CN207863491U - Building construction formwork component - Google Patents
Building construction formwork component Download PDFInfo
- Publication number
- CN207863491U CN207863491U CN201820108958.6U CN201820108958U CN207863491U CN 207863491 U CN207863491 U CN 207863491U CN 201820108958 U CN201820108958 U CN 201820108958U CN 207863491 U CN207863491 U CN 207863491U
- Authority
- CN
- China
- Prior art keywords
- measurement pipe
- concrete
- building construction
- construction formwork
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model discloses a kind of building construction formwork components, it is related to technical field of building construction, its key points of the technical solution are that including the reference block being arranged on floor, reference block includes metallic plate and measurement pipe, the end face of measurement pipe is concordant with the bottom surface of metallic plate, and seal ring is fixedly connected in measurement pipe.The outer wall that the utility model solves the existing measurement pipe being placed on roof is generally upper relatively smooth, in concrete setting, since the temperature around measurement pipe is different from concrete and measures pipe surface smoother, so that concrete defective tightness when being connect with measurement pipe, it is easy to appear certain gaps, in rainy days, rainwater can flow into this gap along the outer wall of measurement pipe, and then it flows into floor, so that the structure in floor is impregnated by rainwater, the problem of intensity of floor may being impacted, so that rainwater will not be flowed into along the outer wall of measurement pipe in floor.
Description
Technical field
The utility model is related to technical field of building construction, more particularly to a kind of building construction formwork component.
Background technology
In actual life, the construction of building is generally completed using the mode of template casting concrete, is building roof
When, usually first template is placed, is put by reinforcing bar hog frame, is then being poured, when in order to ensure to pour roof
Roof flush is generally provided with pre-embedded block on roof, measurement pipe is provided on pre-embedded block so that poured in staff
It can there are one for comparing the benchmark of height when concrete so that the surface for the roof that staff pours out is more concordant,
And setting measurement pipe can also make staff that need not open up measured hole on floor again when measuring slab thickness, generally exist
Measurement pipe is still cast in concrete by staff when pouring, and only exposes the opening part of measurement pipe so that work people
Member only needs to stretch into measuring scale into measurement pipe the thickness that can conveniently measure floor.
But the outer wall of the existing measurement pipe being placed on roof is generally upper relatively smooth, in concrete setting,
Since the temperature around measurement pipe is different from concrete and measures pipe surface smoother so that concrete is connect with measurement pipe
When defective tightness, it is easy to there is certain gap, in rainy days, rainwater can flow into this seam along the outer wall of measurement pipe
Gap, and then flow into floor so that the structure in floor is impregnated by rainwater, may be impacted to the intensity of floor.
Utility model content
The purpose of this utility model is to provide a kind of building construction formwork components, it to existing by being arranged in floor
On reference block on measurement pipe be improved so that when concrete and measurement pipe contact, gap smaller between the two, and
And connection is more closely.
The above-mentioned purpose of the utility model technical scheme is that:
A kind of building construction formwork component, including the reference block that is arranged on roof, the reference block include metallic plate with
And the measurement pipe of setting on a metal plate, the end face of the measurement pipe is concordant with the bottom surface of metallic plate, fixed in the measurement pipe
It is connected with for preventing water along the seal ring for measuring gap between pipe outer wall inflow measurement pipe and concrete, is poured in staff
When building concrete, the height of seal ring is set above concrete layer.
By using above-mentioned technical proposal, when in use, first reference block is placed on floor, and seal ring is fixed
It is connected in measurement pipe, then staff's casting concrete on floor, and the height of concreting is poured as only
By measurement pipe close to nozzle position expose sub-fraction, and seal ring be located at concrete layer upside and not with concrete layer
Contact so that seal ring will block after concrete setting in the gap occurred with measurement pipe contact position so that rainwater when raining
When flowing downward along measurement pipe outer wall, stopped by seal ring so that rainwater is along the table of seal ring away from survey
The direction of buret outer wall flows away, and rainwater will not enter gap, and by concrete and can generally be surveyed at work in staff
The contact position of buret outer wall is set as with certain slope, and is slightly above other positions close to the position for measuring pipe outer wall,
So that rainwater will not enter in gap in flowing.By being fixedly connected with seal ring in measurement pipe so that rainwater will not
Enter floor along the gap between measurement pipe and concrete.
The utility model is further arranged to:The mode that the seal ring is connected through a screw thread is fixedly connected on measurement pipe
On.
By using above-mentioned technical proposal so that the connection between seal ring and measurement pipe is more convenient, and staff
It is also more convenient when needing to replace seal ring.
The utility model is further arranged to:It is provided with sealing strip between the seal ring and measurement pipe.
By using above-mentioned technical proposal so that the connection between measurement pipe and seal ring more closely, and in sealing
Water on the upside of ring is stopped by sealing strip, will not flow into screw thread along the outer wall of measurement pipe.
The utility model is further arranged to:The protective plug coordinated with measurement pipe is provided in the measurement pipe.
By using above-mentioned technical proposal, when staff's casting concrete, sometimes accidentally by concreting into
In measurement pipe, concrete solidifies in measurement pipe so that measuring scale is being stretched into measurement pipe progress slab thickness by staff
When test, the concrete in measurement pipe can cause to interfere to measuring scale so that the slab thickness that staff measures is not accurate enough
Really, enter concrete in measurement pipe in order to prevent, the protective plug coordinated with measurement pipe is provided in measurement pipe.
The utility model is further arranged to:It is provided on the protective plug for preventing protective plug to be fully inserted into measurement pipe
Blocking portion, the blocking portion integrally be more than protective plug.
By using above-mentioned technical proposal so that protective plug is when in measurement pipe, under the action of blocking portion, prevents
Shield plug will not be fully inserted into measurement pipe.
The utility model is further arranged to:The blocking portion is integrally more than nozzle one end of measurement pipe.
By using above-mentioned technical proposal so that when protective plug is inserted into measurement pipe, blocking portion lid is located in measurement pipe, blocking
The nozzle of measurement pipe is blocked in portion completely so that rainwater will not flow downward along the outer wall at measurement pipe nozzle
The utility model is further arranged to:The blocking portion is fixedly connected with draw ring in the one side of measurement pipe.
By using above-mentioned technical proposal, when protective plug is mounted in measurement pipe, in order to enable protective plug is convenient for from survey
It is extracted in buret, blocking portion is fixedly connected with draw ring in the one side of measurement pipe so that staff is carrying out slab thickness
Measurement when, it is only necessary to pull draw ring, can conveniently remove protective plug, then measuring scale is stretched into measurement pipe, from
And carry out the measurement of slab thickness.
The utility model is further arranged to:Be provided with saw-tooth ring on the outer wall of the measurement pipe, the saw-tooth ring it is oblique
Facing towards side of the measurement pipe far from metallic plate.
By using above-mentioned technical proposal, in order to enable concrete and the gap smaller between pipe outer wall is measured, and coagulation
Soil is connect more closely with measurement pipe, and in the more difficult inflow concrete layer of rainwater, saw is provided on the outer wall of measurement pipe
Ring gear, and the inclined-plane of saw-tooth ring is towards side of the measurement pipe far from metallic plate.Therefore by concreting when on floor,
Concrete is connected with the saw-tooth ring in measurement pipe so that the gap between concrete and measurement pipe becomes tortuous, both makes
Rainwater is not easily accessed in gap, but also what is connected between measurement pipe and concrete is more secured.
In conclusion the utility model has the advantages that:
1, by being fixedly connected with seal ring in measurement pipe so that rainwater will not be along between measurement pipe and concrete
Gap enters floor;
2, by being provided with protective plug in measurement pipe so that for staff in casting concrete, concrete will not be into
Enter measurement pipe;
3, by the way that saw-tooth ring of the inclined-plane towards measurement pipe nozzle is arranged in the junction of measurement pipe and concrete so that coagulation
Gap smaller of the soil in solidification between measurement pipe, and gap is bending so that and water is more difficult to enter floor.
Description of the drawings
Fig. 1 is that the schematic diagram in roof is arranged in reference block in embodiment 1;
Fig. 2 is the structure chart that measurement pipe is contacted with concrete in embodiment 1;
Fig. 3 is the enlarged drawing in the portions A in Fig. 2.
In figure, 1, roof;2, reference block;21, metallic plate;22, measurement pipe;3, seal ring;4, sealing strip;5, protective plug;
6, blocking portion;7, draw ring;8, saw-tooth ring.
Specific implementation mode
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment 1:A kind of building construction formwork component, as shown in Figure 1, including the reference block 2 being arranged on roof 1, base
Quasi- block 2 includes metallic plate 21 and the measurement pipe 22 being arranged on metallic plate 21, wherein the end face of measurement pipe 22 and metallic plate 21
Bottom surface it is concordant.
As shown in Fig. 2, building construction formwork component further includes being arranged in measurement pipe 22 for preventing water along measurement pipe
22 outer walls flow into the seal ring 3 in gap between measurement pipe 22 and concrete.Here the mode that seal ring 3 is connected through a screw thread is solid
Surely it is connected in measurement pipe 22, in order to enable the connection between measurement pipe 22 and seal ring 3 is more closely, with reference to Fig. 3, is measuring
Sealing strip 4 is provided between pipe 22 and seal ring 3.
As shown in Fig. 2, when in use, first reference block 2 is placed on floor, and seal ring 3 is fixedly connected on survey
On buret 22, then staff's casting concrete on floor, and the height of concreting is poured will only to measure
Pipe 22 exposes sub-fraction close to the position of nozzle, and seal ring 3 is located at the upside of concrete layer and is not connect with concrete layer
It touches so that seal ring 3 will block after concrete setting in the gap occurred with 22 contact position of measurement pipe so that rainwater when raining
When flowing downward along 22 outer wall of measurement pipe, by the blocking of seal ring 3 so that rainwater is along the surface of seal ring 3 to remote
Direction from 22 outer wall of measurement pipe flows away, and rainwater will not enter gap, and staff at work generally can be by coagulation
The contact position of soil and 22 outer wall of measurement pipe is set as with certain slope, and is slightly above close to the position of 22 outer wall of measurement pipe
Other positions so that rainwater will not enter in gap in flowing.By being fixedly connected with seal ring 3 in measurement pipe 22,
So that rainwater will not enter floor along the gap between measurement pipe 22 and concrete.
In staff's casting concrete, sometimes accidentally by concreting into measurement pipe 22, concrete exists
It is solidified in measurement pipe 22 so that measuring scale when being stretched into the test of the progress slab thickness of measurement pipe 22 by staff, measurement pipe
Concrete in 22 can cause to interfere to measuring scale so that the slab thickness that staff measures is not accurate enough, in order to prevent
Enter concrete in measurement pipe 22, the protective plug 5 coordinated with measurement pipe 22 is provided in measurement pipe 22.And on protective plug 5
It is provided with the blocking portion 6 for preventing protective plug 5 to be fully inserted into measurement pipe 22, the whole pipe for being more than measurement pipe 22 of blocking portion 6
Mouth one end, the lid of blocking portion 6 are located in measurement pipe 22, the nozzle of measurement pipe 22 are blocked completely so that rainwater will not be along measurement
Outer wall at 22 nozzle of pipe flows downward.When protective plug 5 is mounted in measurement pipe 22, in order to enable protective plug 5 is convenient for from survey
It is extracted in buret 22, blocking portion 6 is fixedly connected with draw ring 7 in the one side of measurement pipe 22 so that staff is carrying out building
When the measurement of plate thickness, it is only necessary to pull draw ring 7, can conveniently remove protective plug 5, then measuring scale is stretched into measurement
In pipe 22, to carry out the measurement of slab thickness.
As shown in Fig. 2, in order to enable gap smaller between 22 outer wall of concrete and measurement pipe, and concrete and measurement pipe
22 connections more closely, in the more difficult inflow concrete layer of rainwater, are provided with saw-tooth ring 8 on the outer wall of measurement pipe 22,
And the inclined-plane of saw-tooth ring 8 is towards side of the measurement pipe 22 far from metallic plate 21.Therefore by concreting when on floor,
Concrete is connected with the saw-tooth ring 8 in measurement pipe 22 so that the gap between concrete and measurement pipe 22 becomes tortuous, both
So that rainwater is not easily accessed in gap, but also what is connected between measurement pipe 22 and concrete is more secured.
The application method of the utility model is:First reference block 2 is placed on floor, and seal ring 3 is fixedly connected
In measurement pipe 22, then staff's casting concrete on floor, and the height of concreting is poured only will
Measurement pipe 22 close to nozzle position expose sub-fraction, and seal ring 3 be located at concrete layer upside and not with concrete
Layer contact so that seal ring 3 will block after concrete setting in the gap occurred with 22 contact position of measurement pipe so that when raining
Rainwater along 22 outer wall of measurement pipe when flowing downward, by the blocking of seal ring 3 so that rainwater along seal ring 3 surface
It is flowed away to the direction far from 22 outer wall of measurement pipe, rainwater will not enter gap, and can generally be incited somebody to action at work in staff
The contact position of concrete and 22 outer wall of measurement pipe is set as with certain slope, and is omited close to the position of 22 outer wall of measurement pipe
Higher than other positions so that rainwater will not enter in gap in flowing.By being fixedly connected with sealing in measurement pipe 22
Ring 3 so that rainwater will not enter floor along the gap between measurement pipe 22 and concrete.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability
Field technique personnel can as needed make the present embodiment the modification of not creative contribution after reading this specification, but
As long as all being protected by Patent Law in the right of the utility model.
Claims (8)
1. a kind of building construction formwork component, it is characterised in that:Including being arranged in roof(1)On reference block(2), the benchmark
Block(2)Including metallic plate(21)And it is arranged in metallic plate(21)On measurement pipe(22), the measurement pipe(22)End face with
Metallic plate(21)Bottom surface it is concordant, the measurement pipe(22)On be fixedly connected and be useful for preventing water along measurement pipe(22)Outer wall stream
Enter measurement pipe(22)The seal ring in gap between concrete(3), in staff's casting concrete, seal ring(3)Height
Degree is set above concrete layer.
2. building construction formwork component according to claim 1, it is characterised in that:The seal ring(3)Connected by screw thread
The mode connect is fixedly connected on measurement pipe(22)On.
3. building construction formwork component according to claim 2, it is characterised in that:The seal ring(3)With measurement pipe
(22)Between be provided with sealing strip(4).
4. building construction formwork component according to claim 3, it is characterised in that:The measurement pipe(22)On be provided with
Measurement pipe(22)The protective plug of cooperation(5).
5. building construction formwork component according to claim 4, it is characterised in that:The protective plug(5)Upper setting is useful
In preventing protective plug(5)It is fully inserted into measurement pipe(22)Blocking portion(6), the blocking portion(6)It is whole to be more than protective plug(5).
6. building construction formwork component according to claim 5, it is characterised in that:The blocking portion(6)It is whole to be more than survey
Buret(22)Nozzle one end.
7. building construction formwork component according to claim 6, it is characterised in that:The blocking portion(6)Away from measurement pipe
(22)One side on be fixedly connected with draw ring(7).
8. building construction formwork component according to claim 7, it is characterised in that:The measurement pipe(22)Outer wall on set
It is equipped with saw-tooth ring(8), the saw-tooth ring(8)Inclined-plane towards measurement pipe(22)Far from metallic plate(21)Side.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820108958.6U CN207863491U (en) | 2018-01-22 | 2018-01-22 | Building construction formwork component |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820108958.6U CN207863491U (en) | 2018-01-22 | 2018-01-22 | Building construction formwork component |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207863491U true CN207863491U (en) | 2018-09-14 |
Family
ID=63462933
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820108958.6U Active CN207863491U (en) | 2018-01-22 | 2018-01-22 | Building construction formwork component |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207863491U (en) |
-
2018
- 2018-01-22 CN CN201820108958.6U patent/CN207863491U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106584654A (en) | Production process for prefabricated reinforced concrete duct pieces | |
CN110617083A (en) | Real-time intelligent monitoring and alarming construction method for tunnel lining concrete compactness | |
CN108333109B (en) | Concrete structure internal crack monitoring device and method | |
CN109139051A (en) | A kind of tunnel grouting structure and construction | |
CN207348469U (en) | A kind of constructional column pours device | |
CN207863491U (en) | Building construction formwork component | |
CN111576232B (en) | Linear control construction method for precast beam top plate | |
CN207863480U (en) | A kind of building construction formwork component being arranged in roof | |
CN207863481U (en) | A kind of building construction formwork component | |
CN207363274U (en) | The control prospecting tools of superelevation wall column concreting thickness | |
CN209243781U (en) | It is a kind of for underground engineering main body construction seam and post-cast strip waterproof construction | |
CN210827105U (en) | High-speed railway bridge deck system structure based on prefabricated cable groove | |
CN106013254B (en) | A kind of construction method of the concrete works swaging die with skeleton | |
CN209703563U (en) | A kind of cast-in-place well room steel form of circle | |
CN207920623U (en) | A kind of information-based monitoring system of tunnel lining trolley concrete cast | |
CN216921375U (en) | Concrete anti-seepage structure | |
CN209637234U (en) | A kind of concrete floor slab placement concrete thickness caliberating device | |
CN205421648U (en) | A hollow anti device that floats of box for hollow superstructure of cast -in -place concrete | |
CN209837114U (en) | Advanced water stop structure of foundation bottom plate post-cast strip | |
CN109653252A (en) | A kind of cast-in-place well room steel form of circle and construction method | |
CN208137954U (en) | A kind of armpit Angle formwork for structure of the subway construction | |
CN212872157U (en) | Automatic detection device for filling fullness of filling layer under plate type ballastless track plate | |
CN220365061U (en) | Simple post-pouring belt plugging device | |
CN220100229U (en) | Post-pouring belt ponding prevention structure | |
CN109083193A (en) | Airport pipe gallery standard digital template construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |