CN207862974U - The quick support shuttering system of city integrated piping lane construction - Google Patents
The quick support shuttering system of city integrated piping lane construction Download PDFInfo
- Publication number
- CN207862974U CN207862974U CN201820137424.6U CN201820137424U CN207862974U CN 207862974 U CN207862974 U CN 207862974U CN 201820137424 U CN201820137424 U CN 201820137424U CN 207862974 U CN207862974 U CN 207862974U
- Authority
- CN
- China
- Prior art keywords
- piping lane
- plate
- integrated piping
- hydraulic pressure
- city integrated
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model discloses the quick support shuttering systems of city integrated piping lane construction, it includes comprehensive gallery bottom plate, multiple warehouse partition wall seats to be poured not being equally spaced are fixed on the comprehensive gallery bottom plate, it is provided with plate device at the top of the warehouse partition wall seat to be poured, it is equipped on the plate device for the fixed tensioning mechanism of template, it is installed with more horizontal strainers between plate device at the top of adjacent warehouse partition wall seat to be poured, the top template lower face of the plate device is installed with hydraulic pressure diagonal brace mounting device, it is installed with hydraulic pressure tightening mechanism on the hydraulic pressure diagonal brace mounting device.The support shuttering system can be used in the rapid construction of city integrated piping lane, and the build process of this template system is convenient and efficient, can quickly be moved to next storehouse surface after a storehouse surface pours completion, and then improve construction efficiency.
Description
Technical field
The utility model belongs to underground pipe gallery technical field of construction, and in particular to a kind of city integrated quick branch of piping lane construction
Support template system.
Background technology
Urban Underground pipe gallery engineering refers to building a municipal administration in Urban Underground to share tunnel, by electric power, communication, confession
A variety of municipal pipelines such as water, combustion gas are integrated in one, and " unified planning, unified construction, unified management " are carried out, to accomplish the underground space
Comprehensive utilization and resource it is shared.It is the important infrastructure and " lifeline " for ensureing city operations.It is to implement unified rule
It draws, design, construct and safeguard, be built in public utility of the Urban Underground for laying municipal public use pipeline.Underground integrated pipe
Corridor is played an important role to meeting people's livelihood primary demand and improving city integrated bearing capacity.
The common mode of underground pipe gallery construction at present has:Excavation and cast-in-place construction technology, open cut precast assembly technology, wherein
In excavation and cast-in-place work progress, progress formwork erection is needed to pour, since underground pipe gallery belongs to full underground engineering, and Cabin Design
It is required that air-tightness is high, traditional building template system can not complete the construction requirement of underground pipe gallery.Construction mould traditional simultaneously
Plate build process is comparatively laborious, long construction period, can not adapt to extensive rapid construction requirement.
Utility model content
The purpose of this utility model is to provide the quick support shuttering system of city integrated piping lane construction, the support shuttering systems
System can be used in the rapid construction of city integrated piping lane, and the build process of this template system is convenient and efficient, in a storehouse surface
Next storehouse surface can be quickly moved to after completing by pouring, and then improve construction efficiency.
In order to realize above-mentioned technical characteristic, what the purpose of this utility model was realized in:City integrated piping lane construction
Quick support shuttering system, it includes comprehensive gallery bottom plate, is fixed with and multiple is not equally spaced on the comprehensive gallery bottom plate
Warehouse partition wall seat to be poured, be provided with plate device at the top of the warehouse partition wall seat to be poured, pacify on the plate device
Equipped with for the fixed tensioning mechanism of template, it is installed between the plate device at the top of adjacent warehouse partition wall seat to be poured more
The top template lower face of the horizontal strainer of root, the plate device is installed with hydraulic pressure diagonal brace mounting device, the liquid
It is installed with hydraulic pressure tightening mechanism on pressure diagonal brace mounting device.
The plate device includes outside formwork erection and inside formwork erection, and corner guided mode is provided at the top of the inside formwork erection
Plate is fixed with top template at the top of two pieces of adjacent inside formwork erections, is fixed on the lateral wall of the inside formwork erection multiple
Pedestal is welded, horizontal strainer is connected between the welding pedestal.
The tensioning mechanism includes water-stop opposite-pulling screw rod, and leak-stopping nut and tensioning spiral shell are set on the water-stop opposite-pulling screw rod
Mother, the water-stop opposite-pulling screw rod are fixedly mounted on the outside formwork erection and inside formwork erection of plate device.
The horizontal strainer includes tensioning sleeve, and the both ends of the tensioning sleeve are coordinated by screw-driven respectively pacifies
Equipped with the first tensioning screw and the second tensioning screw, the other end of first tensioning screw and the second tensioning screw is respectively articulated with
On the welding pedestal of plate device.
The hydraulic pressure diagonal brace mounting device includes connection top plate, and the bottom end of the connection top plate, which is inverted, is fixed with the first support
Column and the second support column are fixed with web beam between first support column and the second support column.
The hydraulic pressure tightening mechanism includes first hydraulic cylinder and second hydraulic cylinder, and it is oblique that the first hydraulic cylinder is hinged on hydraulic pressure
On the first support column for supportting mounting device, piston-rod end is hinged on the welding pedestal of plate device;Second hydraulic pressure
Cylinder is hinged on the second support column of hydraulic pressure diagonal brace mounting device, and piston-rod end is hinged on the welding pedestal of plate device
On, the first hydraulic cylinder and second hydraulic cylinder are in arranged crosswise or outer " eight " word arrangement.
City integrated piping lane is separated into natural gas storehouse, electricity by the warehouse partition wall seat to be poured at the top of the comprehensive gallery bottom plate
Power storehouse, steam cabin and comprehensive storehouse.
The utility model has the advantages that:
By using above-mentioned support shuttering system, can conveniently be poured applied to city integrated piping lane quick
Construction, this template system is built conveniently, and stable structure can by the horizontal strainer in casting process
The spacing of convenient adjusting template, and then ensure the consistency of poured piping lane partition board wall;In addition pass through hydraulic pressure stretching machine
Structure not only facilitates formwork erection process, subsequent form removal process is also facilitated, during form removal, it is only necessary to unclamp first hydraulic cylinder
The dismounting operation of template can be realized with second hydraulic cylinder;Poured at one section completion after can easily be moved to next section into
Row pours, and then improves and pour efficiency, reduces the labor intensity of operating personnel.
Description of the drawings
The utility model is described in further detail with reference to the accompanying drawings and examples.
Fig. 1 is the utility model overall structure diagram.
In figure:Plate device 1, tensioning mechanism 2, hydraulic pressure diagonal brace mounting device 3, horizontal strainer 4, hydraulic pressure tightening mechanism
5, natural gas storehouse 6, warehouse partition wall seat 7 to be poured, comprehensive gallery bottom plate 8, electric power storehouse 9, steam cabin 10, comprehensive storehouse 11;
Inside formwork erection 101, outside formwork erection 102, top template 103, welding pedestal 104, corner guided mode plate 105;
Leak-stopping nut 201, water-stop opposite-pulling screw rod 202, tensioning nut 203;
Connect top plate 301, web beam 302, the first support column 303, the second support column 304;
First tensioning screw 401, tensioning sleeve 402, the second tensioning screw 403;
First hydraulic cylinder 501, second hydraulic cylinder 502.
Specific implementation mode
The embodiment of the utility model is described further below in conjunction with the accompanying drawings.
The quick support shuttering system as shown in Figure 1, city integrated piping lane is constructed, it includes comprehensive gallery bottom plate 8, described comprehensive
It closes and is fixed with multiple warehouse partition wall seats 7 to be poured not being equally spaced, the warehouse partition wall seat 7 to be poured on gallery bottom plate 8
Top be provided with plate device 1, be equipped on the plate device 1 for the fixed tensioning mechanism 2 of template, it is adjacent to wait pouring
It is installed with more horizontal strainers 4, the top of the plate device 1 between the plate device 1 at 7 top of warehouse partition wall seat
103 lower face of template is installed with hydraulic pressure diagonal brace mounting device 3, and liquid is installed on the hydraulic pressure diagonal brace mounting device 3
Press tightening mechanism 5.It by using above-mentioned support shuttering system, can be used in the rapid construction of city integrated piping lane, ensureing
While construction quality, construction efficiency is improved.
Further, the plate device 1 includes outside formwork erection 102 and inside formwork erection 101, the inside formwork erection 101
Top is provided with corner guided mode plate 105, and top template 103 is fixed at the top of two pieces of adjacent inside formwork erections 101, described interior
It is fixed with multiple welding pedestals 104 on the lateral wall of edge-on mould 101, horizontal strainer is connected between the welding pedestal 104
4.Above-mentioned outside formwork erection 102 pours formwork erection for the entire exterior wall of piping lane, and then ensure that the quality of exterior wall, and described is interior
Edge-on mould 101 is used to support the inner chamber body of piping lane, carries out formwork erection support to inner wall, passes through the top template 103 in addition
It can be used in pouring for backform, can be used in being connected with support device by the welding pedestal 104.
Further, the tensioning mechanism 2 includes water-stop opposite-pulling screw rod 202, is set on the water-stop opposite-pulling screw rod 202
Leak-stopping nut 201 and tensioning nut 203, the water-stop opposite-pulling screw rod 202 are fixedly mounted on the outside formwork erection 102 of plate device 1
On inside formwork erection 101.It, can be by phase by water-stop opposite-pulling screw rod 202 by using in above-mentioned 2 course of work of tensioning mechanism
It is fixed between two pieces of adjacent templates, the purpose of leak-stopping is played by the leak-stopping nut 201.
Further, the horizontal strainer 4 includes tensioning sleeve 402, and the both ends of the tensioning sleeve 402 lead to respectively
It crosses screw-driven cooperation and the first tensioning screw 401 and the second tensioning screw 403 is installed, first tensioning screw 401 and the
The other end of two tensioning screws 403 is respectively hinged on the welding pedestal 104 of plate device 1.Pass through the tensioning sleeve
402, in the course of work, when spacing between needing adjusting template, it is only necessary to rotate tensioning sleeve 402, pass through tensioning sleeve
First tensioning screw 401 at 402 drive both ends and the second tensioning screw 403 are in turn fixed template.
Further, the hydraulic pressure diagonal brace mounting device 3 includes connection top plate 301, and the bottom end of the connection top plate 301 is fallen
It sets and is fixed with the first support column 303 and the second support column 304, it is fixed between first support column, 303 and second support column 304
There is web beam 302.Can be used in that hydraulic pressure tightening mechanism 5 is fixedly mounted by the hydraulic pressure diagonal brace mounting device 3.
Further, the hydraulic pressure tightening mechanism 5 includes first hydraulic cylinder 501 and second hydraulic cylinder 502, first liquid
Cylinder pressure 501 is hinged on the first support column 303 of hydraulic pressure diagonal brace mounting device 3, and piston-rod end is hinged on plate device 1
It welds on pedestal 104;The second hydraulic cylinder 502 is hinged on the second support column 304 of hydraulic pressure diagonal brace mounting device 3, is lived
Stopper rod end is hinged on the welding pedestal 104 of plate device 1, and the first hydraulic cylinder 501 and second hydraulic cylinder 502 are in intersection
Arrangement or outer " eight " word arrangement.In the course of work, when needing stretching plate device, it is only necessary to start first hydraulic cylinder 501
With second hydraulic cylinder 502, and then piston rod is pushed, and then template is held out against by piston rod, realize the fixation of template.
It is completed when pouring, during form removal, it is only necessary to hydraulic cylinder, entirety be sent out to carry above-mentioned support shuttering system and be
It can.
Further, city integrated piping lane is separated by the warehouse partition wall seat 7 to be poured at 8 top of the comprehensive gallery bottom plate
Natural gas storehouse 6, electric power storehouse 9, steam cabin 10 and comprehensive storehouse 11.By being separated into different warehouses, meets city piping lane and build need
It wants.
The course of work and operation principle of the utility model:
When needing to carry out city integrated piping lane construction, then installation form device 1 first is pacified between plate device 1
Tensioning mechanism 2, hydraulic pressure diagonal brace mounting device 3, horizontal strainer 4 and hydraulic pressure tightening mechanism 5 are filled, waiting for above-mentioned apparatus, installation is complete
Later, the distance between template is regulated;Finally, it proceeds by and pours, after completion to be poured, after concrete setting is good,
When needing form removal, it is only necessary to send out hydraulic cylinder, and then unclamp plate device, then integrally carry above-mentioned support shuttering system and be
It can.
Above-described embodiment is used for illustrating the utility model, rather than limits the utility model, in this practicality
In novel spirit and scope of the claims, to any modifications and changes that the utility model is made, this reality is both fallen within
With novel protection domain.
Claims (7)
- The quick support shuttering system 1. city integrated piping lane is constructed, it is characterised in that:It includes comprehensive gallery bottom plate(8), described Comprehensive gallery bottom plate(8)On be fixed with multiple warehouse partition wall seats to be poured not being equally spaced(7), the warehouse to be poured every Wall base(7)Top be provided with plate device(1), the plate device(1)On be equipped with for the fixed tensioning mechanism of template (2), adjacent warehouse partition wall seat to be poured(7)The plate device at top(1)Between be installed with more horizontal strainers (4), the plate device(1)Top template(103)Lower face is installed with hydraulic pressure diagonal brace mounting device(3), the liquid Press diagonal brace mounting device(3)On be installed with hydraulic pressure tightening mechanism(5).
- The quick support shuttering system 2. city integrated piping lane according to claim 1 is constructed, it is characterised in that:The template Device(1)Including outside formwork erection(102)With inside formwork erection(101), the inside formwork erection(101)Top be provided with corner guided mode Plate(105), in two pieces of adjacent inside formwork erections(101)Top be fixed with top template(103), the inside formwork erection(101) Lateral wall on be fixed with multiple welding pedestals(104), the welding pedestal(104)Between connect horizontal strainer(4).
- The quick support shuttering system 3. city integrated piping lane according to claim 1 is constructed, it is characterised in that:The tensioning Mechanism(2)Including water-stop opposite-pulling screw rod(202), the water-stop opposite-pulling screw rod(202)On be set with leak-stopping nut(201)And tensioning Nut(203), the water-stop opposite-pulling screw rod(202)It is fixedly mounted on plate device(1)Outside formwork erection(102)With inside formwork erection (101)On.
- The quick support shuttering system 4. city integrated piping lane according to claim 1 is constructed, it is characterised in that:The level Strainer(4)Including tensioning sleeve(402), the tensioning sleeve(402)Both ends respectively pass through screw-driven cooperation installation There is the first tensioning screw(401)With the second tensioning screw(403), first tensioning screw(401)With the second tensioning screw (403)The other end be respectively hinged at plate device(1)Welding pedestal(104)On.
- The quick support shuttering system 5. city integrated piping lane according to claim 1 is constructed, it is characterised in that:The hydraulic pressure Diagonal brace mounting device(3)Including connecting top plate(301), the connection top plate(301)Bottom end be inverted be fixed with the first support column (303)With the second support column(304), first support column(303)With the second support column(304)Between be fixed with web beam (302).
- The quick support shuttering system 6. city integrated piping lane according to claim 1 is constructed, it is characterised in that:The hydraulic pressure Tightening mechanism(5)Including first hydraulic cylinder(501)And second hydraulic cylinder(502), the first hydraulic cylinder(501)It is hinged on hydraulic pressure Diagonal brace mounting device(3)The first support column(303)On, piston-rod end is hinged on plate device(1)Welding pedestal (104)On;The second hydraulic cylinder(502)It is hinged on hydraulic pressure diagonal brace mounting device(3)The second support column(304)On, it lives Stopper rod end is hinged on plate device(1)Welding pedestal(104)On, the first hydraulic cylinder(501)And second hydraulic cylinder (502)In arranged crosswise or outer " eight " word arrangement.
- The quick support shuttering system 7. city integrated piping lane according to claim 1 is constructed, it is characterised in that:The synthesis Gallery bottom plate(8)The warehouse partition wall seat to be poured at top(7)City integrated piping lane is separated into natural gas storehouse(6), electric power storehouse (9), steam cabin(10)With comprehensive storehouse(11).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820137424.6U CN207862974U (en) | 2018-01-26 | 2018-01-26 | The quick support shuttering system of city integrated piping lane construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820137424.6U CN207862974U (en) | 2018-01-26 | 2018-01-26 | The quick support shuttering system of city integrated piping lane construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207862974U true CN207862974U (en) | 2018-09-14 |
Family
ID=63458965
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820137424.6U Active CN207862974U (en) | 2018-01-26 | 2018-01-26 | The quick support shuttering system of city integrated piping lane construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207862974U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113914364A (en) * | 2021-11-30 | 2022-01-11 | 中国二十冶集团有限公司 | Comprehensive pipe gallery construction method and one-side formwork structure of side wall of comprehensive pipe gallery |
-
2018
- 2018-01-26 CN CN201820137424.6U patent/CN207862974U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113914364A (en) * | 2021-11-30 | 2022-01-11 | 中国二十冶集团有限公司 | Comprehensive pipe gallery construction method and one-side formwork structure of side wall of comprehensive pipe gallery |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103498523B (en) | Floor system | |
CN205530344U (en) | Utility tunnel is pour to split type no mould | |
CN205969436U (en) | Horizontal many storekeepers corridor mould | |
CN105971007A (en) | Split type non-formwork pouring underground comprehensive pipe gallery | |
CN207862974U (en) | The quick support shuttering system of city integrated piping lane construction | |
CN206478303U (en) | The supporting structure of heat distribution pipeline in pipe gallery | |
CN204754216U (en) | But telescopic tube | |
CN208668462U (en) | A kind of pipe gallery supporting structure | |
CN207934066U (en) | One kind exempting from vertical support overlapping piping lane device | |
CN203394019U (en) | Frame type template structure for placing of concrete | |
CN203834809U (en) | Steel pipe column structure for steel pipe column concrete side pouring method | |
CN216640449U (en) | Combined module supporting structure for flood bank protection slope | |
CN206902768U (en) | A kind of post-cast strip adjustable supporting | |
CN109183843A (en) | Fabricated assembly overall concrete pipe gallery and construction | |
CN205604289U (en) | Can resist single storehouse underground pipe gallery of large deformation | |
CN210002280U (en) | road and bridge crack reinforcing structure | |
CN213471655U (en) | Concrete water pipe internal pouring device for water supply and drainage | |
CN212983875U (en) | Building construction is with building foundation ditch bearing structure convenient to installation demolishs | |
CN109235709B (en) | Full cast-in-place outer wall structure of building | |
CN203797264U (en) | Counterweight base for mounting outdoor device of communication engineering | |
CN109403516B (en) | Basement exterior wall construction method | |
CN102635374B (en) | Support die structure in tunnel | |
CN206987050U (en) | Concrete-filled steel tube truss building and its agent structure | |
CN207176735U (en) | A kind of pipe gallery formwork for placing fixes device | |
CN207176736U (en) | A kind of pipe gallery formwork for placing unit and by its assembled formwork for placing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |