CN207878714U - A kind of sub- wall of assembled light concrete - Google Patents

A kind of sub- wall of assembled light concrete Download PDF

Info

Publication number
CN207878714U
CN207878714U CN201820102547.6U CN201820102547U CN207878714U CN 207878714 U CN207878714 U CN 207878714U CN 201820102547 U CN201820102547 U CN 201820102547U CN 207878714 U CN207878714 U CN 207878714U
Authority
CN
China
Prior art keywords
wall
sub
layer
assembled light
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820102547.6U
Other languages
Chinese (zh)
Inventor
林军华
覃广
袁石江
张功新
程斌
王迎飞
刘德贞
倪荪
孙瞻
刘少聪
罗彦
张琨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC FOURTH HARBOR ENGINEERING BUREAU HARBOUR ENGINEERING DESIGN INSTITUTE Co Ltd
Original Assignee
CCCC FOURTH HARBOR ENGINEERING BUREAU HARBOUR ENGINEERING DESIGN INSTITUTE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC FOURTH HARBOR ENGINEERING BUREAU HARBOUR ENGINEERING DESIGN INSTITUTE Co Ltd filed Critical CCCC FOURTH HARBOR ENGINEERING BUREAU HARBOUR ENGINEERING DESIGN INSTITUTE Co Ltd
Priority to CN201820102547.6U priority Critical patent/CN207878714U/en
Application granted granted Critical
Publication of CN207878714U publication Critical patent/CN207878714U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of sub- walls of assembled light concrete, the wall body structure of sub- wall includes first layer lightweight concrete, latticed first layer cracking resistance muscle, first layer tension rib, light sandwich layer, second layer tension rib, latticed second layer cracking resistance muscle and second layer lightweight concrete successively from the inside to the outside, and pre-embedded pipe and oblique cutting reinforcing bar are equipped in wall.The sub- wall of assembled light concrete of the utility model can achieve the effect that mechanization Fast Installation is constructed.Wall is poured into a mould integral after being bound by vertical muscle, the stirrup of reserved tension rib and constructional column;It pours into a mould integral after the reserved tension rib of wall indulges muscle with column, stirrup is bound, improves between wall and the globality between wall and column;Separated with floor, beam by installing extruded sheet on wall top, improves the anti-seismic performance of building structure.

Description

A kind of sub- wall of assembled light concrete
Technical field
The utility model is related to a kind of fabricated sub- walls of lightweight concrete.
Background technology
It is pointed out in " General Office of the State Council is about the instruction for greatly developing assembled architecture ", implements the 18 of party comprehensively It is big and 18 three in, in four, the fifth plenary session and central urbanization working conference, central urban work conference key agreement, conscientiously The CPC Central Committee and the State Council's decision and deployment are implemented, according to " five in one " total arrangement and " four comprehensively " strategic, are firmly established With carry out innovation, coordination, green, opening, shared idea of development, according to be applicable in, economy, safety, green, beauty are wanted It asks, pushes mode of construction innovation, greatly develop assembly concrete building and steel building, assembled architecture is continuously improved and exists Ratio in new building.Adhere to standardized designs, factorial praluction, prefabricated construction, integrated finishing, information system management, Intelligent Application, improves technical level and construction quality, promotes building industry transition and upgrade.
Traditional wall construction technique generally uses common brick, Dinas brickes, air-entrained concrete building block etc. to be built by laying bricks or stones.These There are many deficiencies in common materials for wall:
(1) common brick refers to solid clay brick, and because it destroys arable land in process of production, waste of resource pollutes environment, at present state Family takes the measure forbidden to protect farmland and environment;
(2) Dinas brickes is to allow to mix pigment and additive using sand and lime as primary raw material, is prepared through blank, compacting It is molded, through common Dinas brickes made of autoclave curing, sanded brick surfacing is smooth, poor with the bonding of mortar, be easy to cause Gaul cracks.Absorption speed is slow, blocked up coat of plaster, be easy to cause mortar trickling cracking.It is strong with mortar bonding after building by laying bricks or stones Degree is not high, causes masonry shear strength relatively low, influences the use in earthquake protection area to a certain extent.
(3) air-entrained concrete building block, be using calcareous material (cement or lime), siliceous material (sand or flyash etc.) and Foaming agent (generally use aluminium powder) generates silicate Tuo Bomolai through adding water to be chemically reacted under high-temperature steam curing hydrothermal condition Stone etc., forms the lightweight entirety with uniform gas cell distribution, and porosity is up to 70%~80%.Since porosity is very big, make it Effective loaded area is reduced, therefore intensity is generally all relatively low.Due to there is no skeleton soil in air entrained concrete, hydrated product Crystallization degree is higher, and plastic deformation is small, therefore without apparent crackle before stress destruction, once it is cracked, it will collapse immediately Destruction is split, this is different from the property of normal concrete, therefore the elasticity modulus of air entrained concrete is less than normal concrete.Aerating is mixed Solidifying soil product is light material, is used as materials for wall, the quality of unit area is smaller, therefore its sound-insulation capability is low.
, there is technique backwardness in above-mentioned three kinds common material masonry panels, need largely manually to carry out removing brick, slurrying, Build by laying bricks or stones, brooming, plaster etc., process is more, and mechanization degree is low, inefficiency, in the case where craftsmanship is horizontal irregular, Construction quality is difficult to be protected, and faces working at height danger again.To solve the above-mentioned problems, it is proposed that a kind of assembled Lightweight concrete wall construction technology.
Utility model content
The utility model provides a kind of sub- wall of fabricated lightweight concrete, is suitable for the construction wall of frame structure Construction, by precast wall body, lifting wall, effective connection of wall and column, beam, floor can realize building rapid construction.
To achieve the goals above, the utility model uses following technical scheme:A kind of assembled light concrete Wall, the wall body structure of sub- wall include first layer lightweight concrete, latticed first layer cracking resistance muscle, the successively from the inside to the outside One layer of tension rib, light sandwich layer, second layer tension rib, latticed second layer cracking resistance muscle and second layer lightweight concrete, wall It is equipped with pre-embedded pipe and oblique cutting reinforcing bar in vivo.
Pre-buried hanging ring is additionally provided in wall, each one of pre-buried hanging ring or so is made of, reinforcing bar penetrates through the length of wall reinforcing bar Side, hanging ring ring body protrude from the top of wall.
Cracking resistance muscle uses the steel wire of fenestral fabric or is process by bar-mat reinforcement, and is covered in entire metope, and two Spacing between layer cracking resistance muscle is 5-15cm.
Tension rib is made of screw-thread steel, enters wall 35cm, exposed 25cm, is arranged by 0.5m spacing along sub- wall long side.
The spacing of a diameter of 8 millimeters of oblique cutting reinforcing bar, adjacent oblique cutting reinforcing bar is 0.3 meter.
Multigroup screw hole through walls is reserved in wall, screw hole two through walls is one group, is located at sub- wall length side To same straight line on, the sub- wall of assembled light concrete be equipped with location adjusting device, location adjusting device have it is multigroup, Every group includes two wall end adjusters and a ground surface end adjuster, installs the adjusting of wall end respectively in two screw holes through walls Device installs ground surface end adjuster on ground, and ground surface end adjuster and two wall end segment devices use oblique connection strut and water respectively Flushconnection strut is hingedly connected together.
Wall top is provided with the tongue and groove of outer recessed convex, the tongue and groove of the bottom end setting evagination indent of wall.
The sub- wall of assembled light concrete of the utility model uses prefabrication mode, and precision is high, realizes machinery Change continuous production, not only labor intensity is low, and production efficiency is high, and surface of wall is smooth, is not necessarily to plaster, and construction quality is good;Wall Size can arbitrarily be adjusted according to different parts, the door-window opening on wall, and pipeline, wire box etc. can be according to design drawings pre- It carries out default and pre-buried during system, is significantly reduced the pipeline installation fluting of traditional wall, pipe laying and mends the constructions such as slot, and Substantially building waste is not generated, the various processes that on-site conventional construction method is greatly reduced are interlocked, and the peace of site operation is reduced Full blast danger.
Lightweight concrete used by the sub- wall of assembled light concrete of the utility model has porous structure lightweight Moisture is continuously replenished in hydration reaction in material, the water absorbing properties that this structure has, to the shape between cement and coarse aggregate The impermeability of lightweight concrete is improved at a closely knit interface, porous material itself also has thermal and insulating performance, and Light sandwich layer is set in wall, and can use up a step reduces the dead weight of wall, and can improve the sound insulation, heat preservation, thermal insulation of wall Energy.
The location adjusting device of assembled light concrete wall can be quickly in place, and accurately the verticality of adjustment wall and Horizontal position, fixed wall reach the construction of mechanization Fast Installation.Wall by the vertical muscle of reserved tension rib and constructional column, It is poured into a mould after stirrup binding integral;It pours into a mould integral after the reserved tension rib of wall indulges muscle with column, stirrup is bound, improves wall Between and the globality between wall and column;Separated with floor, beam by installing extruded sheet on wall top, improves building The anti-seismic performance of structure.
Description of the drawings
Fig. 1 is the layered structure schematic diagram of the sub- wall of assembled light concrete of the utility model.
Fig. 2 a are sectional schematic diagram of the sub- wall of assembled light concrete of the utility model when as exterior wall.
Fig. 2 b are bow direction view of the sub- wall of assembled light concrete of the utility model when as exterior wall.
Fig. 2 c are that the sub- wall of assembled light concrete of the utility model uses location adjusting device when as exterior wall When schematic diagram.
Fig. 3 a are section signal of the sub- wall of assembled light concrete of the utility model when as interior wall or partition wall Figure.Fig. 3 b are bow direction view of the sub- wall of assembled light concrete of the utility model when as interior wall or partition wall.
Fig. 3 c are that the sub- wall of assembled light concrete of the utility model uses positioning to adjust when as interior wall or partition wall Schematic diagram when regulating device.
Fig. 4 is delay-pour joint schematic diagram between the sub- wall of assembled light concrete and wall.
Fig. 5 is the sub- wall of assembled light concrete and structural column connection diagram.
Assembled light concrete walls 1, second layer lightweight concrete 2, second layer cracking resistance muscle 3, light sandwich layer 4, first Layer cracking resistance muscle 5, hanging ring 6, tension rib 7 reserve screw hole 8 through walls, and first layer lightweight concrete 9 stays Sunken wire tube 10, oblique cutting muscle 11, wall top tongue and groove 12, wall bottom end tongue and groove 13, upper layer floor slab bottoms tongue and groove 14, lower layer's floor slab tops tongue and groove 15, upper floor Plate 16, lower layer's floor 17, extruded sheet 18, wall end adjuster 19, oblique continuous strut 20, ground surface end adjuster 21, horizontal direction connect Continuous strut 22, stirrup 23 indulge muscle 24, the concrete 25 of constructional column strength grade, the concrete 26 of structural column strength grade.
Specific implementation mode
It is as shown in Figure 1 the structure of the sub- wall of assembled light concrete of the utility model, the wall body structure of sub- wall Include first layer lightweight concrete 9, latticed first layer cracking resistance muscle 5, the tension rib 7 of first layer, lightweight successively from the inside to the outside Laminboard layer 4, the tension rib 7 of the second layer, latticed second layer cracking resistance muscle 3 and second layer lightweight concrete 2, interior be equipped with of wall are stayed Sunken wire tube 10 and oblique cutting muscle 11.Pre-buried hanging ring 6 is additionally provided in wall, each one of pre-buried hanging ring or so is made of, reinforcing bar is passed through reinforcing bar Across the length direction of wall, hanging ring ring body protrudes from the top of wall.
By taking prefabricated and installation specification is 290cm*430cm*20cm exterior walls as an example, illustrate the specific implementation of the utility model Mode.
1, pre- system wall:Building masonry wall is resolved into several sub- walls according to architecture construction figure, between sub- wall It is reserved with last-cost joint gap width, reserves the last-cost joint gap width 0.3m connected between sub- wall, the apparent size of two sub- walls 1 It is 290cm*200cm*20cm.
2, steps are as follows for the sub- wall of prefabricated lightweight concrete:
(1) it is laid with layer of plastic film on smooth prefabricated place as end template, is made in the way of " lying low " And the template of sub- wall surrounding is installed, form height presses the thickness 20cm of wall, leave a door unlocked in advance on sub- wall, window, hole.Such as Fig. 2 a Shown in each figures of~2c, when group wall is exterior wall, setting wall top tongue and groove 12, installs sub- wall when installing sub- wall upper end template Wall bottom end tongue and groove 13 is set when the template of body lower end;
(2) cast first layer lightweight concrete 9, thickness 5cm, lightweight concrete uses thick bone of the light-weight aggregate as concrete Material, using fine sand, flyash as fine aggregate, forms with cement mixing, and it is 0.5~1% that addition, which accounts for concrete batching gross mass, Water-reducing agent and 8~12% impervious agent, intensity C15 or more, density is in 1800kg/m3Below.Wherein water-reducing agent and impervious agent Use conventional existing water-reducing agent and impervious agent then.
(3) first layer cracking resistance muscle 5, steel wire diameter 5mm, grid spacing 10cm*10cm are completely spread;
(4) installation first layer tension rib 7, specification are the screw-thread steel of diameter 16mm, length 60cm, enter wall 35cm, exposed 25cm is arranged along sub- wall long side by 0.5m spacing;
(5) two hanging rings 6 are installed, spacing 1m, using 18 reinforcing bar of diameter, length runs through wall long side;
(6) installation light sandwich layer 4, apparent size 230cm*140cm*10cm, material uses polystyrene extruded sheet, With heat preservation, heat-insulated, fire protecting performance.
(7) installation second layer tension rib 7, specification are the screw-thread steel of diameter 16mm, length 60cm, enter wall 35cm, exposed 25cm is arranged along sub- wall long side by 0.5m spacing;
(8) second layer cracking resistance muscle 5, steel wire diameter 5mm, grid spacing 10cm*10cm are completely spread;
(9) pre-embedded pipe 10;
(10) oblique cutting reinforcing bar 11 is required, using diameter 8mm reinforcing bars, spacing 0.3m;
(11) cast second layer lightweight concrete 2, levelling, thickness 5cm, lightweight concrete uses haydite concrete, prepares Intensity is C15;
(12) form removal after reaching 80% to intensity is conserved, is stacked after number neat.
3, sub- wall lifting and installation, steps are as follows:
(1) when lower layer's floor 17 is poured into a mould, branch film and pour into a mould form lower layer's floor slab tops tongue and groove 15, with sub- wall bottom end look forward to Mouth 13 corresponds to;
(2) it is levelling to be laid with one layer of 2~3cm waterproof mortar;
(3) tower crane is used to lift the sub- wall 1 accordingly numbered, the hanging ring 6 of crane hook and sub- wall 1 interlocks, and lifting is simultaneously It falls on predetermined installation site;
(4) the installation wall end adjuster 19 on reserved screw hole through walls 8, the installation ground surface end adjuster 21 on ground, The wall end adjuster 19 on top is connected with ground surface end adjuster 21 using oblique continuous strut 20, the wall end adjuster 19 in lower part Be connected using horizontal continuity strut 22 with ground surface end adjuster 21, continuous strut and be hingedly between the adjuster at its both ends Connection, by revolving the verticality and levelness that continuous strut is adjustable positioning wall.
(5) suspension hook is unloaded, lifting is completed.
4, the connection of sub- wall, steps are as follows:
Last-cost joint gap between (1) two width wall arranged between sub- wall by constructional column requirement and indulges muscle 24 and stirrup 23, son The reserved tension rib 7 of wall binds integral with vertical muscle 24, stirrup 23, and mixing for C30 or more intensity is poured into a mould after the installation form of both sides Solidifying soil;
(2) the reserved tension rib of sub- wall indulges muscle 24 with adjacent pillars, stirrup 23 is bound, and column template is installed, using structural column The concrete 26 that strength grade requires is poured into a mould, and column and wall are formed entirety;
(3) extruded sheet 18, thickness 5cm are installed on sub- wall top, the template and reinforcing bar of installation upper floor plate 16 are poured mixed Upper layer floor 16, sub- wall 1 are poured integral, one layer of wall of completion and structure construction by solidifying soil;
(4) step (3) is repeated, building main body construction is successively completed.
5, after concrete strength reaches and tears film condition open, the continuous strut 22 of horizontal direction, oblique continuous strut 20, ground are removed Adjuster 21, metope end adjuster 19 are held, construction template, column template, floor and beam forms is removed, completes construction.

Claims (7)

1. a kind of sub- wall of assembled light concrete, which is characterized in that the wall body structure of sub- wall includes successively from the inside to the outside First layer lightweight concrete, latticed first layer cracking resistance muscle, first layer tension rib, light sandwich layer, second layer tension rib, net The second layer cracking resistance muscle and second layer lightweight concrete of trellis, wall is interior to be equipped with pre-embedded pipe and oblique cutting reinforcing bar.
2. the sub- wall of assembled light concrete according to claim 1, which is characterized in that be additionally provided with pre-buried hang in wall Ring, each one of pre-buried hanging ring or so, is made of reinforcing bar, and reinforcing bar penetrates through the long side of wall, and hanging ring ring body protrudes from the top of wall.
3. the sub- wall of assembled light concrete according to claim 1, which is characterized in that cracking resistance muscle uses latticed knot The steel wire of structure is process by bar-mat reinforcement, and is covered in entire metope, and the spacing between two layers of cracking resistance muscle is 5-15cm.
4. the sub- wall of assembled light concrete according to claim 1, which is characterized in that tension rib is by screw-thread steel structure At, enter wall 35cm, exposed 25cm, along sub- wall long side by 0.5m spacing arrange.
5. the sub- wall of assembled light concrete according to claim 1, which is characterized in that a diameter of the 8 of oblique cutting reinforcing bar The spacing of millimeter, adjacent oblique cutting reinforcing bar is 0.3 meter.
6. the sub- wall of assembled light concrete according to claim 1, which is characterized in that be reserved with multigroup wear in wall Wall screw hole, screw hole two through walls is one group, is located on the same straight line of sub- wall length direction, the assembled is light The sub- wall of matter concrete be equipped with location adjusting device, location adjusting device have it is multigroup, every group include two wall end adjusters and one A ground surface end adjuster installs wall end adjuster respectively in two screw holes through walls, and ground surface end adjuster, ground are installed on ground Face end adjuster is hingedly connected together using oblique connection strut and horizontal connection strut respectively with two wall end segment devices.
7. the sub- wall of assembled light concrete according to claim 1, it is characterised in that:Wall top is provided with outer recessed The tongue and groove of convex, the tongue and groove of the bottom end setting evagination indent of wall.
CN201820102547.6U 2018-01-22 2018-01-22 A kind of sub- wall of assembled light concrete Active CN207878714U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820102547.6U CN207878714U (en) 2018-01-22 2018-01-22 A kind of sub- wall of assembled light concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820102547.6U CN207878714U (en) 2018-01-22 2018-01-22 A kind of sub- wall of assembled light concrete

Publications (1)

Publication Number Publication Date
CN207878714U true CN207878714U (en) 2018-09-18

Family

ID=63507803

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820102547.6U Active CN207878714U (en) 2018-01-22 2018-01-22 A kind of sub- wall of assembled light concrete

Country Status (1)

Country Link
CN (1) CN207878714U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853785A (en) * 2019-01-22 2019-06-07 河南聚誉帆工程技术咨询有限公司 Assembled integral fills partition wall and fabrication and installation method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853785A (en) * 2019-01-22 2019-06-07 河南聚誉帆工程技术咨询有限公司 Assembled integral fills partition wall and fabrication and installation method

Similar Documents

Publication Publication Date Title
CN101818539B (en) Assembled integral building and construction method thereof
CN106013811B (en) A kind of installation method of assembled architecture
CN108130964A (en) A kind of construction method of assembled light concrete wall
CN105317137B (en) Precast wall body, wallboard and its construction method and prefabricated panel production method
CN104358341B (en) Building brickwork and masonry construction method of building brickwork
CN201738600U (en) Assembled integrated type building
CN101831986B (en) Precast composite outer insulated wall plate and manufacturing method thereof
CN103321257A (en) Anti-cracking seepage-proof construction method for ultra-long mass concrete structure basement
CN101858114A (en) Construction method for cast-in-place integral light-weight partition wall
CN107190891B (en) A kind of Building Skin rammed earth wall preparation method
CN101285330A (en) Environment protection type structure thermal insulation concrete block, masonry and method for anti-knock domestic architecture
CN106592426A (en) Prefabricated template system for transverse pre-stress overall width reinforced concrete bridge deck and construction method
CN110258848A (en) A kind of construction method of building energy conservation CL composite shear wall
CN105780976B (en) Compound concrete shear wall structure and its concreting method
CN104074305B (en) A kind of self-heat conserving decoration integrated Multi-function light concrete composite plates and curtain wall
CN209482591U (en) Prefabricated molds shell structure column construction structure
CN105239718A (en) Integral heat insulation wallboard building system
CN103572966A (en) Construction method for silo funnel liner
CN105201101A (en) Light aggregate concrete small hollow block building masonry construction method
CN109898698B (en) Construction method of antique building wire seam wall
CN105019593B (en) Building heat preservation prefabricated section and modular arrangement of reinforcement cast-in-place method construction method thereof
CN207878714U (en) A kind of sub- wall of assembled light concrete
CN207110214U (en) A kind of prefabricated interior fill concrete wallboard
CN106894538A (en) Filling wall and agent structure concrete integral shaping method