CN207878415U - A kind of floating sewage blocking structure applied to long piled wharf - Google Patents

A kind of floating sewage blocking structure applied to long piled wharf Download PDF

Info

Publication number
CN207878415U
CN207878415U CN201721419162.4U CN201721419162U CN207878415U CN 207878415 U CN207878415 U CN 207878415U CN 201721419162 U CN201721419162 U CN 201721419162U CN 207878415 U CN207878415 U CN 207878415U
Authority
CN
China
Prior art keywords
anchor ear
slot
intercept net
mainboard
mentioned
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721419162.4U
Other languages
Chinese (zh)
Inventor
刘鹏晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Original Assignee
Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Municipal Engineering Design Insitute Group Co Ltd filed Critical Shanghai Municipal Engineering Design Insitute Group Co Ltd
Priority to CN201721419162.4U priority Critical patent/CN207878415U/en
Application granted granted Critical
Publication of CN207878415U publication Critical patent/CN207878415U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of a kind of floating sewage blocking structures applied to long piled wharf, including pile foundation, it is transversely provided with intercept net between two adjacent pile bases, the lower part of intercept net is equipped with buoyant means, the both sides of intercept net and buoyant means are equipped with the slot of a genesis analysis, slot is fixedly connected by anchor ear mechanism with pile foundation, the both sides of intercept net and buoyant means may be contained in the slot of both sides, buoyant means resist intercept net, intercept net and buoyant means and move towards upper and lower displacement along the groove body of slot upwards.Technique effect:It is not restricted by fluctuation in stage, is satisfied under various water level operating modes and blocks dirty requirement;Slim and graceful compared with conventional fixed-type steel grating web frame, consumptive material is few;Anchor ear slot is Demountable, blocks dirty structure and is easily installed and overhauls, highly practical.

Description

A kind of floating sewage blocking structure applied to long piled wharf
Technical field
The utility model is related to the technical fields of trash block system, and the one kind for being specifically applied to long piled wharf is floating type Dirty structure is blocked, more particularly to its mechanical connecting structure.
Background technology
Binjiang city of bordering on the sea often is attacked by natural calamities such as typhoon, heavy rain, high tide level and floods, floating on water House refuse, waste construction material etc. usually enter with flow action below long piled wharf, are not easily cleaned, simultaneously for some codes Rubbish is easily accumulated there are the region of certain interval with land-based area and seriously affect landscape in head rear.In the prior art, fixation is mostly used Formula steel grating net satisfaction blocks dirty function, and what the cell structure that large area need to be arranged simultaneous could meet low tide and high tide level blocks dirty need It asks, and mostly stationary structure, structure bulky and steel structure anti-corrosion paint, which reach, to be not easy the later stage after service life and overhaul.
Invention content
The purpose of this utility model is to provide a kind of a kind of floating sewage blocking structures applied to long piled wharf, not by water The restriction of position fluctuation, disclosure satisfy that and block dirty requirement under various water level operating modes, slim and graceful compared with conventional fixed-type steel grating web frame, It is easily installed and overhauls simultaneously, overcome shortcoming and defect existing in the prior art.
To achieve the goals above, the technical solution of the utility model is:One kind applied to long piled wharf floating type is blocked Dirty structure, including pile foundation, intercept net is transversely provided between two adjacent pile bases, and the lower part of intercept net is equipped with buoyant means, blocks The both sides for cutting net and buoyant means are equipped with the slot of a genesis analysis, and slot is fixedly connected by anchor ear mechanism with pile foundation, The both sides of intercept net and buoyant means may be contained in the slot of both sides, and buoyant means resist intercept net upwards, intercept net and floating Body device moves towards upper and lower displacement along the groove body of slot.
The utility model discloses a kind of floating sewage blocking structure applied to long piled wharf, technique effects:Not by water level The restriction of fluctuation is satisfied under various water level operating modes and blocks dirty requirement;It is slim and graceful compared with conventional fixed-type steel grating web frame, consumptive material It is few;Anchor ear slot is Demountable, blocks dirty structure and is easily installed and overhauls, highly practical.
Description of the drawings
Fig. 1 is the utility model floating sewage blocking structural facades schematic diagram.
Fig. 2 is the utility model floating sewage blocking structural profile illustration.
Fig. 3 is the utility model floating sewage blocking structure intercepts net schematic diagram.
Fig. 4 is the utility model floating sewage blocking structure slot and anchor ear structural scheme of mechanism.
Fig. 5 is the 1-1 of Fig. 4 to structural schematic diagram.
Fig. 6 is the 2-2 phase structure schematic diagrames of Fig. 4.
Fig. 7 is the utility model floating sewage blocking structure case study on implementation floor map.
Fig. 8 is the utility model floating sewage blocking structure case study on implementation diagrammatic cross-section.
Wherein:
1, pile foundation;
2, intercept net;
3, slot;
4, expanded steel diamond mesh;
5, chan frame;
6, steel pipe;
7, pvc pipe;
8, fixation steel plate;
9, mainboard;
10, outer side seal board;
11, trough floor;
12, bolt;
13, extension;
14, anchor ear piece;
15, stiffener;
16, bolts assemblies substrate;
17, bending part;
18, stiffener plate;
19, thick node steel plate;
20, floor;
21, fixing bolt;
22, bottom sealing plate.
Specific implementation mode
The technical solution of the utility model is clearly and completely described below in conjunction with attached drawing, it is clear that described Embodiment is the utility model a part of the embodiment, instead of all the embodiments.Based on the embodiments of the present invention, originally The every other embodiment that field those of ordinary skill is obtained without making creative work, belongs to this practicality Novel protected range.
It is in the description of the present invention, it should be noted that term "center", "upper", "lower", "left", "right", " perpendicular Directly ", the orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings, and is only The utility model and simplifying describes for ease of description, do not indicate or imply the indicated device or element must have it is specific Orientation, with specific azimuth configuration and operation, therefore should not be understood as limiting the present invention.In addition, term " the One ", " second " is used for description purposes only, and is not understood to indicate or imply relative importance.
The utility model discloses a kind of a kind of floating sewage blocking structure applied to long piled wharf, including pile foundation 1, areas It is not in the prior art:Intercept net 2 is transversely provided between two adjacent pile bases 1, the lower part of intercept net 2 is filled equipped with floating body It sets, the both sides of intercept net 2 and buoyant means are equipped with the slot 3 of a genesis analysis, and slot 3 passes through anchor ear mechanism and pile foundation 1 It is fixedly connected, the both sides of intercept net 2 and buoyant means may be contained in the slot 3 of both sides, and buoyant means resist intercept net upwards 2, intercept net 2 and buoyant means move towards upper and lower displacement along the groove body of slot 3.
In the specific implementation, the chan frame 5 that the intercept net 2 is distributed by rectangular-shaped expanded steel diamond mesh 4 and enclosing shape It constitutes, chan frame 5 is distributed in 4 outer rim of expanded steel diamond mesh in shape is enclosed.Fixed frame using 14b channel steels as intercept net 2 Frame forms garbage barrier net, and a 8mm thickness nodes steel plate 19 is arranged in each angle point, increases globality.Expanded steel diamond mesh 4 selects aperture The expanded metal lath of 24*60mm, thickness 6mm.
In the specific implementation, the upper limb and lower edge of the buoyant means are respectively arranged with the steel pipe 6 of a cross direction profiles, and two Parallelly distribute on has a several pvc pipes 7 between root steel pipe 6,6 outer diameter 150mm of steel pipe, thickness 5mm, pvc pipe outer diameter 150mm, two By the longitudinally disposed connection of fixation steel plate 8 in one between steel pipe 6 and several pvc pipes 7, fixation steel plate thickness 6mm is fixed A comb part pilot hole is offered at steel plate 8, above-mentioned steel pipe 6 and pvc pipe 7 are through at successively in the pipe fitting pilot hole of fixation steel plate 8, Fixation steel plate 8 is distributed with above-mentioned steel pipe 6 and the perpendicular shape of pvc pipe 7.Fixation steel plate 8 is for fixing above-mentioned steel pipe 6 and pvc pipe 7.Pvc pipe plays main floating body, and the weight that quantity setting is considered as top garbage barrier net is determined by calculation, and meets float structure Be submerged in below the water surface, garbage barrier net structure bubble through the water column always play the role of it is full-time block it is dirty.
In the specific implementation, the slot 3 is made of mainboard 9, outer side seal board 10, trough floor 11, mainboard 9 and outer side seal board 10 be in parallelly distribute in space, and mainboard 9, outer side seal board 10 constitute the both sides cell wall of slot 3, and above-mentioned trough floor 11 is located at master Between plate 9 and outer side seal board 10,11 both sides of trough floor are respectively perpendicular to be arranged with mainboard 9 and outer side seal board 10, and the one of trough floor 11 The stitching portion of lateral edges and mainboard 9, which is fixed, welds, and trough floor is provided with floor 20 at 11 other side, and the floor 20 is vertically and slot bottom Plate 11 is distributed, also, the floor 20 and above-mentioned outer side seal board 10 are in parallelly distribute on, and bolt hole, bolt hole are offered on floor 20 It is inside provided with bolt 12, outer side seal board 10 is connect by above-mentioned bolt 12 with floor 20, extension 13 and the above-mentioned anchor ear of mainboard 9 Mechanism is fixedly connected, and the anchor ear mechanism is made of the semicircular anchor ear piece of two panels 14, extension 13 and the above-mentioned anchor ear of mainboard 9 Piece 14 is fixedly connected, and one piece of stiffener 15 is equipped between trough floor 11 and anchor ear piece 14, one end of stiffener 15 is perpendicular to slot bottom Plate 11 is arranged, and the other end of stiffener 15 is fixedly connected with above-mentioned anchor ear piece 14, and the inside edge of stiffener 15 is perpendicular to mainboard 9 Extension 13 be arranged, the semicircular anchor ear piece of two panels 14, which is filled the span of a man's arms, lives in state pile foundation 1, and bottom sealing plate 22 is equipped at the lower end of slot 3.
In the specific implementation, mainboard 9, outer side seal board 10, trough floor 11, bottom sealing plate thickness be 14mm.
In the specific implementation, the thickness of above-mentioned anchor ear piece 14 is 14mm, and the thickness of stiffener 15 is also 14mm, floor 20 Thickness is 10mm.
In the specific implementation, slot, hooping structure are that detachable structure is easily installed and overhauls.
In the specific implementation, the both ends of the anchor ear piece 14 are respectively equipped with a bolts assemblies substrate 16, bolts assemblies substrate Bending part 17 is formed between 16 and 14 end of anchor ear piece, it is in three that formation is approximate between 14 outer wall of anchor ear piece and bolts assemblies substrate 16 Angular stiffener plate 18, the semicircular anchor ear piece of above-mentioned two panels 14 are filled the span of a man's arms on above-mentioned pile foundation 1, and the two of two panels anchor ear piece 14 It is mutually permanently connected by the fixing bolt 21 being set on bolts assemblies substrate 16 between end.
As shown in Figures 7 and 8, the example by floating sewage blocking structure setting the edge after harbour, it is solid by anchor ear slot Due between heel row pile foundation, when installation, is first fixed anchor ear slot by bolt and pile foundation, then by floating sewage blocking main structure body It is installed in slot by the gap handling of harbour rear(Outer side seal board is not installed at this time), by side seal outside slot after bearing calibration Plate will block dirty structure level direction by bolt and fix, and the guaranteed water level fluctuation phase blocks dirty structure vertical and moves up and down in the water surface, full Foot blocks dirty requirement.
Schematically the utility model and embodiments thereof to be described, description is not limiting, attached drawing institute Show one of the embodiment of only the utility model.The connection type disclosed in the utility model is applied to more generally complete prefabricated It, can be according to pipe gallery connection type, to reserving trepanning, pin, water-swellable waterproof washer when pipe gallery connecting node Number and distribution mode are suitably adjusted.Therefore, if others skilled in the art are in the feelings for creating objective without departing from the utility model Under condition, within the spirit and principle of the utility model, any modification, equivalent substitution, improvement and etc. done, using with the skill The similar means of structural connection of art scheme and case study on implementation, belong to the scope of protection of the utility model.

Claims (5)

1. applied to a kind of floating sewage blocking structure of long piled wharf, including pile foundation(1), it is characterised in that:Two adjacent piles Base(1)Between be transversely provided with intercept net(2), intercept net(2)Lower part be equipped with buoyant means, intercept net(2)With buoyant means Both sides are equipped with the slot of a genesis analysis(3), slot(3)Pass through anchor ear mechanism and pile foundation(1)It is fixedly connected, intercept net (2)It may be contained within the slot of both sides with the both sides of buoyant means(3)Interior, buoyant means resist intercept net upwards(2), intercept net (2)With buoyant means along slot(3)Groove body move towards upper and lower displacement.
2. a kind of floating sewage blocking structure according to claim 1 applied to long piled wharf, it is characterised in that:It is described to block Cut net(2)By rectangular-shaped expanded steel diamond mesh(4)With the chan frame for enclosing shape distribution(5)It constitutes, chan frame(5)In enclosing Shape is distributed in expanded steel diamond mesh(4)Outer rim.
3. a kind of floating sewage blocking structure according to claim 1 applied to long piled wharf, it is characterised in that:It is described floating The upper limb and lower edge of body device are respectively arranged with the steel pipe of a cross direction profiles(6), two steel pipes(6)There is parallelly distribute between if Dry root pvc pipe(7), two steel pipes(6)With several pvc pipes(7)Between pass through longitudinally disposed fixation steel plate(8)Connection is in one Body, fixation steel plate(8)Place offers a comb part pilot hole, above-mentioned steel pipe(6)And pvc pipe(7)It is through at fixation steel plate successively(8) Pipe fitting pilot hole in, fixation steel plate(8)With above-mentioned steel pipe(6)And pvc pipe(7)Perpendicular shape distribution.
4. a kind of floating sewage blocking structure according to claim 1 applied to long piled wharf, it is characterised in that:It is described to insert Slot(3)By mainboard(9), outer side seal board(10), trough floor(11)It constitutes, mainboard(9)With outer side seal board(10)In flat in space Row distribution, mainboard(9), outer side seal board(10)Constitute slot(3)Both sides cell wall, above-mentioned trough floor(11)Positioned at mainboard(9) With outer side seal board(10)Between, trough floor(11)Both sides are respectively perpendicular and mainboard(9)With outer side seal board(10)Setting, trough floor (11)One side edge and mainboard(9)Stitching portion fix welding, trough floor(11)Floor is provided at the other side(20), the rib Plate(20)Vertically and trough floor(11)Distribution, also, the floor(20)With above-mentioned outer side seal board(10)In parallelly distribute on, floor (20)On offer bolt hole, be provided with bolt in bolt hole(12), outer side seal board(10)Pass through above-mentioned bolt(12)With floor (20)Connection, mainboard(9)Extension(13)It is fixedly connected with above-mentioned anchor ear mechanism, the anchor ear mechanism is semicircular by two panels Anchor ear piece(14)It constitutes, mainboard(9)Extension(13)With above-mentioned anchor ear piece(14)It is fixedly connected, trough floor(11)With anchor ear piece (14)Between be equipped with one piece of stiffener(15), stiffener(15)One end perpendicular to trough floor(11)Setting, stiffener(15)'s The other end and above-mentioned anchor ear piece(14)It is fixedly connected, stiffener(15)Inside edge perpendicular to mainboard(9)Extension(13) Setting, the semicircular anchor ear piece of two panels(14)It fills the span of a man's arms and lives in state pile foundation(1), slot(3)Lower end at be equipped with bottom sealing plate(22).
5. a kind of floating sewage blocking structure according to claim 4 applied to long piled wharf, it is characterised in that:Described armful Hoop pieces(14)Both ends be respectively equipped with a bolts assemblies substrate(16), bolts assemblies substrate(16)With anchor ear piece(14)Between end Form bending part(17), anchor ear piece(14)Outer wall and bolts assemblies substrate(16)Between form approximate stiffener plate triangular in shape (18), the above-mentioned semicircular anchor ear piece of two panels(14)It fills the span of a man's arms in above-mentioned pile foundation(1)On, two panels anchor ear piece(14)Both ends between By being set to bolts assemblies substrate(16)On fixing bolt(21)It is mutually permanently connected.
CN201721419162.4U 2017-10-31 2017-10-31 A kind of floating sewage blocking structure applied to long piled wharf Active CN207878415U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721419162.4U CN207878415U (en) 2017-10-31 2017-10-31 A kind of floating sewage blocking structure applied to long piled wharf

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721419162.4U CN207878415U (en) 2017-10-31 2017-10-31 A kind of floating sewage blocking structure applied to long piled wharf

Publications (1)

Publication Number Publication Date
CN207878415U true CN207878415U (en) 2018-09-18

Family

ID=63500644

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721419162.4U Active CN207878415U (en) 2017-10-31 2017-10-31 A kind of floating sewage blocking structure applied to long piled wharf

Country Status (1)

Country Link
CN (1) CN207878415U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110894713A (en) * 2019-03-28 2020-03-20 自然资源部第二海洋研究所 Wharf protection structure with high safety performance

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110894713A (en) * 2019-03-28 2020-03-20 自然资源部第二海洋研究所 Wharf protection structure with high safety performance
CN110894713B (en) * 2019-03-28 2021-01-08 自然资源部第二海洋研究所 Wharf protection structure

Similar Documents

Publication Publication Date Title
US7364385B1 (en) Protective flood barrier
US20170002532A1 (en) Method for river/lake level regulation and water conservancy system
CN106836275B (en) Landscape eco-friendly retaining wall for rapidly protecting tillite slope and implementation method
US5252002A (en) Natural bottom culvert and method for installation
EA027010B1 (en) Retention device for liquids or free flowing substances
Morris et al. Ground motions and damage observations in the Marlborough region from the 2013 Lake Grassmere earthquake
EP2545221B1 (en) "l" shape universal structural elements and methods of its use
CN207878415U (en) A kind of floating sewage blocking structure applied to long piled wharf
KR200449689Y1 (en) A compound erosion control dam
CN207714348U (en) A kind of deep basal pit fast rainfall device
RU2310034C2 (en) Shore-protective retaining structure
RU2525405C1 (en) Method to strengthen slope with geocellular geosynthetic material
CN212103878U (en) Breakwater component and breakwater structure thereof
CN203270470U (en) Comprehensive prevention and control facility structure suitable for wind and sand of railway of plateau river wide-valley section
JP5407995B2 (en) Filling reinforcement structure
CN208763024U (en) A kind of internal support of foundation pit structure
CN112031119B (en) Large-section flood discharge ditch for mountainous terrain and construction method thereof
CN211498458U (en) Bridge deck waterproof structure of steel truss bridge
US4293245A (en) Structural system and structural elements for use and construction of earth filled walls
AU753030B2 (en) Structural modules
RU60538U1 (en) FLIGHT BEAM STRUCTURE
JP6519705B1 (en) Flood prevention water stop structure
CN215105050U (en) Dyke reinforcing structure
CN203238660U (en) Open-type reinforced concrete frame foundation for retaining wall
CN103243738A (en) Foundation for open type retaining wall with reinforced concrete frame

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant