CN207975188U - A kind of simple embedded earth anchor - Google Patents
A kind of simple embedded earth anchor Download PDFInfo
- Publication number
- CN207975188U CN207975188U CN201820408254.0U CN201820408254U CN207975188U CN 207975188 U CN207975188 U CN 207975188U CN 201820408254 U CN201820408254 U CN 201820408254U CN 207975188 U CN207975188 U CN 207975188U
- Authority
- CN
- China
- Prior art keywords
- earth anchor
- fixes sleeve
- groove
- chock
- ontology
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010586 diagram Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000000916 dilatatory effect Effects 0.000 description 1
- 238000000605 extraction Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model discloses a kind of simple embedded earth anchors, including earth anchor ontology, groove, motion bar, fixed baffle and connecting plate, the lower surface of the earth anchor ontology is fixedly arranged in the middle of main chock, and the lower surface outer end of earth anchor ontology offers sliding slot, the groove is reserved in the upper surface middle part of earth anchor ontology, and the top of groove is connected with each other by connecting shaft and fixes sleeve, the motion bar is mounted on the inside of fixes sleeve, and the top of motion bar is provided with link, the fixed baffle is separately positioned on the left and right sides of fixes sleeve, and the inside of fixed baffle is connected with each other by pull rod and fixes sleeve, it is connected with each other by crane arm and hook at left and right sides of the lower section of the connecting plate, and hook is mounted on the outside of pull rod.The simple embedded earth anchor is respectively arranged with main chock and secondary chock in the lower face of earth anchor ontology, and the setting of main chock and secondary chock increases the stable connection between device entirety and ground.
Description
Technical field
The utility model is related to earth anchor technical field, specially a kind of simple embedded earth anchor.
Background technology
In power construction, it is often necessary to carry out hoisting operation, it is dilatory to be fixed often through earth anchor in hoisting operation
Rope, cable wind rope etc., earth anchor generally do embedded part embedment underground by steel wire rope, steel pipe, reinforced concrete precast member, round log etc. and make,
But the stable connection between existing earth anchor and ground need to be improved.In view of the above-mentioned problems, on the basis of original earth anchor
Upper carry out innovative design.
Utility model content
The purpose of this utility model is to provide a kind of simple embedded earth anchors, existing to solve to propose in above-mentioned background technology
There is the problem of stable connection between earth anchor and ground need to be improved.
To achieve the above object, the utility model provides the following technical solutions:A kind of simple embedded earth anchor, including earth anchor
The lower surface of ontology, groove, motion bar, fixed baffle and connecting plate, the earth anchor ontology is fixedly arranged in the middle of main chock, and earth anchor
The lower surface outer end of ontology offers sliding slot, while the inside of sliding slot is equipped with secondary chock, and the groove is reserved in earth anchor ontology
Upper surface middle part, and the top of groove is connected with each other by connecting shaft and fixes sleeve, and the motion bar is mounted on fixing sleeve
The inside of cylinder, and the top of motion bar is provided with link, the fixed baffle is separately positioned on the left and right sides of fixes sleeve, and
The inside of fixed baffle is connected with each other by pull rod and fixes sleeve, passes through crane at left and right sides of the lower section of the connecting plate
Arm is connected with each other with hook, and is linked up with mounted on the outside of pull rod.
Preferably, the secondary chock is provided with 2 groups on the outside of main chock, and every group is provided with 4, while secondary chock is in
Lean outward ramp-like structure.
Preferably, the inner surface of the outer surface of the connecting shaft and groove is in thread-like structure, and the length of connecting shaft
Equal to the depth of groove.
Preferably, the lower section of the fixes sleeve constitutes dismounting mounting structure by connecting shaft and earth anchor ontology.
Preferably, the lower section of the link constitutes lifting structure by motion bar and fixes sleeve, and fixes sleeve is outer
Side is symmetrically arranged with 2 pull rods and fixed baffle.
Preferably, the lower section of the connecting plate constitutes dismounting mounting structure by hook and pull rod, and the diameter linked up with is small
In the length of connecting plate.
Compared with prior art, the utility model has the beneficial effects that:The simple embedded earth anchor, under earth anchor ontology
End face is respectively arranged with main chock and secondary chock, and the setting of main chock and secondary chock increases the company between device entirety and ground
Stability is connect, and is additionally provided with the connecting shaft of dismounting mounting structure above earth anchor ontology, while being passed through above connecting shaft
Fixes sleeve is connected with motion bar, is both provided with pull rod in the both sides of fixes sleeve, the outside of pull rod can be connected with hook, pass through
The crane arm of hook top integrally slings device, makes itself and surface separation.
