CN207779594U - TBM execution conditions detecting earth stress of lower all the period of time systems - Google Patents

TBM execution conditions detecting earth stress of lower all the period of time systems Download PDF

Info

Publication number
CN207779594U
CN207779594U CN201721633264.6U CN201721633264U CN207779594U CN 207779594 U CN207779594 U CN 207779594U CN 201721633264 U CN201721633264 U CN 201721633264U CN 207779594 U CN207779594 U CN 207779594U
Authority
CN
China
Prior art keywords
tbm
period
table top
execution conditions
detecting earth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721633264.6U
Other languages
Chinese (zh)
Inventor
于新凯
郝元麟
全海
杨旭
李建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201721633264.6U priority Critical patent/CN207779594U/en
Application granted granted Critical
Publication of CN207779594U publication Critical patent/CN207779594U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

The utility model discloses a kind of TBM execution conditions detecting earth stress of lower all the period of time system, especially a kind of TBM execution conditions detecting earth stress of lower all the period of time systems for high altitude localities geological stress testing field.TBM execution conditions detecting earth stress of lower all the period of time system used by the utility model, including wind band, test platform, jack up unit, transport vehicle, test equipment, fixing piece, the test platform includes table top and the supporting rack that is arranged below table top, the transport vehicle is located at below table top, the test equipment is fixed on the table top of test platform, between transport vehicle and wind band, the fixing piece is fixedly connected with test platform for the test equipment and table top.Can under TBM execution conditions all the period of time carry out detecting earth stress, and may be implemented it is whole fast move, it is convenient and efficient, it is time saving and energy saving.

Description

TBM execution conditions detecting earth stress of lower all the period of time systems
Technical field
The utility model is related to a kind of TBM execution conditions detecting earth stress of lower all the period of time systems, especially a kind of for height TBM execution conditions detecting earth stress of the lower all the period of time systems of Altitude Regions geological stress testing field.
Background technology
Since 21st century, the industries such as traffic, water conservancy and hydropower and energy are rapidly developed, and the mankind live in the earth's crust The breadth and depth in dynamic space constantly extension and extends, especially in recent years China in high slope, high-ground stress, buried length The topography and geomorphologies such as tunnel complex area, has built numerous geotechnical engineerings.Have more and more numbers it was demonstrated that earth's surface and underground work The rock excavation that journey construction period is carried out tends to cause a series of deformations associated with stress release and breakoff phenomenon, this With regard to needs, Stress Field Distribution rule has sufficient understanding over the ground, and the research most direct approach of the stress field regularity of distribution is exactly to carry out Detecting earth stress, but in recent years, the deep and long tunnels of some complicated geographical reliefs mostly use tunneling boring tunnel piercing when excavating Machine (TBM) is constructed, and when TBM normal operations, can not ensure have enough spaces to carry out detecting earth stress, therefore the prior art Detecting earth stress only could be carried out in TBM idle periods, and the TBM operations occupied time is longer, therefore use The detecting earth stress system of the prior art greatly reduces working efficiency, affects construction speed.
Utility model content
The technical problem to be solved by the utility model is to provide one kind can under TBM execution conditions all the period of time carry out ground Stress test, and can realize that entirety fast moves, convenient and efficient, time saving and energy saving test system.
The utility model solves TBM execution conditions detecting earth stress of lower all the period of time system used by its technical problem, packet Wind band, test platform, jack up unit, transport vehicle, test equipment, fixing piece are included, the test platform includes that table top and setting exist Supporting rack below table top, the transport vehicle are located at below table top, and the test equipment is fixed on the table top of test platform, institute Test equipment and table top are stated between transport vehicle and wind band, the fixing piece is fixedly connected with test platform, the raising dress The lower end set is fixed on transport vehicle, and the fixing piece is located at the top of jack up unit.
Further, being provided with bolster between the fixing piece and jack up unit.
Further, the bolster is sleeper.
Further, the jack up unit is jack.
The utility model has the beneficial effects that:TBM execution conditions detecting earth stress of the lower all the period of time system of the application will be surveyed It tries equipment and table top is arranged between transport vehicle and wind band, to the ingenious region for avoiding TBM constructions.Using the application's TBM execution conditions detecting earth stress of lower all the period of time systems do not interfere with the normal construction of TBM so that detecting earth stress and TBM are applied Work can be carried out at the same time, and all periods can be made all to be fully used in this way, the period without avoiding TBM constructions, real Showed the target of all the period of time detecting earth stress, can thus greatly save the duration, significantly improved production efficiency, quickening construct into Degree.It can utilize the jack up unit on transport vehicle will when installing test request and needing to carry the test equipment of the application It is fixed on to fix and upper test platform is increased to certain altitude, the supporting rack of test platform is made to be detached from supporting plane, it is then sharp With transport vehicle, test platform and test equipment are transported to designated position.After test platform reaches designated position, raising dress It sets and test platform decline certain altitude is allowed to make, supporting rack falls on the secure support of shape pairwise testing system on the supporting plane in tunnel It can start test job of the test equipment to crustal stress afterwards.
Description of the drawings
Fig. 1 is the structural representation of the utility model;
Parts, position and number in figure:Wind band 1, jack up unit 3, transport vehicle 4, test equipment 5, is consolidated test platform 2 Determine part 6, sleeper 7, supporting rack 8.
Specific implementation mode
The utility model is described in further detail below in conjunction with the accompanying drawings.
As shown in Figure 1, TBM execution conditions detecting earth stress of the lower all the period of time systems of the utility model, including wind band 1, survey Platform 2, jack up unit 3, transport vehicle 4, test equipment 5, fixing piece 6 are tried, the test platform 2 includes table top and is arranged in table top The supporting rack 8 of lower section, the transport vehicle 4 are located at below table top, and the test equipment 5 is fixed on the table top of test platform 2, institute Test equipment 5 and table top are stated between transport vehicle 4 and wind band 1, the fixing piece 6 is fixedly connected with test platform 2, described The lower end for rising device 3 is fixed on transport vehicle 4, and the fixing piece 6 is located at the top of jack up unit 3.The TBM construction items of the application Test equipment 5 and table top are arranged between transport vehicle 4 and wind band 1 part detecting earth stress of lower all the period of time system, are kept away to ingenious The region of TBM constructions is opened.Therefore the normal of TBM has not been interfered with using all the period of time detecting earth stress system of the application to apply Work so that detecting earth stress and TBM constructions can be carried out at the same time, and all periods can be made all to be fully used in this way, without It needs to avoid the period that TBM constructs, realizing the target of all the period of time detecting earth stress, can thus greatling save the duration, show It writes and improves production efficiency, accelerate construction progress.It can when installing test request and needing to carry the test equipment 5 of the application Upper test platform 2 is increased to certain altitude so that fixation will be fixed on using the jack up unit 3 on transport vehicle 4, keeps test flat The supporting rack 8 of platform 2 is detached from supporting plane, then utilizes transport vehicle 4, test platform 2 and test equipment 5 are transported specific bit It sets.After test platform 2 reaches designated position, jack up unit 3, which allows test platform 2 to decline certain altitude, to be made, and supporting rack 8 falls on tunnel It can start test work of the test equipment 5 to crustal stress on the supporting plane in road after the secure support of shape pairwise testing system Make.
In order to carry out effective protection to liter system platform and test equipment 5, ensure the precision of test, the application is also in institute It states and is provided with bolster between girder steel and jack up unit 3, mitigate jack up unit 3 between the starting stage and fixing piece 6 of lifting Impact, to ensure that test equipment 5 will not be damaged because of impact.
The bolster is sleeper 7.Bolster convenient material drawing is used as using sleeper 7, it is at low cost, make simple, buffering effect Fruit is good.
Jack up unit 3 is jack, and the application preferentially uses jack as jack up unit 3, and use is efficient and convenient, raising Height can adjust.Fixing piece 6 uses I-steel girder steel in the specific implementation.
Embodiment 1
In the present embodiment, jack up unit 3 uses two symmetrically placed 20t jack, fixing piece 6 to use I-steel steel Beam.7 quantity of sleeper is consistent with jack quantity, and when test system needs to carry, girder steel is fixed on 2 bracket of test platform Above, sleeper 7 and jack are placed between girder steel and transport vehicle 4, are risen by will entirely test system to jack pressurization, Then it can be carried it to designated position by transport vehicle 4, entire transportational process is convenient and efficient, time saving and energy saving.
TBM constructions can not be influenced completely using the detecting earth stress system of the application in the period of TBM constructions may be used yet To carry out detecting earth stress, and can be needed quickly and easily to be moved to designated position according to test.

Claims (5)

1.TBM execution conditions detecting earth stress of lower all the period of time systems, it is characterised in that:Including wind band (1), test platform (2), rise Device (3), transport vehicle (4), test equipment (5), fixing piece (6) are risen, the test platform (2) includes table top and is arranged in table top The supporting rack (8) of lower section, the transport vehicle (4) are located at below table top, and the test equipment (5) is fixed on test platform (2) On table top, the test equipment (5) and table top are located between transport vehicle (4) and wind band (1), and the fixing piece (6) is flat with test Platform (2) is fixedly connected, and the lower end of the jack up unit (3) is fixed on transport vehicle (4), and the fixing piece (6) is located at raising dress Set the top of (3).
2. TBM execution conditions detecting earth stress of lower all the period of time system as described in claim 1, it is characterised in that:Described solid Determine part (6) and is provided with bolster between raising.
3. TBM execution conditions detecting earth stress of lower all the period of time system as claimed in claim 2, it is characterised in that:The buffering Part is sleeper (7).
4. TBM execution conditions detecting earth stress of lower all the period of time system as described in claim 1, it is characterised in that:The raising Device (3) is jack.
5. TBM execution conditions detecting earth stress of lower all the period of time system as claimed in claim 4, it is characterised in that:It is described very heavy Top is symmetricly set on transport vehicle (4).
CN201721633264.6U 2017-11-29 2017-11-29 TBM execution conditions detecting earth stress of lower all the period of time systems Active CN207779594U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721633264.6U CN207779594U (en) 2017-11-29 2017-11-29 TBM execution conditions detecting earth stress of lower all the period of time systems

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721633264.6U CN207779594U (en) 2017-11-29 2017-11-29 TBM execution conditions detecting earth stress of lower all the period of time systems

Publications (1)

Publication Number Publication Date
CN207779594U true CN207779594U (en) 2018-08-28

Family

ID=63232466

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721633264.6U Active CN207779594U (en) 2017-11-29 2017-11-29 TBM execution conditions detecting earth stress of lower all the period of time systems

Country Status (1)

Country Link
CN (1) CN207779594U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107884107A (en) * 2017-11-29 2018-04-06 中国电建集团成都勘测设计研究院有限公司 TBM execution conditions detecting earth stress of lower all the period of time systems
CN109281676A (en) * 2018-10-31 2019-01-29 中铁工程装备集团有限公司 A kind of shield machine or TBM optimization system suitable for high altitude low air pressure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107884107A (en) * 2017-11-29 2018-04-06 中国电建集团成都勘测设计研究院有限公司 TBM execution conditions detecting earth stress of lower all the period of time systems
CN107884107B (en) * 2017-11-29 2023-11-21 中国电建集团成都勘测设计研究院有限公司 Full-time-period ground stress testing system under TBM construction condition
CN109281676A (en) * 2018-10-31 2019-01-29 中铁工程装备集团有限公司 A kind of shield machine or TBM optimization system suitable for high altitude low air pressure
CN109281676B (en) * 2018-10-31 2020-06-09 中铁工程装备集团有限公司 Shield tunneling machine or TBM (tunnel boring machine) optimization system suitable for high altitude and low air pressure

Similar Documents

Publication Publication Date Title
CN104018837B (en) A kind of interval filling gob-side entry retaining method processing planted agent's spoil
CN103256053B (en) Excavation and construction method of underground cavity ball coronary dome
CN105697013A (en) Contractible temporary support for tunneling tunnel
CN104047629B (en) The method that thin coal bed fully-mechanized mining gob side entry retaining directional drilling extraction closes on lower coal-bed gas
CN207779594U (en) TBM execution conditions detecting earth stress of lower all the period of time systems
CN102966359A (en) Working face ventilation oxidization zone roof control method
CN203362198U (en) Track walking type immediate support device of fully-mechanized drivage roadway
CN203499559U (en) Conveniently moved hydraulic anchoring drill for roadway
CN104405392B (en) Three soft high seam tunnel jackings are kept on file anchor rete cord active support longwall top coal caving method
CN208950604U (en) One kind reinforcing support construction for bias small-clear-distance tunnel surface grouting
CN205210083U (en) A model for digging up mine similar material simulation experiment excavation
CN201214786Y (en) Tree root type multi-support pile
CN203271739U (en) Support for electric coal drill
CN203067006U (en) Hydraulic support
CN104420824A (en) Convenient moving type hydraulic anchoring drilling machine for tunnel
CN205977257U (en) Mining excavation is walking prop and entry driving machine for working face
CN107884107A (en) TBM execution conditions detecting earth stress of lower all the period of time systems
CN203452796U (en) Vertical shaft base structure for shield machine to pass through
CN210003292U (en) Large-deformation advanced releasing structure of high-stress soft rock tunnel
CN207633149U (en) A kind of auxiliary system of underpass construction
CN106121704B (en) A kind of mining excavation working face walking prop, traveling method and development machine
CN206038676U (en) Physical simulation experimental frame suitable for simulation complex geological condition
CN202578699U (en) Soil-engineering centrifugal machine hole-digging mechanical arm
CN102226404B (en) Method for retracting surplus hydraulic supports of fully mechanized mining face
CN211173933U (en) Pneumatic jumbolter

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant