RU2009114214A - METHOD FOR LAYING A MAIN PIPELINE WHEN CONSTRUCTING A DEEP WATER TRANSITION - Google Patents

METHOD FOR LAYING A MAIN PIPELINE WHEN CONSTRUCTING A DEEP WATER TRANSITION Download PDF

Info

Publication number
RU2009114214A
RU2009114214A RU2009114214/06A RU2009114214A RU2009114214A RU 2009114214 A RU2009114214 A RU 2009114214A RU 2009114214/06 A RU2009114214/06 A RU 2009114214/06A RU 2009114214 A RU2009114214 A RU 2009114214A RU 2009114214 A RU2009114214 A RU 2009114214A
Authority
RU
Russia
Prior art keywords
laying
pipeline
water
during
along
Prior art date
Application number
RU2009114214/06A
Other languages
Russian (ru)
Other versions
RU2418222C2 (en
Inventor
Василий Владимирович Бельшов (RU)
Василий Владимирович Бельшов
Original Assignee
Василий Владимирович Бельшов (RU)
Василий Владимирович Бельшов
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Василий Владимирович Бельшов (RU), Василий Владимирович Бельшов filed Critical Василий Владимирович Бельшов (RU)
Priority to RU2009114214/06A priority Critical patent/RU2418222C2/en
Publication of RU2009114214A publication Critical patent/RU2009114214A/en
Application granted granted Critical
Publication of RU2418222C2 publication Critical patent/RU2418222C2/en

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Pipeline Systems (AREA)

Abstract

Способ прокладки устройства для транспортировки газа и жидкостей при строительстве глубоководного перехода, представляющее собой взвешенный в воде трубопровод, удерживаемый у дна в рабочем состоянии с помощью якорей и тросов, отличающийся от других способов тем, что прокладку нитки трубопровода производят путем ее последовательной сборки из длинных плетей на суше, погружения в воду на всей протяженности перехода на не препятствующей судоходству глубине по кратчайшему маршруту и дальнейшего затопления всего трубопровода с учетом рельефа дна, ускоряющий технологический процесс прокладки, уменьшающий дорогостоящие земляные работы и позволяющий применять его для широких диапазонов глубин и типоразмеров трубопроводов ввиду отсутствия сильной деформации труб в процессе укладки на дно, а в случае их заполнения водой и отсутствия перепадов давления внутри и снаружи трубы во время технологического процесса. A method of laying a device for transporting gas and liquids during the construction of a deep sea passage, which is a pipeline suspended in water, kept at the bottom in working condition with anchors and cables, which differs from other methods in that the pipeline is laid by sequentially assembling it from long lashes on land, immersion in water along the entire length of the transition at a depth not preventing the navigation along the shortest route and further flooding of the entire pipeline, taking into account rel bottom efa, accelerating the laying process, reducing expensive earthwork and allowing it to be used for a wide range of depths and sizes of pipelines due to the absence of severe deformation of the pipes during laying on the bottom, and if they are filled with water and there are no pressure drops inside and outside the pipe during technological process.

Claims (1)

Способ прокладки устройства для транспортировки газа и жидкостей при строительстве глубоководного перехода, представляющее собой взвешенный в воде трубопровод, удерживаемый у дна в рабочем состоянии с помощью якорей и тросов, отличающийся от других способов тем, что прокладку нитки трубопровода производят путем ее последовательной сборки из длинных плетей на суше, погружения в воду на всей протяженности перехода на не препятствующей судоходству глубине по кратчайшему маршруту и дальнейшего затопления всего трубопровода с учетом рельефа дна, ускоряющий технологический процесс прокладки, уменьшающий дорогостоящие земляные работы и позволяющий применять его для широких диапазонов глубин и типоразмеров трубопроводов ввиду отсутствия сильной деформации труб в процессе укладки на дно, а в случае их заполнения водой и отсутствия перепадов давления внутри и снаружи трубы во время технологического процесса. A method of laying a device for transporting gas and liquids during the construction of a deep sea passage, which is a pipeline suspended in water, kept at the bottom in working condition with anchors and cables, which differs from other methods in that the pipeline is laid by sequentially assembling it from long lashes on land, immersion in water along the entire length of the transition at a depth not preventing the navigation along the shortest route and further flooding of the entire pipeline, taking into account rel bottom efa, accelerating the laying process, reducing expensive earthwork and allowing it to be used for a wide range of depths and sizes of pipelines due to the absence of severe deformation of the pipes during laying on the bottom, and if they are filled with water and there are no pressure drops inside and outside the pipe during technological process.
RU2009114214/06A 2009-04-15 2009-04-15 Method to lay manifold pipeline in construction of deep-water passage RU2418222C2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2009114214/06A RU2418222C2 (en) 2009-04-15 2009-04-15 Method to lay manifold pipeline in construction of deep-water passage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2009114214/06A RU2418222C2 (en) 2009-04-15 2009-04-15 Method to lay manifold pipeline in construction of deep-water passage

Publications (2)

Publication Number Publication Date
RU2009114214A true RU2009114214A (en) 2010-10-20
RU2418222C2 RU2418222C2 (en) 2011-05-10

Family

ID=44023748

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2009114214/06A RU2418222C2 (en) 2009-04-15 2009-04-15 Method to lay manifold pipeline in construction of deep-water passage

Country Status (1)

Country Link
RU (1) RU2418222C2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2539043C1 (en) * 2013-08-13 2015-01-10 Федеральное государственное автономное образовательное учреждение высшего профессионального образования "Северный (Арктический) федеральный университет имени М.В. Ломоносова" (САФУ) Method to install pipe canal under northern conditions
RU2684227C1 (en) * 2018-04-28 2019-04-04 Евгений Эдуардович Головинов Device for measurement of channel deformations
CN109334683B (en) * 2018-12-03 2020-04-10 西京学院 Submarine vacuum pipeline traffic system and push-type laying method thereof
RU2724367C1 (en) * 2020-02-18 2020-06-23 Валерий Иванович Паутов Method of trench pipeline laying through rivers with high water flow rate

Also Published As

Publication number Publication date
RU2418222C2 (en) 2011-05-10

Similar Documents

Publication Publication Date Title
EA201071353A1 (en) METHOD AND LAYING SYSTEM OF UNDERWATER PIPELINES UNDER THE WATER BOTTOM
PE20121298A1 (en) BACKGROUND INTERVENTION
MY150727A (en) Method for laying a pipeline having an inner corrosion proof cladding
KR101403455B1 (en) Underwater base structure for wind turbine tower, and constructing method thereof
RU2009114214A (en) METHOD FOR LAYING A MAIN PIPELINE WHEN CONSTRUCTING A DEEP WATER TRANSITION
EA201390239A1 (en) METHOD OF CARRYING OUT DOMESTIC WORK
CN105544573A (en) Water pressure jetting type well completion construction method of dewatering tube well
MA38987B1 (en) Process for constructing a well for exploiting a deposit under a seabed or an ocean floor
CN204614336U (en) Simulation pipe-line solid hydrate generates, the device of blocking and de-plugging
DE602006014683D1 (en) PIPING STRUCTURE AND METHOD FOR LAYING AND USING A PIPING WITH SUCH A PIPE STRUCTURE
JP2011173050A (en) Method and apparatus for isolating carbon dioxide
RU2560129C1 (en) Method of installation of underwater pipeline
AU2017267504A1 (en) Subsea buoyancy systems
ATE529607T1 (en) METHOD FOR LAYING LONG OBJECTS UNDERWATER
RU2584764C2 (en) Method of laying underground main pipeline
CN205857140U (en) A kind of novel oil fence
TWM628491U (en) Deep ocean water intake system
RU2010132394A (en) DEVICE FOR PREVENTING OIL OR GAS CONDENSATE IN THE SEA IN DAMAGE TO MARINE WELLS
KR20070105295A (en) Method for laying pipe line on bottom of the sea
CN106090625A (en) A kind of buried jet chimney leakage inspection method
Hovland Was the Makarov bank natural blowout, 1958, supersonic
CN205172623U (en) Quick water injection device of flame proof basin
RU139591U1 (en) UNDERGROUND OIL PIPELINE DEVICE IN Trench with rubble
GB2480738A (en) Subsea oil leak capture device
MX2014013956A (en) Method of laying a pipeline.

Legal Events

Date Code Title Description
MM4A The patent is invalid due to non-payment of fees

Effective date: 20150416