CN207846426U - Detachable pipeline buttress pours device - Google Patents
Detachable pipeline buttress pours device Download PDFInfo
- Publication number
- CN207846426U CN207846426U CN201820099847.3U CN201820099847U CN207846426U CN 207846426 U CN207846426 U CN 207846426U CN 201820099847 U CN201820099847 U CN 201820099847U CN 207846426 U CN207846426 U CN 207846426U
- Authority
- CN
- China
- Prior art keywords
- semi
- halves
- cylindrical case
- buttress
- case
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Detachable pipeline buttress pours device, including symmetrically arranged two halves can pairing semi-cylindrical case (1), be located on the outside of case opening face upper and lower part the ledge (2) with connecting hole, it is symmetrical be opened in two halves semi-cylindrical case be open Middle face semicircle orifice (3), be sleeved on semicircle orifice aperture mortar leakage prevention cushion rubber (4), across two halves semi-cylindrical case ledge up and down by connection bolt (5) that two halves semi-cylindrical case is connected and fixed, be installed on the handle (6) of semi-cylindrical case lateral surface.Using the utility model, can fast pouring go out the unified concrete buttress of size, the buttress stabilized structure that pours, neat appearance, and construction efficiency is high.
Description
Technical field
The utility model belongs to construction technical field of tools, and the pipeline buttress big for quantity, buttress is intensive pours
It builds.
Background technology
When carrying out fire protection pipeline transverse tube and drainage pipeline transverse tube construction and installation, it is often necessary to make pipeline buttress, especially
When co-layer draining toilet and roof fire protection pipeline are installed, buttress is more.The prior art is typically first used when building buttress by laying bricks or stones
Brick is supported on pipeline in the following, then being fixed and troweling outer surface with cement mortar again.In this way, the buttress of making by
In brick difference and artificial gimmick difference, often size differs, and height is different, occupies that ground is big, and speed of application is slow, and buttress
Structure built on the sand, is easy to be damaged, and outer perception is also poor.
Invention content
The purpose of this utility model is to solve the problems, such as of the existing technology, provides a kind of quick construction, can make to pour
Buttress stabilized structure, size be consistent with height, neat appearance detachable pipeline buttress pours device.
The purpose of this utility model is achieved through the following technical solutions:
Detachable pipeline buttress pours device, including symmetrically arranged two halves can the semi-cylindrical case of pairing, position respectively
The ledge with connecting hole on the outside of case opening face upper and lower part symmetrical is opened in two halves semi-cylindrical case opening face
The semicircle orifice at middle part, the mortar leakage prevention cushion rubber for being sleeved on semicircle orifice aperture, across two halves semi-cylindrical case ledge up and down by two
Connection bolt that half semi-cylindrical case is connected and fixed, the handle for being installed on semi-cylindrical case lateral surface.
Semi-cylindrical case described in the utility model is made of PVC material or cast iron or steel.
Using the utility model, only transverse tube need to be installed on two halves semi-cylindrical cover by two halves semi-cylindrical case pairing
In the circular hole that two semicircle orifices are combined to form in the middle part of shell, the two halves semi-cylindrical case of pairing is connected and fixed shape with connection bolt
At pipe, then the casting concrete into pipe, after concrete setting, removes connection bolt, dismantles two halves semi-cylindrical
Case forms cylindric buttress, transverse tube is firmly fixed in buttress.The utility model is easy to use, pours buttress province
Shi Shengli can provide construction efficiency significantly, the buttress stabilized structure poured, and geomery is unified, convenient for smoothly docking pipeline, and
Good appearance is clean and tidy, takes up little area.The utility model is reusable, reduces construction cost.
Description of the drawings
Fig. 1 is that the utility model clamps the schematic diagram before support transverse tube;
Fig. 2 is that the utility model clamps the schematic diagram after support transverse tube;
Fig. 3 is the schematic diagram of the buttress formed after the utility model is removed.
Specific implementation mode
The content of the utility model is expanded on further with reference to the accompanying drawings of the specification.
As shown in Figure 1 and Figure 2, the detachable pipeline buttress of the utility model pour device include symmetrically arranged two halves can
The semi-cylindrical case 1 of pairing, be located at case opening face upper and lower part on the outside of the ledge 2 with connecting hole, symmetrically
The semicircle orifice 3 for being opened in two halves semi-cylindrical case opening Middle face, passes through the mortar leakage prevention cushion rubber 4 for being sleeved on semicircle orifice aperture
The ledge up and down of two halves semi-cylindrical case by the connection bolt 5 that two halves semi-cylindrical case is connected and fixed, be installed on semicolumn
The handle 6 of 1 lateral surface of shape case.The semi-cylindrical case 1 preferably uses PVC material to make, light and low cost, it is also possible to
Cast iron or steel make.
The application method of the utility model is as follows:
A. as shown in Figure 1, first semi-cylindrical case 1 to be separated to two halves;
B. as shown in Fig. 2, between transverse tube 7 is set to two halves semi-cylindrical case, by two halves semi-cylindrical case pairing,
Transverse tube is snap-fit in the circular hole that two semicircle orifices 3 are combined to form in the middle part of two halves semi-cylindrical case, with connection bolt 5 by pairing
Two halves semi-cylindrical case be connected and fixed to form pipe, constitute one and pour device, while determining that mortar leakage prevention cushion rubber 4 is tightly close to
In transverse tube outer surface;
C. pour that device is suitable for reading to pour into concrete from pipe, vibration compacting smoothes out upper surface;
D. after concrete setting reaches prescribed strength, connection bolt is removed, dismantles two halves semi-cylindrical case, that is, forms circle
Column buttress 8, as shown in figure 3, being firmly fixed in buttress 8 by horizontal, 7.
It can be that the transverse tube fast pouring of buttress is needed to go out the unified concrete buttress of size using the utility model, realize
Smoothly docking pipeline.It solves buttress and builds that size differs, construction speed is slow, the common fault of poor appearance by laying bricks or stones.
Claims (2)
1. detachable pipeline buttress pours device, which is characterized in that including symmetrically arranged two halves can pairing semi-cylindrical cover
Shell (1), is symmetrically opened in two halves half at the ledge (2) with connecting hole being located on the outside of case opening face upper and lower part
The semicircle orifice (3) of cylindric case opening Middle face, passes through two halves semicircle at the mortar leakage prevention cushion rubber (4) for being sleeved on semicircle orifice aperture
The ledge up and down of column case by the connection bolt (5) that two halves semi-cylindrical case is connected and fixed, be installed on semi-cylindrical case
(1) handle (6) of lateral surface.
2. detachable pipeline buttress according to claim 1 pours device, which is characterized in that semi-cylindrical case (1) is adopted
It is made of PVC material or cast iron or steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820099847.3U CN207846426U (en) | 2018-01-22 | 2018-01-22 | Detachable pipeline buttress pours device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820099847.3U CN207846426U (en) | 2018-01-22 | 2018-01-22 | Detachable pipeline buttress pours device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207846426U true CN207846426U (en) | 2018-09-11 |
Family
ID=63415639
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820099847.3U Active CN207846426U (en) | 2018-01-22 | 2018-01-22 | Detachable pipeline buttress pours device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207846426U (en) |
-
2018
- 2018-01-22 CN CN201820099847.3U patent/CN207846426U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206503169U (en) | A kind of integral basement tower crane and raft plate seam construction | |
CN103470046B (en) | The casting method of ultra-high steel tube concrete column tremie method concrete casting device | |
CN205530344U (en) | Utility tunnel is pour to split type no mould | |
CN202660067U (en) | Waterproof sleeve preventing wall body leakage | |
CN105971007A (en) | Split type non-formwork pouring underground comprehensive pipe gallery | |
CN207469307U (en) | A kind of gang form structure of the inspection shaft cast-in-place construction of town road pipeline | |
CN108755972A (en) | Prefabricated component feet and its application method | |
CN207812508U (en) | Poured band of outer wall of basement formwork erection device | |
CN207846426U (en) | Detachable pipeline buttress pours device | |
CN211113740U (en) | Prestressed steel cylinder concrete pipe with base | |
CN202945741U (en) | Non-vibrating concrete column of steel tube | |
CN107327046A (en) | A kind of steel pipe bundle combining structure | |
CN209429046U (en) | Gravity dam transverse joint drainage channel structure | |
CN204690801U (en) | Formwork erecting structure is hung in basement roof ater-casting | |
CN206752632U (en) | Plastic reinforcing steel composite construction municipal drainage inspection shaft | |
CN208830457U (en) | Steel caisson stop water | |
CN207633342U (en) | A kind of bridge pile foundation pile crown abolishes device | |
CN206844652U (en) | Pipe hole need not hang the new template of mould | |
CN107762135A (en) | The construction method of skin scaffold wall connecting piece | |
CN203514332U (en) | Casing for blocking dewatering tube well of post-cast strip | |
CN110093948A (en) | Variable cross-section Pipe rack and its construction method suitable for rapid construction | |
CN206941657U (en) | A kind of basement post-pouring zone water sealing structure | |
CN107023061B (en) | Assembled plastic municipal drainage inspection well and construction method | |
CN104912209B (en) | Bars In Poured Concrete Slab reserved holes of pipes plugging device and processing and plugging construction method | |
CN207960164U (en) | Prefabricated enclosure wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |