CN207701937U - A kind of para-seismic support for pipes - Google Patents
A kind of para-seismic support for pipes Download PDFInfo
- Publication number
- CN207701937U CN207701937U CN201721637481.2U CN201721637481U CN207701937U CN 207701937 U CN207701937 U CN 207701937U CN 201721637481 U CN201721637481 U CN 201721637481U CN 207701937 U CN207701937 U CN 207701937U
- Authority
- CN
- China
- Prior art keywords
- pipe clamp
- anchor bolt
- channel steel
- brace channel
- fixed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model discloses a kind of para-seismic support for pipes, including main brace structure, inclined support structure and fixed structure, main brace structure includes main brace channel steel, across main brace channel steel all-teeth screw and be fixedly connected on first anchor bolt on all-teeth screw top, main brace channel steel side is provided with screw rod lock, main brace channel steel is fixed on by screw rod lock in all-teeth screw, all-teeth screw is connected by the first anchor bolt with concrete layer, inclined support structure includes two diagonal brace channel steels, adjustable hinge fitting at diagonal brace channel steel both ends and the second anchor bolt for being connect with adjustable hinge fitting are set, fixed structure includes the first pipe clamp and the second pipe clamp, first pipe clamp and the second pipe clamp are fixed on pipeline, first pipe clamp top is fixed on all-teeth screw bottom end, two diagonal brace channel steels are fixedly connected with the first pipe clamp and the second pipe clamp respectively;A kind of the purpose of this utility model is to provide installations para-seismic support for pipes simple, reasonable for structure, that security risk and reduction economic loss can be reduced when earthquake occurs.
Description
Technical field
The utility model is related to a kind of para-seismic support for pipes, belong to shake-proof technology field.
Background technology
In building electromechanical engineering, the installation of pipeline is frequently necessary to use support of pipelines, branch of the support of pipelines as pipeline
Support structure, its stability and safety are extremely important, existing support of pipelines consider only resist pipeline gravity and
Ensure that it uses function, not yet considers that when an earthquake occurs, the seismic force effects that pipeline is born can make pipeline that dislocation occur, fall
It falls, electromechanical engineering system is made to be unable to operate normally, cause unnecessary economic loss, and hidden with very big safety
Suffer from.
Utility model content
The purpose of this utility model is to provide it is a kind of installation it is simple, reasonable for structure, peace can be reduced when earthquake occurs
Full hidden danger and the para-seismic support for pipes for reducing economic loss, to solve the problems, such as to propose in background technology.
To achieve the above object, the utility model uses following technical scheme:A kind of para-seismic support for pipes, including main brace knot
Structure, inclined support structure and fixed structure, the main brace structure include main brace channel steel, the all-teeth screw across main brace channel steel and fixation
It is connected to first anchor bolt on all-teeth screw top, main brace channel steel side is provided with screw rod lock, and the main brace channel steel passes through
Screw rod lock is fixed in all-teeth screw, and the all-teeth screw is connected by the first anchor bolt with concrete layer, the inclined support structure
Including two diagonal brace channel steels, be arranged diagonal brace channel steel both ends adjustable hinge fitting and be arranged on diagonal brace channel steel top can
It includes the first pipe clamp and the second pipe clamp, first pipe clamp and the to adjust the second anchor bolt of hinge fitting connection, the fixed structure
Two pipe clamps are fixed on pipeline, and first pipe clamp top is fixed on all-teeth screw bottom end, and two diagonal brace channel steels are by can
Hinge fitting is adjusted to be fixedly connected respectively with the first pipe clamp and the second pipe clamp.
Further, it includes upper layer pipe clamp, lower layer's pipe clamp and the first fixing bolt, institute that first pipe clamp, which is bimetallic tube folder,
State upper layer pipe clamp and all-teeth screw bottom end be fixed on by self-locking nut, first fixing bolt sequentially pass through upper layer pipe clamp, under
It is fixed by self-locking nut after layer pipe clamp, adjustable hinge fitting.
Further, second pipe clamp top is fixedly connected by self-locking nut with adjustable hinge fitting, and described second
Pipe clamp bottom end is provided with the second fixing bolt, and second pipe clamp bottom end is fixed by the second fixing bolt.
Further, the all-teeth screw passes through self-locking with the first anchor bolt, the adjustable hinge fitting and the second anchor bolt
Nut is fixedly connected, and the diagonal brace channel steel is fixedly connected with adjustable hinge fitting by moulding wing nut.
Further, first anchor bolt is to adapt to the rear base expanding and base expanding anchor bolt of cracked concrete performance with the second anchor bolt.
Further, the main brace channel steel, all-teeth screw, the first anchor bolt, diagonal brace channel steel, adjustable hinge fitting, the second anchor
Bolt, the first pipe clamp, the second pipe clamp are all made of galvanizing by dipping or electrogalvanizing preservative treatment.
After adopting the above technical scheme, the utility model compared with the background art, has the following advantages that:The utility model is pacified
Fill it is simple, reasonable for structure, security risk can be reduced when earthquake occurs and reduce economic loss;It when mounted can be according to need
Adjust adjustable hinge fitting, change the support angle of diagonal brace channel steel, two diagonal brace channel steels respectively with the first pipe clamp, the second pipe clamp
Connection, two diagonal brace channel steels provide two skewed horizontal loads, and self-locking nut can be prevented in earthquake due to nut caused by vibrations
It loosens, the use of the first anchor bolt and the second anchor bolt can prevent the holder in earthquake from falling off from concrete layer.
Description of the drawings
Fig. 1 is the main structure diagram of the utility model.
Fig. 2 is the side structure schematic view of the utility model.
Fig. 3 is the overlooking structure diagram of the utility model.
In figure:10, main brace channel steel;11, screw rod latches;20, all-teeth screw;21, the first anchor bolt;30, diagonal brace channel steel;40、
Adjustable hinge fitting;41, the second anchor bolt;50, the first pipe clamp;51, upper layer pipe clamp;52, lower layer's pipe clamp;53, the first fixing bolt;
60, the second pipe clamp;61, the second fixing bolt;70, self-locking nut;80, wing nut is moulded.
Specific implementation mode
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, below in conjunction with attached drawing and implementation
Example, the present invention will be further described in detail.It should be appreciated that specific embodiment described herein is only used to explain
The utility model is not used to limit the utility model.
Embodiment
It please refers to Fig.1, Fig. 2 and Fig. 3, the utility model discloses a kind of para-seismic support for pipes, including main brace structure, diagonal brace
Structure and fixed structure, the main brace structure include main brace channel steel 10, the all-teeth screw 20 across main brace channel steel 10 and fixation
It is connected to first anchor bolt 21 on 20 top of all-teeth screw, 10 side of main brace channel steel is provided with screw rod lock 11, the main brace
Channel steel 10 is fixed on by screw rod lock 11 in all-teeth screw 20, and the all-teeth screw 20 passes through the first anchor bolt 21 and concrete layer
Connection, the inclined support structure includes two diagonal brace channel steels 30, be arranged 30 both ends of diagonal brace channel steel adjustable hinge fitting 40 and
The second anchor bolt 41 being connect with the adjustable hinge fitting 40 being arranged on 30 top of diagonal brace channel steel, the fixed structure include the first pipe
Folder 50 and the second pipe clamp 60, first pipe clamp, 50 and second pipe clamp 60 are fixed on pipeline, and 50 top of the first pipe clamp is solid
Be scheduled on 20 bottom end of all-teeth screw, two diagonal brace channel steels 30 by adjustable hinge fitting 40 respectively with the first pipe clamp 50 and second
Pipe clamp 60 is fixedly connected.
In the present embodiment:First pipe clamp 50 is that bimetallic tube folder includes upper layer pipe clamp 51, lower layer's pipe clamp 52 and first
Fixing bolt 53, the upper layer pipe clamp 51 are fixed on 20 bottom end of all-teeth screw, first fixing bolt by self-locking nut 70
53 sequentially pass through upper layer pipe clamp 51, lower layer's pipe clamp 52, adjustable hinge fitting 40 after fixed by self-locking nut 70;Second pipe
It presss from both sides 60 tops to be fixedly connected with adjustable hinge fitting 40 by self-locking nut 70, it is solid that 60 bottom end of the second pipe clamp is provided with second
Determine bolt 61,60 bottom end of the second pipe clamp is fixed by the second fixing bolt 61;The all-teeth screw 20 and the first anchor bolt 21,
The adjustable hinge fitting 40 is fixedly connected by self-locking nut 70 with the second anchor bolt 41, the diagonal brace channel steel 30 and adjustable hinge
Connector 40 is fixedly connected by moulding wing nut 80;First anchor bolt, 21 and second anchor bolt 41 is to adapt to cracked concrete
The rear base expanding and base expanding anchor bolt of energy;The main brace channel steel 10, all-teeth screw 20, the first anchor bolt 21, diagonal brace channel steel 30, adjustable hinge fitting
40, the second anchor bolt 41, the first pipe clamp 50, the second pipe clamp 60 are all made of galvanizing by dipping or electrogalvanizing preservative treatment.
The utility model installation is simple, reasonable for structure, security risk and the economic damage of reduction can be reduced when earthquake occurs
It loses;Pipeline is fixed on the first pipe clamp 50, in the second pipe clamp 60,50 top of the first pipe clamp is fixedly connected with all-teeth screw 20, and
One pipe clamp, 50 side is fixedly connected by adjustable hinge fitting 40 with diagonal brace channel steel 30, and two diagonal brace channel steels 30 are by being arranged at it
The adjustable hinge fitting 40 of bottom end is fixedly connected with the first pipe clamp 50 and the second pipe clamp 60 respectively, and all-teeth screw 20 passes through self-locking spiral shell
Mother 70 is fixedly connected with the first anchor bolt 21, and diagonal brace channel steel 30 is by being arranged 40 and second anchor bolt of adjustable hinge fitting on its top
41 are fixedly connected, and the first anchor bolt 21 is fixedly connected with the second anchor bolt 41 with concrete layer;It can adjust as needed when mounted
Adjustable hinge fitting 40, changes the support angle of diagonal brace channel steel 30, and two diagonal brace channel steels 30 are managed with the first pipe clamp 50, second respectively
60 connection of folder, two diagonal brace channel steels 30 provide two skewed horizontal loads, and self-locking nut 70 can be prevented in earthquake since vibrations are made
At nut loosening, the use of the first anchor bolt 21 and the second anchor bolt 41 can prevent the holder in earthquake from falling off from concrete layer.
The preferable specific implementation mode of the above, only the utility model, but the scope of protection of the utility model is not
It is confined to this, any one skilled in the art within the technical scope disclosed by the utility model, can readily occur in
Change or replacement, should be covered within the scope of the utility model.Therefore, the scope of protection of the utility model should
It is subject to the protection scope in claims.
Claims (6)
1. a kind of para-seismic support for pipes, including main brace structure, inclined support structure and fixed structure, it is characterised in that:The main brace knot
Structure include main brace channel steel, across main brace channel steel all-teeth screw and be fixedly connected on first anchor bolt on all-teeth screw top, institute
It states main brace channel steel side and is provided with screw rod lock, the main brace channel steel is fixed on by screw rod lock in all-teeth screw, described complete
Tooth screw rod is connected by the first anchor bolt with concrete layer, and the inclined support structure includes two diagonal brace channel steels, is arranged in diagonal brace channel steel
The adjustable hinge fitting at both ends and the second anchor bolt being connect with the adjustable hinge fitting being arranged on diagonal brace channel steel top, it is described solid
It includes the first pipe clamp and the second pipe clamp to determine structure, and first pipe clamp and the second pipe clamp are fixed on pipeline, first pipe clamp
Top is fixed on all-teeth screw bottom end, and two diagonal brace channel steels are managed with the first pipe clamp and second respectively by adjustable hinge fitting
Folder is fixedly connected.
2. a kind of para-seismic support for pipes as described in claim 1, it is characterised in that:First pipe clamp is that bimetallic tube folder includes
Upper layer pipe clamp, lower layer's pipe clamp and the first fixing bolt, the upper layer pipe clamp are fixed on all-teeth screw bottom end, institute by self-locking nut
It states after the first fixing bolt sequentially passes through upper layer pipe clamp, lower layer's pipe clamp, adjustable hinge fitting and is fixed by self-locking nut.
3. a kind of para-seismic support for pipes as described in claim 1, it is characterised in that:Second pipe clamp top passes through self-locking spiral shell
Female to be fixedly connected with adjustable hinge fitting, second pipe clamp bottom end is provided with the second fixing bolt, second pipe clamp bottom end
It is fixed by the second fixing bolt.
4. a kind of para-seismic support for pipes as described in claim 1, it is characterised in that:The all-teeth screw and the first anchor bolt, institute
It states adjustable hinge fitting to be fixedly connected by self-locking nut with the second anchor bolt, the diagonal brace channel steel passes through with adjustable hinge fitting
Modeling wing nut is fixedly connected.
5. a kind of para-seismic support for pipes as described in claim 1, it is characterised in that:First anchor bolt is with the second anchor bolt
Adapt to the rear base expanding and base expanding anchor bolt of cracked concrete performance.
6. a kind of para-seismic support for pipes as described in claim 1, it is characterised in that:The main brace channel steel, all-teeth screw, first
Anchor bolt, diagonal brace channel steel, adjustable hinge fitting, the second anchor bolt, the first pipe clamp, the second pipe clamp are all made of galvanizing by dipping or electrogalvanizing is anti-
Corruption processing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721637481.2U CN207701937U (en) | 2017-11-30 | 2017-11-30 | A kind of para-seismic support for pipes |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721637481.2U CN207701937U (en) | 2017-11-30 | 2017-11-30 | A kind of para-seismic support for pipes |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207701937U true CN207701937U (en) | 2018-08-07 |
Family
ID=63024560
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721637481.2U Active CN207701937U (en) | 2017-11-30 | 2017-11-30 | A kind of para-seismic support for pipes |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207701937U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109138201A (en) * | 2018-08-28 | 2019-01-04 | 浙江甬泰工程技术有限公司 | A kind of self-locking type para-seismic support being easily installed |
-
2017
- 2017-11-30 CN CN201721637481.2U patent/CN207701937U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109138201A (en) * | 2018-08-28 | 2019-01-04 | 浙江甬泰工程技术有限公司 | A kind of self-locking type para-seismic support being easily installed |
CN109138201B (en) * | 2018-08-28 | 2020-07-24 | 浙江甬泰工程技术有限公司 | Self-locking anti-seismic support convenient to install |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206861059U (en) | A kind of antidetonation comprehensive pipeline hanger system | |
CN206874971U (en) | A kind of gate antidetonation suspension and support | |
CN106969208A (en) | A kind of gate antidetonation suspension and support | |
CN108105472A (en) | A kind of locking antidetonation suspension and support for pipe laying | |
CN108150720A (en) | A kind of locking antidetonation suspension and support for pipe laying | |
JP6404583B2 (en) | Ceiling hanging bolt, ceiling material mounting device and universal joint | |
CN207701937U (en) | A kind of para-seismic support for pipes | |
CN205025117U (en) | Adjustable bearing diagonal is used in assembly type structure prefabricated component installation | |
CN211423687U (en) | Air pipe single-side double-longitudinal anti-seismic support | |
CN207421506U (en) | A kind of antidetonation suspension and support of warm ventilation pipe | |
CN203008247U (en) | Novel siphon draining suspension system | |
CN208442395U (en) | A kind of antidetonation water pipe list hangs Bidirectional supporting | |
CN204112729U (en) | Pipe well inner sleeve reserves fixed support | |
CN210007291U (en) | special cable anti-seismic support for pipe gallery | |
CN210978758U (en) | Multi-tube double-lateral anti-seismic support | |
CN205896419U (en) | Secondary suspends pipeline square steel chain union piece of vertically combatting earthquake in midair | |
CN209818911U (en) | But height-adjusting's antidetonation gallows | |
CN205480099U (en) | Anti -knock connecting base | |
CN210398228U (en) | Monitoring camera support based on power transmission tower | |
CN209754566U (en) | Box steel fastening device with axial clamping function | |
CN211369561U (en) | Concrete conveying pipe vertical section fixing device | |
CN212986287U (en) | Integral type antidetonation two-way fixed bolster and pipeline antidetonation hang structure | |
CN208417761U (en) | A kind of fastening pipe clamp | |
CN207063676U (en) | Swing suspension column | |
CN208793418U (en) | A kind of screw rod connector and para-seismic support |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |