CN207686736U - With the service channel combined steel section of jurisdiction at main tunnel connecting position - Google Patents

With the service channel combined steel section of jurisdiction at main tunnel connecting position Download PDF

Info

Publication number
CN207686736U
CN207686736U CN201820049120.4U CN201820049120U CN207686736U CN 207686736 U CN207686736 U CN 207686736U CN 201820049120 U CN201820049120 U CN 201820049120U CN 207686736 U CN207686736 U CN 207686736U
Authority
CN
China
Prior art keywords
jurisdiction
section
service channel
main tunnel
combined steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820049120.4U
Other languages
Chinese (zh)
Inventor
丁修恒
文毅然
董子博
石雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Civil Engineering Co Ltd of CREC
Urban Rail Transit Engineering Branch of Shanghai Civil Engineering Co Ltd of CREC
Ningbo Rail Transit Group Co Ltd
Original Assignee
Shanghai Civil Engineering Co Ltd of CREC
Urban Rail Transit Engineering Branch of Shanghai Civil Engineering Co Ltd of CREC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Civil Engineering Co Ltd of CREC, Urban Rail Transit Engineering Branch of Shanghai Civil Engineering Co Ltd of CREC filed Critical Shanghai Civil Engineering Co Ltd of CREC
Priority to CN201820049120.4U priority Critical patent/CN207686736U/en
Application granted granted Critical
Publication of CN207686736U publication Critical patent/CN207686736U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a kind of service channel combined steel sections of jurisdiction at main tunnel connecting position, it is to use combined steel section of jurisdiction for the service channel at main tunnel connecting position, combined steel section of jurisdiction refers to setting every steel pipe sheet to two parts by the radian fission in the main tunnel of respective place circumferential location, a part is the fixing pipe segment being located in service channel, and another part is the interim section of jurisdiction section for needing to remove;Implement to dismount using straight bolt between fixing pipe segment and interim section of jurisdiction section.The utility model uses combined steel section of jurisdiction, implements to dismount using straight bolt, it is no longer necessary to be cut off at the scene, greatly improve site operation efficiency, also greatly be beneficial to ensure construction quality.

