CN207974103U - The isolating device of cast-in-situ bored pile pile crown - Google Patents

The isolating device of cast-in-situ bored pile pile crown Download PDF

Info

Publication number
CN207974103U
CN207974103U CN201820140656.7U CN201820140656U CN207974103U CN 207974103 U CN207974103 U CN 207974103U CN 201820140656 U CN201820140656 U CN 201820140656U CN 207974103 U CN207974103 U CN 207974103U
Authority
CN
China
Prior art keywords
pile crown
pile
cast
isolating device
situ bored
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820140656.7U
Other languages
Chinese (zh)
Inventor
苏秋
倪小健
赵卫献
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201820140656.7U priority Critical patent/CN207974103U/en
Application granted granted Critical
Publication of CN207974103U publication Critical patent/CN207974103U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model is related to a kind of isolating device of cast-in-situ bored pile pile crown, the steel reinforcement cage for being sheathed on pile crown to be formed, isolating device includes:Pallet compatible with the diameter of pile crown to be formed offers multiple through holes, through hole setting corresponding with the vertical vertical reinforcement on steel reinforcement cage on pallet;And vertically it is fixedly arranged on the casing on pallet, casing is arranged correspondingly with through hole, and the top seal of casing, bottom opening are connected to corresponding through hole, by the way that casing is sheathed on concrete of the corresponding vertical reinforcement vertical reinforcement is isolated with subsequently pours on steel reinforcement cage.The problem of in subsequently taking out the work progress of pile crown, pile crown can be pulled out using simple hoisting machinery, the top out-of-flatness for removing the cast-in-situ bored pile after pile crown in the prior art is solved, damages the vertical reinforcement of cast-in-situ bored pile.The present apparatus it is easy to operate, it is time saving and energy saving, effect is high.

