- Publication number
- CN207846202U CN207846202U CN201820174840.3U CN201820174840U CN207846202U CN 207846202 U CN207846202 U CN 207846202U CN 201820174840 U CN201820174840 U CN 201820174840U CN 207846202 U CN207846202 U CN 207846202U
- Authority
- CN
- China
- Prior art keywords
- cylinder
- master cylinder
- double steel
- temporary supports
- auxiliary
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a kind of double steel cylinder temporary supports for precast beam installation, double steel cylinder temporary supports include steel plate, master cylinder, auxiliary cylinder, master cylinder diameter is more than auxiliary cylinder diameter, master cylinder bottom welding steel, the built-in fine sand of master cylinder, is placed on the bent cap for having poured completion, the auxiliary cylinder concrete filled, auxiliary cylinder is mounted in master cylinder after age to be achieved, forms double steel cylinder temporary supports;The utility model is easy to make, and installation is easy, reusable, overcomes precast beam construction temporary support and removes difficult situation, the construction quality of prefabricated beam bridge is improved, especially suitable for the precast beams bridge construction such as precast hollow slab, prefabricated case beam.
Description
Technical field
The utility model is related to double steel cylinders in a kind of temporary support more particularly to a kind of precast beam installation to prop up temporarily
Seat.
Background technology
In the construction of precast prestressed concrete upper beam, according to construction technology, precast beam is transported after Liang Chang completes
To on-site hoisting, the bearing that when lifting uses is secondary to install permanent bearing, temporary support again when pouring continuous segment for temporary support
Play the role of extremely important in precast beam lifting, it directly affects the construction quality of bed rearrangement bridge.Conventionally employed interim branch
Seat more generally precast concrete block, wood directly buy commercially available temporary support.Although precast concrete block has
There are enough rigidity and intensity, can guarantee the stabilization of precast beam, but dismounting is relatively difficult, expends the time, efficiency is low;Wood holds
It is readily removable to remove, but deformation may be shunk under the weight of precast beam, it can not ensure precast beam construction quality;Commercially available interim branch
Seat is expensive, increases construction input.
Therefore, it is badly in need of needing a kind of reasonable for structure, easy to demolition, the temporary support with certain rigidity.
Invention content
In order to keep precast beam easy for installation, fast, accelerate site operation progress, ensures cast-in-place rear bed rearrangement bridge precast beam construction
Quality, the utility model proposes a kind of simple in structure, low cost, rigidity is big, is adjusted, the readily removable temporary support removed.
To achieve the above object, the utility model proposes following technical solutions:Double steel cylinder temporary supports include steel plate,
Master cylinder, auxiliary cylinder, master cylinder diameter are more than auxiliary cylinder diameter, master cylinder bottom welding steel, and master cylinder built-in fine sand is filled out in the auxiliary cylinder
Concrete, auxiliary cylinder are mounted in master cylinder.
Preferably, steel plate length of side master cylinder diameter.
Preferably, fine sand is closely knit, fills and leads up, concrete fills up auxiliary cylinder.
The double steel cylinder temporary supports of the utility model have the advantages that compared with traditional temporary support:
1, simple in structure, it is easy to make, the concrete used structure can pour remaining concrete based on, and fine sand can
Live material-taking on-site, low manufacture cost are reusable.
2, the rigidity of structure is big, is unlikely to deform, and precast beam construction quality is guaranteed.
3, it overcomes temporary support and removes difficult situation, avoid destroying beam body in demolishing process, construction is safer
Reliably.
4, speed block is removed, construction efficiency is high, shortens the period, reduces management cost.
Description of the drawings
Fig. 1 is the double steel cylinder temporary support sectional views of the utility model.
Fig. 2 is the double steel cylinder temporary support vertical views of the utility model.
Each component label in figure:1-steel plate;2-master cylinders;3-auxiliary cylinders;4-fine sands;5-concrete.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are not under the premise of making the creative labor
The every other embodiment obtained, shall fall within the protection scope of the present invention.
As shown in Figs. 1-2, double steel cylinder temporary supports include steel plate 1, master cylinder 2, auxiliary cylinder 3, and 2 diameter of master cylinder is more than auxiliary cylinder
3 diameters, 2 bottom welding steel 1 of the master cylinder, 2 built-in fine sand 4 of master cylinder are placed on the bent cap for having poured completion, fine sand 4 exists
Through closely knit processing in master cylinder 2, it is filled to about 3/4 position of 2 depth of master cylinder, concrete 5 is filled up in the auxiliary cylinder 3, smoothed out, wait for up and down
Auxiliary cylinder 3 is mounted in master cylinder 2 after reaching age.
Wherein, 2 diameter 219mm of master cylinder, wall thickness 4mm, auxiliary cylinder 3 diameter 159mm, wall thickness 4mm, the height of auxiliary cylinder 3 and master cylinder 2
It can be depending on on-site actual situations.
When making the utility model, two steel pipes of suitable diameter are first cut into the master cylinder 2 that length is 15cm-20cm
With auxiliary cylinder 3, the cutting of steel plate 1 is square, and the length of side is more than 2 diameter 2cm of master cylinder, and the welding of master cylinder 2 on the steel plate 1 is poured in auxiliary cylinder 3
Concrete 5 is built, is conserved after smoothing out up and down.
The temporary support of the utility model is when in use:According to construction technology, general every piece of precast beam need to place two per side
A temporary support, surveying and locating positions the position of temporary support, master cylinder 2 is placed on oriented bent cap, built-in to master cylinder 2
Fine sand controls temporary support elevation by adjusting fine sand depth, and precast beam is mounted on temporary support using crane or Bridge Erector
On, after the completion of lifting, permanent bearing is installed, the cast-in-place continuous segment of assembled formwork, after the completion of maintenance, with water by temporary support master cylinder 2
Interior fine sand 4 is gone out, and the total elevation of temporary support declines, and is drawn off taking out, moves to next working face and be continuing with.
The above is only the preferred embodiment of the utility model only, is not intended to limit the utility model, all at this
Within the spirit and principle of utility model, any modification, equivalent replacement, improvement and so on should be included in the utility model
Protection domain within.
Claims (3)
1. a kind of double steel cylinder temporary supports for precast beam installation, it is characterised in that:Double steel cylinder temporary supports include steel
Plate(1), master cylinder(2), auxiliary cylinder(3), master cylinder(2)Diameter is more than auxiliary cylinder(3)Diameter, the master cylinder(2)Bottom welding steel(1),
Master cylinder(2)Built-in fine sand(4), the auxiliary cylinder(3)Concrete filled(5), auxiliary cylinder(3)Mounted on master cylinder(2)It is interior.
2. double steel cylinder temporary supports according to claim 1, it is characterised in that:Steel plate(1)The length of side is more than master cylinder(2)Diameter.
3. double steel cylinder temporary supports according to claim 1, it is characterised in that:Fine sand(4)It is filled to master cylinder(2)Depth about 3/4
Position, concrete(5)Fill up auxiliary cylinder(3).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820174840.3U CN207846202U (en) | 2018-02-01 | 2018-02-01 | A kind of double steel cylinder temporary supports for precast beam installation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820174840.3U CN207846202U (en) | 2018-02-01 | 2018-02-01 | A kind of double steel cylinder temporary supports for precast beam installation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207846202U true CN207846202U (en) | 2018-09-11 |
Family
ID=63414231
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820174840.3U Active CN207846202U (en) | 2018-02-01 | 2018-02-01 | A kind of double steel cylinder temporary supports for precast beam installation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207846202U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113550231A (en) * | 2021-08-06 | 2021-10-26 | 中船第九设计研究院工程有限公司 | Method for erecting bridge precast beam slab by using sand box type temporary support |
-
2018
- 2018-02-01 CN CN201820174840.3U patent/CN207846202U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113550231A (en) * | 2021-08-06 | 2021-10-26 | 中船第九设计研究院工程有限公司 | Method for erecting bridge precast beam slab by using sand box type temporary support |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106758887A (en) | The whole bridge decentralization method for dismounting of continuous bridge | |
CN207616844U (en) | Foundation platform precast concrete side form and molding machine | |
CN107724533A (en) | A kind of Super High Core Walls Structure beam and vertical structure connection method | |
CN103498425A (en) | Full-dismounting combination type multifunctional bracket supporting structure and construction method thereof | |
CN201666157U (en) | Inverted arch integral type moving die carrier | |
CN101487293A (en) | Concrete pouring method for beam-column joints with different strength grades | |
CN203429641U (en) | Single-side supporting formwork reinforcing structure system for building construction | |
CN104831639A (en) | Consolidation and release construction method for 0# blocks of ultra-wide non-uniform continuous beam | |
CN105525571A (en) | Construction method of anti-collision wall | |
CN207846202U (en) | A kind of double steel cylinder temporary supports for precast beam installation | |
CN209482709U (en) | A kind of in-situ concrete wall subsiding crack typified form | |
CN203022222U (en) | Wholly-cast ring beam of brick-concrete building support | |
CN106988228A (en) | Prestressed concrete continuous beam girder construction process | |
CN206448272U (en) | Roadbed side slope arched framework one-time-shaped mould | |
CN109356185A (en) | A kind of prefabricated pier foundation of regeneration monolith and its construction method | |
CN206625553U (en) | For pouring the formwork bracing system of high-low bay structure simultaneously | |
CN105040709A (en) | Construction method for support replacement of fender-post retaining and protecting of deep foundation pit | |
CN102767378B (en) | Double-column type tunnel portal method for bent frame construction tunnel | |
CN104746434B (en) | Closure segment formwork system without dismantling outer formwork | |
CN104164882A (en) | Construction method for building support structural beam foundation on slope and structure thereof | |
CN206052565U (en) | A kind of beam-column type bracket | |
CN215594483U (en) | Cantilever beam rear-dismantling wall on structural floor slab | |
CN214245823U (en) | Advance through structure of new and old structure girder on two sides of mid-partition wall | |
CN110043060A (en) | A method of landing frame column is changed to beam post structures | |
CN205382505U (en) | Board -like concrete air cooling platform basis of rib is erected in area |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |