CN207847548U - A kind of movable drilling platform of side slope construction - Google Patents
A kind of movable drilling platform of side slope construction Download PDFInfo
- Publication number
- CN207847548U CN207847548U CN201820080347.5U CN201820080347U CN207847548U CN 207847548 U CN207847548 U CN 207847548U CN 201820080347 U CN201820080347 U CN 201820080347U CN 207847548 U CN207847548 U CN 207847548U
- Authority
- CN
- China
- Prior art keywords
- slope
- tripod
- sliding
- anchor bolt
- operating platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Earth Drilling (AREA)
Abstract
The utility model provides a kind of movable drilling platform of side slope construction, including tripod, operating platform and sliding slot, two sliding slots are arranged in parallel on the slope of high slope, there are one tripods for setting on every sliding slot, it is provided with sliding rail on the bevel edge of tripod, sliding rail is in sliding fit with the sliding chute, operating platform is horizontally set on the upper end of two tripods, drilling machine is provided on operating platform, the drill bit face slope of drilling machine, hoist engine is provided on tripod, one end of the steel wire rope of hoist engine is fixed in the top of the slope of high slope.Activity drilling platform provided by the utility model has many advantages, such as that drilling efficiency is high, easy to operate.
Description
Technical field
The utility model is related to construction equipment technical fields, more particularly to a kind of running drill for side slope construction
Hole platform.
Background technology
High slope typically refers to the soil-slope that height is 20 meters or more or the rock side slope that height is 30 meters or more, in order to
It prevents high slope from weathering off, flowstone stream mud occurs, the disasters such as falls stone, cave in, coming down, needs to reinforce high slope
Protective treatment is a kind of common protecting hand by carrying out the protection of anchor shaft anchor cable sash beam after drilling on the slope of high slope again
Section.In order to drill in high slope, need to build drilling platform, high slope drilling platform mostly uses scaffold and takes at present
If scaffold is set with ratio of slope.It needing to carry out scaffold building calculating before construction, platform stabilization is poor, needs to dismantle installation back and forth,
It is time-consuming and laborious.High slope drilling platform is the operation platform device of high slope drilling construction, must can not in side slope construction
It is few, but set up that equal in the process there are more limiting factors mobile.
Invention content
The purpose of this utility model is to provide a kind of movable drilling platform for the side slope construction that drilling efficiency is high.
To achieve the goals above, movable drilling platform provided by the utility model includes tripod, operating platform and cunning
Slot, two sliding slots are arranged in parallel on the slope of high slope, tripod there are one settings on every sliding slot, on the bevel edge of tripod
It is provided with sliding rail, sliding rail is in sliding fit with the sliding chute, and operating platform is horizontally set on the upper end of two tripods, is set on operating platform
It is equipped with drilling machine, the drill bit face slope of drilling machine is provided with hoist engine on tripod, and one end of the steel wire rope of hoist engine is fixed on height
In the top of the slope of side slope.
Further embodiment is that the first gag lever post and the second gag lever post are horizontally arranged between two sliding slots, the first limit
Bar is located at the upper end of sliding slot, and the second gag lever post is located at the lower end of sliding slot.
Further embodiment is that the first anchor bolt is provided in top of the slope, and the first anchor bolt is located at prolonging for two sliding slots
One end of the centre of long line, steel wire rope is fixed on anchor bolt.
Further embodiment is, the both sides of the first anchor bolt are symmetrical arranged there are two the second anchor bolt, two second
Anchor bolt is located on the extended line of two sliding slots, is connected through the hinge between the second anchor bolt and the upper end of sliding slot.
Further scheme is that the periphery of operating platform is provided with guard rail, and the height of guard rail is more than or waits
In 1.2m.
Further embodiment is that operating platform is spliced by multiple bamboo slab rubbers, and tripod is welded by more channel steels.
The utility model has the beneficial effects that:Tripod structure improves the stability of whole system so that bore operation
Process is safer.Constantly discharge steel wire rope by hoist engine so that tripod moves from top to bottom on slope, due to sliding rail and
The cooperation of sliding slot so that the movement of tripod is sufficiently stable, is constantly drilled on the slope by drilling machine, tripod to
During lower movement, the drilling on slope can be completed, and drilling efficiency is high.
Description of the drawings
Fig. 1 is the structural schematic diagram of the activity drilling platform embodiment of the utility model.
Fig. 2 is the sliding groove structure schematic diagram of the activity drilling platform embodiment of the utility model.
The utility model is described in further detail with reference to the accompanying drawings and embodiments.
Specific implementation mode
It is the structural schematic diagram of the activity drilling platform embodiment of the utility model referring to Fig. 1, Fig. 1.In the present embodiment,
The height of high slope is 40m, and movable drilling platform is arranged on the slope of high slope 1, is fixedly installed in the top of the slope 2 of high slope
First anchor bolt 3.Movable drilling platform includes tripod 4 and operating platform 5, and tripod 4 is welded by more channel steels, behaviour
Make platform 5 to be spliced by multiple bamboo slab rubbers, the weight of operating platform is effectively reduced using bamboo slab rubber.Operating platform 5
Periphery is provided with guard rail 50, and the height of guard rail 50 is not less than 1.2m.Operating platform 5 is horizontally set on tripod 4
Upper end is provided with drilling machine 6,60 face slope 1 of the drill bit setting of drilling machine 6 on operating platform 5.Volume is installed on tripod 4
Machine 7 is raised, one end of the steel wire rope 70 of hoist engine 7 is fixedly connected with the first anchor bolt 3.Extension of the surface on slope 1 along slope
Direction is provided with sliding slot 10, and sliding rail is provided on the bevel edge of tripod 4(It is invisible in Fig. 1), sliding rail is slidably matched with sliding slot 10.
Reinforcing bar 40 is provided between the bevel edge and right-angle side of tripod 4, reinforcing bar 40 improves the stability of tripod 4.Tripod 4
Right-angle side and the outer of operating platform 5 between be also equipped with reinforcing bar 41.
It is the sliding groove structure schematic diagram of the activity drilling platform embodiment of the utility model referring to Fig. 2, Fig. 2.It is put down on slope 1
Capable is provided with two sliding slots 10, is respectively provided with there are one tripod 4 and sliding rail in the top of each sliding slot 10, two tripods
It is additionally provided with connecting rod between 4, tripod 4 is further reinforced by connecting rod.Laterally it is arranged between two sliding slots 10
There are the first gag lever post 11 and the second gag lever post 12, the first gag lever post 11 to be located at the upper end of sliding slot 10, the second gag lever post 12, which is located at, to be slided
The lower end of slot 10.The junction of first gag lever post 11 and sliding slot 10 is fixed by anchor bolt 13, and the end of anchor bolt 13 is inserted
Enter in slope 1.The junction of second gag lever post 12 and sliding slot 10 is fixed by anchor bolt 14, and the end of anchor bolt 14 is inserted into
In slope 1.Stability of the benefit of first gag lever post 11 and the second gag lever post 12 in addition to that can increase sliding slot 10 is set, it can be with
The moving range of the sliding rail of tripod 4 is limited, anti-anti-slip track is skidded off out of sliding slot 10.Referring also to Fig. 1, top of the slope 2 is in the first anchor
The monosymmetric setting of fixing bolt 3 is there are two the second anchor bolt, the problem of due to viewing angles, 3 He of the first anchor bolt
Second anchor bolt is overlapped in Fig. 1.Two the second anchor bolts are located on the extended line of two sliding slots 10, the first anchor bolt
3 are located at the centre of the extended line of two sliding slots 10.Connected by hinge 8 between second anchor bolt and the upper end of sliding slot 10
It connects, hinge 8 further improves the safety coefficient of sliding slot 10.
The course of work of the movable drilling platform of the utility model is described in detail in combination with Fig. 1 and Fig. 2.Due to this practicality
The height of novel high slope reaches 40m, therefore the length on slope 1 is longer, can be divided into multistage and carry out bore operation, each section
Boring procedure all same is now illustrated for wherein one section.Boring procedure carries out from top to bottom, and steel is tightened by hoist engine 7
Cord 70 so that tripod 4 is still on slope 1, is drilled to the surface on slope 1 by drill bit 60.After boring what a hole,
Hoist engine 7 discharges steel wire rope 70 so that tripod 4 moves down a certain distance along sliding slot 10, and hoist engine 7 stretches tight strength steel again
Cord 70 drills to the surface on the slope 1 of the position by above-mentioned same mode.Tripod 4 is sliding in moving process
Rail is always positioned in sliding slot 10 so that the mobile stabilization of tripod 4.By constantly discharge steel wire rope 70 slope 1 surface
Interval drill.The structure of tripod 4 is sufficiently stable, and bore operation process safety is reliable, need not dismantle triangle repeatedly
Frame can bore a large amount of hole on slope 1, and drilling efficiency is high.
Certainly, above-described embodiment is only the preferable embodiment of the utility model, and when practical application can also have more
Variation, for example, it is also possible to which standing screw is changed into spud pile etc., within the spirit and principle of the utility model, is done
Any modification, equivalent substitution, improvement and etc., should be included in the protection domain of the utility model claims.
Claims (6)
1. a kind of movable drilling platform of side slope construction, it is characterised in that:
Including tripod, operating platform and sliding slot, two sliding slots are arranged in parallel on the slope of high slope, the every cunning
Setting is provided with sliding rail there are one the tripod on slot on the bevel edge of the tripod, and the sliding rail is slided with the sliding slot
Cooperation, the operating platform is horizontally set on the upper end of two tripods, drilling machine is provided on the operating platform, described
Slope described in the drill bit face of drilling machine is provided with hoist engine on the tripod, and one end of the steel wire rope of the hoist engine is fixed
In the top of the slope of the high slope.
2. activity drilling platform according to claim 1, it is characterised in that:
The first gag lever post and the second gag lever post are horizontally arranged between two sliding slots, first gag lever post is located at the cunning
The upper end of slot, second gag lever post are located at the lower end of the sliding slot.
3. activity drilling platform according to claim 1, it is characterised in that:
The first anchor bolt is provided in the top of the slope, first anchor bolt is located in the extended line of two sliding slots
Between, one end of the steel wire rope is fixed on the anchor bolt.
4. activity drilling platform according to claim 3, it is characterised in that:
The both sides of first anchor bolt are symmetrical arranged there are two the second anchor bolt, and two second anchor bolts are located at
On the extended line of two sliding slots, it is connected through the hinge between second anchor bolt and the upper end of the sliding slot.
5. activity drilling platform according to any one of claims 1 to 4, it is characterised in that:
The periphery of the operating platform is provided with guard rail, and the height of the guard rail is greater than or equal to 1.2m.
6. activity drilling platform according to claim 5, it is characterised in that:
The operating platform is spliced by multiple bamboo slab rubbers, and the tripod is welded by more channel steels.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820080347.5U CN207847548U (en) | 2018-01-16 | 2018-01-16 | A kind of movable drilling platform of side slope construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820080347.5U CN207847548U (en) | 2018-01-16 | 2018-01-16 | A kind of movable drilling platform of side slope construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207847548U true CN207847548U (en) | 2018-09-11 |
Family
ID=63415073
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820080347.5U Expired - Fee Related CN207847548U (en) | 2018-01-16 | 2018-01-16 | A kind of movable drilling platform of side slope construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207847548U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109281323A (en) * | 2018-10-23 | 2019-01-29 | 中交二公局第三工程有限公司 | A kind of roadbed side slope rockbolt installation device |
CN110578476A (en) * | 2019-09-24 | 2019-12-17 | 朔黄铁路发展有限责任公司 | Slope drilling construction platform |
CN115898267A (en) * | 2022-11-22 | 2023-04-04 | 中交四航工程研究院有限公司 | Anchoring and drilling device and system for slope reinforcement construction |
-
2018
- 2018-01-16 CN CN201820080347.5U patent/CN207847548U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109281323A (en) * | 2018-10-23 | 2019-01-29 | 中交二公局第三工程有限公司 | A kind of roadbed side slope rockbolt installation device |
CN110578476A (en) * | 2019-09-24 | 2019-12-17 | 朔黄铁路发展有限责任公司 | Slope drilling construction platform |
CN110578476B (en) * | 2019-09-24 | 2021-10-22 | 朔黄铁路发展有限责任公司 | Slope drilling construction platform |
CN115898267A (en) * | 2022-11-22 | 2023-04-04 | 中交四航工程研究院有限公司 | Anchoring and drilling device and system for slope reinforcement construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207847548U (en) | A kind of movable drilling platform of side slope construction | |
CN106351679A (en) | Soil similar coal working face fully sealed shield support device | |
CN203822175U (en) | Drilling machine rack | |
CN204921009U (en) | Coal mine tunnel struts support | |
CN110258528B (en) | Assembled and inserted self-clamping type prefabricated hollow underground continuous wall and construction method thereof | |
CN203053721U (en) | Coal rock heading machine large-gradient testing stand | |
CN204570684U (en) | A kind of anchor head of Recyclable anchor rope is fixed and guiding device | |
CN113175331B (en) | Rapid construction equipment and method for weak surrounding rock fiber net pre-supporting structure | |
CN213775393U (en) | Temporary operation platform for tunnel support based on cantilever excavator | |
CN213418456U (en) | Building scaffold wall connecting piece | |
CN104989274B (en) | A kind of positioning of transmission line of electricity rock-bolt drilling machine and mobile device | |
CN210858596U (en) | Mast telescopic assembly system of percussion coring drilling machine | |
CN210370726U (en) | Underground coal mine support device | |
CN106239740A (en) | A kind of board drilling equipment | |
CN211285633U (en) | Foundation ditch supporting device for civil engineering | |
CN206457830U (en) | A kind of construction prefabricated components assembling structure | |
CN221722725U (en) | Auxiliary bracket of body jumbolter | |
CN219455522U (en) | Asphalt concrete panel slope coring device | |
CN213626551U (en) | Civil engineering construction supporting structure | |
CN203362050U (en) | Umbrella drill seizing hook beam supporting tower | |
CN217923616U (en) | Foundation pit supporting device for building construction | |
CN218479818U (en) | Simple safety protection platform suitable for underground mine | |
CN214196355U (en) | Arched shock-absorbing support frame structure for coal mine tunnel | |
CN221195087U (en) | Anti-collapse support for coal mining | |
CN218062221U (en) | Anchoring drilling machine structure capable of being assembled, disassembled and fixed on excavator |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180911 Termination date: 20220116 |
|
CF01 | Termination of patent right due to non-payment of annual fee |