CN208008327U - A kind of erecting by overhang based on logistics storehouse support platform - Google Patents
A kind of erecting by overhang based on logistics storehouse support platform Download PDFInfo
- Publication number
- CN208008327U CN208008327U CN201820318741.8U CN201820318741U CN208008327U CN 208008327 U CN208008327 U CN 208008327U CN 201820318741 U CN201820318741 U CN 201820318741U CN 208008327 U CN208008327 U CN 208008327U
- Authority
- CN
- China
- Prior art keywords
- girder
- profile steel
- nut
- erecting
- plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Leg Units, Guards, And Driving Tracks Of Cranes (AREA)
Abstract
The utility model discloses a kind of erectings by overhang based on logistics storehouse support platform, including girder, the track girder being connected on girder, track girder is the H profile steel that open end is respectively facing the left and right sides, the bottom surface of H profile steel is provided with the extension extended to both sides, mounting plate is arranged in the bottom surface of the strength plates being both provided at left and right sides of H profile steel above extension, H profile steel;Mounting plate bottom is fixedly connected with pendant, and cavity is opened up inside pendant, and backing plate is arranged in cavity inside, and screw mandrel top is located in cavity, lead screw bottom end is extended to across backing plate below pendant;It is provided with the tapped through hole passed through for the lead screw on backing plate, the first nut, the second nut are arranged on lead screw, the first nut is located at pendant bottom, and the second nut is located above backing plate.The utility model is embodied as Material Flow platform and provides a kind of dedicated hoisting structure, to reduce the purpose that cost simplifies structure to solve the problems, such as to use gantry crane to carry out the handling at Material Flow platform in the prior art.
Description
Technical field
The utility model is related to logistic storage fields, and in particular to a kind of hanging dress based on logistics storehouse support platform
It sets.
Background technology
Logistic storage is exactly to utilize self-built or lease storehouse, place, storage, keeping, handling, dispatching cargo.Storage
It is an important component of modern logistics, is played a crucial role in logistics system, is manufacturer's research and planning
Emphasis.Efficient and rational storage can help manufacturer accelerate goods and materials flowing speed, reduce cost, ensure production it is smooth into
Row, and may be implemented that resource is effectively controlled and managed.The development experience of storage different period of history and stage, from original
Artificial storage intelligent storage till now, the efficiency of the support by various new and high technologies to storage, storage obtained substantially
The raising of degree.With the fast development of Electronic Commerce in China, logistics storage dispensing service already becomes China E-Commerce Business the most
The industry link of core, therefore logistics storage dispensing etc. also becomes the most important thing of industry development.In the prior art, in order to carry
To the space availability ratio in warehouse, newly-built storage structures mostly starts, toward aerial development, to be in particular in and build various forms height
Material Flow platform, hanging raising structure carries out vertical transfer to cargo accordingly need to set for this.However, the prior art
In be mostly using existing gantry crane structure in warehouse workshop, or be individually for Material Flow platform configuration gantry crane structure into
Row lifting, it is not only complicated, cost is higher, but also aerial hanging structure inside storehouse can be caused excessively complicated, it is very inconvenient
In fast operating and use.
Utility model content
It is existing to solve the purpose of this utility model is to provide a kind of erecting by overhang based on logistics storehouse support platform
It is a kind of special to be embodied as the offer of Material Flow platform for the problem of carrying out the handling at Material Flow platform using gantry crane in technology
Hoisting structure, with reduce cost simplify structure purpose.
The utility model is achieved through the following technical solutions:
A kind of erecting by overhang based on logistics storehouse support platform, including girder, the track girder being connected on girder are described
Track girder is the H profile steel that open end is respectively facing the left and right sides, and the bottom surface of the H profile steel is provided with the extension extended to both sides
Portion, the strength plates being both provided at left and right sides of the H profile steel above extension, the bottom surface setting installation of the H profile steel
Plate, the strength plates, extension, mounting plate pass through bolt and are attached;The mounting plate bottom is fixedly connected with extension
Part opens up cavity inside the pendant, and backing plate is arranged in the cavity inside bottom surface, further includes lead screw, the top position of the lead screw
In in cavity, the bottom end of lead screw extends to across backing plate below pendant;It is provided on the backing plate and passes through for the lead screw
Tapped through hole is arranged the first nut, the second nut on the lead screw, and first nut is located at pendant bottom, second spiral shell
Mother is located above backing plate.
For in the prior art without for Material Flow platform Special-purpose hanger hang it is standby, can only use gantry crane carry out object
The problem of flowing the lifting of support platform, the utility model proposes a kind of erecting by overhang based on logistics storehouse support platform,
Track girder is connected on girder, and track girder uses H profile steel, structure very simple that can greatly reduce production and installation cost,
With very high economic value.Wherein track girder is the H profile steel that open end is respectively facing the left and right sides, and H profile steel bottom is by prolonging
Extending portion extends outwardly, therefore the lower surface of H profile steel is wider, consequently facilitating installation strength plate, installation station is provided for strength plates.Cause
This, strength plates are located at the top of H profile steel bottom surface, and mounting plate is located at the lower section of H profile steel bottom surface, passes through screw bolt passes intensity
Plate, extension, mounting plate realize being stably connected between H profile steel and mounting plate.Strength plates and mounting plate are equal in the utility model
The anti-of H profile steel entirety can be greatly improved by the reinforcement of upper and lower both sides in intensity for improving H profile steel lower surface and carrying
Tensile strength, to improve the lifted load of the utility model entirety.Mounting plate bottom is fixedly connected with pendant, and sky is opened up inside pendant
Chamber, the cavity inside bottom surface setting backing plate avoid pendant from being worn by lead screw and the second nut for being protected to pendant
Failure.Lead screw sequentially passes through the tapped through hole on backing plate out of cavity, is extended downwardly across pendant lower surface, existing for connecting
Lifting derricking gear in technology.Since the utility model does not lead existing lifting derricking gear such as electric block, lifting
Chain etc. is improved, therefore and is not claimed.Lead screw is fixed by the first nut, convenient for adjusting silk outside pendant
Relative distance between bar and pendant;And the second nut is located at cavity inside, for limiting backing plate and being suppressed, avoids padding
Plate is rotated with lead screw, and backing plate is also avoided to loosen the displacement for causing lead screw, to greatly improve the use of the utility model
Stability and safety.The utility model is simple in structure, cheap, is mounted on the top girder of Material Flow platform in warehouse
On, when use, need to only connect derricking gear on lead screw, you can realize the vertical lifting at Material Flow platform, no longer need to install
The structure of gantry crane bulky complex is installed gantry crane there are no two track girders being mutually parallel are needed, it is only necessary to a track
The installation to entire hanging structure can be realized in beam, greatly simplifies mounting structure, reduces installation requirements, is conducive to simultaneously
The case where simplifying the aerial hanging structure inside storehouse, excessive gantry crane is avoided to interfere with each other occurs, and improves operation convenience.
Preferably, the extension is integrally formed with H profile steel.Ensure the structural integrity between extension and H profile steel, from
And the stabilization and the degree of reliability connected to pendant is improved, improve the safety in utilization of the utility model.
Preferably, the backing plate is the carbide alloy board of 5~10mm of thickness.Backing plate in cavity inside for a long time by lead screw and
The abrasion of second nut, once backing plate fails, abrasion extends on pendant ontology, i.e., pendant can be caused impaired so that this structure
Security risk increases suddenly, therefore preferred backing plate is the carbide alloy board of 5~10mm thickness in this programme, greatly improves the wear-resisting of backing plate
Performance reduces the security risk during the utility model use, prolongs the service life.
Preferably, further include the third nut being set on lead screw, the third nut is located in cavity, third nut position
Above the second nut.By the way that third nut to be tightened in the top of the second nut, foot is also provided for the upper surface of the second nut
Enough big frictional resistance, so that the lower surface of the second nut is held out against with backing plate, the upper surface of the second nut and third nut
It holds out against so that the second nut structure is securely difficult to generate loosening or shaking, so that it is guaranteed that limit and pressure of second nut to backing plate
System is all powerful enough, and the structural stability and stability in use of the utility model are improved with this, further increases the utility model
Service life, reduce frequency of maintenance.
Preferably, the H profile steel and the connection structure of girder are:End of main beam side anchors the first hanging plate, the first hanging plate
Outside is fixedly connected with loading plate, is connected at the top of the bottom bearing plate and H profile steel, is contacted with girder lower surface at the top of H profile steel.This
A kind of preferred connection type between the H profile steel and girder as track girder is given in scheme, is exposed to suitable for end outer
Main beam structure use, specially the side of end of main beam anchor the first hanging plate, by being held with what the first hanging plate was fixedly connected
Support plate so that connect at the top of loading plate and H profile steel, to realize being stably connected between H profile steel and girder by loading plate.This
Scheme the end of girder carry out with the connection of H profile steel, when use, only need to be at girder both ends respectively with H profile steel according to this programme
In structure be attached, you can be mounted on what H profile steel was stablized below girder by the principles of 2 boning out, to realize
Simply to the connection of H profile steel, the fixed form compared to traditional track girder complexity can greatly simplify installation procedure, and
And through testing, tensile strength of the H profile steel in girder lower part remains unchanged substantially compared to existing track beam structure in this programme.
Preferably, further include the first spring being connected at the top of H profile steel between the first hanging plate bottom, first spring
In tensional state.By the reset force of the first spring in tensional state, upward pulling force is provided always for H profile steel, with
This bearing down for overcoming the utility model suffered during lifting so that H profile steel keep during the work time as far as possible with
The contact of girder lower surface reduces the issuable deformation of H profile steel, improves the stability of H profile steel.Meanwhile passing through the first spring
Presence, can also effectively buffer the slight vibrations of H profile steel caused by cargo gravity during lifting, play excellent damping effect
Fruit, to further increase safety coefficient.
Preferably, the H profile steel and the connection structure of girder are:Girder lower surface anchors the second hanging plate, the second hanging plate bottom
Hard alloy blocks facing each other are fixed at the top of portion, H profile steel, are consolidated by I-steel between opposite two pieces of hard alloy blocks
Fixed connection.This programme is suitable for the uses such as the enough workshop storehouses of height, the second hanging plate is anchored to the lower surface of girder, therefore
For being not exposed to outer girder for end, the simple connection to H profile steel can be also carried out, to the applicable model with bigger
It encloses.It is connected with hard alloy blocks, I-steel, hard alloy blocks between second hanging plate and H profile steel in turn from top to bottom, passes through two pieces
Hard alloy blocks ensure tensile strength, are carried out with length by I-steel, and the storehouse to meet different floor heights is installed, while I-steel
It is arranged between two pieces of hard alloy blocks, in contrast can plays the function of flexible connection, improve the overall flexibility of this structure
With torsional property.
Preferably, the hard alloy blocks are in hollow tubulose.Tubular structure has better yield strength, compared to pure
Solid structure can preferably resist micro plastic deformation, simultaneously because tubular structure be also by cemented carbide material make and
At, therefore remain able to ensure excellent tensile property, further increase the safety coefficient of the utility model.
Preferably, second spring is set in the hard alloy blocks, one end of the second spring is fixed on I-steel,
The other end is fixed on girder lower surface or H profile steel upper surface, and the second spring is in tensional state.It is for being located at I-shaped
For hard alloy blocks above steel, one end of internal second spring is fixed on the upper surface of I-steel, the other end is fixed on
The lower surface of girder;For the hard alloy blocks below I-steel, one end of internal second spring is fixed on work
The lower surface of word steel, the other end are fixed on the upper surface of H profile steel.Two second springs are preferably axis collinear so that two
The active force of two springs can be completely superimposed, and the vibrations that H profile steel is subject in the longitudinal direction can be quickly by two the second bullets
Spring is offset, and is played excellent cushioning effect, while the second spring that can also be in tensional state by two, is H profile steel
Always upward pulling force is provided, with the bearing down that this overcomes the utility model suffered during lifting, reducing H profile steel may
The deformation of generation improves the stability of H profile steel.
The utility model compared with prior art, has the following advantages and advantages:
A kind of erecting by overhang based on logistics storehouse support platform of the utility model, it is simple in structure, cheap, it is mounted on
In warehouse on the top girder of Material Flow platform, when use, need to only connect derricking gear on lead screw, you can realize logistics branch
The vertical lifting at platform is supportted, the structure of installation gantry crane bulky complex is no longer needed to, there are no need two track girders being mutually parallel
Gantry crane is installed, it is only necessary to which the installation to entire hanging structure can be realized in a track girder, greatly simplifies installation
Structure reduces installation requirements, while being conducive to simplify the aerial hanging structure inside storehouse, avoids excessive gantry crane mutual
The case where interference, occurs, and improves operation convenience.
Description of the drawings
Attached drawing described herein is used for providing further understanding the utility model embodiment, constitutes the one of the application
Part does not constitute the restriction to the utility model embodiment.In the accompanying drawings:
Fig. 1 is the structural schematic diagram of the utility model specific embodiment 1;
Fig. 2 is the connection diagram of the utility model specific embodiment 2;
Connection side views of the Fig. 3 between 2 middle girder of the utility model specific embodiment and H profile steel;
Fig. 4 is the connection diagram of the utility model specific embodiment 3.
Label and corresponding parts title in attached drawing:
1- girders, 2-H shaped steel, 3- extensions, 4- strength plates, 5- mounting plates, 6- pendants, 7- cavitys, 8- backing plates, 9-
Bar, the first nuts of 10-, the second nuts of 11-, 12- third nuts, the first hanging plates of 13-, 14- loading plates, the first springs of 15-, 16-
Second hanging plate, 17- hard alloy blocks, 18- I-steel, 19- second springs.
Specific implementation mode
To make the purpose of this utility model, technical solution and advantage be more clearly understood, with reference to embodiment and attached drawing,
The utility model is described in further detail, and the exemplary embodiment and its explanation of the utility model are only used for explaining this
Utility model is not intended to limit the scope of the present invention.
Embodiment 1:
A kind of erecting by overhang based on logistics storehouse support platform as shown in Figure 1, including girder, are connected on girder
Track girder, the track girder are the H profile steel 2 that open end is respectively facing the left and right sides, and the bottom surface of the H profile steel 2 is provided with to two
The extension 3 that side extends, the left and right sides of the H profile steel 2 is both provided with the strength plates 4 above extension 3, the H types
Mounting plate 5 is arranged in the bottom surface of steel 2, and the strength plates 4, extension 3, mounting plate 5 pass through bolt and be attached;It is described
5 bottom of mounting plate is fixedly connected with pendant 6, and cavity 7 is opened up inside the pendant 6, and backing plate 8 is arranged in 7 inner bottom surface of the cavity, also
Including lead screw 9, the top of the lead screw 9 is located in cavity 7, the bottom end of lead screw 9 extends to 6 lower section of pendant across backing plate 8;Institute
The tapped through hole for being provided on backing plate 8 and being passed through for the lead screw 9 is stated, the first nut 10, the second spiral shell are arranged on the lead screw 9
Mother 11, first nut 10 are located at 6 bottom of pendant, and second nut 11 is located at 8 top of backing plate.
Embodiment 2:
A kind of erecting by overhang based on logistics storehouse support platform as shown in Figure 1 to Figure 3, on the basis of embodiment 1,
The extension 3 is integrally formed with H profile steel 2.The backing plate 8 is the carbide alloy board of thickness 8mm.Further include being set in lead screw 9
On third nut 12, the third nut 12 is located in cavity 7, and third nut 12 is located at 11 top of the second nut.The H-type
Steel 2 and the connection structure of girder 1 are:1 end sides of girder anchor the first hanging plate 13, and 13 outside of the first hanging plate is fixedly connected with carrying
Plate 14,14 bottom of the loading plate are connected with 2 top of H profile steel, and 2 top of H profile steel is contacted with 1 lower surface of girder.In the present embodiment
Loading plate 14 is steel plate.Further include the first spring 15 being connected between the top of H profile steel 2 and 13 bottom of the first hanging plate, described the
One spring 15 is in tensional state.
Embodiment 3:
A kind of erecting by overhang based on logistics storehouse support platform as best shown in figs. 1 and 4, on the basis of embodiment 1,
The H profile steel 2 and the connection structure of girder 1 are:1 lower surface of girder anchors the second hanging plate 16,16 bottom of the second hanging plate, H shaped steel
Hard alloy blocks 17 facing each other are fixed at 2 tops, are fixed by I-steel 18 between opposite two pieces of hard alloy blocks 17
Connection.The hard alloy blocks 17 are in hollow tubulose.Second spring 19, second bullet are set in the hard alloy blocks 17
One end of spring 19 is fixed on I-steel 18, and the other end is fixed on 2 upper surface of 1 lower surface of girder or H profile steel, the second spring
19 are in tensional state.
Above-described specific implementation mode, to the purpose of this utility model, technical solution and advantageous effect carried out into
One step is described in detail, it should be understood that the foregoing is merely specific embodiment of the present utility model, is not used to limit
Determine the scope of protection of the utility model, within the spirit and principle of the utility model, any modification for being made equally is replaced
It changes, improve, should be included within the scope of protection of this utility model.
Claims (9)
1. a kind of erecting by overhang based on logistics storehouse support platform, including girder (1), the track girder being connected on girder (1),
It is characterized in that, the track girder is the H profile steel (2) that open end is respectively facing the left and right sides, the bottom surface of the H profile steel (2) is set
It is equipped with the extension (3) extended to both sides, is both provided at left and right sides of the H profile steel (2) strong above extension (3)
Plate (4) is spent, the bottom surface setting mounting plate (5) of the H profile steel (2), the strength plates (4), extension (3), mounting plate (5) are from upper
And it is attached by bolt down;Mounting plate (5) bottom is fixedly connected with pendant (6), and cavity is opened up inside the pendant (6)
(7), cavity (7) the inner bottom surface setting backing plate (8), further includes lead screw (9), the top of the lead screw (9) is located at cavity (7)
The bottom end of interior, lead screw (9) is extended to across backing plate (8) below pendant (6);It is provided with for the lead screw on the backing plate (8)
(9) tapped through hole passed through is arranged the first nut (10), the second nut (11), first nut (10) on the lead screw (9)
Positioned at pendant (6) bottom, second nut (11) is located above backing plate (8).
2. a kind of erecting by overhang based on logistics storehouse support platform according to claim 1, which is characterized in that described to prolong
Extending portion (3) is integrally formed with H profile steel (2).
3. a kind of erecting by overhang based on logistics storehouse support platform according to claim 1, which is characterized in that the pad
Plate (8) is the carbide alloy board of 5~10mm of thickness.
4. a kind of erecting by overhang based on logistics storehouse support platform according to claim 1, which is characterized in that further include
The third nut (12) being set on lead screw (9), the third nut (12) are located in cavity (7), and third nut (12) is located at
Above second nut (11).
5. a kind of erecting by overhang based on logistics storehouse support platform according to claim 1, which is characterized in that the H
Shaped steel (2) and the connection structure of girder (1) are:Girder (1) end sides anchor the first hanging plate (13), the first hanging plate (13) outside
It is fixedly connected with loading plate (14), is connected at the top of loading plate (14) bottom and H profile steel (2), H profile steel (2) top and girder (1)
Lower surface contacts.
6. a kind of erecting by overhang based on logistics storehouse support platform according to claim 5, which is characterized in that further include
It is connected to the first spring (15) between the first hanging plate (13) bottom at the top of H profile steel (2), first spring (15), which is in, draws
Stretch state.
7. a kind of erecting by overhang based on logistics storehouse support platform according to claim 1, which is characterized in that the H
Shaped steel (2) and the connection structure of girder (1) are:Girder (1) lower surface anchors the second hanging plate (16), the second hanging plate (16) bottom, H
Hard alloy blocks (17) facing each other are fixed at the top of shaped steel (2), pass through work between opposite two pieces of hard alloy blocks (17)
Word steel (18) is fixedly connected.
8. a kind of erecting by overhang based on logistics storehouse support platform according to claim 7, which is characterized in that described hard
Matter alloy block (17) is in hollow tubulose.
9. a kind of erecting by overhang based on logistics storehouse support platform according to claim 8, which is characterized in that described hard
Setting second spring (19) in matter alloy block (17), one end of the second spring (19) is fixed on I-steel (18), another
End is fixed on girder (1) lower surface or H profile steel (2) upper surface, and the second spring (19) is in tensional state.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820318741.8U CN208008327U (en) | 2018-03-08 | 2018-03-08 | A kind of erecting by overhang based on logistics storehouse support platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820318741.8U CN208008327U (en) | 2018-03-08 | 2018-03-08 | A kind of erecting by overhang based on logistics storehouse support platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208008327U true CN208008327U (en) | 2018-10-26 |
Family
ID=63887279
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820318741.8U Active CN208008327U (en) | 2018-03-08 | 2018-03-08 | A kind of erecting by overhang based on logistics storehouse support platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208008327U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108483250A (en) * | 2018-03-08 | 2018-09-04 | 中国五冶集团有限公司 | Hanging structure for Material Flow platform |
CN111747002A (en) * | 2020-07-01 | 2020-10-09 | 吉安县苏运物流有限公司 | A cable suspension device for commodity circulation storehouse supporting platform |
-
2018
- 2018-03-08 CN CN201820318741.8U patent/CN208008327U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108483250A (en) * | 2018-03-08 | 2018-09-04 | 中国五冶集团有限公司 | Hanging structure for Material Flow platform |
CN111747002A (en) * | 2020-07-01 | 2020-10-09 | 吉安县苏运物流有限公司 | A cable suspension device for commodity circulation storehouse supporting platform |
CN111747002B (en) * | 2020-07-01 | 2021-08-24 | 江西裕康医药有限公司 | A cable suspension device for commodity circulation storehouse supporting platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208008327U (en) | A kind of erecting by overhang based on logistics storehouse support platform | |
CN102992198A (en) | Bridge crane having climbing function | |
CN108483250A (en) | Hanging structure for Material Flow platform | |
CN102285610B (en) | Hydraulic hoisting device and using method thereof | |
CN109989784A (en) | A kind of subway dispersing platform | |
CN102050377B (en) | Method for installing combined hoist and oil production platform drilling equipment | |
CN206307907U (en) | Novel lightweight loading trolley | |
CN203513083U (en) | Combined hanger special for bundled slender materials | |
CN201031066Y (en) | Rack hanging chip structure | |
CN215629794U (en) | Gate telescopic pull rod | |
CN201703384U (en) | Support device | |
CN211687913U (en) | Full-machine hanger | |
CN202117863U (en) | Multi-layer tower barrel supporting device | |
CN207673022U (en) | A kind of new type of light gauge steel composite concrete wallboard hanging apparatus | |
CN208036265U (en) | A kind of hub motor type sky iron dynamic structure of high damping performance | |
CN210260874U (en) | Air cavity type air rail wheel | |
CN207000380U (en) | A kind of good bumper of anti-collision effect | |
CN206126729U (en) | Safety brake mechanism | |
CN201678344U (en) | Layout structure of elevator tractor | |
CN205397859U (en) | Petroleum pipeline hoist | |
CN205734792U (en) | A kind of rotary wheel of water turbine maintenance framed bent | |
CN220011829U (en) | Hoisting hanging beam for harbour piece sundries | |
CN205678274U (en) | A kind of damping device of antimony glycol feedstock transportation pipeline | |
CN201553564U (en) | Straight arm frame assembling and disassembling gantry crane | |
CN110528693B (en) | Self-adaptive steel structure connecting joint and connecting method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |