CN208055772U - Rail reinforcement device - Google Patents

Rail reinforcement device Download PDF

Info

Publication number
CN208055772U
CN208055772U CN201820465225.8U CN201820465225U CN208055772U CN 208055772 U CN208055772 U CN 208055772U CN 201820465225 U CN201820465225 U CN 201820465225U CN 208055772 U CN208055772 U CN 208055772U
Authority
CN
China
Prior art keywords
rail
lift beam
slideway
horizontal lift
reinforcement device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820465225.8U
Other languages
Chinese (zh)
Inventor
于雷鸣
陈培红
刘丹
于彪
冯明
陶毅
任玉龙
董晓琴
车春利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Sixth Group Co Ltd
China Railway Sixth Group Hohhot Railway Construction Co Ltd
Original Assignee
China Railway Sixth Group Co Ltd
China Railway Sixth Group Hohhot Railway Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixth Group Co Ltd, China Railway Sixth Group Hohhot Railway Construction Co Ltd filed Critical China Railway Sixth Group Co Ltd
Priority to CN201820465225.8U priority Critical patent/CN208055772U/en
Application granted granted Critical
Publication of CN208055772U publication Critical patent/CN208055772U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of rail reinforcement device comprising if being equidistantly set to the dry slide consistent with rail direction with several sleepers that rail length direction is perpendicular, above sleeper below rail, the equidistantly horizontal lift beam of several rolling bars above slideway, transmission above rolling bar, the skate on slideway corresponding with horizontal lift beam precalculated position and sliding into the haulage gear on direction set on slideway.Advantage is:1, it compares crane lifting to set up, the slide-in of the big horizontal lift beam of hand fit's hoist engine progress is easier to grasp erection precision, is not susceptible to position offset, makes whole system uniform force, increases the stability of system;2, it can effectively avoid big machinery construction to both wired security risk, construction safety coefficient is high;3, equipment and materials is common and cheap, and construction cost is low;4, easy to operation, difficulty of construction is low.

Description

Rail reinforcement device
Technical field:
The utility model is related to a kind of bracing means more particularly to a kind of rail reinforcement devices.
Background technology:
With the high speed development of China railways in recent years, railway mileage is increasingly longer, and Business Line construction of railway project also exists Proportion is more and more in construction of railway project.Business Line construction of railway project first has to ensure that traffic safety does not influence again Construction speed, difficulty of construction is high, security risk is big.And in Business Line construction of railways, it is entirely to construct to circuit reinforce The most important thing of journey.
The currently used mode reinforced to circuit mostly uses D type construction beams, horizontal by being set up in support stake Lift beam supports D type construction beam systems, and horizontal lift beam is made to play the role of connection support stake and D type construction beams, by train and Circuit gravity load is transmitted to by horizontal lift beam in support stake, and horizontal lift beam then needs to set up using large-scale hoisting machinery lifting.
But this method has the following disadvantages:1, when large-scale hoisting machinery sets up horizontal lift beam, the more difficult grasp of precision is held Position offset easily occurs, makes whole system discontinuity, influences the stability of system;2, Business Line employs large-scale hoisting machinery It is big to carry out horizontal lift beam underpass road difficulty, security risk is high, easy tos produce security risk;3, Business Line employs large-scale hoisting machinery It needs to block circuit, influences railway transportation;4, track blockade needs multiple unit cooperations, and labor intensive, material resources are larger.
Utility model content:
The rail reinforcement device that the purpose of this utility model is to provide a kind of difficulty of construction is low, safety coefficient is high.
The utility model is implemented by following technical solution:
Rail reinforcement device comprising equidistantly perpendicular with the rail length direction below rail If several sleepers, are equidistantly set on the slideway dry slide consistent with the rail direction above the sleeper Horizontal lift beam that several rolling bars of side, transmission are set to above the rolling bar is set to institute corresponding with the horizontal lift beam precalculated position It states the skate on slideway and slides into the haulage gear on direction set on the slideway.
Further, the sleeper includes channel steel and the solid wood that matches with the channel steel size, and the solid wood passes through spiral shell Nail is fixedly connected with the channel steel.
Further, the haulage gear is hoist engine, and the hoist engine is connect by steel wire rope with the horizontal lift beam.
Further, the slideway slides into direction along the horizontal lift beam and is equipped with along slope.
Further, the gradient on the suitable slope is 1%.
The advantages of the utility model:
1, it compares crane lifting to set up, the slide-in of the big horizontal lift beam of hand fit's hoist engine progress is easier to grasp erection essence Degree, is not susceptible to position offset, makes whole system uniform force, increase the stability of system;2, mainframe can effectively be avoided To both wired security risk, construction safety coefficient is high for tool construction;3, equipment and materials is common and cheap, and construction cost is low; 4, easy to operation, difficulty of construction is low.
Description of the drawings:
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only It is some embodiments of the utility model, for those of ordinary skill in the art, in the premise not made the creative labor Under, other drawings may also be obtained based on these drawings.
Fig. 1 is the structural schematic diagram of the present embodiment;
Fig. 2 is the schematic cross-section of the present embodiment.
In figure:Sleeper 1, channel steel 1-1, solid wood 1-2, slideway 2, rolling bar 3, horizontal lift beam 4, skate 5, haulage gear 6, hoist engine 6-1, steel wire rope 6-2.
Specific implementation mode:
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work The every other embodiment obtained, shall fall within the protection scope of the present invention.
Embodiment 1:
Rail reinforcement device as shown in Figure 1 and Figure 2 comprising be equidistantly set to below rail and rail length If the perpendicular several sleepers 1 in direction, are equidistantly set to slideway at the dry slide 2 consistent with rail direction above sleeper 1 Several rolling bars 3 of 2 tops, transmission are set to the horizontal lift beam 4 of 3 top of rolling bar, are set to slideway corresponding with horizontal 4 precalculated position of lift beam Skate 5 on 2 and the haulage gear 6 on the slide-in of slideway 2 direction, ensure haulage gear 6 with slideway 2 in same straight line On, it avoids that deviation phenomenon occurs in distraction procedure;Skate 5 limits horizontal lift beam 4, and it is predetermined to can avoid the horizontal arrival of lift beam 4 It behind position, continues to move along under the action of inertia, ensures that horizontal lift beam 4 is accurate in place.
Sleeper 1 includes channel steel 1-1 and the solid wood 1-2 to match with channel steel 1-1 sizes, and solid wood 1-2 passes through screw and channel steel 1-1 is fixedly connected.
Haulage gear 6 is hoist engine 6-1, and hoist engine 6-1 connect by steel wire rope 6-2 with horizontal lift beam 4, in the present embodiment A pulley is placed on steel wire rope 6-2, single-strand rope 6-2 is become bifilar, hauling speed can be become to original half, is protected Horizontal 4 uniform speed slow of lift beam is demonstrate,proved to advance.
Slideway 2 slides into direction along horizontal lift beam 4 and is equipped with along slope, and the gradient along slope is 1%, and horizontal lift beam 4 is made to slide into precalculated position It is more smoothly.
It is coated with lubricant on slideway 2, reduces the frictional force between slideway 2 and rolling bar 3, it is easier to draw.
In the present embodiment, the spacing between adjacent rail sleepers 1 is 60cm.
When the present embodiment is in use, it needs that horizontal lift beam 4 is put into rolling just first with crane, then passes through hoist engine 6-1 Horizontal lift beam 4 is drawn to precalculated position, it, can be by the drag velocity of control hoist engine 6-1, to ensure horizontal lift in distraction procedure 4 uniform speed slow of beam advances;Horizontal lift beam 4 is jacked up using jack after reaching precalculated position, puts horizontal lift beam 4 after withdrawing from rolling bar 3 It is lower.Depending on the horizontal spacing lifted between 4 top of beam and rail foot is according to D type construction beam operation instructions.
The above is only the preferred embodiment of the utility model only, is not intended to limit the utility model, all at this Within the spirit and principle of utility model, any modification, equivalent replacement, improvement and so on should be included in the utility model Protection domain within.

