CN207919322U - Bicycle occupation bridge pillarwork - Google Patents

Bicycle occupation bridge pillarwork Download PDF

Info

Publication number
CN207919322U
CN207919322U CN201721781393.XU CN201721781393U CN207919322U CN 207919322 U CN207919322 U CN 207919322U CN 201721781393 U CN201721781393 U CN 201721781393U CN 207919322 U CN207919322 U CN 207919322U
Authority
CN
China
Prior art keywords
section
web
cross
pillarwork
pipeline section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721781393.XU
Other languages
Chinese (zh)
Inventor
林四新
叶代成
饶健辉
林国斌
曾芳芳
洪天识
林丁榜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xiamen Municipal Construction And Development Co Ltd
In Sanhang (xiamen) Engineering Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Original Assignee
Xiamen Municipal Construction And Development Co Ltd
In Sanhang (xiamen) Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiamen Municipal Construction And Development Co Ltd, In Sanhang (xiamen) Engineering Co Ltd filed Critical Xiamen Municipal Construction And Development Co Ltd
Priority to CN201721781393.XU priority Critical patent/CN207919322U/en
Application granted granted Critical
Publication of CN207919322U publication Critical patent/CN207919322U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of bicycle occupation bridge pillarworks comprising cushion cap, pier stud and footing, the pier stud setting is on the cushion cap top, and the footing is arranged in the cushion cap lower part, and the pier stud includes:Variable cross-section portion and the cross-section portion being connect with the bottom in the variable cross-section portion, and the shape all same of each cross section in variable cross-section portion.The bicycle occupation bridge pillarwork of the utility model can sectional, welding, convenience in transport, construction efficiency be high at the scene;And structure is slim and graceful, solid reliable, low cost.