Description of the drawings
Fig. 1 is the utility model overall structure diagram;
Fig. 2 is the utility model earth anchor body bottom portion structural schematic diagram;
Fig. 3 is the utility model earth anchor ontology overlooking structure diagram.
In figure:1, earth anchor ontology, 2, main chock, 3, sliding slot, 4, secondary chock, 5, groove, 6, connecting shaft, 7, fixes sleeve,
8, motion bar, 9, link, 10, pull rod, 11, fixed baffle, 12, hook, 13, crane arm, 14, connecting plate.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
The every other embodiment obtained, shall fall within the protection scope of the present invention.
- 3 are please referred to Fig.1, the utility model provides a kind of technical solution:A kind of simple embedded earth anchor, including earth anchor sheet
Body 1, main chock 2, sliding slot 3, secondary chock 4, groove 5, connecting shaft 6, fixes sleeve 7, motion bar 8, link 9, pull rod 10, fixed gear
Plate 11, hook 12, crane arm 13 and connecting plate 14, the lower surface of earth anchor ontology 1 are fixedly arranged in the middle of main chock 2, and earth anchor
The lower surface outer end of ontology 1 offers sliding slot 3, while the inside of sliding slot 3 is equipped with secondary chock 4, and secondary chock 4 is in main chock 2
Outside is provided with 2 groups, and every group is provided with 4, while secondary chock 4 increases device entirety and ground in the ramp-like structure that leans outward
Stable connection between face, groove 5 is reserved in the upper surface middle part of earth anchor ontology 1, and the top of groove 5 passes through connecting shaft 6
It being connected with each other with fixes sleeve 7, the outer surface of connecting shaft 6 and the inner surface of groove 5 are in thread-like structure, and connecting shaft 6
Length is equal to the depth of groove 5, and stable connection is also relatively strong while being threaded in installation easy to disassemble, and motion bar 8 is installed
The top of the inside of fixes sleeve 7, and motion bar 8 is provided with link 9, the lower section of fixes sleeve 7 passes through connecting shaft 6 and earth anchor
Ontology 1 constitutes dismounting mounting structure, and convenient for carrying out dismounting assembling to device, the lower section of link 9 passes through motion bar 8 and fixes sleeve
7 constitute lifting structure, and the outside of fixes sleeve 7 is symmetrically arranged with 2 pull rods 10 and fixed baffle 11, can pass through 9 He of link
Pull rod 10 removes earth anchor ontology 1, and fixed baffle 11 is separately positioned on the left and right sides of fixes sleeve 7, and fixed baffle 11
Inside is connected with each other by pull rod 10 and fixes sleeve 7, at left and right sides of the lower section of connecting plate 14 by crane arm 13 with
Hook 12 is connected with each other, and links up with 12 outsides for being mounted on pull rod 10, and the lower section of connecting plate 14 passes through hook 12 and 10 structure of pull rod
At dismounting mounting structure, and the diameter of hook 12 is less than the length of connecting plate 14, and hook 12 is avoided to be slid from 10 outside of pull rod.
Operation principle:A hole is cut on ground first, earth anchor ontology 1 is placed into hole, earth anchor sheet is now placed in
The main chock 2 of 1 lower surface of body can be inserted into secondary chock 4 in soil, increase the stable connection between earth anchor ontology 1 and ground
Property, connecting shaft 6 is installed at this time, it, can since the outer surface of connecting shaft 6 and the inner surface of groove 5 are in shape of threads
It is threadedly coupled between groove 5 by being rotatablely connected axis 6, connection is steady while being threaded in installation easy to disassemble
Solidity is also relatively strong, the then extraction out of fixes sleeve 7 by motion bar 8, and it is fixed, at this time can be to earth anchor ontology 1
It is buried, in addition to this when removing earth anchor ontology 1, the operation can be completed by crane, in the process, will first be hung
Hook 12 is mounted on the outside of pull rod 10, the lifting of earth anchor ontology 1 can be completed by crane arm 13, here it is this simply to enter
The operation principle of ground formula earth anchor.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is appreciated that can these embodiments be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaiied
Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.
Claims (6)
1. a kind of simple embedded earth anchor, including earth anchor ontology (1), groove (5), motion bar (8), fixed baffle (11) and connection
Plate (14), it is characterised in that:The lower surface of the earth anchor ontology (1) is fixedly arranged in the middle of main chock (2), and earth anchor ontology (1)
Lower surface outer end offers sliding slot (3), while the inside of sliding slot (3) is equipped with secondary chock (4), and the groove (5) is reserved in ground
The upper surface middle part of anchor ontology (1), and the top of groove (5) is connected with each other by connecting shaft (6) and fixes sleeve (7), it is described
Motion bar (8) is mounted on the inside of fixes sleeve (7), and the top of motion bar (8) is provided with link (9), the fixed baffle
(11) it is separately positioned on the left and right sides of fixes sleeve (7), and the inside of fixed baffle (11) passes through pull rod (10) and fixing sleeve
Cylinder (7) is connected with each other, mutual with hook (12) by crane arm (13) at left and right sides of the lower section of the connecting plate (14)
Connection, and link up with the outside that (12) are mounted on pull rod (10).
2. a kind of simple embedded earth anchor according to claim 1, it is characterised in that:The pair chock (4) is in main chock
(2) 2 groups are provided on the outside of, and every group is provided with 4, while secondary chock (4) is in the ramp-like structure that leans outward.
3. a kind of simple embedded earth anchor according to claim 1, it is characterised in that:The outer surface of the connecting shaft (6)
Inner surface with groove (5) is in thread-like structure, and the length of connecting shaft (6) is equal to the depth of groove (5).
4. a kind of simple embedded earth anchor according to claim 1, it is characterised in that:The lower section of the fixes sleeve (7)
Dismounting mounting structure is constituted by connecting shaft (6) and earth anchor ontology (1).
5. a kind of simple embedded earth anchor according to claim 1, it is characterised in that:Pass through below the link (9)
Motion bar (8) and fixes sleeve (7) constitute lifting structure, and be symmetrically arranged on the outside of fixes sleeve (7) 2 pull rods (10) and
Fixed baffle (11).
6. a kind of simple embedded earth anchor according to claim 1, it is characterised in that:The lower section of the connecting plate (14) is logical
Cross the length that the diameter that hook (12) constitutes dismounting mounting structure, and link up with (12) with pull rod (10) is less than connecting plate (14).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820408254.0U CN207975188U (en) | 2018-03-26 | 2018-03-26 | A kind of simple embedded earth anchor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820408254.0U CN207975188U (en) | 2018-03-26 | 2018-03-26 | A kind of simple embedded earth anchor |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207975188U true CN207975188U (en) | 2018-10-16 |
Family
ID=63766136
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820408254.0U Expired - Fee Related CN207975188U (en) | 2018-03-26 | 2018-03-26 | A kind of simple embedded earth anchor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207975188U (en) |
-
2018
- 2018-03-26 CN CN201820408254.0U patent/CN207975188U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201864516U (en) | Lifting appliance special for overhauling isolating switch | |
CN101806107B (en) | Side column connecting node of thin steel plate shear wall | |
CN201260050Y (en) | 220KV bracket for replacing bus bar column insulator | |
CN207975188U (en) | A kind of simple embedded earth anchor | |
CN209260578U (en) | Longitudinal temporary connecting structure of suspension bridge concrete stiffening girder installation | |
CN207354115U (en) | Photovoltaic fish-bellied type cable-rod structure | |
CN203096597U (en) | Bridge suspender connecting device | |
CN203050218U (en) | Standard knot hoisting support for jacking | |
CN202988556U (en) | Special lifting appliance for angle-steel type frame body | |
CN214798598U (en) | Novel cable mechanization is laid and is turned to device | |
CN211078160U (en) | Culvert pipe lifting device for municipal construction | |
CN204715349U (en) | Tenon joint type resistance to plucking connector | |
CN103738852A (en) | Weight testing device of crane | |
CN203129202U (en) | Deviation rectifying device for tube pile | |
CN204914204U (en) | Solid side of prestressing force stake five covers of stretch -draw for mechanical connection | |
CN210623781U (en) | Mining trusteeship device | |
CN102277999A (en) | Large-section portal steel structure holding pole | |
CN211622526U (en) | Attached cantilever beam | |
CN205779855U (en) | A kind of large-scale mud pit slush pump levitation device for pile foundation construction | |
CN205046523U (en) | Assembled ditch | |
CN207686679U (en) | A kind of cord winder, middle mast and rotary drilling rig | |
CN202561404U (en) | Hoisting device | |
CN219731988U (en) | Turnover hanging bar adjusting device under deep hole | |
CN204456164U (en) | A kind of spliced pedestal of communication tower | |
CN204491583U (en) | For the reinforcement structure of fluid concrete stake |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181016 |