind of overflow monitoring device
CN206680951U (en) A kind of channel protection structure of hydraulic engineering
CN204529890U (en) Quick-action opening blocking-up device before State of Blast Furnace
CN204702793U (en) A kind of gold and silver smelting apparatus
CN211420210U (en) Intermediate frequency furnace slag iron automatic separation device
CN107952951B (en) A kind of induction furnace steel ingot stripper apparatus and its application method
CN203284060U (en) Electrode salvaging device for electric furnace or refined-smelting ladle furnace
CN207026469U (en) The flow control device of Cleanliness of Molten Steel in a kind of raising casting process
CN207567320U (en) A kind of electroslag furnace with high reliability electrode clamping device
CN105967042A (en) Lifting and transporting device for metal solution
CN205904429U (en) Novel middle package forever serves as a contrast structure
CN105397077B (en) Filtering type is subcontracted
CN208378961U (en) A kind of fixture for electroslag furnace consutrode and dummy electrode
CN209275980U (en) A kind of liquid metals ingot casting shaping demoulding sling
CN204999522U (en) Longmen hoist that can protect against radiation hotly
CN209352961U (en) A kind of crystallizer for electroslag refining furnace

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 441700 hujiajing village, economic and Technological Development Zone, Gucheng County, Xiangyang City, Hubei Province (in the Industrial Park)

Patentee after: Hubei New Jinyang Resources Co.,Ltd.

Address before: 441700 hujiajing village, economic and Technological Development Zone, Gucheng County, Xiangyang City, Hubei Province (in the Industrial Park)

Patentee before: HUBEI JINYANG RESOURCES Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181116