Description

Bicycle occupation bridge pillarwork
Technical field
The utility model is related to structural engineering field more particularly to a kind of bicycle occupation bridge pillarworks.
Background technology
China is that the maximum country of bicycle ownership has especially with flourishing for shared bicycle in the world The bicycle of the characteristics such as green, body-building, convenient will occupy an important position in the trip of people.But current China lacks bicycle Accommodation road, bicycle, pedestrian and motor vehicle mixing go together, thus lead to Frequent Accidents, both affected the driving of motor vehicle Efficiency also brings security risk to bicycle and pedestrian, reduces the comfort and convenience of cycling trip.
Utility model content
The utility model is directed to the drawbacks described above of the prior art, provides a kind of bicycle occupation bridge pillarwork, ties Structure is simple, easy to assembly, low cost.
Technical solution adopted by the utility model to solve its technical problems is:
There is provided a kind of bicycle occupation bridge pillarwork comprising cushion cap, pier stud and footing, the pier stud setting exist The cushion cap top, the footing are arranged in the cushion cap lower part, and the pier stud includes:Variable cross-section portion and with the variable cross-section The cross-section portion of the bottom connection in portion, and the shape all same of each cross section in variable cross-section portion.
Preferably, the cross section in the variable cross-section portion and cross-section portion is ellipse, and the cross in the variable cross-section portion Area of section is gradually reduced from top to bottom.
Preferably, the variable cross-section portion includes:First semicircle pipeline section, the first web, the second semicircle pipeline section and the second abdomen Plate;The first semicircle pipeline section, the first web, the second semicircle pipeline section and the second web are sequentially connected, and are cut with surrounding described become Face;And the top of the first semicircle pipeline section and the second semicircle pipeline section is bent outwards.
Preferably, the first semicircle pipeline section and the second semicircle pipeline section include sequentially connected several straight from top to bottom Line segment.
Preferably, the cross-section portion includes:Positioned at the third semicircle pipeline section of the first semicircle pipeline section bottom, positioned at institute State the third web of the first web bottom, positioned at the 4th semicircle pipeline section of the second semicircle pipeline section bottom and positioned at described the 4th web of two web bottoms.
Preferably, the footing includes:Anchoring base and the support portion being arranged on the anchoring base.
Preferably, the support portion peripheral surface is provided with several external stiffeners, and setting inside the support portion Inside stiffener arranged in a crossed manner.
Preferably, the anchoring base lower surface is provided with several anchor ribs.
The advantageous effect of technical solutions of the utility model is:
The bridge structure of the utility model can sectional, welding, convenience in transport, construction efficiency be high at the scene;And structure Merrily and lightheartedly, solid reliable, low cost.
Description of the drawings
Below in conjunction with accompanying drawings and embodiments, the utility model is described in further detail, in attached drawing:
Fig. 1 is the overall structure figure of bicycle occupation bridge pillarwork in the embodiments of the present invention one;
Fig. 2 is the overall structure figure of pier stud in the embodiments of the present invention one;
Fig. 3 is the Structure explosion diagram of pier stud in the embodiments of the present invention one;
Fig. 4 is the first semicircle pipeline section in the embodiments of the present invention one, the first web, the second semicircle pipeline section, the second abdomen The structure chart of plate;
Fig. 5 a are the structure charts of footing in the embodiments of the present invention one;
Fig. 5 b are the vertical views of the structure of footing in the embodiments of the present invention one;
Fig. 6 is the spelling schematic diagram of two cathetus section of the embodiments of the present invention;
Fig. 7 is the structure chart of internal stiffener in the embodiments of the present invention two.
Specific implementation mode
In order to make the purpose of this utility model, technical solution and advantage be more clearly understood, below in conjunction with attached drawing and reality Example is applied, the present invention will be further described in detail.It should be understood that specific embodiment described herein is only used for It explains the utility model, is not used to limit the utility model.
Embodiment one:
As shown in Figure 1, the bicycle occupation bridge pillarwork of the utility model includes cushion cap 100, for carrying steel case The pier stud 200 and at least one footing 300 of beam P, the pier stud 200 are arranged in 100 top of the cushion cap, the footing 300 It is arranged in 100 lower part of the cushion cap.
Specifically, as shown in Fig. 2, the pier stud 100 includes:Variable cross-section portion 101 and bottom with the variable cross-section portion 101 The cross-section portion 102 of portion's connection;In the present embodiment, the cross section 102 in the variable cross-section portion 101 and cross-section portion is ellipse Shape, and the shape all same of 101 each cross section of the variable cross-section portion, meanwhile, the cross-sectional area in the variable cross-section portion 101 from It is gradually reduced under, up big and down small structure is consequently formed, thus increased and the contact of 100 structure of pier stud (such as steel box-girder P) Area increases load-bearing capacity.
Further, as shown in figure 3, the variable cross-section portion 101 includes:First semicircle pipeline section 1011, the first web 1012, Second semicircle pipeline section 1013 and the second web 1014;The first semicircle pipeline section 1011, the first web 1012, the second semi-circular tube Section 1013 and the second web 1014 are sequentially connected and (such as weld), to surround the variable cross-section portion 101;And first semicircle The top of pipeline section 1011 and the second semicircle pipeline section 1013 is bent outwards.Corresponding, the cross-section portion 102 includes: Third semicircle pipeline section 1021 positioned at the first semicircle pipeline section bottom, the third web positioned at first web bottom 1022, the 4th positioned at the 4th semicircle pipeline section 1023 of the second semicircle pipeline section bottom and positioned at second web bottom Web 1024.
As shown in figure 4, the first semicircle pipeline section 1011 and the second semicircle pipeline section 1013 include from top to bottom successively Several straightways of connection, in the present embodiment, the straightway has 4, is L1-L4, and the interconnecting piece of each straightway gives phase Transversal, and each straightway, the first web 1012 and the second web 1014 with a hook at the end repair cut surplus (surplus 8-12mm, it is excellent It is selected as 10mm).
As shown in Fig. 5 a-5b, the footing 300 includes:Anchoring base 301 and setting are on the anchoring base 301 Support portion 302 (can be cylindrical steel structure).Add specifically, being provided with several outsides around 302 peripheral surface of the support portion Strength plate 303, and inside stiffener 304 arranged in a crossed manner is arranged in 302 inside of the support portion.Further, it is that enhancing structure is strong Degree, 301 lower surface of the anchoring base are provided with several anchor ribs 305, it is preferred that the anchor rib 305 can form several Concentric structure, so that uniform force.
Embodiment two:
The present embodiment additionally provides a kind of construction method of above-mentioned bicycle occupation bridge pillarwork comprising following step Suddenly:
S1, straight-seam pipes are cut in half as two semicircles, obtaining several straightways, (each straightway is a semicircle Pipe is straightway in each semicircle length of tube), third semicircle pipeline section and the 4th semicircle pipeline section, semicircle after incision can be by The effect of material internal stress in coiling process and flick, cause half circular diameter after cutting to become larger or lose circle, it is therefore necessary into Row flame straightening is handled, by the control of tube coupling out-of-roundness in the regular claimed range of manufacture;First semicircle pipeline section, the second semicircle pipeline section With a hook at the end to ask to repair when blanking and cuts surplus (surplus 8-12mm, preferably 10mm);Again by several straightways on moulding bed spelling (such as Fig. 6), docking site give intersection coordinate, and adjust it is linear after progress positioning welding, to form described the first half Pipe section and the second semicircle pipeline section;When welding, using CO2Gas shielded welding is completed, the first semicircle pipeline section after welding, the Two semicircle pipeline sections must carry out linear repetition measurement, and must be polished on the outside of butt weld, to ensure impression quality, if repetition measurement is unqualified Then carry out flame straightening processing;Finally, the first semicircle pipeline section, the second semicircle pipeline section completing to weld are carried out non-destructive testing, is closed It is for use after lattice;In addition, the first semicircle pipeline section and the second semicircle pipeline section welding groove are the bilateral V-butt of single side, can use It after the cutting of hand handle cutter, polishes according to the requirement of manufacture rule, reaches the given bevel angle of qualification of welding procedure and root face ruler It is very little;
S2, cutting form first web, the second web, third web and the 4th web;Likewise, the first web And second with a hook at the end to repair at the top of web and cut surplus (surplus 8-12mm, preferably 10mm);Likewise, each web welds slope Mouth is also the bilateral V-butt of single side, after can using the cutting of hand handle cutter, polishes according to the requirement of manufacture rule, reaches welding procedure The given bevel angle of evaluation and root face size;
S3, welding the first semicircle pipeline section, the second semicircle pipeline section, the first web and the second web, form the change Cross-section;
S4, the welding third semicircle pipeline section, the 4th semicircle pipeline section, third web and the 4th web, form described etc. Cross-section;
S5, variable cross-section section and cross-section section are crouched on platform and spelled, carry out tunneling boring docking, the variable cross-section section after spelling with Cross-section section should check that each portion's size, especially intermediate diagonal line are poor;Positioning welding is carried out after each dimensional gaughing qualification;Welding is made CO is used when industry2Gas shielded arc welding carries out variable cross-section section and the intersegmental welding of cross-section;Each portion's size is checked after welding, to deformation Position is corrected, and is carried out non-destructive testing;
S6, cutting form the external stiffener and internal stiffener;The internal stiffener blanking gives tolerance -6 ~-4mm (as shown in Figure 7), and internal stiffener is first welded as entirety, it is being welded to inside the support portion;
When external stiffener welding, bisector and external stiffener bars position line first are marked in support portion peripheral surface, Then external stiffener spelling and positioning welding are carried out, thus will the external stiffener be welded to the support portion peripheral surface with And on anchoring base;
And the external stiffener positioning welding it is complete after, check bottom plane, such as external stiffener is not same flat In face, then external stiffener must be reinstalled, external stiffener out of plumb must then polish or mechanical process;
S7, the anchor rib is fixed in the anchoring base lower surface, forms the footing;
And S8, top and lower part that the pier stud, footing are correspondingly arranged to the cushion cap respectively.
It should be noted that the technical characteristic in above-described embodiment one, two can carry out arbitrary combination, and the skill being composed Art scheme belongs to the scope of protection of the utility model.
In conclusion the bicycle occupation bridge pillarwork and its construction method of the utility model can segmentation groups at the scene Dress, welding, convenience in transport, construction efficiency are high;And multi-point welding technique is used, structure is slim and graceful, solid reliable.

Claims (8)

1. a kind of bicycle occupation bridge pillarwork comprising cushion cap, pier stud and footing, the pier stud setting are held described Platform top, the footing are arranged in the cushion cap lower part, which is characterized in that the pier stud includes:Variable cross-section portion and with it is described The cross-section portion of the bottom connection in variable cross-section portion, and the shape all same of each cross section in variable cross-section portion.
2. bicycle occupation bridge pillarwork as described in claim 1, which is characterized in that the variable cross-section portion and wait cut The cross section of face is ellipse, and the cross-sectional area in the variable cross-section portion is gradually reduced from top to bottom.
3. bicycle occupation bridge pillarwork as described in claim 1, which is characterized in that the variable cross-section portion includes:The One semi-circular tube section, the first web, the second semicircle pipeline section and the second web;The first semicircle pipeline section, the first web, the second half Pipe section and the second web are sequentially connected, to surround the variable cross-section portion;And the first semicircle pipeline section and the second semicircle The top of pipeline section is bent outwards.
4. bicycle occupation bridge pillarwork as claimed in claim 3, which is characterized in that the first semicircle pipeline section and Second semicircle pipeline section is including sequentially connected several straightways from top to bottom.
5. bicycle occupation bridge pillarwork as claimed in claim 4, which is characterized in that the cross-section portion includes:Position Third semicircle pipeline section in the first semicircle pipeline section bottom, the third web positioned at first web bottom, be located at it is described 4th semicircle pipeline section of the second semicircle pipeline section bottom and the 4th web positioned at second web bottom.
6. bicycle occupation bridge pillarwork as claimed in claim 5, which is characterized in that the footing includes:Anchor bottom Seat and the support portion being arranged on the anchoring base.
7. bicycle occupation bridge pillarwork as claimed in claim 6, which is characterized in that around the support portion peripheral surface Several external stiffeners are provided with, and inside stiffener arranged in a crossed manner is set inside the support portion.
8. bicycle occupation bridge pillarwork as claimed in claim 7, which is characterized in that the anchoring base lower surface is set It is equipped with several anchor ribs.
CN201721781393.XU 2017-12-19 2017-12-19 Bicycle occupation bridge pillarwork Expired - Fee Related CN207919322U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721781393.XU CN207919322U (en) 2017-12-19 2017-12-19 Bicycle occupation bridge pillarwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721781393.XU CN207919322U (en) 2017-12-19 2017-12-19 Bicycle occupation bridge pillarwork

Publications (1)

Publication Number Publication Date
CN207919322U true CN207919322U (en) 2018-09-28

Family

ID=63606799

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721781393.XU Expired - Fee Related CN207919322U (en) 2017-12-19 2017-12-19 Bicycle occupation bridge pillarwork

Country Status (1)

Country Link
CN (1) CN207919322U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035243A (en) * 2017-12-19 2018-05-15 中交三航(厦门)工程有限公司 Bicycle occupation bridge pillarwork and its construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035243A (en) * 2017-12-19 2018-05-15 中交三航(厦门)工程有限公司 Bicycle occupation bridge pillarwork and its construction method
CN108035243B (en) * 2017-12-19 2024-02-06 中交三航局第六工程(厦门)有限公司 Bridge pier column structure special for bicycle and construction method thereof

Similar Documents

Publication Publication Date Title
CN104439740B (en) A kind of welding method for blast furnace top flange
CN108146578A (en) A kind of manufacturing method of two phase stainless steel chemical tanker topside segmentation
CN107988908A (en) The total assembling method of tubular arch
CN110185138A (en) A kind of welding ball grid and its method for assembling and welding
CN102839747A (en) Construction method for steel structure truss of super high-rise special structure
CN103523168B (en) CSS platform connecting bridge area segmentation manufacturing process and special skew moulding bed
CN102601498A (en) Welding method for U-shaped ribs of orthotropic plate of bridge girder
CN108103938A (en) A kind of double deck module solid trial assembly method of large steel girder
CN105445434A (en) Pipeline steel pipe on-site girth welding evaluation method
CN104763156A (en) Assembling method of steel safety housing bottom seal head of nuclear power plant
CN105290573A (en) Welding method of medium-sized storage tank of 1000m<3>00Cr14Ni14Si4 steel
CN109079437A (en) Large size liquefied gas storage multilayer limb end socket arrangement and method for construction peculiar to vessel
CN207919322U (en) Bicycle occupation bridge pillarwork
CN102995553B (en) Arch rib of reinforced concrete arch bridge and erection support and manufacture method of arch rib
CN206917026U (en) A kind of steel disc shape node component for special-shaped Curtain wall frame
CN105905261A (en) Vertical general assembly jig frame for container ship lashing bridge
CN108894580B (en) Construction process of flare tower
CN205100572U (en) A support is adjusted in space pipe truss structure high altitude butt joint
CN107165317A (en) It is a kind of to be used for the steel disc shape node component and application process of special-shaped Curtain wall frame
CN106323169A (en) Sphere center coordinate positioning method
CN113714674A (en) Batch welding method for steel structure TKY nodes
CN108035243A (en) Bicycle occupation bridge pillarwork and its construction method
CN100366855C (en) Inclined triangular pyramid truss type frame construction and method for making, mounting and measuring the same
CN116275909A (en) Manufacturing method of heavy round square variable diameter node
CN209256164U (en) A kind of moulding bed device built for flare tower

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180928

Termination date: 20201219