Claims (5)

1. rail reinforcement device, which is characterized in that it include equidistantly below the rail with the rail length side If dry slide consistent with the rail direction to perpendicular several sleepers, above the sleeper is equidistantly set to Horizontal lift beam that several rolling bars above the slideway, transmission are set to above the rolling bar is set to and the horizontal lift beam precalculated position Skate on the corresponding slideway and the haulage gear on slideway slide-in direction.
2. rail reinforcement device according to claim 1, which is characterized in that the sleeper include channel steel and with it is described The solid wood that channel steel size matches, the solid wood are fixedly connected by screw with the channel steel.
3. rail reinforcement device according to claim 1, which is characterized in that the haulage gear is hoist engine, institute Hoist engine is stated to connect with the horizontal lift beam by steel wire rope.
4. rail reinforcement device according to claim 1, which is characterized in that the slideway slides into along the horizontal lift beam Direction is equipped with along slope.
5. rail reinforcement device according to claim 4, which is characterized in that the gradient on the suitable slope is 1%.
CN201820465225.8U 2018-03-30 2018-03-30 Rail reinforcement device Expired - Fee Related CN208055772U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820465225.8U CN208055772U (en) 2018-03-30 2018-03-30 Rail reinforcement device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820465225.8U CN208055772U (en) 2018-03-30 2018-03-30 Rail reinforcement device

Publications (1)

Publication Number Publication Date
CN208055772U true CN208055772U (en) 2018-11-06

Family

ID=63988113

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820465225.8U Expired - Fee Related CN208055772U (en) 2018-03-30 2018-03-30 Rail reinforcement device

Country Status (1)

Country Link
CN (1) CN208055772U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258210A (en) * 2019-06-18 2019-09-20 中铁六局集团有限公司 A kind of track strengthening is with wearing I-steel guide device and its operating method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110258210A (en) * 2019-06-18 2019-09-20 中铁六局集团有限公司 A kind of track strengthening is with wearing I-steel guide device and its operating method
CN110258210B (en) * 2019-06-18 2024-03-12 中铁六局集团有限公司 I-steel penetrating guide device for line reinforcement and operation method thereof

Similar Documents

Publication Publication Date Title
CN101418542B (en) Cable system construction method of spatial self-anchored rope-suspension bridge
CN103669216A (en) Steel box girder scattered-splicing sliding device and installation method
CN102359069A (en) Existing line reinforcing method in under-crossing railway frame bridge small-included angle large-height inclined jacking construction
CN203855866U (en) Large-span frame bridge overhead roof with beams convenient to construct
CN103669215B (en) Vertical-horizontal overall-sliding type side mold of fulcrum-few support
CN201825671U (en) Hoisting trolley for track plate
CN105152032A (en) Installing method for bridge crane in enclosed environment workshop
CN206680871U (en) Boom device is transported on a kind of four rail beams
CN105484162B (en) Suspension bridge construction stiff girder secondary on the bank swings moving device and method
CN205223872U (en) Drag and hang novel string of basket structure of convolution
CN205152788U (en) But telescopic bridge testing platform of antihunting
CN201506952U (en) Temporary cable matched hanging basket building concrete cable stayed bridge without supporting frame
CN208088097U (en) A kind of three-tower suspension bridge erection of main beam constructing structure
CN204753406U (en) Basket is hung with double track from anchor formula rhombus to passenger dedicated line construction
CN102190249B (en) Method for hoisting equipment positioned at bottom of multilayer frame platform
CN203452009U (en) Self-walking device for mounting steel beam
CN208055772U (en) Rail reinforcement device
CN202148493U (en) Existing line reinforcing device in inclined jacking construction of penetrating railway frame bridge from the lower part with small incline angle and large height
CN208965416U (en) A kind of safeguard structure of large span frame bridge jack-in process existing railway
CN201712610U (en) Beam transportation flat machine
CN206956533U (en) A kind of railway and the horizontal multiple bay frame pier of track traffic
CN104929000A (en) Sectional railway track laying machine set and assembling method thereof
CN206329024U (en) Hanging large-span steel-reinforced concrete structure construction steel platform
CN105603882A (en) Continuous beam mid-span closure construction method achieving uninterrupted power of contact line and structure of method
CN205355673U (en) High -speed railway of not stopping transport across device's span beam rotary mechanism

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181106