CN207863502U - A kind of Construction of Steel Structure life line bracket - Google Patents
A kind of Construction of Steel Structure life line bracket Download PDFInfo
- Publication number
- CN207863502U CN207863502U CN201721702808.XU CN201721702808U CN207863502U CN 207863502 U CN207863502 U CN 207863502U CN 201721702808 U CN201721702808 U CN 201721702808U CN 207863502 U CN207863502 U CN 207863502U
- Authority
- CN
- China
- Prior art keywords
- connecting plate
- construction
- steel structure
- steel
- life line
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 52
- 239000010959 steel Substances 0.000 title claims abstract description 52
- 238000010276 construction Methods 0.000 title claims abstract description 24
- 230000000149 penetrating effect Effects 0.000 claims abstract description 8
- 238000009434 installation Methods 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Emergency Lowering Means (AREA)
Abstract
The utility model discloses a kind of Construction of Steel Structure life line brackets, it is desirable to provide a kind of Construction of Steel Structure life line bracket of high construction efficiency.It includes upright bar, is fixedly installed on the connecting plate of upright bar lower end, and the nut being set on connecting plate is screwed in the screw rod on nut, and the backing plate being set on connecting plate;Open slot is arranged in the one of avris of connecting plate, the backing plate is fixedly installed at the downside of open slot open end, the nut be fixedly installed on it is at the upside of open slot open end and opposite with backing plate, by screw screw rod can make the lower end of screw rod between backing plate at a distance from change;For the upper through-hole of steel wire penetrating, the lower through-hole for steel wire penetrating is arranged in the top of the connecting plate for the upper end setting of the upright bar.The utility model can effectively improve working efficiency, and significantly reduce construction cost.
Description
Technical field
The utility model is related to steel structures in construction works auxiliary instrument technical fields, more particularly, to a kind of Construction of Steel Structure
Life line bracket.
Background technology
Steel construction industry development in China's is rapid at present, is especially widely used in skyscraper, large-span space structure.Steel knot
Structure construction worker faces prodigious risk when walking or operating on girder steel, wherein the person occurs to fall to be maximum
Risk.How preferably to be ensured personal safety in Pre-tensioned Steel Structures, is a urgent problem.
Utility model content
The purpose of this utility model is intended to overcome the shortcomings of the prior art, provides one kind and is convenient to mount and dismount, reliability
By force, the Construction of Steel Structure life line bracket of safety.
In order to solve the above-mentioned technical problem, the utility model is achieved through the following technical solutions:
A kind of Construction of Steel Structure life line bracket, one end when use state upward is known as upper end, under the other end is known as
End;Including upright bar, it is fixedly installed on the connecting plate of upright bar lower end, the nut being set on connecting plate is screwed in the spiral shell on nut
Bar, and the backing plate that is set on connecting plate;Open slot, the backing plate fixed setting is arranged in the one of avris of connecting plate
At the downside of open slot open end, the nut be fixedly installed on it is at the upside of open slot open end and opposite with backing plate, lead to
Cross screw screw rod can make the lower end of screw rod between backing plate at a distance from change;The upper end of the upright bar is arranged for steel wire penetrating
Upper through-hole, the connecting plate top setting for steel wire penetrating lower through-hole.
Preferably, the upright bar uses length to be made of the DN36mm steel pipes of 480mm.
Preferably, the connecting plate is made of the steel plate of 5mm.
Preferably, the screw rod uses M16 screw rods.
Preferably, the backing plate uses length × width x thickness for the steel plate of 35 × 35 × 5mm.
Preferably, the steel pipe is used with connecting plate and is welded to connect.
Preferably, the connecting plate is used with nut and is welded to connect.
Preferably, the connecting plate is used with backing plate and is welded to connect.
Compared with prior art, the utility model has the following advantages that:
The life rope support installation of the utility model is more convenient compared to traditional welding holder, and safety,
Reliably, working efficiency is effectively increased, and due to being detachably used in turn, construction cost can be effectively reduced.
Description of the drawings
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment
Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only
It is some embodiments of the utility model, for those of ordinary skill in the art, in the premise not made the creative labor
Under, it can also be obtained according to these attached drawings other attached drawings.
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the top perspective view of Fig. 1.
Fig. 3 is the schematic diagram of the utility model installation condition.
Schematic diagram when Fig. 4 is the utility model construction usage.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are not under the premise of making the creative labor
The every other embodiment obtained, shall fall within the protection scope of the present invention.
Construction of Steel Structure life line bracket shown in Fig. 1-4, one end when use state upward are known as upper end, the other end
Referred to as lower end;Including upright bar 1, be fixedly installed on the connecting plate 3 of 1 lower end of upright bar, the nut 5 being set on connecting plate 3, screw in
Screw rod 2 on nut 5, and the backing plate 4 that is set on connecting plate 3;Open slot is arranged in 3 one of avris of the connecting plate,
The backing plate 4 is fixedly installed at the downside of open slot open end, and the nut 5 is fixedly installed on the upside of open slot open end
Place and opposite with backing plate 4, by screw screw rod 2 can make the lower end of screw rod 2 between backing plate 4 at a distance from change;The upright bar
The upper through-hole 7 for steel wire penetrating is arranged in 1 upper end, and the top setting of the connecting plate 3 is logical for the lower part of steel wire penetrating
Hole 6.
As specific technical solution, the upright bar 1 uses length to be made of the DN36mm steel pipes of 480mm, is ensureing by force
Under the premise of degree, there is lighter weight.The connecting plate 3 is made of the steel plate of 5mm.The screw rod 2 uses M16 screw rods.
The backing plate 4 uses length × width x thickness for the steel plate of 35 × 35 × 5mm.The steel pipe is used with connecting plate 3 and is welded to connect.It is described
Connecting plate 3 is used with nut 5 and is welded to connect.The connecting plate 3 is used with backing plate 4 and is welded to connect.
Before girder steel 10 lifts, holder is installed on girder steel 10 in advance, and in the upper through-hole of holder 7 and lower through-hole 6
Upper installation steel wire rope 20, holder spacing are not more than 3m.Adjusting screw rod anchors into nut length first when installation, and holder is enable smoothly to wear
Enter 10 upper flange of girder steel, then fastening screw, so that screw rod, upper flange, backing plate is completely embedded, fixation.Then twice are put on
Steel wire rope 20 is lifted with girder steel 10.After the completion of girder steel 10 is lifted and fastened, holder is connected firmly with girder steel 10, so behaviour
Make worker when 10 top of girder steel is walked and is operated, directly safety belt can be fixed on the steel wire rope on holder, avoid work
People can not be protected when back is constructed and caused by it is dangerous.After the completion of girder steel 10 welds, in profiled sheet laying construction, with
Striking while profiled sheet is laid with.By adjusting screw rod, holder is enable smoothly to be taken out from girder steel 10, company is utilized after taking-up
The lower through-hole of fishplate bar reeves 20, and smooth handling support is gone downstairs, convenient and quick.
The above is only the preferred embodiment of the utility model only, is not intended to limit the utility model, all at this
Within the spirit and principle of utility model, any modification, equivalent replacement, improvement and so on should be included in the utility model
Protection domain within.
Claims (8)
1. a kind of Construction of Steel Structure life line bracket, one end when use state upward is known as upper end, and the other end is known as lower end;
It is characterized in that:Including upright bar(1), it is fixedly installed on upright bar(1)The connecting plate of lower end(3), it is set to connecting plate(3)On spiral shell
It is female(5), screw in nut(5)On screw rod(2), and it is set to connecting plate(3)On backing plate(4);The connecting plate(3)Its
In avris open slot, the backing plate are set(4)It is fixedly installed at the downside of open slot open end, the nut(5)Gu
Surely it is set at the upside of open slot open end and and backing plate(4)Relatively, by screwing screw rod(2)It can make screw rod(2)Lower end
With backing plate(4)Between distance change;The upright bar(1)Upper end setting for steel wire penetrating upper through-hole(7), described
Connecting plate(3)Top setting for steel wire penetrating lower through-hole(6).
2. Construction of Steel Structure life line bracket according to claim 1, it is characterised in that:The upright bar(1)Use length for
The DN36mm steel pipes of 480mm are made.
3. Construction of Steel Structure life line bracket according to claim 1 or claim 2, it is characterised in that:The connecting plate(3)Using
The steel plate of 5mm is made.
4. Construction of Steel Structure life line bracket according to claim 1 or claim 2, it is characterised in that:The screw rod(2)Using M16
Screw rod.
5. Construction of Steel Structure life line bracket according to claim 1 or claim 2, it is characterised in that:The backing plate(4)Using length ×
Width x thickness is the steel plate of 35 × 35 × 5mm.
6. Construction of Steel Structure life line bracket according to claim 1 or claim 2, it is characterised in that:The upright bar(1)With connecting plate
(3)Using being welded to connect.
7. Construction of Steel Structure life line bracket according to claim 1 or claim 2, it is characterised in that:The connecting plate(3)With nut
(5)Using being welded to connect.
8. Construction of Steel Structure life line bracket according to claim 1 or claim 2, it is characterised in that:The connecting plate(3)With backing plate
(4)Using being welded to connect.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721702808.XU CN207863502U (en) | 2017-12-10 | 2017-12-10 | A kind of Construction of Steel Structure life line bracket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721702808.XU CN207863502U (en) | 2017-12-10 | 2017-12-10 | A kind of Construction of Steel Structure life line bracket |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207863502U true CN207863502U (en) | 2018-09-14 |
Family
ID=63468450
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721702808.XU Expired - Fee Related CN207863502U (en) | 2017-12-10 | 2017-12-10 | A kind of Construction of Steel Structure life line bracket |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207863502U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109381831A (en) * | 2018-11-21 | 2019-02-26 | 中建二局第建筑工程有限公司 | A kind of safety device |
-
2017
- 2017-12-10 CN CN201721702808.XU patent/CN207863502U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109381831A (en) * | 2018-11-21 | 2019-02-26 | 中建二局第建筑工程有限公司 | A kind of safety device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207863502U (en) | A kind of Construction of Steel Structure life line bracket | |
CN207093932U (en) | Construction spring hanger | |
CN205805002U (en) | A kind of safety rope fixing device for job site | |
CN208858177U (en) | Steel Structure Installation lifeline sets up device | |
CN214995799U (en) | Tool type wall hanging cantilever frame | |
CN211369496U (en) | Triangular anti-shaking support piece for scaffold | |
CN208545993U (en) | Building hoist basement top plate returns back to top structure | |
CN205476399U (en) | Install scaffold on steel construction | |
CN202324586U (en) | Integral attached device attached with lifting scaffold | |
CN201771170U (en) | Diagonal rod for bracing frame or scaffold | |
CN201381615Y (en) | Exterior wall cladding connecting device | |
CN202729581U (en) | Jaw mouth clamp for pipeline hoisting | |
CN112942777A (en) | Ultrahigh-layer periphery protection cyclic telescopic detachable cantilever structure and mounting method | |
CN201714048U (en) | Chrysanthemum clip connection type scaffold | |
CN212639698U (en) | Pipe group fixing hanger | |
CN201722912U (en) | Transverse support rod of scaffold | |
CN206432671U (en) | The new anti-pendulum ring of transmission line of electricity falling proof device | |
CN103410272B (en) | Tube truss structure lower chord promotes fixed point device | |
CN217071214U (en) | Adjustable portable cantilever type fixed fire receiving hopper device for super high-rise section steel column | |
CN204386031U (en) | The crossbeam of bar and triangle gusset taken by a kind of band | |
CN107253677A (en) | A kind of firm engineering tower crane of underframe | |
CN204727501U (en) | Tower crane attachment device for complex building | |
CN201253431Y (en) | Aloft work fail-safe device | |
CN203499273U (en) | Tube truss structure upper chord lifting fixed-point device | |
CN211871224U (en) | Small-size hoist and mount electric hoist |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180914 |