CN207751517U - Substation operation environmental monitoring system - Google Patents
Substation operation environmental monitoring system Download PDFInfo
- Publication number
- CN207751517U CN207751517U CN201721657515.4U CN201721657515U CN207751517U CN 207751517 U CN207751517 U CN 207751517U CN 201721657515 U CN201721657515 U CN 201721657515U CN 207751517 U CN207751517 U CN 207751517U
- Authority
- CN
- China
- Prior art keywords
- rtu
- data acquisition
- sensor
- substation operation
- mobile phone
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Telephonic Communication Services (AREA)
- Arrangements For Transmission Of Measured Signals (AREA)
Abstract
The utility model discloses a kind of substation operation environmental monitoring systems, include mainly that data acquire RTU;The input terminal of data acquisition RTU is separately connected sensor noise, air velocity transducer, PM2.5/PM10 sensors, Temperature Humidity Sensor, rain sensor, sensor of thunder and lightning, and the output end of above-mentioned data acquisition RTU is separately connected background monitoring host and mobile phone.The system passes through all kinds of parameter signal sensors, by in substation operation environment noise, wind speed, pollution degree (particulate matter), humiture, rainfall, thunder and lightning Real-time Monitoring Data acquisition after by wireless communication transmission to server or mobile phone terminal Centralized Monitoring, to realize comprehensive grasp to substation operating mode.It is not only time saving, saving of labor, laborsaving in this way, patrolling dimension class personnel can easily formulate as needed with targetedly making an inspection tour maintenance plan, but also can guarantee that substation operation is safe and reliable.
Description
Technical field
The utility model belongs to substation intelligent monitoring technical field more particularly to a kind of substation operation environmental monitoring system
System.
Background technology
Unattended operation transformer station distribution at present more disperses, and running environment is of all kinds, so that patrolling dimension class personnel, especially
The outlying teams and groups in suburb can not know substation operation environment in time, it is difficult to formulate to have in extreme meteorological condition and targetedly patrol
Depending on maintenance plan.
Utility model content
The technical problem to be solved by the present invention is to provide a kind of substation operation environmental monitoring systems, in order to becoming
The various important parameters of power station running environment carry out real-time automatic monitoring.
In order to solve the above technical problems, the utility model uses following technical scheme:
Substation operation environmental monitoring system includes mainly that data acquire RTU;The input terminal of data acquisition RTU connects respectively
Sensor noise, air velocity transducer, PM2.5/PM10 sensors, Temperature Humidity Sensor, rain sensor, sensor of thunder and lightning are connect,
The output end of above-mentioned data acquisition RTU is separately connected background monitoring host and mobile phone.
The output end of data acquisition RTU carries out communication with background monitoring host by Ethernet and connect.
The output end of data acquisition RTU carries out communication with mobile phone by GSM message and connect.
The output end of data acquisition RTU is attached through cloud platform and mobile phone, and the output end of data acquisition RTU passes through GPRS
It wirelessly carries out communication with cloud platform to connect, cloud platform carries out communication with mobile phone by 3G/4G networks and connect.
For existing unattended operation transformer station it is on duty there are the problem of, inventor designs and has made a kind of substation operation
Environmental monitoring system includes mainly that data acquire RTU;The input terminal of data acquisition RTU is separately connected sensor noise, wind speed passes
Sensor, PM2.5/PM10 sensors, Temperature Humidity Sensor, rain sensor, sensor of thunder and lightning, above-mentioned data acquisition RTU's is defeated
Outlet is separately connected background monitoring host and mobile phone.The system is by all kinds of parameter signal sensors, by substation operation environment
In noise, wind speed, pollution degree (particulate matter), humiture, rainfall, thunder and lightning Real-time Monitoring Data automatic collection after by wireless
Communication transfer is to server or mobile phone terminal Centralized Monitoring, to realize comprehensive grasp to substation operating mode.In this way, patrolling
Dimension class personnel can be easily formulated as needed with targetedly making an inspection tour maintenance plan, not only time saving, saving of labor, laborsaving, but also can be protected
It is safe and reliable to demonstrate,prove substation operation.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model substation operation environmental monitoring system.
In figure:1 sensor noise, 2 air velocity transducers, 3PM2.5/PM10 sensors, 4 Temperature Humidity Sensors, 5 rainfall pass
Sensor, 6 lightning monitoring sensors, 7 data acquire RTU, 8 background monitoring hosts, 9 mobile phones, 10 cloud platforms.
Specific implementation mode
One, basic structure
As shown in Figure 1, the substation operation environmental monitoring system of the utility model, includes mainly that data acquire RTU 7;Number
It is separately connected sensor noise 1, air velocity transducer 2, PM2.5/PM10 sensors 3, temperature and humidity sensing according to the input terminal of acquisition RTU
Device 4, rain sensor 5, sensor of thunder and lightning.Wherein, the output end of data acquisition RTU passes through Ethernet and background monitoring host 8
Carry out communication connection;The output end of data acquisition RTU carries out communication by GSM message and mobile phone 9 and connect or data acquisition
The output end of RTU is attached through cloud platform 10 with mobile phone, data acquire RTU output end by GPRS wirelessly with cloud platform into
Row communication connection, cloud platform carry out communication with mobile phone by 3G/4G networks and connect.
Each sensor is installed on same place, is supported by special stand, is connect respectively with host, and real-time various dimensions monitoring becomes
Electric equipment running environment.
