CN208010412U - The bypath system of double reheat Turbo-generator Set - Google Patents

The bypath system of double reheat Turbo-generator Set Download PDF

Info

Publication number
CN208010412U
CN208010412U CN201721817368.2U CN201721817368U CN208010412U CN 208010412 U CN208010412 U CN 208010412U CN 201721817368 U CN201721817368 U CN 201721817368U CN 208010412 U CN208010412 U CN 208010412U
Authority
CN
China
Prior art keywords
high pressure
pipeline
double reheat
generator set
cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721817368.2U
Other languages
Chinese (zh)
Inventor
唐丽丽
王建伟
王鑫
田志强
翟璇
王娟
胥睿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DEC Dongfang Turbine Co Ltd
Original Assignee
DEC Dongfang Turbine Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DEC Dongfang Turbine Co Ltd filed Critical DEC Dongfang Turbine Co Ltd
Priority to CN201721817368.2U priority Critical patent/CN208010412U/en
Application granted granted Critical
Publication of CN208010412U publication Critical patent/CN208010412U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Control Of Turbines (AREA)

Abstract

The utility model discloses a kind of bypath systems applied to double reheat Turbo-generator Set, and for existing double reheat bypath system pipeline complexity, cost is higher, controls complicated problem, has invented a kind of succinct bypath system.The system includes extra high pressure steam bypass conduit and high steam bypass conduit, the super-pressure bypass conduit is drawn from the pipeline before ultra-high pressure cylinder main inlet throttle-stop valve, the gland steam exhauster for introducing ultra-high pressure cylinder, makes the extra high pressure steam from boiler partly or entirely be discharged into single reheat device;The high pressure turbine by pipeline is drawn from the pipeline before high pressure cylinder gate, introduces condenser, the high steam from single reheat device is made partly or entirely to be discharged into condenser.The system simplifies structure, reduces the manufacturing cost and operating cost of unit under the premise of meeting bypass basic function and performance.

Description

The bypath system of double reheat Turbo-generator Set
Technical field
The utility model is related to the bypath system of Turbo-generator Set, specifically a kind of double reheat Turbo-generator Set Bypath system.
Background technology
Turbo-generator Set is needed through bypath system in special operation conditions such as startup, shutdown, removal of loads by vapor portion Or all lay down, to maintain system thermodynamic equilibrium, ensure unit safety.
Currently, once reheating, two class type of double reheat, their bypath system structure are poor for powerful fired power generating unit Different very big, the bypath system of single reheat unit is fairly simple, only level-one bypass conduit, and bypass duct one end is from steam turbine high pressure It is picked out on pipeline before main inlet throttle-stop valve, the other end accesses condenser, and the high steam from boiler is directly unloaded toward condenser.By this The function of road system is to improve unit starting performance:Main vapour pressure can be controlled in unit starting, with adapt to unit level pressure or The requirement of sliding pressure operation is shortened and starts the time;Recovered steam avoids medium-loss;In load rejection, boiler also can guarantee In hot stand-by duty, quickly to open machine.
The bypath system of double reheat power generation sets is then more complicated, shares three-level, as shown in Figure 1 and Figure 2, first order bypass System is to unload extra high pressure steam toward single reheat device, and second level bypath system is to unload the high steam after single reheat toward two Secondary reheater, third level bypath system are to unload the middle pressure steam after double reheat toward condenser.The original intention of this structure design, It is in order to protect first and second reheater, because in the unit starting stage, if as single reheat unit, only setting by level-one Road, steam directly unload past condenser, will not have working medium in reheater, dry combustion method situation occur, it is dry that three-level bypass can avoid reheater It burns.But the disadvantage is that bypass series is more, shunt valve Taoist priest is complicated, installation trouble, and Steam Parameters For Extra-supercritical Units Height, tubing material require very high, price, complicated bypath system to keep power plant's initial investment big, and maintenance cost is high.
However, with the progress of material technology, boiler reheater has used more excellent heat resisting steel, the temperature allowable of material The fire box temperature at position where degree is far above reheater, although the steam parameter of double reheat power generation sets is than single reheat unit Height, fire box temperature is also higher than the fire box temperature of single reheat unit, but still within the allowable temperature of reheater material, reheating Device can still bear dry combustion method.That is, after material update, it is limited to traditional concept, double reheat power generation sets is still designed as three Grade bypath system is excessively complicated, it is not necessary that, it can simplify.
Double reheat Turbo-generator Set it is efficient, the U.S. has just put into operation the first in the world platform ultra supercritical early in nineteen fifty-seven Double reheat fired power generating unit, but because of double reheat power generation sets system complex, involve great expense, and the cost of fuel was cheaper at that time, Power plant is still willing to that single reheat unit, double reheat fired power generating unit is selected not to be promoted rapidly.With the rising of fuel price, state Exhaust gas discharge limitation is increasingly stringenter on border, and double reheat power generation sets have returned to the visual field of people again, becomes current main Type is widely used.How to simplify the structure of double reheat power generation sets, reduce manufacture, operating cost, is that the unit promotes and applies Problem to be solved.
Invention content
The purpose of this utility model is that the redundant configuration of the bypath system of Double reheat steam turbine system is reduced, with letter Change ultra supercritical double reheat power generation sets structure, reduces manufacture, operating cost, a kind of side applied to Double reheat steam turbine is provided Road system.
The technical solution of the utility model is:
A kind of bypath system of double reheat Turbo-generator Set, which is characterized in that the system includes super-pressure shunt valve Road(Extra high pressure steam bypass conduit)With high pressure turbine by pipeline(High steam bypass conduit), the super-pressure bypass conduit is from super Drawn on pipeline before high pressure cylinder main inlet throttle-stop valve, introduce the gland steam exhauster of ultra-high pressure cylinder, make extra high pressure steam part from boiler or All it is discharged into single reheat device;The high pressure turbine by pipeline is drawn from the pipeline before high pressure cylinder gate, introduces condenser, makes to come It is partly or entirely discharged into condenser from the high steam of single reheat device.
Steam flow control valve is equipped in the super-pressure bypass conduit.
Further, pressure reducing valve, cooling valve and water spray isolating valve are additionally provided in the super-pressure bypass conduit.
Steam flow control valve is equipped in the high pressure turbine by pipeline.
Further, pressure reducing valve, desuperheat valve and water spray isolating valve are additionally provided in the high pressure turbine by pipeline.
The capacity of the super-pressure bypass conduit is 30%~100%BMCR, and the capacity of high pressure turbine by pipeline is 30%~100% BMCR。
The double reheat Turbo-generator Set includes ultra-high pressure cylinder, high pressure cylinder, intermediate pressure cylinder, low pressure (LP) cylinder and condenser, In, high pressure cylinder, intermediate pressure cylinder is cylinder combined structures or divide cylinder structure.
The beneficial effects of the utility model:
Under the premise of keeping bypath system basic function and performance, redundant configuration is reduced, bypath system is simplified Structure, to reduce the manufacturing cost and operating cost of double reheat power generation sets.
Description of the drawings
Fig. 1 is the bypath system figure of high, the middle pressure combined cylinder turbine of existing double reheat
Fig. 2 is the bypath system figure that existing double reheat is high, middle pressure divides cylinder unit
Fig. 3 is the bypath system figure of high, the middle pressure combined cylinder turbine of the utility model double reheat
Fig. 4 is the bypath system figure that the utility model double reheat is high, middle pressure divides cylinder unit
Code name meaning in figure:1-ultra-high pressure cylinder, 2-high pressure cylinders, 3-intermediate pressure cylinders, 4-low pressure (LP) cylinders, 5-generators, 6- Condenser, 7-boilers, 8-steam flow control valves(Super-pressure bypass valve), 9-super-pressure bypass conduits, 10-steam flows Regulating valve(High pressure bypass valve), 11-high pressure turbine by pipelines.
Specific implementation mode
Embodiment one
Referring to Fig. 3:It is the bypath system figure of high, the middle pressure combined cylinder turbine of the utility model double reheat, unit includes superelevation Cylinder pressure 1, high pressure cylinder 2, intermediate pressure cylinder 3, low pressure (LP) cylinder 4, generator 5, condenser 6, boiler 7.Wherein, high pressure cylinder 2, intermediate pressure cylinder 3 are to close Cylinder structure.
The bypath system of the unit is total to two-stage, and first order super-pressure bypath system pipeline 9 is before 1 main inlet throttle-stop valve of ultra-high pressure cylinder It is drawn on pipeline, introduces the gland steam exhauster of ultra-high pressure cylinder 1, which is equipped with steam flow control valve 8, is steamed for adjusting bypass Steam flow amount makes the extra high pressure steam from boiler partly or entirely be discharged into the single reheat device of boiler 7;It is additionally provided on the pipeline 9 Pressure reducing valve, cooling valve, water spray isolating valve(It is not shown in figure), with mitigate super-pressure reject steam to the temperature of single reheat device, Compression shock.
Second level hp by-pass system pipeline 11 is drawn from the pipeline before 2 porthole of high pressure cylinder, introduces condenser 6, the pipe Road 11 is equipped with steam flow control valve 10 makes the high steam portion from single reheat device for adjusting reject steam flow Divide or be all discharged into condenser 6, pressure reducing valve, cooling valve, water spray isolating valve are additionally provided on the pipeline 11(It is not shown in figure), to subtract Temperature of the light high pressure turbine by steam to condenser 6, compression shock.
The capacity of super-pressure bypass conduit is 30%~100%BMCR, and the capacity of high pressure turbine by pipeline is 30%~100% BMCR。
Embodiment two
Referring to Fig. 4:It is the bypath system figure that the utility model double reheat is high, middle pressure divides cylinder unit, unit includes superelevation Cylinder pressure 1, high pressure cylinder 2, intermediate pressure cylinder 3, low pressure (LP) cylinder 4, generator 5, condenser 6, boiler 7.Wherein, high pressure cylinder 2, intermediate pressure cylinder 3 are point Cylinder structure.
The bypath system of the unit is total to two-stage, and first order super-pressure bypath system pipeline 9 is before 1 main inlet throttle-stop valve of ultra-high pressure cylinder It is drawn on pipeline, introduces the gland steam exhauster of ultra-high pressure cylinder 1, which is equipped with steam flow control valve 8, is steamed for adjusting bypass Steam flow amount makes the extra high pressure steam from boiler partly or entirely be discharged into the single reheat device of boiler 7;It is additionally provided on the pipeline 9 Pressure reducing valve, cooling valve, water spray isolating valve(It is not shown in figure), with mitigate super-pressure reject steam to the temperature of single reheat device, Compression shock.
Second level hp by-pass system pipeline 11 is drawn from the pipeline before 2 porthole of high pressure cylinder, introduces condenser 6, the pipe Road 11 is equipped with steam flow control valve 10 makes the high steam portion from single reheat device for adjusting reject steam flow Divide or be all discharged into condenser 6, pressure reducing valve, cooling valve, water spray isolating valve are additionally provided on the pipeline 11(It is not shown in figure), to subtract Temperature of the light high pressure turbine by steam to condenser 6, compression shock.
The capacity of super-pressure bypass conduit is 30%~100%BMCR, and the capacity of high pressure turbine by pipeline is 30%~100% BMCR。

Claims (7)

1. a kind of bypath system of double reheat Turbo-generator Set, which is characterized in that the system includes super-pressure bypass conduit With high pressure turbine by pipeline, the super-pressure bypass conduit is drawn from the pipeline before ultra-high pressure cylinder main inlet throttle-stop valve, introduces ultra-high pressure cylinder Gland steam exhauster, the high pressure turbine by pipeline draws from the pipeline before high pressure cylinder gate, introduces condenser.
2. the bypath system of double reheat Turbo-generator Set as described in claim 1, which is characterized in that by the super-pressure Steam flow control valve is equipped in the pipeline of road.
3. the bypath system of double reheat Turbo-generator Set as claimed in claim 2, which is characterized in that by the super-pressure Pressure reducing valve, cooling valve and water spray isolating valve are additionally provided in the pipeline of road.
4. the bypath system of double reheat Turbo-generator Set as described in claim 1, which is characterized in that the high pressure turbine by Steam flow control valve is equipped in pipeline.
5. the bypath system of double reheat Turbo-generator Set as claimed in claim 4, which is characterized in that the high pressure turbine by Pressure reducing valve, desuperheat valve and water spray isolating valve are additionally provided in pipeline.
6. the bypath system of double reheat Turbo-generator Set as described in claim 1, which is characterized in that by the super-pressure The capacity of road pipeline is 30%~100%BMCR, and the capacity of high pressure turbine by pipeline is 30%~100%BMCR.
7. the bypath system of double reheat Turbo-generator Set as described in claim 1, which is characterized in that the double reheat Turbo-generator Set includes ultra-high pressure cylinder, high pressure cylinder, intermediate pressure cylinder, low pressure (LP) cylinder and condenser, wherein high pressure cylinder, intermediate pressure cylinder are to close Cylinder structure divides cylinder structure.
CN201721817368.2U 2017-12-22 2017-12-22 The bypath system of double reheat Turbo-generator Set Active CN208010412U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721817368.2U CN208010412U (en) 2017-12-22 2017-12-22 The bypath system of double reheat Turbo-generator Set

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721817368.2U CN208010412U (en) 2017-12-22 2017-12-22 The bypath system of double reheat Turbo-generator Set

Publications (1)

Publication Number Publication Date
CN208010412U true CN208010412U (en) 2018-10-26

Family

ID=63880857

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721817368.2U Active CN208010412U (en) 2017-12-22 2017-12-22 The bypath system of double reheat Turbo-generator Set

Country Status (1)

Country Link
CN (1) CN208010412U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109630221A (en) * 2018-11-30 2019-04-16 东方电气集团东方汽轮机有限公司 A kind of double reheat power generation sets system and method suitable for depth peak regulation
CN114991894A (en) * 2022-04-27 2022-09-02 东方电气集团东方汽轮机有限公司 Turbine system with high load rate at full operation section of limited volume working medium and operation method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109630221A (en) * 2018-11-30 2019-04-16 东方电气集团东方汽轮机有限公司 A kind of double reheat power generation sets system and method suitable for depth peak regulation
CN114991894A (en) * 2022-04-27 2022-09-02 东方电气集团东方汽轮机有限公司 Turbine system with high load rate at full operation section of limited volume working medium and operation method
CN114991894B (en) * 2022-04-27 2023-07-04 东方电气集团东方汽轮机有限公司 Turbine system with limited volume working medium full-operation section and high load rate and operation method

Similar Documents

Publication Publication Date Title
CN108643980A (en) Ultra-high pressure cylinder and high intermediate pressure cylinder carry the double reheat power generation sets of additional backheat grade
CN104806308B (en) A kind of prioritization scheme of ultra supercritical double reheat power generation sets
JP6067535B2 (en) Steam turbine plant start-up method
CN104454038B (en) Double reheat steam turbine start up system and Starting mode
CN110056853A (en) Boiler thermodynamic system and its control method
EP2698507B1 (en) System and method for temperature control of reheated steam
RU2070293C1 (en) Method of operation of steam turbine plant and steam turbine plant for realization of this method
CN204283513U (en) Double reheat steam turbine start up system
CN104533554B (en) A kind of new and effective water supply heat back system for single reheat unit
CN208010412U (en) The bypath system of double reheat Turbo-generator Set
CN104061027B (en) The high temperature steam-extracting cooling system of Double reheat steam turbine thermodynamic system
CN205332246U (en) Direct current stove steady voltage blowpipe system
CN203499735U (en) Combined cycle co-generation system
JP2012102711A (en) Temperature reducing device steam heat recovery facilities
CN205172657U (en) Double reheat ultra supercritical unit by transformation of subcritical coal -fired generating set
CN104456519B (en) A kind of new and effective water supply heat back system for double reheat power generation sets
CN207920680U (en) The bypath system of double reheat Turbo-generator Set
CN206755145U (en) Turbine high-pressure bypasses desuperheat water lines
CN211174241U (en) Heat recovery coke oven waste heat power generation system based on main pipe system
JPH05248604A (en) Waste heat recovery boiler
CN105298564B (en) Secondary reheating ultra-supercritical unit improved through subcritical coal-fired power generation unit
CN203978523U (en) The high temperature steam-extracting cooling system of Double reheat steam turbine thermodynamic system
JP7066572B2 (en) Temporary piping system for boiler blow-out and boiler blow-out method
RU120144U1 (en) POWER UNIT WITH THE UNITED STOP-CONTROL VALVE ON THE LINES OF STEAM CONDITION TO THE STEAM TURBINE AND WITH THE STOP VALVES ON THE LINES OF STEAM DISCHARGE TO THE CONDENSER
CN112082147A (en) Low-pressure superheater system of waste heat boiler