Description

The isolating device of cast-in-situ bored pile pile crown
Technical field
The utility model is related to the realm of building construction, espespecially a kind of isolating device of cast-in-situ bored pile pile crown.
Background technology
Currently, when bored pile construction, bored concrete pile top mark height usually is out design stake top absolute altitude
0.5m~1.0m forms the superfilled area of concrete, that is, pile crown, for ensuring pile foundation concrete strength.Concrete is super Irrigated area will be cut in bearing platform construction.
Usually there are two types of modes for the traditional restructuring bankrupt of pile crown:One kind going deep into pile crown manually to remove hangs muscle using pneumatic pick Remaining pile crown is abolished again after steel reinforcement cage main reinforcement;Another kind is that quartering hammer progress directly hammer is broken.It is past when conventional method is abolished Impaired, pile crown out-of-flatness the quality problems toward the bar bending that causes to go deep into pile crown, dust pollution is serious, while consuming a large amount of Manpower, machinery, time-consuming and quality can not ensure.
Utility model content
The purpose of the utility model is to overcome the defects of the prior art, provide a kind of isolation dress of cast-in-situ bored pile pile crown It sets, solves the problems, such as bar bending pile crown out-of-flatness when cast-in-situ bored pile pile crown is abolished in the prior art.
Realizing the technical solution of above-mentioned purpose is:
The utility model provides a kind of isolating device of cast-in-situ bored pile pile crown, the steel for being sheathed on pile crown to be formed On muscle cage, the isolating device includes:
Pallet compatible with the diameter of pile crown to be formed offers multiple through holes, the perforation on the pallet Hole setting corresponding with the vertical reinforcement on the steel reinforcement cage;And
The casing being vertically fixedly arranged on the pallet, described sleeve pipe are arranged correspondingly with the through hole, and described The top seal of casing, bottom opening are connected to corresponding through hole, right on the steel reinforcement cage by the way that described sleeve pipe to be sheathed on Concrete of the vertical reinforcement answered the vertical reinforcement is isolated with subsequently pours.
The advantageous effect of the isolating device of the utility model cast-in-situ bored pile pile crown:
The present apparatus by casing by being sheathed on the corresponding reinforcing bar of steel reinforcement cage and pallet is positioned at pile crown bottom to be formed At designed elevation, to which the reinforcing bar of pile crown is isolated with the concrete subsequently poured, in subsequently taking out the work progress of pile crown, Pile crown can be pulled out using simple hoisting machinery, solves the top for removing the cast-in-situ bored pile after pile crown in the prior art Out-of-flatness, the problem of damaging the reinforcing bar of cast-in-situ bored pile.The present apparatus it is easy to operate, it is time saving and energy saving, effect is high.
The isolating device of the utility model cast-in-situ bored pile pile crown further improvement lies in that, the inner wall interval of described sleeve pipe It is fixed with the laciniation for fixing the vertical reinforcement.
The isolating device of the utility model cast-in-situ bored pile pile crown further improvement lies in that, the pallet be with it is to be formed Pile crown the compatible Circular Plate of diameter, Circular Plate inner circular hole is adapted with the size of concrete pump pipe.
The isolating device of the utility model cast-in-situ bored pile pile crown further improvement lies in that, the bore of described sleeve pipe is more than The diameter of corresponding vertical reinforcement on the steel reinforcement cage.
The isolating device of the utility model cast-in-situ bored pile pile crown further improvement lies in that, the length of described sleeve pipe is more than The length of corresponding vertical reinforcement on the steel reinforcement cage.
The isolating device of the utility model cast-in-situ bored pile pile crown further improvement lies in that, on the internal face of described sleeve pipe Be installed with the vertically disposed ring flat-plate of described sleeve pipe, it is serrated face that the annular surface in described sleeve pipe is located on the ring flat-plate.
Description of the drawings
Fig. 1 is the structural schematic diagram of the isolating device of the utility model cast-in-situ bored pile pile crown.
Fig. 2 to Fig. 3 is the construction procedure schematic diagram of the isolating device of the utility model cast-in-situ bored pile pile crown.
Fig. 4 is the sectional view of the A-A of Fig. 1.
Specific implementation mode
The utility model is described in further detail in the following with reference to the drawings and specific embodiments.
Refering to fig. 1, it is shown that the structural schematic diagram of the isolating device of the utility model cast-in-situ bored pile pile crown.Refering to Fig. 2 To Fig. 3, it is shown that the construction procedure schematic diagram of the isolating device of the utility model cast-in-situ bored pile pile crown.In conjunction with Fig. 1 to Fig. 3 institutes Show, the isolating device of the utility model cast-in-situ bored pile pile crown is used to be sheathed on the steel reinforcement cage of pile crown 10 to be formed, isolation Device includes:Pallet 20 compatible with the diameter of pile crown 10 to be formed offers multiple through holes, through hole on pallet 20 Setting corresponding with the vertical reinforcement on steel reinforcement cage;And it is vertically fixedly arranged on the casing 30 on pallet 20, casing 30 and perforation Hole is arranged correspondingly, and the top seal of casing 30, and bottom opening is connected to corresponding through hole, by by 30 sets of casing Concrete of the corresponding vertical reinforcement vertical reinforcement is isolated with subsequently pours on steel reinforcement cage.The present apparatus will be by that will cover pipe sleeve It is positioned at the designed elevation of pile crown bottom to be formed set on the corresponding reinforcing bar of steel reinforcement cage and pallet, to by the steel of pile crown Muscle is isolated with the concrete subsequently poured, in subsequently taking out the work progress of pile crown, can be pulled out using simple hoisting machinery Except pile crown, solves the top out-of-flatness for removing the cast-in-situ bored pile after pile crown in the prior art, damage cast-in-situ bored pile The problem of reinforcing bar.The present apparatus it is easy to operate, it is time saving and energy saving, effect is high.
One better embodiment of the isolating device as the utility model cast-in-situ bored pile pile crown, refering to Fig. 4, it is shown that The sectional view of the A-A of Fig. 1.In conjunction with shown in Fig. 1 to Fig. 4, the inner wall of casing 30 is fixed at intervals the sawtooth for fixing vertical reinforcement Shape structure 40, to which when casing 30 is sheathed on vertical reinforcement, the laciniation 40 and vertical reinforcement of 30 inner wall of casing paste If fixing, the frictional resistance between casing 30 and vertical reinforcement is increased, prevents casing 30 and vertical reinforcement from slipping, ensure that The connection of casing 30 and vertical reinforcement during casting concrete.
In the present embodiment, be installed on the internal face of casing 30 with 30 vertically disposed ring flat-plate of casing, be located on ring flat-plate Annular surface in casing 30 is serrated face.
One better embodiment of the isolating device as the utility model cast-in-situ bored pile pile crown, in conjunction with Fig. 1 and Fig. 2 institutes Show, pallet 20 is Circular Plate compatible with the diameter of pile crown 10 to be formed, Circular Plate inner circular hole and concrete pump pipe Size be adapted.Circular Plate inner circular hole is worn for the conduit of casting concrete.After casting concrete, at Circular Plate Concrete be brittle, be easily destroyed and pull out during removing pile crown 10.In the present embodiment, the bore of casing 30 is big In the diameter of the corresponding vertical reinforcement of steel reinforcement cage.The length of casing 30 is more than the length of the corresponding vertical reinforcement of steel reinforcement cage.
In conjunction with shown in Fig. 2 and Fig. 3, in the construction process, the casing 30 of the present apparatus is sheathed on the vertical reinforcement of pile crown, And pallet 20 is positioned at the designed elevation of 10 bottom of pile crown to be formed, finally casting concrete, shape above pallet 20 At pile crown 10, during removing pile crown 10, using crane hanging component pile crown 10, so that pile crown 10 is detached from drill-pouring Pile head.
The isolating device of the utility model cast-in-situ bored pile pile crown has the beneficial effect that:
The present apparatus by casing by being sheathed on the corresponding vertical reinforcement of steel reinforcement cage and pallet is positioned at pile crown bottom to be formed At the designed elevation in portion, to which the vertical reinforcement of pile crown to be isolated with the concrete subsequently poured, applying for pile crown is subsequently being taken out During work, pile crown can be pulled out using simple hoisting machinery, the drilling after removing pile crown in the prior art is solved and fills Note the top out-of-flatness of stake, the problem of damaging the vertical reinforcement of cast-in-situ bored pile.Easy to operate, the time saving and energy saving, work(of the present apparatus Effect is high.
The utility model is described in detail above in association with attached drawing embodiment, those skilled in the art can root Many variations example is made to the utility model according to above description.Thus, certain details in embodiment should not be constituted to this practicality Novel restriction, the utility model will be using the ranges that the appended claims define as the scope of protection of the utility model.

Claims (6)

1. a kind of isolating device of cast-in-situ bored pile pile crown, the steel reinforcement cage for being sheathed on pile crown to be formed, feature exist In the isolating device includes:
Pallet compatible with the diameter of pile crown to be formed, offers multiple through holes on the pallet, the through hole with The corresponding setting of vertical reinforcement on the steel reinforcement cage;And
The casing being vertically fixedly arranged on the pallet, described sleeve pipe is arranged correspondingly with the through hole, and described sleeve pipe Top seal, bottom opening is connected to corresponding through hole, corresponding on the steel reinforcement cage by the way that described sleeve pipe to be sheathed on Concrete of the vertical reinforcement the vertical reinforcement is isolated with subsequently pours.
2. the isolating device of cast-in-situ bored pile pile crown as described in claim 1, which is characterized in that the inner wall interval of described sleeve pipe It is fixed with the laciniation for fixing the vertical reinforcement.
3. the isolating device of cast-in-situ bored pile pile crown as described in claim 1, which is characterized in that the pallet be with it is to be formed Pile crown the compatible Circular Plate of diameter, Circular Plate inner circular hole is adapted with the size of concrete pump pipe.
4. the isolating device of cast-in-situ bored pile pile crown as described in claim 1, which is characterized in that the bore of described sleeve pipe is more than The diameter of corresponding vertical reinforcement on the steel reinforcement cage.
5. the isolating device of cast-in-situ bored pile pile crown as described in claim 1, which is characterized in that the length of described sleeve pipe is more than The length of corresponding vertical reinforcement on the steel reinforcement cage.
6. the isolating device of cast-in-situ bored pile pile crown as described in claim 1, which is characterized in that on the internal face of described sleeve pipe Be installed with the vertically disposed ring flat-plate of described sleeve pipe, it is serrated face that the annular surface in described sleeve pipe is located on the ring flat-plate.
CN201820140656.7U 2018-01-26 2018-01-26 The isolating device of cast-in-situ bored pile pile crown Expired - Fee Related CN207974103U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820140656.7U CN207974103U (en) 2018-01-26 2018-01-26 The isolating device of cast-in-situ bored pile pile crown

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820140656.7U CN207974103U (en) 2018-01-26 2018-01-26 The isolating device of cast-in-situ bored pile pile crown

Publications (1)

Publication Number Publication Date
CN207974103U true CN207974103U (en) 2018-10-16

Family

ID=63769893

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820140656.7U Expired - Fee Related CN207974103U (en) 2018-01-26 2018-01-26 The isolating device of cast-in-situ bored pile pile crown

Country Status (1)

Country Link
CN (1) CN207974103U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109629557A (en) * 2018-12-18 2019-04-16 五冶集团上海有限公司 A kind of cast-in-situ bored pile pile crown isolating device and its application method
CN110656644A (en) * 2019-09-26 2020-01-07 广东省建筑工程机械施工有限公司 Reinforcement cage erecting structure and method for breaking pile head of cast-in-place pile through static blasting by reverse construction method
CN111218936A (en) * 2019-12-11 2020-06-02 山东鲁桥建设有限公司 Construction method for rapidly and nondestructively breaking pile head
CN111877312A (en) * 2020-07-13 2020-11-03 中国一冶集团有限公司 Pile head separation type device and pile breaking construction method
CN113089669A (en) * 2021-03-29 2021-07-09 中国十九冶集团有限公司 Pile head breaking device for large-diameter cast-in-place pile and using method thereof
CN113293755A (en) * 2021-05-28 2021-08-24 福建九鼎建设集团有限公司 Pile head isolation device and construction operation method thereof
CN114541394A (en) * 2022-02-21 2022-05-27 陕西建工机械施工集团有限公司 Construction method convenient for breaking pile head of cast-in-place pile

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109629557A (en) * 2018-12-18 2019-04-16 五冶集团上海有限公司 A kind of cast-in-situ bored pile pile crown isolating device and its application method
CN110656644A (en) * 2019-09-26 2020-01-07 广东省建筑工程机械施工有限公司 Reinforcement cage erecting structure and method for breaking pile head of cast-in-place pile through static blasting by reverse construction method
CN110656644B (en) * 2019-09-26 2024-02-09 广东省建筑工程机械施工有限公司 Reinforcement cage erecting structure and method for breaking pile head of cast-in-place pile through reverse static blasting
CN111218936A (en) * 2019-12-11 2020-06-02 山东鲁桥建设有限公司 Construction method for rapidly and nondestructively breaking pile head
CN111877312A (en) * 2020-07-13 2020-11-03 中国一冶集团有限公司 Pile head separation type device and pile breaking construction method
CN111877312B (en) * 2020-07-13 2022-05-20 中国一冶集团有限公司 Pile head separation type device and pile breaking construction method
CN113089669A (en) * 2021-03-29 2021-07-09 中国十九冶集团有限公司 Pile head breaking device for large-diameter cast-in-place pile and using method thereof
CN113293755A (en) * 2021-05-28 2021-08-24 福建九鼎建设集团有限公司 Pile head isolation device and construction operation method thereof
CN114541394A (en) * 2022-02-21 2022-05-27 陕西建工机械施工集团有限公司 Construction method convenient for breaking pile head of cast-in-place pile

Similar Documents

Publication Publication Date Title
CN207974103U (en) The isolating device of cast-in-situ bored pile pile crown
CN102286970A (en) Whole process construction method of driven cast-in-place piles and special device for same
CN110529041B (en) Self-soil-taking type double-layer full casing pipe for inclined pile hole forming and construction method thereof
CN210031772U (en) Concrete bored concrete pile cuts a spacer
CN215715279U (en) Pile head breaking device for concrete cast-in-place pile
JP4366597B2 (en) Cutting and removing existing piles
CN206736920U (en) A kind of internal-expansion type pipe drawing device
CN214695564U (en) A protect a structure more for construction of karst cave area bridge pile foundation
CN213978954U (en) Construction tool for quickly separating pile head of cast-in-place pile
CN113174953B (en) Pretreatment structure of super-irrigation part of pile top of cast-in-place pile
CN109680681A (en) A kind of pile crown restructuring bankrupt of cast-in-situ bored pile
CN205894063U (en) A complete set of pipe long spiral drilling filling pile presses cage ware
CN112726784B (en) Full-prefabricated PC sewer inspection well component assembly structure and construction method
CN211447786U (en) Turnover pull ring used on shear wall
CN113668529A (en) Construction method for breaking and removing pile head with template based on steel wedge-shaped gap
CN112609694A (en) Pile head breaking device and construction method thereof
CN207846432U (en) Foundation pit enclosure pile driving construction casing device
CN206554106U (en) Conehead muscle body posttension pile foundation
CN220080008U (en) Pile pulling device
CN209099976U (en) A kind of Telescopic drill rod casing applied in MJS construction
CN206233237U (en) A kind of boosting guider for transferring steel pile casting
CN210104722U (en) Tubular pile convenient to site operation
CN209339151U (en) A kind of fishing device pouring conduit for bored concrete pile
CN220813869U (en) Grouting pipe
CN209779723U (en) Pore-forming device with soil hole capable of rectifying inclination

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181016