Description

With the service channel combined steel section of jurisdiction at main tunnel connecting position
Technical field
The utility model is related to applied in shield method Freezing Method for Cross-passage Construction with main tunnel connecting position at service channel Steel pipe sheet.
Background technology
One kind is disclosed in the application for a patent for invention file that application publication number is CN106948833A, and " pin-connected panel contact is logical Road structure and construction method ", shield method get in touch with can road construction in, for the service channel at main tunnel connecting position Steel pipe sheet is using structure shape as shown in fig. 4 a, and every steel pipe sheet is the identical conventional cylindrical section steel pipe sheet 11 of structure, assembled Complete cycle is in cylindrical tube afterwards, and Fig. 4 b show the connecting position in main tunnel 21 and service channel 22 using this cylindrical section steel pipe sheet The structure type at place;In order to make the structure of service channel 22 not invade main tunnel boundary, after the completion of service channel 22 tunnels, need The part service channel steel pipe sheet in main tunnel and service channel joint area is cut off in the radian in the hole tunnels Nei Anzhu 21, such as schemed Cut-out 12 shown in 4b.But in site operation, since work surface is narrow, hole internal cutting process work efficiency is very low, operation wind Danger is big, it is difficult to ensure construction quality.
Utility model content
The utility model is provided at a kind of and main tunnel connecting position to avoid above-mentioned deficiency of the prior art Service channel combined steel section of jurisdiction and construction method ensure construction quality to improve construction efficiency.
The utility model is to solve technical problem to adopt the following technical scheme that:
The design feature of the utility model and the service channel combined steel section of jurisdiction at main tunnel connecting position:For with master Service channel at tunnel connecting position uses combined steel section of jurisdiction, and the combined steel section of jurisdiction refers to by every steel pipe sheet by each Two parts are set as from the radian fission in the main tunnel of place circumferential location, a part is to be located in service channel to fix section of jurisdiction Section, another part are the interim section of jurisdiction sections for needing to remove;Straight bolt is utilized between the fixing pipe segment and interim section of jurisdiction section Implement dismounting.
The utility model and the design feature of the service channel combined steel section of jurisdiction at main tunnel connecting position are lain also in:It will Seam in the every steel pipe sheet between fixing pipe segment and interim section of jurisdiction section is set as straightway so that by each steel pipe sheet Complete cycle after fixing pipe segment assembly is connected the polygonized structure to be formed with each straightway.
Compared with the prior art, the utility model has the beneficial effect that:
1, the utility model uses combined steel section of jurisdiction, real using straight bolt between fixing pipe segment and interim section of jurisdiction section Apply dismounting, it is no longer necessary to be cut off at the scene, greatly improve site operation efficiency, also greatly be beneficial to ensure engineering Quality.
2, the utility model largely facilitates adding for steel pipe sheet for every steel pipe sheet using straightway approximation circular arc Work makes.
Description of the drawings
Fig. 1 is the utility model site operation schematic diagram;
Fig. 2 is fixing pipe fragment structure schematic diagram in the utility model;
Fig. 3 is interim section of jurisdiction segment structure schematic diagram in the utility model;
Fig. 4 a are conventional cylindrical section steel pipe sheet structural schematic diagram in the prior art;
Fig. 4 b are cut-out schematic diagram in the prior art;
Figure label:11 conventional cylindrical section steel pipe sheets, 12 cut-outs, 21 main tunnels, 22 service channels, 23 fix section of jurisdiction Section, 24 interim section of jurisdiction sections.
Specific implementation mode
Referring to Fig. 1, Fig. 2 and Fig. 3, in the present embodiment with the service channel combined steel section of jurisdiction at main tunnel connecting position Structure type is:Combined steel section of jurisdiction, combined steel section of jurisdiction are used for the service channel 22 at 21 connecting position of main tunnel Refer to setting every steel pipe sheet to two parts by the radian fission in the main tunnel of respective place circumferential location, a part is position The fixing pipe segment 23 in service channel, another part are the interim section of jurisdiction sections 24 for needing to remove;Fixing pipe segment 23 with face When section of jurisdiction section 24 between using straight bolt implement dismounting.
In specific implementation, the seam between fixing pipe segment 23 in every steel pipe sheet and interim section of jurisdiction section 24 is pressed into two-end-point Position is set as straightway so that by the complete cycle after 23 assembly of fixing pipe segment in each steel pipe sheet is to connect to being formed with each straightway Trisection line polygonized structure, using the circular arc in the close main tunnel of the polygon of proximal segment line, using trisection line compared with circular arc point From design, can be very big simplified making work section, reduce cost of manufacture, the machining accuracy of conventional steel pipe piece can be met the requirements.
The utility model can greatly improve construction efficiency, reduce site operation amount, improve site operation environment, reduce Operating risk.
In work progress, it is attached, is made using straight bolt first between fixing pipe segment 23 and interim section of jurisdiction section 24 Its entirety is rendered as conventional cylindrical section steel pipe sheet, and assembled, tunneling construction is carried out using usual manner for cylindrical section steel pipe sheet When completion, portal interface implements closure and joint weld by construction requirement, completes entrance construction;Then, it is hung in tunnel top Chain block tenses interim section of jurisdiction section 24 using chain block, removes the straight bolt in corresponding interim section of jurisdiction section 24, completion group The dismounting of section of jurisdiction is closed, ensures that service channel section of jurisdiction does not invade shield tunnel limit.

Claims (2)

1. a kind of service channel combined steel section of jurisdiction at main tunnel connecting position, it is characterized in that:
Combined steel section of jurisdiction is used for the service channel at main tunnel connecting position, the combined steel section of jurisdiction refers to will be every Piece steel pipe sheet is set as two parts by the radian fission in the main tunnel of respective place circumferential location, and a part is to be located at contact to lead to Fixing pipe segment (23) in road (22), another part are the interim section of jurisdiction sections (24) for needing to remove;In the fixing pipe segment (23) implement to dismount using straight bolt between interim section of jurisdiction section (24).
2. the service channel combined steel section of jurisdiction according to claim 1 at main tunnel connecting position, it is characterized in that:It will Seam in the every steel pipe sheet between fixing pipe segment (23) and interim section of jurisdiction section (24) is set as straightway so that by each Complete cycle in steel pipe sheet after the assembly of fixing pipe segment is connected the polygonized structure to be formed with each straightway.
CN201820049120.4U 2018-01-12 2018-01-12 With the service channel combined steel section of jurisdiction at main tunnel connecting position Active CN207686736U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820049120.4U CN207686736U (en) 2018-01-12 2018-01-12 With the service channel combined steel section of jurisdiction at main tunnel connecting position

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820049120.4U CN207686736U (en) 2018-01-12 2018-01-12 With the service channel combined steel section of jurisdiction at main tunnel connecting position

Publications (1)

Publication Number Publication Date
CN207686736U true CN207686736U (en) 2018-08-03

Family

ID=62991913

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820049120.4U Active CN207686736U (en) 2018-01-12 2018-01-12 With the service channel combined steel section of jurisdiction at main tunnel connecting position

Country Status (1)

Country Link
CN (1) CN207686736U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108005686A (en) * 2018-01-12 2018-05-08 中铁上海工程局集团有限公司 With the service channel combined steel section of jurisdiction at main tunnel connecting position and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108005686A (en) * 2018-01-12 2018-05-08 中铁上海工程局集团有限公司 With the service channel combined steel section of jurisdiction at main tunnel connecting position and construction method

Similar Documents

Publication Publication Date Title
CN108005686A (en) With the service channel combined steel section of jurisdiction at main tunnel connecting position and construction method
CN106934159A (en) A kind of assembled point bit digitizing type selecting assembling method of duct pieces of shield tunnel
CN105507908B (en) A kind of large cross-section tunnel branch-cut bridge Duan Sanlian encircles construction technology
CN103551750A (en) Welded pipe and manufacturing method thereof
CN105862589A (en) Manufacturing method for broken-line-shaped double-joint stud welded chord member with anchor boxes
CN104533433A (en) Starting method of small-radius curve tunnel
CN207686736U (en) With the service channel combined steel section of jurisdiction at main tunnel connecting position
CN105710551A (en) Welding method for double-layered tube
EP3868979B1 (en) Method for tensioning prefabricated component employing centroid tracking and seam width control
CN203725998U (en) Welding assembly and valve body
CN104343117A (en) Concrete pipe pile connector
CN103952985A (en) Hammering closing repair method for fatigue crack of steel bridge
CN105171261A (en) Welding method of large steel making converter body
CN109048180A (en) The method welded with locating piece
CN105195637A (en) Bimetal composite pipe liquid expansion forming feeding device and process
CN106907156B (en) Multi-edge tail shield structural member assembly point manufacturing method
CN207688667U (en) A kind of sintering flue sealing structure
CN211777462U (en) Light positioning die for assembling pipe pieces
CN205660331U (en) Seamless steel pipe ring flange welding die set
CN211081879U (en) Prefabricated lining circular seam staggered joint assembling structure for tunneling tunnel by mechanical method
CN210948678U (en) Shield constructs quick-witted shield tail clearance gushes water and gushes sand plugging device
CN104594421B (en) A kind of installation method of cutter suction dredger reamer beam length axis hole twisted branch frame
CN107906973B (en) Sintering flue sealing structure
CN204879134U (en) Hydraulic pressure connects body structure with steel pipe
CN110005450B (en) Waterproof structure for subway station and shield tunnel interface and construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210903

Address after: 200040 No. 278 Jiangchang Third Road, Jing'an District, Shanghai

Patentee after: SHANGHAI CIVIL ENGINEERING Co.,Ltd. OF CREC

Patentee after: NINGBO RAIL TRANSIT GROUP Co.,Ltd.

Patentee after: SHANGHAI CIVIL ENGINEERING CO., LTD. OF CREC URBAN RAIL TRANSIT ENGINEERING Co.

Address before: 200436 Zhabei District, Shanghai JIANGCHANG three road 272, 278

Patentee before: SHANGHAI CIVIL ENGINEERING Co.,Ltd. OF CREC

Patentee before: SHANGHAI CIVIL ENGINEERING CO., LTD. OF CREC URBAN RAIL TRANSIT ENGINEERING Co.

TR01 Transfer of patent right