CN207586981U - The risk assessment of the area power grid method of operation and aid decision-making system - Google Patents

The risk assessment of the area power grid method of operation and aid decision-making system Download PDF

Info

Publication number
CN207586981U
CN207586981U CN201721768700.0U CN201721768700U CN207586981U CN 207586981 U CN207586981 U CN 207586981U CN 201721768700 U CN201721768700 U CN 201721768700U CN 207586981 U CN207586981 U CN 207586981U
Authority
CN
China
Prior art keywords
signal
cpu
power grid
risk assessment
electric network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721768700.0U
Other languages
Chinese (zh)
Inventor
魏莉莉
詹乐贵
杨昌洪
张波文
张亚维
张显文
王朝琴
郭德平
刘君
黎婧
林先堪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Power Grid Co Ltd
Original Assignee
Guizhou Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Power Grid Co Ltd filed Critical Guizhou Power Grid Co Ltd
Priority to CN201721768700.0U priority Critical patent/CN207586981U/en
Application granted granted Critical
Publication of CN207586981U publication Critical patent/CN207586981U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The utility model is related to a kind of area power grid method of operation risk assessment and aid decision-making systems, belong to electrical network field.The system includes electric network information collector, signal transmission device, signal receiver, wave filter, converter, amplifier, CPU, server, database and memory module;Electric network information collector, signal transmission device, signal receiver, wave filter, converter, amplifier, CPU, server and database are sequentially connected, and CPU is also connected simultaneously with memory module;After signal is by filter filtering, analog-to-digital conversion is carried out by converter, signal amplification is carried out by amplifier again, then the digital signal that CPU readings receive, it is handled with reference to the data of server calls lane database, it is transmitted to memory module simultaneously and carries out data storage, realizes the risk assessment of electric network information.Relevant information of the utility model in a manner of power grid after the processing such as receiving, filtering, amplifying by signal, carries out visualization output, intuitively shows the assessment result of power grid as input condition.

Description

The risk assessment of the area power grid method of operation and aid decision-making system
Technical field
The utility model belongs to electrical network field, is related to the risk assessment of the area power grid method of operation and aid decision-making system.
Background technology
China is with the development of power grid, and the safety challenge of power grid is increasing, and a large amount of electric power scholars make much thus Contribution.The main contents of Study of Risk Evaluation Analysis for Power System can be divided into component-level risk assessment and system-level risk assessment.
Component-level risk assessment:Electric system is by a large amount of generator, overhead transmission line, cable, transformer, open circuit The compositions such as device, disconnecting switch and reactive-load compensation equipment.Element stoppage in transit is the basic reason of thrashing, and system risk assessment is first First to determine the outage model of element.Component failure is divided into independent and two classes of correlation and stops transport, and stops transport per a kind of can further press again Pattern is segmented.In most cases, recoverable forced outage is only included in, also planned outage is simulated sometimes.It passes Ageing failure is not considered in the risk assessment of system, and considers that the model of component ageing failure conditions is more reasonable in practice, is obtained Result more gear to actual circumstances.What risk assessment considered first is the risk assessment of element, but with previous component reliability research Unlike, element risk assessment will not only carry out the foundation of mathematical model, and also need to develop real-time monitoring system, system The cost of new equipment is purchased after counting primary equipment failure, and carries out some measurement experiments.
System-level risk assessment:The property analyzed according to system mode the research of system-level security risk assessment at this stage Qualitative classification can substantially divide into two aspects of static security risk-assessment and dynamic security risk-assessment. Whether static security risk assessment characterization system can fully meet the workload demand of user and the constraints of system operation, Therefore static security risk-assessment relates only to the limit of system, carries out the abundance analysis of system without requiring Dynamic and transient analysis process;Dynamic secure estimation analysis then shows responding ability of the system to dynamic and transient disturbance, therefore The disturbance occurred in system and its consequence are evaluated.Usual dynamic secure estimation will carry out transient state, voltage stability point Analysis.With the development of system, collapse of voltage and cascading failure accident gradually protrude, and the analysis of both of these problems are had become quiet State safety analysis important component.At present, the most of risk assessment technologies used in engineer application belong to static security Property analysis scope, risk indicator be also mostly abundance size index rather than totality risk indicator.
Safe operation of electric network risk assessment, domestic correlative study substantially experienced three phases:Certainty evaluation stage, Probability assessment stage and Risk Assessment Stage.Certainty assessment usually only considers that the accident of most serious, the knot of assessment occur for system Fruit is overly conservative, and the cost paid is higher, uneconomical.Probability assessment generally only considers the size of risk probability of happening but does not consider The consequence order of severity that risk occurs, and risk assessment combines risk accidents probability of happening and risk schedule severity, wind Product of the danger value for the two, assessment result can reflect the risk level residing for system.
At present, based on the research of risk assessment also in the elementary step, the practice being usually taken is:In certain constraint Under the conditions of, to respectively drafting pre-program, to carry out single or more comprehensive economic index or single operation of power networks, management related Index assessed.These assessments are all to have carried out relevant assessment with regard to some aspect of power grid or certain several aspect, and Major part is assessed with qualitatively language, lacks certain theoretical foundation, and assessment result is excessively subjective and coarse so that comments Estimate result to have a greatly reduced quality.
Invention content
In view of this, the purpose of this utility model is to provide a kind of area power grid method of operation risk assessment to determine with auxiliary Plan system.
In order to achieve the above objectives, the utility model provides following technical solution:
The risk assessment of the area power grid method of operation and aid decision-making system, including electric network information collector, signal transmission device, Signal receiver, wave filter, converter, amplifier, CPU, server, database and memory module;
The electric network information collector, signal transmission device, signal receiver, wave filter, converter, amplifier, CPU, clothes Business device and database are sequentially connected, and CPU is also connected simultaneously with memory module;
Electric network information collector is used to acquire the operation data of power grid, and signal transmission device is used for the transmission of signal, and signal connects Receive device be used for signal reception, after signal is by filter filtering, by converter carry out analog-to-digital conversion, then by amplifier into Row signal amplifies, and the digital signal that then CPU readings receive is handled, together with reference to the data of server calls lane database When be transmitted to memory module carry out data storage, realize the risk assessment of electric network information.
Further, which further includes LED cutout screens, and the LED cutout screens are connect with CPU, for visualizing wind Dangerous assessment result.
The beneficial effects of the utility model are:Relevant information of the utility model in a manner of power grid as input condition, After the processing such as receiving, filtering, amplifying by signal, visualization output is carried out, intuitively shows the assessment result of power grid, mitigates operation The workload of dispatcher.
Description of the drawings
In order to make the purpose of this utility model, technical solution and advantageous effect clearer, the utility model provides as follows Attached drawing illustrates:
Fig. 1 is Tthe utility model system structure diagram.
Specific embodiment
Below in conjunction with attached drawing, the preferred embodiment of the utility model is described in detail.
As shown in Figure 1, the risk assessment of the area power grid method of operation and aid decision-making system, including electric network information collector, Signal transmission device, signal receiver, wave filter, converter, amplifier, CPU, server, database and memory module;
The electric network information collector, signal transmission device, signal receiver, wave filter, converter, amplifier, CPU, clothes Business device and database are sequentially connected, and CPU is also connected simultaneously with memory module;
Electric network information collector is used to acquire the operation data of power grid, and signal transmission device is used for the transmission of signal, and signal connects Receive device be used for signal reception, after signal is by filter filtering, by converter carry out analog-to-digital conversion, then by amplifier into Row signal amplifies, and the digital signal that then CPU readings receive is handled, together with reference to the data of server calls lane database When be transmitted to memory module carry out data storage, realize the risk assessment of electric network information.
The system further includes LED cutout screens, and the LED cutout screens are connect with CPU, for visualizing risk assessment knot Fruit.Project carries out primary equipment command simulation operation using simulated environment, is based on using the method for operation under simulated environment The security risk assessment work of network topology structure.Simulated environment is made of electric network model, figure and real time operation mode, simulation Environment and run-time environment isolation, any operation done under simulated environment do not influence real time environment.Work as dispatching automation It, being capable of manual mode realization simulated environment and EMS data when electric network model, figure or the method for operation change in system EMS Synchronization.
Using network topology, operational simulation technology when risk assessment operates, the network model of practical power systems is established, it is real Existing once-through operation automated topology coloring and automatic safe are checked, main to realize the anti-error check of system topological:
The anti-misoperation locking of equipment operation is realized according to the topological relation between electrical island state and electrical equipment.It is not depended on In the latching relation of Manual definition's equipment room, the automatic variation for adapting to electrical equipment and topological structure of electric is sent out in power network wiring During changing, anit-misoperation rules are safeguarded without user.
Finally illustrate, preferred embodiment above is merely intended for describing the technical solutions of the present application, but not for limiting the present application, to the greatest extent Pipe has been described in detail the utility model by above preferred embodiment, but those skilled in the art should manage Solution, can in the form and details make it various changes, without departing from the utility model claims book institute The range of restriction.

Claims (2)

1. the risk assessment of the area power grid method of operation and aid decision-making system, it is characterised in that:The system is adopted including electric network information Storage, signal transmission device, signal receiver, wave filter, converter, amplifier, CPU, server, database and memory module;
The electric network information collector, signal transmission device, signal receiver, wave filter, converter, amplifier, CPU, server It is sequentially connected with database, CPU is also connected simultaneously with memory module;
Electric network information collector is used to acquire the operation data of power grid, and signal transmission device is used for the transmission of signal, signal receiver For the reception of signal, after signal is by filter filtering, analog-to-digital conversion is carried out, then carry out letter by amplifier by converter Number amplification, then the digital signal that receives of CPU readings, is handled with reference to the data of server calls lane database, is passed simultaneously It is sent to memory module and carries out data storage, realize the risk assessment of electric network information.
2. area power grid method of operation risk assessment according to claim 1 and aid decision-making system, it is characterised in that:It should System further includes LED cutout screens, and the LED cutout screens are connect with CPU, for visualizing risk evaluation result.
CN201721768700.0U 2017-12-18 2017-12-18 The risk assessment of the area power grid method of operation and aid decision-making system Active CN207586981U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721768700.0U CN207586981U (en) 2017-12-18 2017-12-18 The risk assessment of the area power grid method of operation and aid decision-making system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721768700.0U CN207586981U (en) 2017-12-18 2017-12-18 The risk assessment of the area power grid method of operation and aid decision-making system

Publications (1)

Publication Number Publication Date
CN207586981U true CN207586981U (en) 2018-07-06

Family

ID=62739082

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721768700.0U Active CN207586981U (en) 2017-12-18 2017-12-18 The risk assessment of the area power grid method of operation and aid decision-making system

Country Status (1)

Country Link
CN (1) CN207586981U (en)

Similar Documents

Publication Publication Date Title
CN103414251B (en) A kind of substation network communication analogue system based on IEC61850
CN104715035B (en) Checking method and device for correctness of virtual terminator association configuration of intelligent substation
CN103823433B (en) Method for realizing relay protection equipment on-line monitoring by use of communication process analysis
CN107749667B (en) Real-time monitoring method for information and state of intelligent substation protection pressing plate
CN105914881A (en) Intelligent transformer station advanced application system
CN104539051B (en) A kind of secondary equipment of intelligent converting station online evaluation system
CN103823199A (en) Automatic detection system and detection method for intelligent substation relay protection testing device
CN108923953A (en) A kind of virtual main station system of power remote machine debugging
CN107491569B (en) Transformer substation system fault online simulation method based on IEC61850 standard GOOSE and SV technology
CN111884347B (en) Power data centralized control system for multi-source power information fusion
CN104090194A (en) Intelligent substation relay protection noninvasive test system and method
CN105573283B (en) The foundation in substation equipment function association storehouse and the filter method of event correlation information group
CN106570781B (en) Intelligent substation monitoring information step-by-step acceptance method based on three-layer two-network structure
CN107742925A (en) The hard pressing plate method for inspecting of transformer station based on three-level network
CN104063761A (en) SCADA data development system based on smart grid
KR20190119207A (en) An artificial intelligence-based parameter setting value automatic calculation protection relays
CN207586981U (en) The risk assessment of the area power grid method of operation and aid decision-making system
CN111130116B (en) Scheduling operation power flow checking method based on key topology change item identification
CN104579817A (en) Communication loop test method based on GOOSE (generic object-oriented substation event) logics
CN109586406B (en) Third-generation intelligent substation analog quantity in-situ module test system and application method thereof
CN105224729A (en) Based on the information access method of inspection of substation secondary device panoramic information simulation
CN102629761B (en) AVC system power grid model maintenance method and system thereof
CN105005941A (en) Service rule based examining method for virtual secondary circuit between intelligent station devices
CN112101799B (en) Standard state dividing method and device based on wind farm data
CN115587635A (en) Transformer area line loss analysis method and system based on neutral point deviation judgment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant