CN207621486U - Intelligent undersea pipe-laying device - Google Patents

Intelligent undersea pipe-laying device Download PDF

Info

Publication number
CN207621486U
CN207621486U CN201820439438.3U CN201820439438U CN207621486U CN 207621486 U CN207621486 U CN 207621486U CN 201820439438 U CN201820439438 U CN 201820439438U CN 207621486 U CN207621486 U CN 207621486U
Authority
CN
China
Prior art keywords
auxiliary
pipeline
laying
ship
intelligent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820439438.3U
Other languages
Chinese (zh)
Inventor
孙维广
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HENGTAI GLOBAL OFFSHORE ENGINEERING (TIANJIN) Co Ltd
Original Assignee
HENGTAI GLOBAL OFFSHORE ENGINEERING (TIANJIN) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HENGTAI GLOBAL OFFSHORE ENGINEERING (TIANJIN) Co Ltd filed Critical HENGTAI GLOBAL OFFSHORE ENGINEERING (TIANJIN) Co Ltd
Priority to CN201820439438.3U priority Critical patent/CN207621486U/en
Application granted granted Critical
Publication of CN207621486U publication Critical patent/CN207621486U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model discloses a kind of intelligent undersea pipe-laying devices, including being laid with ship, the main stinger that the stern for being laid with ship is provided with arc and is bent downwards, pipeline hangs down along the main stinger, the position of near Sea Bottom is provided with auxiliary trustship device in the pipeline, the auxiliary trustship device is connected to auxiliary moving device, and the auxiliary moving device can be with the laying ship synchronization marching.Using above-mentioned technical proposal, the intelligent undersea pipe-laying device of the utility model, due to leaning on the position setting auxiliary trustship device of near Sea Bottom after pipeline hangs down, therefore pipeline is made to be carried by the support of trustship device, it is to locally bend due to gravity to avoid pipeline here, to reach good using effect.

Description

Intelligent undersea pipe-laying device
Technical field
The utility model is related to a kind of intelligent undersea pipe-laying devices, belong to submarine cable technical field of construction.
Background technology
Undersea pipe-laying process is typically the groove dug out by ocean ditcher in seabed first for being laid with pipeline, It is laid with again by being laid with ship, the pipeline setting not being laid with is on being laid with ship, as shown in Figure 1, one end of pipeline 1 is extended to Fixed in the groove in seabed, with the Forward for being laid with ship 2, the pipeline 1 on ship is gradually pulled disembarkation and is hung down into seabed In groove, but local buckling can occur when by the position of near Sea Bottom in pipe catenary, be made on the position of the local buckling point 3 It is recessed at the side of pipeline, to easily damage in use.
Utility model content
Therefore, the purpose of the utility model is to overcome defects in the prior art, and pipe can effectively be avoided by providing one kind The intelligent undersea pipe-laying device of local buckling occurs when road pipeline is overhang by the position of near Sea Bottom.
To achieve the goals above, a kind of intelligent undersea pipe-laying device of the utility model, including it is laid with ship, institute It states and is laid with the main stinger that the stern of ship is provided with arc and is bent downwards, pipeline hangs down along the main stinger, in institute It states pipeline and the position of near Sea Bottom is provided with auxiliary trustship device, the auxiliary trustship device is connected to auxiliary moving device, institute Stating auxiliary moving device can be with the laying ship synchronization marching.
The auxiliary moving device is the support vessel positioned at the laying ship rear, and the auxiliary trustship device passes through hawser It is connected to the support vessel.
The auxiliary trustship device is sleeve, and the pipeline passes through described sleeve pipe.
The auxiliary moving device is the seabed moving trolley below the laying ship, is arranged on the seabed moving trolley There are holder, the auxiliary trustship device to be installed on the holder.
The auxiliary trustship device is a frame body, and it is arcwall face that the frame body, which is used to hold in the palm the face for carrying the pipeline,.
Using above-mentioned technical proposal, the intelligent undersea pipe-laying device of the utility model, due to after pipeline hangs down By near Sea Bottom position setting auxiliary trustship device, therefore make pipeline by trustship device support carry, avoid pipeline here because Gravity is to locally bend, to reach good using effect.
Description of the drawings
Fig. 1 is pipeline laying construction schematic diagram in the prior art.
Fig. 2 is the structural schematic diagram of the embodiments of the present invention one.
Fig. 3 is the structural schematic diagram of the embodiments of the present invention two.
Specific implementation mode
Below by way of the drawings and specific embodiments, the utility model is described in further detail.
Embodiment one:
As shown in fig. 2, the present embodiment provides a kind of intelligent undersea pipe-laying devices, including are laid with ship 2, the laying The main stinger 4 that the stern of ship 2 is provided with arc and is bent downwards, pipeline 1 hangs down along the main stinger 4, described Pipeline 1 is provided with auxiliary trustship device by the position of near Sea Bottom, and the auxiliary trustship device is connected to auxiliary moving device, described Assist moving device can be with the laying ship synchronization marching.
The auxiliary moving device is the support vessel 5 positioned at the laying ship rear, and the auxiliary trustship device passes through cable Rope is connected to the support vessel 5.
The auxiliary trustship device is sleeve 6, and the pipeline 1 passes through described sleeve pipe 6.
Embodiment two:
As shown in 3 figures, the present embodiment provides a kind of intelligent undersea pipe-laying devices, including are laid with ship 2, the laying The main stinger 4 that the stern of ship 2 is provided with arc and is bent downwards, pipeline 1 hangs down along the main stinger 4, described Pipeline 1 is provided with auxiliary trustship device by the position of near Sea Bottom, and the auxiliary trustship device is connected to auxiliary moving device, described Assist moving device can be with the laying ship synchronization marching.
The auxiliary moving device is the seabed moving trolley 7 below the laying ship, is set on the seabed moving trolley 7 It is equipped with holder 71, the auxiliary trustship device is installed on the holder 71.
The auxiliary trustship device is a frame body 8, and the frame body 8, which is used to hold in the palm, carries the face of the pipeline 1 as arcwall face.
Using above-mentioned technical proposal, the intelligent undersea pipe-laying device of the utility model, due to after pipeline hangs down By near Sea Bottom position setting auxiliary trustship device, therefore make pipeline by trustship device support carry, avoid pipeline here because Gravity is to locally bend, to reach good using effect.
Obviously, above-described embodiment is only intended to clearly illustrate example, and does not limit the embodiments.For For those of ordinary skill in the art, other various forms of variations or change can also be made on the basis of the above description It is dynamic.There is no necessity and possibility to exhaust all the enbodiments.And obvious variation extended from this or change Among the dynamic protection domain created still in the utility model.

Claims (5)

1. a kind of intelligent undersea pipe-laying device, it is characterised in that:Including being laid with ship, the stern for being laid with ship is provided with Arc and the main stinger being bent downwards, pipeline hang down along the main stinger, and the position of near Sea Bottom is leaned in the pipeline It is provided with auxiliary trustship device, the auxiliary trustship device is connected to auxiliary moving device, and the auxiliary moving device can be with The laying ship synchronization marching.
2. intelligent undersea pipe-laying device as described in claim 1, it is characterised in that:The auxiliary moving device is position Support vessel in the laying ship rear, the auxiliary trustship device are connected to the support vessel by hawser.
3. intelligent undersea pipe-laying device as claimed in claim 2, it is characterised in that:The auxiliary trustship device is one Casing, the pipeline pass through described sleeve pipe.
4. intelligent undersea pipe-laying device as described in claim 1, it is characterised in that:The auxiliary moving device is position In being provided with holder on the seabed moving trolley being laid with below ship, the seabed moving trolley, the auxiliary trustship device is installed In on the holder.
5. intelligent undersea pipe-laying device as claimed in claim 4, it is characterised in that:The auxiliary trustship device is one Frame body, it is arcwall face that the frame body, which is used to hold in the palm the face for carrying the pipeline,.
CN201820439438.3U 2018-03-29 2018-03-29 Intelligent undersea pipe-laying device Expired - Fee Related CN207621486U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820439438.3U CN207621486U (en) 2018-03-29 2018-03-29 Intelligent undersea pipe-laying device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820439438.3U CN207621486U (en) 2018-03-29 2018-03-29 Intelligent undersea pipe-laying device

Publications (1)

Publication Number Publication Date
CN207621486U true CN207621486U (en) 2018-07-17

Family

ID=62831043

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820439438.3U Expired - Fee Related CN207621486U (en) 2018-03-29 2018-03-29 Intelligent undersea pipe-laying device

Country Status (1)

Country Link
CN (1) CN207621486U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116534214A (en) * 2023-05-29 2023-08-04 浙江合兴船业有限公司 Remote control system and method based on deck ship

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116534214A (en) * 2023-05-29 2023-08-04 浙江合兴船业有限公司 Remote control system and method based on deck ship
CN116534214B (en) * 2023-05-29 2024-04-09 浙江合兴船业有限公司 Remote control system and method based on deck ship

Similar Documents

Publication Publication Date Title
CN103527851B (en) Pre-laying process of submarine pipeline start laying system
CN108407976B (en) A kind of high focal plane buoy folding and unfolding method and device
GB2463286B (en) Method and apparatus for at sea pipe abandonment and recovery
CN104696588A (en) Deepwater subsea pipeline starting laying method
CN102454828A (en) Pipeline recycling and discarding technology in deepwater S-shaped submarine pipeline laying process
GB1016439A (en) Method and apparatus for laying submarine pipe lines
BRPI0814450A8 (en) PIPE LAYING APPARATUS AND METHOD
WO2011048480A8 (en) Method of abandoning an underwater pipeline on the bed of a body of water
CN104724553A (en) Device and method for laying and recycling cables
CN207621486U (en) Intelligent undersea pipe-laying device
RU2016141842A (en) DEPLOYMENT AND DIRECT DOCKING OF UNDERWATER PIPELINES
CN102230553B (en) Flexible pipeline for undersea oil transportation and gas transportation
CN103452117A (en) Deepwater bagged sand construction device and deepwater bagged sand construction technology
CN105060133A (en) Launching and retrieval device and method for underwater detection equipment
CN202828026U (en) Pipe support frame for offshore pipe-laying ship
CN205781369U (en) The roller group of S type pipe laying barge stinger tail
CN105805415B (en) The laying method of deep-water subsea pipeline starting
US20140299214A1 (en) Systems and Methods for Offshore Fluid Transfer
CN106628067B (en) Rope tensioning and releasing mechanism for intelligent underwater robot recovery
MX2021004913A (en) Installation of subsea pipelines.
AU2007244951B2 (en) Towing and recovery method for deepwater pipelines and risers
CN112856040B (en) Novel sea area pipeline laying floating assisting method
RU2009114214A (en) METHOD FOR LAYING A MAIN PIPELINE WHEN CONSTRUCTING A DEEP WATER TRANSITION
MY192346A (en) Offshore s-lay pipelaying vessel
CN104179463B (en) Deep Water Drilling Riser vertical means

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180717

CF01 Termination of patent right due to non-payment of annual fee