CN207794622U CN201721640645.7U CN201721640645U CN207794622U CN 207794622 U CN207794622 U CN 207794622U CN 201721640645 U CN201721640645 U CN 201721640645U CN 207794622 U CN207794622 U CN 207794622U
Authority
CN
China
Prior art keywords
plate
articulated shaft
fixinig plate
deflector
fixinig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721640645.7U
Other languages
Chinese (zh)
Inventor
任小红
陈昊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Zhongxing Commodity Concrete LLC
Original Assignee
Chongqing Zhongxing Commodity Concrete LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Zhongxing Commodity Concrete LLC filed Critical Chongqing Zhongxing Commodity Concrete LLC
Priority to CN201721640645.7U priority Critical patent/CN207794622U/en
Application granted granted Critical
Publication of CN207794622U publication Critical patent/CN207794622U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model provides the guiding device poured for ground gap, it is connected to deflector above bottom plate including horizontally disposed bottom plate, the friction plate being fixed below bottom plate, by first axle component and is connected to the support component of deflector side by second hinge component, friction plate is rubber slab;First axle component includes being perpendicularly fixed at the first fixinig plate above bottom plate, being perpendicularly fixed at the second fixinig plate of deflector side and be flexibly connected piece with what the first fixinig plate and the second fixinig plate were hinged respectively by the first articulated shaft and the second articulated shaft;Second hinge assembly includes being perpendicularly fixed at deflector and being hinged by third articulated shaft with the third fixinig plate of second fixinig plate the same side, support component and third fixinig plate, and the first articulated shaft, the second articulated shaft and third articulated shaft are parallel two-by-two.The utility model is of simple structure and low cost, concrete can be effectively prevent to waste, and space hold is small after easy to operate, storage.

Description

The guiding device poured for ground gap
Technical field
The utility model is related to concreting field more particularly to a kind of coagulations for being poured to ground gap Native water conservancy diversion ancillary equipment.
Background technology
Distress in concrete is a kind of universal phenomenon generated due to the effect of various internal and external factors in concrete structure, it Appearance can not only reduce the impermeability of building, influence the use function of building, and the corrosion of reinforcing bar can be caused, mix The carbonization for coagulating soil, reduces the durability of material, influences the bearing capacity of building, therefore the prevention and processing of distress in concrete are straight Connect the safety for affecting building.In order to prevent cast-in-place concrete structure since autogenous shrinkage is uneven or the unequal factor of sedimentation and Harmful cracks are generated, existing way is stayed and set in sole plate, wall, beam corresponding position according to design or job specfication requirement Temporary construction seam, i.e. post-cast strip.If structure is temporarily divided into stem portion by post-cast strip, shunk by component inside, several The post-cast strip is poured again after time, each structure is finally linked to be to whole area.Meanwhile if the concrete structure later stage go out Existing gap, then be also required to repair it, completion method, grouting method, structural strengthening method and coagulation can be used to the repairing in gap Native displacement method etc., wherein concrete replacement method are to handle a kind of method of badly damaged concrete, and the method is first will damage Concrete reject, then replace again into new concrete or other materials.For this reserved post empiricism seam or When the crack that later stage generates is poured, if this kind of gap width is smaller and depth is larger, need to pour using special Equipment is constructed, and in placing installation such as the hose inserted into gap of pump truck front end, will could specially be realized and be carried out standard to gap It really pours, therefore, this casting method is more demanding to placing installation, for the place that pump truck is difficult to reach, then can only pass through On the other hand artificial concrete can then cause concrete waste serious, and concrete on the one hand because of artificial inaccuracy It easily pours down or forth on originally smooth, clean ground and condenses, cause the increasing of later stage cleaning work intensity, virtually also improve Construction cost.
Utility model content
For the problems such as construction cost in the presence of existing concrete crack pouring technique is high, waste of material is serious, The utility model provides the guiding device poured for ground gap, not only easy to use, at low cost, and can effectively solve Waste serious problem.
To achieve the above object, the utility model uses the following technical solution:
For the guiding device that ground gap pours, including horizontally disposed bottom plate, be fixed below bottom plate friction plate, It is connected to deflector above bottom plate by first axle component and deflector side is connected to by second hinge component Support component, wherein:The friction plate is rubber slab;The first axle component includes first be perpendicularly fixed above bottom plate Fixinig plate, the second fixinig plate for being perpendicularly fixed at deflector side and by the first articulated shaft and the second articulated shaft respectively with The flexible connection piece that one fixinig plate and the second fixinig plate are hinged;Second hinge assembly includes being perpendicularly fixed at deflector one The third fixinig plate of side and the third fixinig plate and the second fixinig plate are located at the same side of deflector, the support component and the Three fixinig plates are hinged by third articulated shaft, and the first articulated shaft, the second articulated shaft and third articulated shaft are parallel two-by-two.
The use principle of the utility model is:Two guiding devices are respectively placed in the gap both sides for needing to pour, wherein Floor level is placed on ground, and deflector is turned an angle around the first hinge assembly and is risen by support component skewed horizontal load Come so that the side skewed horizontal load of deflector is supported on bottom in the edge in gap, the other side of deflector by support component Plate upper surface, then two deflectors form funnel shaped flow-guiding mouth in the top in gap, you can concrete is filled by flow-guiding mouth Enter into gap;By the angle for adjusting the adjustable angle deflector of support component;Due to there are two the first hinge assembly tools Articulated shaft can then remain that a side of deflector is touched with ground.
Compared with the prior art, the utility model has the advantages that:The utility model is simple in structure, at low cost It is honest and clean, the waste of material of concrete can be effectively prevent by the utility model, and space hold is small after easy to operate, storage.
Description of the drawings
Fig. 1 is the use state diagram of the utility model.
Fig. 2 is the receiving state schematic diagram of the utility model.
Specific implementation mode
The technical solution in the utility model is further illustrated with reference to the accompanying drawings and embodiments.
As shown in Figure 1, the utility model proposes the guiding device poured for ground gap, including horizontally disposed bottom Plate 1, is connected to the deflector 3 above bottom plate 1 by first axle component and passes through the friction plate 2 for being fixed on 1 lower section of bottom plate Second hinge component is connected to the support component of 3 side of deflector, wherein:
The friction plate 2 is rubber slab, and the bottom of the friction plate 2 is equipped with several zigzag protrusions 21;Pass through rubber slab And its protrusion 21 of bottom can effectively increase the frictional force of itself and ground 8, be not necessarily to when in use through other devices to this practicality It is novel to be fixed, you can to effectively prevent moving when the utility model is used;
The first axle component includes the first fixinig plate 41 for being perpendicularly fixed at 1 top of bottom plate, is perpendicularly fixed at water conservancy diversion Second fixinig plate 42 of 3 side of plate and by the first articulated shaft 43 and the second articulated shaft 44 respectively with the first fixinig plate 41 and The flexible connection piece 45 that two fixinig plates 42 are hinged;
Second hinge assembly include be perpendicularly fixed at 3 side of deflector third fixinig plate 51 and the third fix Piece 51 and the second fixinig plate 42 are located at the same side of deflector 3, and the support component is hinged by third with third fixinig plate 51 Axis 52 is hinged, and the first articulated shaft 43, the second articulated shaft 44 are parallel two-by-two with third articulated shaft 52;
The support component is the supporting rod 6 being hinged on third fixinig plate, the upper surface of the bottom plate 1 be equipped with it is several with The locating slot 11 that 6 radial dimension of supporting rod matches, being used to support when bar 6 is supported in 1 upper surface of bottom plate prevents its sliding;
The close first axle component of the deflector 3 and the side 31 parallel with the first articulated shaft 43 are chess piece side.
As shown in Figure 1, in use, two guiding devices are respectively placed in 9 both sides of gap that need to be poured, two deflectors A funnel shaped flow-guiding mouth is formed, then concrete seven can be poured by flow-guiding mouth in gap, concrete leakage is effectively prevent to be sprinkled upon Waste is generated outside gap, and effectively prevent the pollution to 9 both sides ground 8 of gap.
As shown in Fig. 2, when the utility model is stored, supporting rod 6 is turned to around the second hinge assembly first and is parallel to water conservancy diversion The position of plate 3, then deflector 3 is turned to the position for being parallel to bottom plate 1 around the first hinge assembly, the then entirety of the utility model It is deformed into rough platy structure, thus occupied space is minimum.
Finally illustrate, above example is merely intended for describing the technical solutions of the present application, but not for limiting the present application, although ginseng The utility model is described in detail according to preferred embodiment, it will be understood by those of ordinary skill in the art that, it can be to this The technical solution of utility model is modified or replaced equivalently, without departing from the objective and model of technical solutions of the utility model It encloses, should all cover in the right of the utility model.

Claims (4)

1. the guiding device poured for ground gap, which is characterized in that including horizontally disposed bottom plate, be fixed below bottom plate Friction plate, deflector above bottom plate is connected to by first axle component and water conservancy diversion is connected to by second hinge component The support component of plate side, wherein:The friction plate is rubber slab;The first axle component includes being perpendicularly fixed on bottom plate First fixinig plate of side is perpendicularly fixed at the second fixinig plate of deflector side and by the first articulated shaft and the second articulated shaft Respectively piece is flexibly connected with what the first fixinig plate and the second fixinig plate were hinged;The second hinge component includes being perpendicularly fixed at The third fixinig plate of deflector side and the third fixinig plate and the second fixinig plate are located at the same side of deflector, the support Component is hinged by third articulated shaft with third fixinig plate, and the first articulated shaft, the second articulated shaft and third articulated shaft are parallel two-by-two.
2. the guiding device poured as described in claim 1 for ground gap, it is characterised in that:The bottom of the friction plate Equipped with several zigzags protrusion.
3. the guiding device poured as described in claim 1 for ground gap, it is characterised in that:The support component is hinge The upper surface of the supporting rod being connected on third fixinig plate, the bottom plate is equipped with several positioning to match with supporting rod radial dimension Slot, being used to support when bar is supported in plate upper surface prevents its sliding.
4. the guiding device poured as described in claim 1 for ground gap, it is characterised in that:The deflector is close to One hinge component and the side parallel with the first articulated shaft are chess piece side.
CN201721640645.7U 2017-11-30 2017-11-30 The guiding device poured for ground gap Active CN207794622U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721640645.7U CN207794622U (en) 2017-11-30 2017-11-30 The guiding device poured for ground gap

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721640645.7U CN207794622U (en) 2017-11-30 2017-11-30 The guiding device poured for ground gap

Publications (1)

Publication Number Publication Date
CN207794622U true CN207794622U (en) 2018-08-31

Family

ID=63286196

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721640645.7U Active CN207794622U (en) 2017-11-30 2017-11-30 The guiding device poured for ground gap

Country Status (1)

Country Link
CN (1) CN207794622U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984580A (en) * 2019-12-23 2020-04-10 中国人民解放军63926部队 Multipurpose concrete guiding gutter device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984580A (en) * 2019-12-23 2020-04-10 中国人民解放军63926部队 Multipurpose concrete guiding gutter device

Similar Documents

Publication Publication Date Title
CN104863274B (en) Building dilatation joint waterproof structure
CN210658031U (en) Joint cutting device is used in road and bridge construction
CN108951567B (en) Upturning type flap gate
CN207794622U (en) The guiding device poured for ground gap
CN109024987A (en) Construction method is poured after a kind of toilet shear wall
CN205955191U (en) Constructional column side template device for concreting
CN209368653U (en) A kind of municipal administration pavement crack prosthetic device
CN211772645U (en) Pitch casting machine is used in municipal works construction
CN108589445A (en) A kind of hydraulic pressure rail head rail jack and its application method
CN208702139U (en) A kind of construction template structure of toilet wall
CN208686085U (en) Wall column foot cleanout plugging plate and wall column side template
CN203891470U (en) Fastening bolt for shear wall formwork
CN108756202A (en) A kind of recyclable building builder's jack fixing device and application method
CN206953259U (en) A kind of concrete door sprinkling curing system
CN205857636U (en) A kind of Mortar spraying machine with elevating function
CN108342984A (en) A kind of beach soft foundation trestle and its installation sedimentation method
CN209703544U (en) A kind of native pile foundation of monitoring upright bar
CN209228386U (en) A kind of lining of tunneling Subway Tunnel big cross section stop line two new type formwork trolley
CN204996178U (en) Sedimentation tank that road bridge construction can be cleared up automatically
CN203640227U (en) Mounting structure of floor construction waste collection passage
CN205473284U (en) A device for throwing in river sediment restores material
CN220013330U (en) Concrete pavement repairing equipment
CN204626964U (en) Concreting leak-proof device
CN206902553U (en) A kind of steel sand ejection device
CN204530399U (en) Cast asphalt concrete special edge paver

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant