CN207775931U - A kind of suspension and support fastener inserts - Google Patents

A kind of suspension and support fastener inserts Download PDF

Info

Publication number
CN207775931U
CN207775931U CN201721852459.XU CN201721852459U CN207775931U CN 207775931 U CN207775931 U CN 207775931U CN 201721852459 U CN201721852459 U CN 201721852459U CN 207775931 U CN207775931 U CN 207775931U
Authority
CN
China
Prior art keywords
channel steel
buried channel
suspension
fastener inserts
support fastener
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721852459.XU
Other languages
Chinese (zh)
Inventor
黄益平
李伟
秦凤祥
杨仪威
王运杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Industrial and Energy Engineering Group Co Ltd
Original Assignee
China Construction Industrial Equipment Installation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Industrial Equipment Installation Co Ltd filed Critical China Construction Industrial Equipment Installation Co Ltd
Priority to CN201721852459.XU priority Critical patent/CN207775931U/en
Application granted granted Critical
Publication of CN207775931U publication Critical patent/CN207775931U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a kind of suspension and support fastener inserts, including pre-buried channel steel, the back of the pre-buried channel steel has anchor bolt, it further include at least two groups channel steel fixing piece arranged in parallel, every group of channel steel fixing piece is set between the back side of pre-buried channel steel and grouting template, the verticality of fixed pre-buried channel steel and the distance between with grouting template.Assembled suspension and support fastener inserts provided by the utility model have simple in structure, advantage easy for installation, and the problems such as existing standard degree is high during effectively can overcome installation of embedded parts in the prior art, quality control is bad, and perpendicularity difference, survival rate are low, compactness is bad.

Description

A kind of suspension and support fastener inserts
Technical field
The utility model belongs to infrastructure pipe gallery mounting technique field, and in particular to a kind of assembled suspension and support is pre- Embedded component.
Background technology
Currently, city integrated piping lane is unfolded to implement in nationwide large area, city integrated piping lane is built in Urban Underground The municipal public uses such as electric power, communication, water supply pipeline is concentrated according to planning requirement using it and is laid by the municipal public use tunnel space made In a structures, implement unified planning, design, construction and management.Cable in piping lane needs to install by stent system On piping lane side wall, in terms of technical matters angle, assembled suspension and support has prodigious advantage compared with traditional suspension and support, has Broader development prospect.
Enter corridor pipeline in pipe gallery and assembled engineering is more efficiently met using pre-buried type fabricated product suspension and support Theory.Current existing fabricated product suspension and support, using groups such as C-shaped channel steel, pre-buried channel steel, mating connector, expansion anchors At proximate matter belongs to non-standard component, no national standard guidance, each manufacturing firm's proximate matter mechanics parameter Primary Reference test data, nothing Unified standard, irregular, holder pattern, specification type are more, can not reach unification.There is problems:Such as it is directed to master Body different templates system need to use different construction methods(Excavation, shield, push pipe, prefabricated etc.)Pre-buried channel steel construction;Finished product holder The problems such as there is also quality control is bad, and perpendicularity difference, survival rate are low, compactness is bad simultaneously in pre-buried channel steel work progress. Therefore it needs to be improved existing built-in fitting.
Utility model content
Purpose of utility model:The utility model aim is in view of the deficiencies of the prior art, it is pre-buried to provide a kind of suspension and support The back of component, including pre-buried channel steel, the pre-buried channel steel has anchor bolt, further includes at least two groups channel steel arranged in parallel Fixing piece, every group of channel steel fixing piece are set between the back side of pre-buried channel steel and grouting template, fixed pre-buried channel steel Verticality and with grouting the distance between template.
Further, fixed at least two rows of between the back side and grouting template of the pre-buried channel steel to improve strength of wall body The bar-mat reinforcement parallel with grouting template.
Further, as preferred embodiment, the channel steel fixing piece includes a horizontal S-shaped elastic hook, the S-shaped The anchor bolts of one end of elastic hook and pre-buried channel steel, the other end are resisted against in grouting template.
Further, as preferred embodiment, the channel steel fixing piece further includes a V-type fixed frame, and the V-type is fixed Frame is fixed on the bar-mat reinforcement of grouting template side, and opening upwards, S-shaped elastic hook one end are erected at V-type and fix It is resisted against after on frame in grouting template.
Further, as preferred embodiment, one end of the S-shaped elastic hook is welded on the root of pre-buried channel steel anchor bolt, The other end is set up be welded on V-type fixed frame after be resisted against grouting template on.
Further, it is in the construction process the shadow of length reduction generation caused by elimination channel steel fixing piece forced contraction It rings, ensures that built-in groove is bonded with template, the channel steel fixing piece and the total natural length of the groove depth of pre-buried channel steel are total more than wall 4 ~ 6 mm of thickness.
Further, to avoid in subsequent casting process, concrete pours into pre-buried channel steel, causes built-in fitting that can not make With the both ends of the pre-buried channel steel set end cover, and hollow to be partially filled with expanded material, opening is sealed by diaphragm seal;
Further, as preferred embodiment, the S-shaped elastic hook and V-type fixed frame by 12 round steel of φ make and At.
Advantageous effect:(1)Assembled suspension and support fastener inserts provided by the utility model have it is simple in structure, it is easy for installation The advantages of, and existing standard degree is high, quality control during effectively can overcome installation of embedded parts in the prior art It is bad, the problems such as perpendicularity difference, survival rate are low, compactness is bad;(2)Utility model device fixes grouting template with channel steel Part, which is combined, is fixed pre-buried channel steel, stock utilization is improved, and improve the fixed effect of pre-buried channel steel, after being convenient for The suspension and support installation exercise of phase, built-in fitting are bonded completely with grouting template, improve the planarization of concreting shaped component; (3)Built-in fitting by this process Installation is not necessarily to punch in grouting template, and can keep the preferable verticality of built-in fitting, pole It is big to promote in-site installation efficiency, realize site operation environment dustlessization, high efficiency.
Description of the drawings
Fig. 1 is the overall structure diagram of utility model device;
Wherein:11, pre-buried channel steel before displacement, 1, pre-buried channel steel, 2, anchor bolt, 3, grouting template, 4, bar-mat reinforcement, 51, deformation Preceding S-shaped elastic hook, 5, S-shaped elastic hook, 6, V-type fixed frame, 7, concrete.
Specific implementation mode
Technical solutions of the utility model are described in detail below by attached drawing, but the scope of protection of the utility model It is not limited to the embodiment.
Embodiment 1:The back of a kind of suspension and support fastener inserts, including pre-buried channel steel 1, the pre-buried channel steel 1 has anchor bolt 2, the both ends of pre-buried channel steel set end cover, and hollow to be partially filled with expanded material, opening is sealed by diaphragm seal, this structure is also Including at least two groups channel steel fixing piece arranged in parallel, every group of channel steel fixing piece is set to the back of the body of pre-buried channel steel 1 Between face and grouting template 3, the verticality of fixed pre-buried channel steel 1 and the distance between with grouting template 3.Pre-buried channel steel 1 Fixed at least two rows of bar-mat reinforcements 4 parallel with grouting template between the back side and grouting template 3;Channel steel fixing piece includes a cross The S-shaped elastic hook 5 set, one end of the S-shaped elastic hook 5 are connect with the anchor bolt 2 of pre-buried channel steel, and the other end is resisted against grouting template On 3;Channel steel fixing piece further includes a V-type fixed frame 6, and the V-type fixed frame 6 is fixed on the steel close to 3 side of grouting template On muscle net 4, and opening upwards, described 5 one end of S-shaped elastic hook are resisted against after being erected on V-type fixed frame 6 in grouting template 3; One end of S-shaped elastic hook 5 is welded on the root of pre-buried channel steel anchor bolt 2, the other end is set up be welded on V-type fixed frame 6 after against In grouting template 3;Channel steel fixing piece is more than 4 ~ 6 mm of wall overall thickness with the groove depth total length of pre-buried channel steel;The present embodiment In, S-shaped elastic hook 5 and V-type fixed frame 6 are made by 12 round steel of φ.
Using the pre-buried construction method of installation of above-mentioned suspension and support fastener inserts, include the following steps:
(1)Fastener inserts are selected according to holder installation requirements, and monitor whether load meets demand;
(2)The both ends of pre-buried channel steel are sealed using end cover, backward built-in groove steel hollow part filled and process Material is finally sealed by diaphragm seal;
(3)Fixed grouting template, and built-in fitting is placed in object mounting position, it is illustrated that 11 dotted lines indicate built-in groove before displacement The position of steel is fixed S-shaped elastic hook and V-type fixed frame between pre-buried channel steel and grouting template, is then pushed away from left to right The grouting template in dynamic left side makes pre-buried channel steel and grouting template is good to be bonded, and S-shaped elastic hook is by pressure generation shape left end at this time It is subjected to displacement, it is illustrated that 51 dotted lines indicate S-shaped elastic hook before deformation, and pre-buried channel steel 1 is subjected to displacement target location therewith, until existing at this time Pre-buried channel steel is fixed under the action of both sides grouting template;
(4)Concrete seven pours, and waits for coagulation forming;
(5)Grouting template is removed after concrete seven coagulation forming;
(6)The pre-buried result of built-in fitting is checked according to drawing, and checks whether load meets the requirements.
Existing standard degree during installation of embedded parts in the prior art can be overcome using this structure and construction method Not high, the problems such as quality control is bad, and perpendicularity difference, survival rate are low, compactness is bad, between pre-buried steel tank and grouting template Channel steel fixing piece is set, the utilization for improving material while raising construction quality is promoted the special designing of channel steel fixing piece Rate.
As described above, although the utility model has been indicated and described with reference to specific preferred embodiment, it must not It is construed to the limitation to the utility model itself.In the spirit and scope for not departing from the utility model that appended claims define Under the premise of, it can various changes can be made in the form and details to it.

Claims (8)

1. the back of a kind of suspension and support fastener inserts, including pre-buried channel steel, the pre-buried channel steel has anchor bolt, it is characterised in that: Further include at least two groups channel steel fixing piece arranged in parallel, every group of channel steel fixing piece is set to the back of the body of pre-buried channel steel Between face and grouting template, the verticality of fixed pre-buried channel steel and the distance between with grouting template.
2. suspension and support fastener inserts according to claim 1, it is characterised in that:The back side of the pre-buried channel steel and grouting mold Fixed at least two rows of bar-mat reinforcements parallel with grouting template between plate.
3. suspension and support fastener inserts according to claim 2, it is characterised in that:The channel steel fixing piece includes one horizontal S-shaped elastic hook, the anchor bolts of one end and pre-buried channel steel of the S-shaped elastic hook, the other end be resisted against grouting template on.
4. suspension and support fastener inserts according to claim 3, it is characterised in that:The channel steel fixing piece further includes a V Type fixed frame, the V-type fixed frame is fixed on the bar-mat reinforcement of grouting template side, and opening upwards, the S-shaped elasticity Hook one end is resisted against after being erected on V-type fixed frame in grouting template.
5. suspension and support fastener inserts according to claim 4, it is characterised in that:One end of the S-shaped elastic hook is welded on The root of pre-buried channel steel anchor bolt, the other end set up be welded on V-type consolidate after S-shaped is determined on frame be resisted against grouting template on.
6. suspension and support fastener inserts according to claim 1, it is characterised in that:The channel steel fixing piece and pre-buried channel steel The total natural length of groove depth is more than 4 ~ 6 mm of wall overall thickness.
7. suspension and support fastener inserts according to claim 1, it is characterised in that:The both ends of the pre-buried channel steel set sealed end Lid, hollow to be partially filled with expanded material, opening is sealed by diaphragm seal.
8. suspension and support fastener inserts according to claim 4, it is characterised in that:The S-shaped elastic hook and V-type fixed frame It is made by 12 round steel of φ.
CN201721852459.XU 2017-12-25 2017-12-25 A kind of suspension and support fastener inserts Active CN207775931U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721852459.XU CN207775931U (en) 2017-12-25 2017-12-25 A kind of suspension and support fastener inserts

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721852459.XU CN207775931U (en) 2017-12-25 2017-12-25 A kind of suspension and support fastener inserts

Publications (1)

Publication Number Publication Date
CN207775931U true CN207775931U (en) 2018-08-28

Family

ID=63224577

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721852459.XU Active CN207775931U (en) 2017-12-25 2017-12-25 A kind of suspension and support fastener inserts

Country Status (1)

Country Link
CN (1) CN207775931U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035380A (en) * 2017-12-25 2018-05-15 中建安装工程有限公司 A kind of suspension and support fastener inserts and its pre-buried construction method of installation

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108035380A (en) * 2017-12-25 2018-05-15 中建安装工程有限公司 A kind of suspension and support fastener inserts and its pre-buried construction method of installation
CN108035380B (en) * 2017-12-25 2023-11-21 中建安装集团有限公司 Support and hanger embedded assembly and embedded installation construction method thereof

Similar Documents

Publication Publication Date Title
CN204551483U (en) A kind of to be used for " Two walls unite as one " ground-connecting-wall-Vierendeel girder Joint's connection fabrication
CN110004991B (en) Underground structure anti-floating system based on convex wing foot plate and construction method
CN105780719A (en) Heightened construction method for active service stone building bank protecting wall
CN109914644A (en) A kind of assembled heat insulation masonry wall and preparation method thereof
CN111636437A (en) Permanent-temporary combined supporting system and method for extra-large foundation pit near subway
CN106968692B (en) Tunnel excavation supporting structure and construction method thereof
CN204040062U (en) Prefabricated wedge shape flexible interface assembling piping lane
CN202577363U (en) H-shaped steel joint structure of underground diaphragm wall
CN203583493U (en) Combined lattice steel frame spray anchoring foundation pit supporting structure
CN207775931U (en) A kind of suspension and support fastener inserts
CN108035380A (en) A kind of suspension and support fastener inserts and its pre-buried construction method of installation
CN101871218B (en) Trenchless construction method of underground station space and arc-shaped freezing pipe construction equipment thereof
CN107893431A (en) A kind of assembled suspension and support fastener inserts and its pre-buried construction method of installation
CN107558483A (en) A kind of building foundation and its construction method for installing wallboard
CN205475257U (en) A composite pile anchor supporting construction for deepening excavation
CN111364518A (en) Fixing device for embedded part on side wall of concrete pipe gallery
CN207619987U (en) A kind of prefabricated foundation pit enclosure structure of environment-friendly type underground garage
CN104047273B (en) Power station dissipation and scouring wall and construction method thereof
CN105863649A (en) Underground space construction technique adopting underground excavation and causing little ruin to land surface
CN106088762B (en) A kind of prefabricated assembled round underground granary of insertion slot type encased steel plate
CN206189966U (en) Circular underground granary of slot -in type prefabricated assembled of inside and outside equal steel plated
CN205046569U (en) Annular wind -powered electricity generation foundation structure based on shaping of two ripple steel cylinder
CN211285692U (en) Corrugated steel pipe gallery based on prestressed tendons
CN209434853U (en) It is a kind of to move the arragement construction for changing rear electric power pipe trench
CN106368211A (en) Rectangular concrete piles used for constructing side wall of pipe gallery

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: Road in Qixia District of Nanjing City, Jiangsu Province, No. 6 210023

Patentee after: China Construction Installation Group Co., Ltd.

Address before: Road in Qixia District of Nanjing City, Jiangsu Province, No. 6 210023

Patentee before: China Construction Installation Engineering Co., Ltd.

CP01 Change in the name or title of a patent holder