The running parameter design of each equipment is as follows:
1, data acquire RTU
1 data of table acquire RTU running parameters
2, air velocity transducer
2 air velocity transducer of table
3, PM2.5/PM10 working sensors parameter
3 PM2.5/PM10 working sensor parameters of table
4, Temperature Humidity Sensor
4 Temperature Humidity Sensor running parameter of table
5, rain sensor
Meet GB/T11832-2002《Tipping-bucket rain-gauge》It is required that
Resolution ratio:0.5mm
Detection range:≤8mm/min
Accuracy of measurement:± 2%
Output:Switching value pulse signal
Two, operation principle
The system by all kinds of parameter signal sensors, by substation operation environment noise, wind speed, pollution degree (
Grain object), humiture, rainfall, thunder and lightning Real-time Monitoring Data automatic collection after pass through wireless communication transmission to server or mobile phone
Terminal Centralized Monitoring, to realize comprehensive grasp to substation operating mode.
Wherein, air velocity transducer, PM2.5/PM10 sensors, Temperature Humidity Sensor, rain sensor are for monitoring power transformation
It stands the state of site environment, rational patrol plan may specify according to data result and judge equipment running status;Noise senses
Device sensor of thunder and lightning is combined, and for judging that thunder and lightning closes on situation, notifies outdoor study personnel to withdraw in time.
As needed, which can be arranged automatic alarm prompt, each to sense after pre-setting all types of data alarming values
Device, which collects, is uploaded to data acquisition RTU after data, after data exceed alarming value, data acquire RTU immediately by network with
Short message, the form of mail notice relevant people make an inspection tour maintenance personnel, and making an inspection tour maintenance personnel and being formulated according to prompt has targetedly
Make an inspection tour maintenance plan.
Claims (4)
1. a kind of substation operation environmental monitoring system, it is characterised in that include mainly that data acquire RTU;The data acquisition
The input terminal of RTU is separately connected sensor noise, air velocity transducer, PM2.5/PM10 sensors, Temperature Humidity Sensor, rainfall and passes
The output end of sensor, sensor of thunder and lightning, above-mentioned data acquisition RTU is separately connected background monitoring host and mobile phone.
2. substation operation environmental monitoring system according to claim 1, it is characterised in that:The data acquisition RTU's
Output end carries out communication with background monitoring host by Ethernet and connect.
3. substation operation environmental monitoring system according to claim 1, it is characterised in that:The data acquisition RTU's
Output end carries out communication with mobile phone by GSM message and connect.
4. substation operation environmental monitoring system according to claim 1, it is characterised in that:The data acquisition RTU's
Output end is attached through cloud platform and mobile phone, and the output end of data acquisition RTU is wirelessly communicated with cloud platform by GPRS
Connection, cloud platform carry out communication with mobile phone by 3G/4G networks and connect.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721657515.4U CN207751517U (en) | 2017-12-01 | 2017-12-01 | Substation operation environmental monitoring system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721657515.4U CN207751517U (en) | 2017-12-01 | 2017-12-01 | Substation operation environmental monitoring system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207751517U true CN207751517U (en) | 2018-08-21 |
Family
ID=63148127
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721657515.4U Active CN207751517U (en) | 2017-12-01 | 2017-12-01 | Substation operation environmental monitoring system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207751517U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107741253A (en) * | 2017-12-01 | 2018-02-27 | 广西电网有限责任公司南宁供电局 | Substation operation environmental monitoring system |
-
2017
- 2017-12-01 CN CN201721657515.4U patent/CN207751517U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107741253A (en) * | 2017-12-01 | 2018-02-27 | 广西电网有限责任公司南宁供电局 | Substation operation environmental monitoring system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204883442U (en) | District environmental monitoring device | |
CN102509886A (en) | System for automatically monitoring state of base station antennae | |
CN103134554B (en) | A kind of protective relaying device running environment monitoring device and monitoring method thereof | |
CN202928616U (en) | Transmission line conducting wire icing and galloping on-line monitoring system | |
CN211206462U (en) | Thing networking water quality monitoring system | |
CN104344901A (en) | Temperature monitoring early warning system of transformer substation high voltage switch cabinet | |
CN206431183U (en) | Monitoring alarm temporarily drops in line voltage | |
CN209283265U (en) | One kind can Wireless Networking water surface flow measuring system | |
CN202794300U (en) | Online monitoring device of power transmission line lightening arrester | |
CN207908613U (en) | Overhead transmission line shaft tower comprehensive monitor system | |
CN207352409U (en) | A kind of antenna base station health status monitoring system | |
CN107741253A (en) | Substation operation environmental monitoring system | |
CN207751517U (en) | Substation operation environmental monitoring system | |
CN210373644U (en) | Socialized linkage early warning and purifying system | |
CN209247120U (en) | Based on balance bell-type pressure sensor water level measurement system | |
CN104898580A (en) | Wireless oil pumping unit controller with three-phase electric acquisition | |
CN204155435U (en) | A kind of wireless temperature acquisition system | |
CN207472299U (en) | Remote icing parameter monitoring system based on more rotated conductors | |
CN101778263A (en) | Intelligent power grid wireless monitoring system | |
CN207968069U (en) | photovoltaic plant remote monitoring system based on ZigBee and WiFi | |
CN202870598U (en) | Enterprise heat-supply network monitoring system employing industrial wireless WIA technology | |
CN216144371U (en) | Power supply running state monitoring device | |
CN202869655U (en) | Online temperature monitoring device of high-voltage electrical equipment | |
CN204759717U (en) | PM2. 5 monitoring facilities | |
CN201845423U (en) | Meteorology on-line monitoring system of power transmission line |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |