CN219731988U CN202320941755.6U CN202320941755U CN219731988U CN 219731988 U CN219731988 U CN 219731988U CN 202320941755 U CN202320941755 U CN 202320941755U CN 219731988 U CN219731988 U CN 219731988U
Authority
CN
China
Prior art keywords
hanging
adjusting device
hanging bar
bar adjusting
pin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320941755.6U
Other languages
Chinese (zh)
Inventor
梁月新
王伟刚
澹台旭辉
王雅平
郝瑞星
曹宗胜
陈瑶
张春跃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Sixth Construction Group Co ltd
Original Assignee
Shanxi Sixth Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Sixth Construction Group Co ltd filed Critical Shanxi Sixth Construction Group Co ltd
Priority to CN202320941755.6U priority Critical patent/CN219731988U/en
Application granted granted Critical
Publication of CN219731988U publication Critical patent/CN219731988U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to the technical field of building construction, and discloses a turnover hanging bar adjusting device under a deep hole, which comprises a hanging bar adjusting device, an embedding device and a hanging ring anti-drop device; the hanging bar adjusting device comprises a cross frame and hanging bars, and one ends of the cross frame and the hanging bars are connected; the embedding device comprises a reinforcing rib embedding groove, an anti-falling pin and a pin rod, wherein two grapples are fixed at the other end of the hanging rib, and a reinforcing rib embedding groove is formed between the two grapples; the lifting ring anti-drop device comprises a lifting ring, a sleeve pipe fitting and a traction rope, wherein the sleeve pipe fitting and an anti-drop pin are fixed on the lifting rib, the pin rod is arranged in the anti-drop pin, one end, far away from two grapples, of the pin rod is connected with the traction rope, and the traction rope penetrates through the sleeve pipe fitting and then is connected with the lifting ring. The utility model has the advantages of simple processing, convenient construction, safety, reliability, free length adjustment and repeated utilization, and can be suitable for the requirements of various field operation environments.

Description

Turnover hanging bar adjusting device under deep hole
Technical Field
The utility model relates to the technical field of building construction, in particular to a turnover hanging bar adjusting device under a deep hole.
Background
In the construction of the empty pile of the filling pile, the hoisting of the reinforcement cage needs auxiliary hoisting fixing measures, the traditional construction method is that two or four hanging bars are arranged at the top of the reinforcement cage, the length of each hanging bar is determined according to the elevation of the pile top with the length being effective, the reinforcement cage can not be directly buried into a soil layer for use after the filling pile is poured, and each set of reinforcement cage can cause the waste of two or four hanging bars.
Disclosure of Invention
In view of the above, the utility model aims to provide the turnover hanging bar adjusting device under the deep hole, which has the advantages of simple processing, convenient construction, safety, reliability, free adjustment of length, repeated utilization, suitability for various field operation environment requirements and avoiding the waste of hanging bars.
In order to achieve the above object, the following technical scheme is adopted:
the turnover hanging bar adjusting device under the deep hole comprises a hanging bar adjusting device, an embedding device and a hanging ring anti-drop device;
the hanging bar adjusting device comprises a cross frame and hanging bars, and one ends of the cross frame and the hanging bars are connected;
the embedding device comprises a reinforcing rib embedding groove, an anti-falling pin and a pin rod, wherein two grapples are fixed at the other end of the hanging rib, and a reinforcing rib embedding groove is formed between the two grapples;
the lifting ring anti-drop device comprises a lifting ring, a sleeve pipe fitting and a traction rope, wherein the sleeve pipe fitting and an anti-drop pin are fixed on the lifting rib, the pin rod is arranged in the anti-drop pin, one end, far away from two grapples, of the pin rod is connected with the traction rope, and the traction rope penetrates through the sleeve pipe fitting and then is connected with the lifting ring.
As a further improvement of the utility model, the hauling rope is a steel wire rope.
As a further improvement of the utility model, the length of the derrick is 1.5m, and every 10cm of vertical steel pipes on the inner side of the derrick are provided with 1 channel.
As a further improvement of the utility model, the cross frame is welded and formed by phi 16 deformed steel bars.
As a further improvement of the utility model, the hanging bar adopts phi 12 steel bars.
The beneficial effects of the utility model are as follows: the utility model has the advantages of simple processing, convenient construction, safety, reliability, free adjustment of length, repeated utilization, adaptability to various field operation environment requirements, and good economic and social benefits by adjusting the positions and elevations of the reinforcement cages, meeting the construction quality of the cast-in-place pile, saving resources, improving the construction efficiency, reducing the construction cost and improving the market competitiveness of enterprises.
Drawings
The accompanying drawings, which are included to provide a further understanding of the utility model and are incorporated in and constitute a part of this specification, illustrate embodiments of the utility model and together with the description serve to explain the utility model. In the drawings:
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a schematic view of a part of the present utility model in a locked state;
FIG. 3 is a schematic view of a partial structure of the present utility model in an open state;
FIG. 4 is a schematic representation of the use of the present utility model.
In the figure: 1. the well frame, 2, rings, 3, sleeve pipe fitting, 4, haulage rope, 5, hanging bar, 6, pin rod, 7, strengthening rib embedding groove, 8, anticreep round pin, 9, grapple, 10, steel reinforcement cage.
Detailed Description
It should be noted that, without conflict, the embodiments of the present utility model and features of the embodiments may be combined with each other. The utility model will be described in detail below with reference to the drawings in connection with embodiments.
In order that those skilled in the art will better understand the present utility model, a technical solution in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in which it is apparent that the described embodiments are only some embodiments of the present utility model, not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the present utility model without making any inventive effort, shall fall within the scope of the present utility model.
As shown in fig. 1-4, the turnover hanging bar adjusting device under the deep hole comprises a hanging bar adjusting device, an embedding device and a hanging ring anti-drop device;
the hanging bar adjusting device comprises a cross frame 1 and hanging bars 5, wherein one ends of the cross frame 1 and the hanging bars 5 are connected;
the embedding device comprises a reinforcing rib embedding groove 7, an anti-falling pin 8 and a pin rod 6, wherein two grapples 9 are fixed at the other end of the hanging rib 5, and a reinforcing rib embedding groove 7 is formed between the two grapples 9;
the lifting ring anti-drop device comprises a lifting ring 2, a sleeve pipe fitting 3 and a traction rope 4, wherein the sleeve pipe fitting 3 and an anti-drop pin 8 are fixed on a lifting rib 5, a pin rod 6 is arranged in the anti-drop pin 8, one end, far away from two grapples 9, of the pin rod 6 is connected with the traction rope 4, and the traction rope 4 penetrates through the sleeve pipe fitting 3 and then is connected with the lifting ring 2.
The hauling rope 4 is a steel wire rope.
The length of the derrick 1 is 1.5m, and every 10cm of vertical steel pipes at the inner side of the derrick 1 are provided with 1 channel.
The cross frame 1 is formed by welding phi 16 deformed steel bars.
The hanging bar 5 adopts phi 12 steel bars.
Working principle: when the utility model is used, firstly, the total length of the hanging bar adjusting device and the length of the hanging bar 5 are determined according to the height difference between the elevation of the on-site pile casing and the elevation of the pile top of the cast-in-place pile, the welding extension ensures that the hanging requirement is met, and the welded joint is full and free of slag inclusion. Then, the device is assembled on site, the end parts of reinforcing ribs of the reinforcement cage 10 are clamped into the reinforcing rib embedding grooves 7, the reinforcing ribs of the reinforcement cage 10 are clamped into the upper grapple 9 and the lower grapple 9, and then the pin rod 6 is inserted into the sleeve pipe fitting 3 and the reinforcing rib embedding grooves 7 to play a role of a lock pin. The crane lifts the device, puts into the stake downthehole, confirms the elevation through adjusting the height of hanging muscle adjusting device well head frame 1, waits that the elevation confirms the back, inserts two steel pipes in the well head frame 1.
After the concrete is poured to the position 80cm above the pile top elevation, lifting by using the lifting ring 2, and withdrawing the pin rod 6 for pin removal. The construction is replaced in a reciprocating manner, so that the recycling of the device is completed (the pin rod 6 is pulled out, the reinforcing rib embedding groove 7 and the reinforcing rib of the reinforcing cage 10 are indicated to be unlocked, the crane is slightly hung on the derrick 1, and the hanging rib 5 is pulled out, so that the aim of recycling is fulfilled).
The above description is only of the preferred embodiments of the present utility model and is not intended to limit the present utility model, but various modifications and variations can be made to the present utility model by those skilled in the art. Any modification, equivalent replacement, improvement, component disassembly, or combination thereof, etc. that falls within the spirit and principles of the present utility model should be included in the scope of the present utility model.

Claims (5)

1. Can have enough to meet need hanging bar adjusting device under deep hole, its characterized in that: comprises a hanging bar adjusting device, an embedding device and a hanging ring anti-drop device;
the hanging bar adjusting device comprises a cross frame and hanging bars, and one ends of the cross frame and the hanging bars are connected;
the embedding device comprises a reinforcing rib embedding groove, an anti-falling pin and a pin rod, wherein two grapples are fixed at the other end of the hanging rib, and a reinforcing rib embedding groove is formed between the two grapples;
the lifting ring anti-drop device comprises a lifting ring, a sleeve pipe fitting and a traction rope, wherein the sleeve pipe fitting and an anti-drop pin are fixed on the lifting rib, the pin rod is arranged in the anti-drop pin, one end, far away from two grapples, of the pin rod is connected with the traction rope, and the traction rope penetrates through the sleeve pipe fitting and then is connected with the lifting ring.
2. The underdeep hole turnover hanging bar adjusting device as set forth in claim 1, wherein: the hauling rope is a steel wire rope.
3. The underdeep hole turnover hanging bar adjusting device as set forth in claim 1, wherein: the length of the cross frame is 1.5m, and each 10cm of vertical steel pipes on the inner side of the cross frame are provided with 1 channel.
4. The underdeep hole turnover hanging bar adjusting device as set forth in claim 1, wherein: the cross frame is formed by welding phi 16 deformed steel bars.
5. The underdeep hole turnover hanging bar adjusting device as set forth in claim 1, wherein: the hanging bar adopts phi 12 steel bars.
CN202320941755.6U 2023-04-24 2023-04-24 Turnover hanging bar adjusting device under deep hole Active CN219731988U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320941755.6U CN219731988U (en) 2023-04-24 2023-04-24 Turnover hanging bar adjusting device under deep hole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320941755.6U CN219731988U (en) 2023-04-24 2023-04-24 Turnover hanging bar adjusting device under deep hole

Publications (1)

Publication Number Publication Date
CN219731988U true CN219731988U (en) 2023-09-22

Family

ID=88057148

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320941755.6U Active CN219731988U (en) 2023-04-24 2023-04-24 Turnover hanging bar adjusting device under deep hole

Country Status (1)

Country Link
CN (1) CN219731988U (en)

Similar Documents

Publication Publication Date Title
CN101302760A (en) Ultralong overweight concrete filling pile reinforcement type reinforcing steel bar caging
CN213834278U (en) Dig a major diameter overlength steel reinforcement cage hoist and mount auxiliary device soon
CN206767425U (en) A kind of integral hoisting device for rapid for ground-connecting-wall steel reinforcement cage
CN219731988U (en) Turnover hanging bar adjusting device under deep hole
CN211849454U (en) Steel reinforcement cage is hung and is put and positioner
CN208561439U (en) Marine traffic engineering Large Precast Members do not penetrate lifting hole(eyelet) structure
CN215167862U (en) Be used in no counter weight hanging flower basket of parapet
CN202785255U (en) Turnover hoisting tool for reinforced concrete pipe joint
CN219078843U (en) Reinforcing cage hoisting auxiliary device
CN113417281A (en) Cast-in-place pile-prestressed pipe pile composite pile and construction method thereof
CN102839652A (en) Steel strand cast-in-place pile and construction method thereof
CN214192283U (en) Large-diameter pipe jacking lifting device
CN202441269U (en) Offshore drilling tower
CN201212146Y (en) Reinforcement reinforced bar caging of ultralong and overweight concrete filling pile
CN212740384U (en) Detachable lifting appliance for positioning reinforcement cage
CN206986897U (en) A kind of tethered sliding formula toe slab grouting system
CN219450738U (en) Steel reinforcement cage hanging device for cast-in-place pile
CN217458453U (en) Tubular pile hoisting structure
CN213952232U (en) Reinforcing cage hanging rib replacing device for deep foundation pit cast-in-situ bored pile
CN217051267U (en) Pipe culvert segment lifting appliance
CN212450245U (en) Heavy-calibre concrete downspout lifting device
CN220393060U (en) Heavy steel reinforcement cage hoist and mount fixed platform of major diameter bored concrete pile
CN210066725U (en) Drilled pile reinforcement cage hanging bar capable of being recycled
CN211279035U (en) High-efficient concrete drain pipe shedder