CN207647189U - A kind of construction discharging platform - Google Patents

A kind of construction discharging platform Download PDF

Info

Publication number
CN207647189U
CN207647189U CN201721447318.XU CN201721447318U CN207647189U CN 207647189 U CN207647189 U CN 207647189U CN 201721447318 U CN201721447318 U CN 201721447318U CN 207647189 U CN207647189 U CN 207647189U
Authority
CN
China
Prior art keywords
wall
crossbeam
reinforcing bar
fixed
drag
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721447318.XU
Other languages
Chinese (zh)
Inventor
毛强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201721447318.XU priority Critical patent/CN207647189U/en
Application granted granted Critical
Publication of CN207647189U publication Critical patent/CN207647189U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of construction discharging platforms, the right side of the civil engineering structure is equipped with crossbeam, the left side outer wall of the crossbeam is connected with the outer right wall of civil engineering structure, the inner wall of the crossbeam is equipped with sliding slot, the outer wall of the sliding slot is connected with the inner wall of crossbeam, the inside of the sliding slot is equipped with pulley, and the outer wall of the pulley is connected with the inner wall of sliding slot, and the left side of the crossbeam is equipped with fixed lateral reinforcing bar.The construction discharging platform, under the action of fixed square steel and triangular steel plate, crossbeam and civil engineering structure are linked together, so that crossbeam is formed an entirety with civil engineering structure, keeps the discharging platform that civil engineering structure is built with crossbeam more firm, springboard is enable to be taken out out of crossbeam, to overcome traditional discharging platform lack in the case where road is uneven or miriness can not discharging the shortcomings that, the work fatigue for reducing stevedore, saves construction cost, is suitble to promote and apply.

Description

A kind of construction discharging platform
Technical field
The utility model is related to construction engineering technical field, specially a kind of construction discharging platform.
Background technology
Discharging platform is that various provisional operation consoles are often set up in construction site, can carry out various building finishing and painting etc. by laying bricks or stones Operation in general can be within certain duration for carrying material, and carries out the framework type platform of various operations wherein, claims Be operating platform, it is a variety of that operating platform is divided into movable operation platform, console mode and overhanging type operating platform, also referred to as Transfer platform in the prior art, such as application No. is 201520710363.4 utility model patent includes platform, described flat The side of platform is equipped with supporting rod, and the other side of the platform is equipped with safe fence, and the platform includes fixed frame and is fixed on Loading deck on the fixed frame, the supporting rod is detachable connection with the platform, although the utility model is tied Structure is simple, but there are many deficiencies and defect, in existing equipment, the design existing defects of discharging platform, and pedestal and side plate Connection can not carry pressure caused by a large amount of placing of material when discharging, and be not provided with the facilities such as springboard improve it is anti- Setting of the muddy road surface to discharging inconvenience, in view of these situations, to avoid above-mentioned technical problem, it is necessory to provide a kind of building Construction discharging platform is to overcome the defect in the prior art.
Utility model content
The purpose of this utility model is to provide a kind of construction discharging platforms, to solve to carry in above-mentioned background technology The problem of going out.
To achieve the above object, the utility model provides the following technical solutions:A kind of construction discharging platform, packet It includes:The right side of civil engineering structure, the civil engineering structure is equipped with crossbeam, the left side outer wall of the crossbeam and the outer right wall of civil engineering structure It is connected, the inner wall of the crossbeam is equipped with sliding slot, and the outer wall of the sliding slot is connected with the inner wall of crossbeam, and the inside of the sliding slot is equipped with Pulley, the outer wall of the pulley are connected with the inner wall of sliding slot, and the left side of the crossbeam is equipped with fixed lateral reinforcing bar, described fixed horizontal The left side outer wall of outer right wall and crossbeam to reinforcing bar is connected, and the top of the fixed lateral reinforcing bar is equipped with fixed vertical reinforcement, The outer wall of the fixed vertical reinforcement is connected with the inner wall of fixed lateral reinforcing bar, and the top of the pulley is equipped with springboard, the jump The inner wall overlap joint of the outer wall of plate and sliding slot is connected, and the outer wall of the springboard is overlapped with the outer wall of pulley to be connected, the crossbeam it is upper Surface is equipped with guardrail, and the lower surface of the guardrail is connected with the upper surface of crossbeam, and the inside of the guardrail is equipped with steel wire, described The outer wall of steel wire is connected with the inner wall of guardrail, and the outside of the crossbeam is equipped with the first drag-line, the inner wall of first drag-line with The outer wall of crossbeam is connected, and the right side of first drag-line is equipped with the second drag-line, the outer wall of the outer wall and crossbeam of second drag-line It is connected, the top of second drag-line is equipped with fixed pull ring, and the inner wall of the fixed pull ring is connected with the outer wall of the second drag-line, institute The inner wall for stating fixed pull ring is connected by the second drag-line with the outer wall of crossbeam, the outer wall of the fixed pull ring and civil engineering structure it is interior Wall is connected, and the junction of the fixed lateral reinforcing bar and crossbeam is equipped with fixed square steel, the outer wall of the fixed square steel respectively with it is solid Determine transverse steel with the inner wall of crossbeam to be connected, the right side of the fixed square steel is equipped with triangular steel plate, the left side of the triangular steel plate Outer wall is connected with the outer right wall of fixed square steel, and the left end of the crossbeam is equipped with guiding gutter, the outer wall and crossbeam of the guiding gutter Inner wall be connected, the bottom end of the fixed vertical reinforcement is equipped with hollow reinforcing bar, the upper surface of the hollow reinforcing bar with it is fixed perpendicular To the lower surface of reinforcing bar be connected, between the outer wall of the hollow reinforcing bar be equipped with hook-type reinforcing bar, the inner wall of the hook-type reinforcing bar with return The outer wall of steel bar is connected, and the outer wall of the fixed lateral reinforcing bar is equipped with connection reinforcing bar, the outer wall of the connection reinforcing bar and fixation The inner wall of transverse steel is connected, and the connection reinforcing bar runs through fixed lateral reinforcing bar, the outer wall and civil engineering structure of the connection reinforcing bar Inner wall be connected.
Preferably, the right side of the civil engineering structure is equipped with prefabricated embedded part, left side outer wall and the civil engineering knot of the prefabricated embedded part The outer right wall of structure is connected, and the right side of the prefabricated embedded part is equipped with bearing diagonal, left side outer wall and the prefabricated embedded part of the bearing diagonal Outer right wall be connected, the top of the bearing diagonal is equipped with horizontally-supported, and the horizontally-supported top is equipped with side plate, the side The inner wall of plate is connected with horizontally-supported outer wall, and the top of the side plate is equipped with rain visor, the lower surface and side of the rain visor The outer wall of plate is connected.
Preferably, the outer wall of first drag-line is equipped with fixed rope, the outer wall of the inner wall and the first drag-line of the fixed rope It is connected.
Preferably, the right end of the fixed lateral reinforcing bar is equipped with bail, outer wall and the fixed lateral steel of the bail The inner wall of muscle is connected.
Preferably, the top of first drag-line is equipped with cushion block, the lower surface of the cushion block and the upper surface of civil engineering structure It is connected.
Compared with prior art, the utility model has the beneficial effects that:The construction discharging platform, passes through civil engineering knot Cooperation between structure, crossbeam, fixed lateral reinforcing bar and fixed vertical reinforcement will under the action of fixed square steel and triangular steel plate Crossbeam links together with civil engineering structure, and crossbeam is made to form an entirety with civil engineering structure, and whole bearing capacity is added By force, can place more construction materials, fixed square steel links together fixed lateral reinforcing bar with crossbeam, make civil engineering structure and Connection between fixed lateral reinforcing bar is more stablized, and set square is used to add the connection of fixed square steel and fixed lateral reinforcing bar Gu keeping the discharging platform that civil engineering structure is built with crossbeam more firm, to overcome lacking for traditional discharging platform stability difference Point makes civil engineering structure and crossbeam by the cooperation between the first drag-line, the second drag-line and fixed pull ring under the action of cushion block The discharging platform built is more firm, and cushion block can effectively reduce rubbing between the first drag-line, the second drag-line and civil engineering structure Power is wiped, extends the service life of the first drag-line and the second drag-line, by the cooperation between sliding slot, pulley and bail, in springboard Under the action of, so that springboard is taken out out of crossbeam, to overcome traditional discharging platform lack road it is uneven or In the case of miriness can not discharging the shortcomings that, reduce the work fatigue of stevedore, save construction cost, suitable popularization is answered With.
Description of the drawings
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is the structural schematic diagram of the utility model bail;
Fig. 3 is the structural schematic diagram of the utility model side plate.
In figure:1, civil engineering structure, 2, sliding slot, 3, crossbeam, 4, pulley, 5, fixed lateral reinforcing bar, 6, fixed vertical reinforcement, 7, guardrail, 8, fixed rope, 9, steel wire, the 10, first drag-line, 11, fixed pull ring, the 12, second drag-line, 13, bail, 14, solid Determine square steel, 15, triangular steel plate, 16, guiding gutter, 17, springboard, 18, hollow reinforcing bar, 19, connection reinforcing bar, 20, hook-type reinforcing bar, 21, Prefabricated embedded part, 22, rain visor, 23, bearing diagonal, 24, horizontally-supported, 25, side plate, 26, cushion block.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work The every other embodiment obtained, shall fall within the protection scope of the present invention.
- 3 are please referred to Fig.1, the utility model provides a kind of technical solution:A kind of construction discharging platform, including soil Structure 1 is built, civil engineering structure 1 is construction wall, and for installing crossbeam 3, the right side of civil engineering structure 1 is equipped with prefabricated embedded part 21, prefabricated Embedded part 21 is stainless steel, for bearing diagonal 23, the right side of the left side outer wall and civil engineering structure 1 of prefabricated embedded part 21 to be mounted and connected Side outer wall is connected, and the right side of prefabricated embedded part 21 is equipped with bearing diagonal 23, and bearing diagonal 23 is stainless steel, for connection and affixed side The left side outer wall of plate 25, bearing diagonal 23 is connected with the outer right wall of prefabricated embedded part 21, and the top of bearing diagonal 23 is equipped with horizontally-supported 24, horizontally-supported 24 be stainless steel, and for installing and fixing rain visor 22, horizontally-supported 24 top is equipped with side plate 25, Side plate 25 is stainless steel, and for installing and fixing rain visor 22, the inner wall of side plate 25 is connected with horizontally-supported 24 outer wall, The top of side plate 25 is equipped with rain visor 22, and rain visor 22 is PVC material, pours material for preventing rainwater from falling on discharging platform Wet, the lower surface of rain visor 22 is connected with the outer wall of side plate 25, and the right side of civil engineering structure 1 is equipped with crossbeam 3, and crossbeam 3 is stainless steel Material, for placing construction material, the left side outer wall of crossbeam 3 is connected with the outer right wall of civil engineering structure 1, and the inner wall of crossbeam 3 is set There is sliding slot 2, for placing springboard 17, the outer wall of sliding slot 2 is connected sliding slot 2 with the inner wall of crossbeam 3, and the inside of sliding slot 2 is equipped with pulley 4, pulley 4 is slided for springboard 17 on pulley 4, and convenient for taking out springboard 17, the outer wall of pulley 4 is connected with the inner wall of sliding slot 2, The left side of crossbeam 3 is equipped with fixed lateral reinforcing bar 5, and fixed lateral reinforcing bar 5 is stainless steel, for being reinforced to crossbeam 3, Gu The right end for determining transverse steel 5 is equipped with bail 13, and bail 13 is stainless steel, for being drawn when materials hauling, bail 13 outer wall is connected with the inner wall of fixed lateral reinforcing bar 5, the outer right wall of fixed lateral reinforcing bar 5 and the left side outer wall phase of crossbeam 3 Even, the top of fixed lateral reinforcing bar 5 is equipped with fixed vertical reinforcement 6, and fixed vertical reinforcement 6 is fixed for being reinforced to crossbeam 3 The outer wall of vertical reinforcement 6 is connected with the inner wall of fixed lateral reinforcing bar 5, and the top of pulley 4 is equipped with springboard 17, and springboard 17 is stainless steel Material, for leveling up road, the outer wall of springboard 17 is connected with the inner wall of sliding slot 2 overlap joint, the outer wall of the outer wall and pulley 4 of springboard 17 Overlap joint is connected, and the upper surface of crossbeam 3 is equipped with guardrail 7, and guardrail 7 is stainless steel, the safety for protecting stevedore, guardrail 7 lower surface is connected with the upper surface of crossbeam 3, and the inside of guardrail 7 is equipped with steel wire 9, and steel wire 9 is used to protect stevedore, The outer wall of steel wire 9 is connected with the inner wall of guardrail 7, and the outside of crossbeam 3 is equipped with the first drag-line 10, and the first drag-line 10 is steel wire rope, For being reinforced to crossbeam 3, the outer wall of the first drag-line 10 is equipped with fixed rope 8, and fixed rope 8 is for preventing the first drag-line 10 loose Dynamic, the inner wall of fixed rope 8 is connected with the outer wall of the first drag-line 10, and the top of the first drag-line 10 is equipped with cushion block 26, and cushion block 26 is wood Side extends the service life of the first drag-line 10 for reducing the friction between the first drag-line 10 and civil engineering structure 1, under cushion block 26 Surface is connected with the upper surface of civil engineering structure 1, and the inner wall of the first drag-line 10 is connected with the outer wall of crossbeam 3, the right side of the first drag-line 10 Side is equipped with the second drag-line 12, and the second drag-line 12 is steel wire rope for connecting simultaneously fixed cross beam 3, the outer wall and crossbeam of the second drag-line 12 3 outer wall is connected, and the top of the second drag-line 12 is equipped with fixed pull ring 11, and fixed pull ring 11 is stainless steel, for reinforcing steel White silk grade between cord and crossbeam 3, the inner wall of fixed pull ring 11 are connected with the outer wall of the second drag-line 12, the inner wall of fixed pull ring 11 It is connected with the outer wall of crossbeam 3 by the second drag-line 12, the outer wall of fixed pull ring 11 is connected with the inner wall of civil engineering structure 1, for making The connection of fixed pull ring 11 is more stablized, and the junction of fixed lateral reinforcing bar 5 and crossbeam 3 is equipped with fixed square steel 14, fixed square steel 14 outer wall is connected with the inner wall of fixed lateral reinforcing bar 5 and crossbeam 3 respectively, the connection for making fixed lateral reinforcing bar 5 and crossbeam 3 More stablize, the right side of fixed square steel 14 is equipped with triangular steel plate 15, and triangular steel plate 15 is stainless steel, for being connected and fixed cross To reinforcing bar 5, the left side outer wall of triangular steel plate 15 is connected with the outer right wall of fixed square steel 14, and the left end of crossbeam 3 is equipped with guiding gutter 16, for exporting ponding, the outer wall of guiding gutter 16 is connected guiding gutter 16 with the inner wall of crossbeam 3, the bottom end of fixed vertical reinforcement 6 Hollow reinforcing bar 18 is installed, hollow reinforcing bar 18 is stainless steel, for reinforcing fixed vertical reinforcement 6, hollow reinforcing bar 18 it is upper Surface is connected with the lower surface of fixed vertical reinforcement 6, for making the connection of hollow reinforcing bar 18 more stablize, hollow reinforcing bar 18 Hook-type reinforcing bar 20 is equipped between outer wall, hook-type reinforcing bar 20 is for reinforcing hollow reinforcing bar 18, inner wall and the hollow steel of hook-type reinforcing bar 20 The outer wall of muscle 18 is connected, and for making the connection of hook-type reinforcing bar 20 more stablize, the outer wall of fixed lateral reinforcing bar 5 is equipped with connection reinforcing bar 19, connection reinforcing bar 19 is used to that fixed lateral reinforcing bar 5 to be connect and be fixed with the fixed mesh that fixed vertical reinforcement 6 forms, and connects The outer wall of reinforcing bar 19 is connected with the inner wall of fixed lateral reinforcing bar 5, for making the connection of connection reinforcing bar 19 more stablize, connects reinforcing bar 19 run through fixed lateral reinforcing bar 5, and the outer wall of connection reinforcing bar 19 is connected with the inner wall of civil engineering structure 1, for making connection reinforcing bar 19 Connection is more firm.
In building engineering construction, a large amount of construction material is often transported in construction site, however construction site Road conditions cannot all meet handling and require substantially, and the road pavement of architectural engineering is all that the last one of whole building engineering is applied Work step is rapid, and unloading work all suffers from this various problems before this, needs to use construction discharging platform, the construction It is drawn by civil engineering structure 1, crossbeam 3, fixed lateral reinforcing bar 5, fixed vertical reinforcement 6, guardrail 7, steel wire 9, first with discharging platform Compositions, the haul vehicles such as rope 10, the second drag-line 12, springboard 17 rest in the side of crossbeam 3, by stevedore by material from vehicle Led on construction discharging platform, from construction with being transported to construction site on discharging platform, this process A large amount of construction material is deposited on construction discharging platform, and guardrail 9 and steel wire 9 can effectively prevent loader People inadvertently falls off in the groove other than civil engineering structure 1, causes the personal injury to stevedore, crossbeam 3 big due to needing to place The construction material of amount, bearing capacity allow for satisfying the use demand, and are drawn in the first drag-line 10 and second that the both sides of crossbeam 3 are installed Rope 12 is connect with fixed rope 8, increases the bearing capacity of crossbeam 3, fixed square steel 14 and triangular steel plate 15 are to crossbeam 3 and civil engineering The junction of structure 1 is reinforced, and crossbeam 3 is prevented to be broken in junction, and fixed lateral reinforcing bar 5, connects fixed vertical reinforcement 6 Reinforcing bar 19 and hook-type reinforcing bar 20 are connect, composition is reinforced grid, reinforced to the connection of crossbeam 3, springboard 17 can be out of crossbeam 3 It taking out, springboard 17 is ridden on the container of vehicle, stevedore can onboard slide construction material along springboard 17 from vehicle, Save stevedore's handling time.
In the description of the present invention, it should be understood that term " coaxial ", " bottom ", " one end ", " top ", " in The orientation of the instructions such as portion ", " other end ", "upper", " side ", " top ", "inner", " front ", " center ", " both ends " or position are closed System is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of describing the present invention and simplifying the description, rather than Indicate or imply that signified device or element must have a particular orientation, with specific azimuth configuration and operation, therefore cannot It is construed as a limitation of the present invention.
In the present invention unless specifically defined or limited otherwise, term " installation ", " setting ", " connection ", " Gu Calmly ", the terms such as " being screwed on " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral; It can be mechanical connection, can also be electrical connection;It can be directly connected, can also indirectly connected through an intermediary, it can be with It is the interaction relationship of the connection or two elements inside two elements, unless otherwise restricted clearly, for this field For those of ordinary skill, the concrete meaning of above-mentioned term in the present invention can be understood as the case may be.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is appreciated that can these embodiments be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaiied Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.

Claims (5)

1. a kind of construction discharging platform, including civil engineering structure (1), it is characterised in that:The right side of the civil engineering structure (1) Equipped with crossbeam (3), the left side outer wall of the crossbeam (3) is connected with the outer right wall of civil engineering structure (1), the crossbeam (3) it is interior Wall is equipped with sliding slot (2), and the outer wall of the sliding slot (2) is connected with the inner wall of crossbeam (3), and the inside of the sliding slot (2) is equipped with pulley (4), the outer wall of the pulley (4) is connected with the inner wall of sliding slot (2), and the left side of the crossbeam (3) is equipped with fixed lateral reinforcing bar (5), the outer right wall of the fixed lateral reinforcing bar (5) is connected with the left side outer wall of crossbeam (3), the fixed lateral reinforcing bar (5) Top be equipped with fixed vertical reinforcement (6), the inner wall phase of the outer wall and fixed lateral reinforcing bar (5) of the fixed vertical reinforcement (6) Even, the top of the pulley (4) is equipped with springboard (17), and the outer wall of the springboard (17) is connected with the inner wall of sliding slot (2) overlap joint, institute The outer wall for stating springboard (17) is connected with the outer wall of pulley (4) overlap joint, and the upper surface of the crossbeam (3) is equipped with guardrail (7), the shield The lower surface on column (7) is connected with the upper surface of crossbeam (3), and the inside of the guardrail (7) is equipped with steel wire (9), the steel wire (9) outer wall is connected with the inner wall of guardrail (7), and the outside of the crossbeam (3) is equipped with the first drag-line (10), first drag-line (10) inner wall is connected with the outer wall of crossbeam (3), and the right side of first drag-line (10) is equipped with the second drag-line (12), and described second The outer wall of drag-line (12) is connected with the outer wall of crossbeam (3), and the top of second drag-line (12) is equipped with fixed pull ring (11), described The inner wall of fixed pull ring (11) is connected with the outer wall of the second drag-line (12), and the inner wall of the fixed pull ring (11) passes through the second drag-line (12) it is connected with the outer wall of crossbeam (3), the outer wall of the fixed pull ring (11) is connected with the inner wall of civil engineering structure (1), described solid The junction for determining transverse steel (5) and crossbeam (3) is equipped with fixed square steel (14), the outer wall of the fixed square steel (14) respectively with it is solid Determine transverse steel (5) with the inner wall of crossbeam (3) to be connected, the right side of the fixed square steel (14) is equipped with triangular steel plate (15), described The left side outer wall of triangular steel plate (15) is connected with the outer right wall of fixed square steel (14), and the left end of the crossbeam (3) is equipped with water guide The outer wall of slot (16), the guiding gutter (16) is connected with the inner wall of crossbeam (3), the bottom end installation of the fixed vertical reinforcement (6) There are hollow reinforcing bar (18), the upper surface of the hollow reinforcing bar (18) to be connected with the lower surface of fixed vertical reinforcement (6), the hollow Hook-type reinforcing bar (20) is equipped between the outer wall of reinforcing bar (18), the inner wall of the hook-type reinforcing bar (20) is outer with hollow reinforcing bar (18) Wall is connected, and the outer wall of the fixed lateral reinforcing bar (5) is equipped with connection reinforcing bar (19), the outer wall of the connection reinforcing bar (19) and fixation The inner wall of transverse steel (5) is connected, and the connection reinforcing bar (19) runs through fixed lateral reinforcing bar (5), the connection reinforcing bar (19) Outer wall is connected with the inner wall of civil engineering structure (1).
2. a kind of construction discharging platform according to claim 1, it is characterised in that:The civil engineering structure (1) Right side is equipped with prefabricated embedded part (21), and the left side outer wall of the prefabricated embedded part (21) is connected with the outer right wall of civil engineering structure (1), institute The right side for stating prefabricated embedded part (21) is equipped with bearing diagonal (23), the right side of the left side outer wall and prefabricated embedded part (21) of the bearing diagonal (23) Side outer wall is connected, and the top of the bearing diagonal (23) is equipped with horizontally-supported (24), and the top of horizontally-supported (24) is equipped with side The inner wall of plate (25), the side plate (25) is connected with the outer wall of horizontally-supported (24), and the top of the side plate (25) is equipped with rain cover The lower surface of plate (22), the rain visor (22) is connected with the outer wall of side plate (25).
3. a kind of construction discharging platform according to claim 1, it is characterised in that:First drag-line (10) Outer wall is equipped with fixed rope (8), and the inner wall of the fixed rope (8) is connected with the outer wall of the first drag-line (10).
4. a kind of construction discharging platform according to claim 1, it is characterised in that:The fixed lateral reinforcing bar (5) right end is equipped with bail (13), and the outer wall of the bail (13) is connected with the inner wall of fixed lateral reinforcing bar (5).
5. a kind of construction discharging platform according to claim 1, it is characterised in that:First drag-line (10) Top is equipped with cushion block (26), and the lower surface of the cushion block (26) is connected with the upper surface of civil engineering structure (1).
CN201721447318.XU 2017-11-02 2017-11-02 A kind of construction discharging platform Expired - Fee Related CN207647189U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721447318.XU CN207647189U (en) 2017-11-02 2017-11-02 A kind of construction discharging platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721447318.XU CN207647189U (en) 2017-11-02 2017-11-02 A kind of construction discharging platform

Publications (1)

Publication Number Publication Date
CN207647189U true CN207647189U (en) 2018-07-24

Family

ID=62885028

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721447318.XU Expired - Fee Related CN207647189U (en) 2017-11-02 2017-11-02 A kind of construction discharging platform

Country Status (1)

Country Link
CN (1) CN207647189U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109555302A (en) * 2019-01-04 2019-04-02 万华节能科技集团股份有限公司 A kind of the hanging basket bracket and its construction technology of thermal-insulating leakage-resistant crossed construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109555302A (en) * 2019-01-04 2019-04-02 万华节能科技集团股份有限公司 A kind of the hanging basket bracket and its construction technology of thermal-insulating leakage-resistant crossed construction

Similar Documents

Publication Publication Date Title
CN104631333B (en) Arch bridge needle beam, stringer and floorings cast-in-place construction travelling bridge and method
CN102019998B (en) Erection embarking method of upper and lower water side cabins
CN203441073U (en) Hoop-type high-altitude guard platform suitable for super high-rise building outline boarder structural column
CN105386411A (en) Multifunctional portal device of suspension bridge pillar top
CN109811633A (en) A kind of corrugated steel and Combined concrete double curvature arched bridge and preparation method thereof
CN108252504A (en) Tube shear wall concrete structure large form hoisting type construction method and constructing device
CN109989348A (en) A kind of concrete construction cantilever form and its construction method
CN103074871B (en) Arc-shaped slope concrete sliding and lifting template
CN207647189U (en) A kind of construction discharging platform
CN205604080U (en) Building construction platform
CN205874987U (en) Simply put up bridge crane
CN205205685U (en) Span wire pier is function portal device at most
CN104495653A (en) Multifunctional large-tonnage beam erecting crane and beam erecting method
CN209585684U (en) A kind of top plate exempts from bracing reinforcement component
CN102535344A (en) Concrete transportation method for bridge body of high-pier bridge in gully region
CN205171343U (en) Combination beam self anchored suspension bridge
CN205653055U (en) Take waterproof type over -and -under type hoist that keeps off rain of canvas
CN206986736U (en) A kind of box girder bridge transverse prestress construction mobile closed formula platform
CN105220609A (en) Compound beam self-anchored suspension bridge and construction technology thereof
CN208594493U (en) A kind of bridge floor widened structure
CN209523123U (en) A kind of working job platform
CN204386449U (en) A kind of photovoltaic green-house electrification component promotes ladder
CN208378287U (en) A kind of simple vertical transport equipment of architecture construction
CN209482687U (en) A kind of Super High exterior frame column construction operation platform
CN208517814U (en) A kind of detachable railing of overflow bridge

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180724

Termination date: 20201102