CN207568221U - The safety guard net of super high steel structure construction - Google Patents
The safety guard net of super high steel structure construction Download PDFInfo
- Publication number
- CN207568221U CN207568221U CN201721538477.0U CN201721538477U CN207568221U CN 207568221 U CN207568221 U CN 207568221U CN 201721538477 U CN201721538477 U CN 201721538477U CN 207568221 U CN207568221 U CN 207568221U
- Authority
- CN
- China
- Prior art keywords
- connecting plate
- steel
- wire rope
- steel wire
- structural column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Emergency Lowering Means (AREA)
Abstract
The utility model discloses a kind of safety guard nets of super high steel structure construction, this protection network includes n-th layer structural column, N+1 layers of structural column, overhanging rack, the first connecting plate, the second connecting plate, third connecting plate, the first steel wire rope and the second steel wire rope, first connecting plate is set on n-th layer structural column lateral surface, second connecting plate and third connecting plate are respectively arranged on lateral surface in N+1 layers of structural column, the bottom end for overhanging rack is set on the first connecting plate, and the first steel wire rope and the second steel wire rope connect the top of the second connecting plate and third connecting plate and overhanging rack respectively.This protection network effectively overcomes the defects of traditional hard protection, simple in structure, easy to make, and it is repeatable utilize, avoid damaging the personnel that fall and it is secondary fall phenomenon, prevent security risk.
Description
Technical field
The utility model is related to a kind of safety guard nets of super high steel structure construction.
Background technology
Currently when super high steel structure is constructed, generally use hard protection on the outside of structure, the outside being just commonly used
Hard protection, fabrication and installation expense is larger, and can not increase with structure height and be promoted.If high-altitude construction personnel sends out accidentally
Raw falling from high altitude, hard protection may cause the personnel that fall compared with major injury in itself, and falling object from high altitude even occurs under normal circumstances,
Object may be occurred and bounce to cause object secondary the phenomenon that falling by falling on hard protection, and there are larger security risks.
Invention content
The technical problem to be solved by the utility model is to provide a kind of safety guard net of super high steel structure construction, sheets
Protection network effectively overcomes the defects of traditional hard protection, simple in structure, easy to make, and repeatable utilization, avoids to the people that falls
Member damage and it is secondary fall phenomenon, prevent security risk.
In order to solve the above technical problems, the safety guard net of the utility model super high steel structure construction includes n-th layer knot
Structure column, N+1 layers of structural column, overhanging rack, the first connecting plate, the second connecting plate, third connecting plate, the first steel wire rope and second
Steel wire rope, first connecting plate are set on the n-th layer structural column lateral surface, second connecting plate and third connecting plate difference
The lateral surface in the N+1 layers of structural column, the bottom end of the overhanging rack are set on first connecting plate, first steel
Cord and the second steel wire rope connect the top of second connecting plate and third connecting plate and overhanging rack respectively.
Further, the overhanging rack includes steel pipe framework, steel fabric sheet and the close mesh safety net of flame retardant type, the steel wire
Piece is layed in the steel pipe framework surface, and the close mesh safety net of flame retardant type is layed in the steel fabric sheet surface.
Further, the steel fabric sheet is three layers, and the aperture of compound steel silk netting from top to bottom is descending.
Further, it is used between first steel wire rope and the second steel wire rope and second connecting plate and third connecting plate
Shape of a hoof wire line shoe connects.
Since the safety guard net of the utility model super high steel structure construction employs above-mentioned technical proposal, i.e. this protection
Net includes n-th layer structural column, N+1 layer structural column, overhangs rack, the first connecting plate, the second connecting plate, third connecting plate, the
One steel wire rope and the second steel wire rope, the first connecting plate are set on n-th layer structural column lateral surface, the second connecting plate and third connecting plate point
The first connecting plate, the first steel wire rope and the second steel wire She Yu not be set in lateral surface, the bottom end for overhanging rack in N+1 layers of structural column
Rope connects the top of the second connecting plate and third connecting plate and overhanging rack respectively.This protection network effectively overcomes traditional hard protection
Defect, it is simple in structure, it is easy to make, and it is repeatable utilize, avoid damaging the personnel that fall and it is secondary fall phenomenon,
Prevent security risk.
Description of the drawings
The utility model is described in further detail with embodiment below in conjunction with the accompanying drawings:
Fig. 1 is the safety guard net schematic diagram of the utility model super high steel structure construction;
Fig. 2 is that rack schematic diagram is overhang in this protection network.
Specific embodiment
Embodiment is as shown in Figure 1, the safety guard net of the utility model super high steel structure construction includes n-th layer structural column
1st, N+1 layers of structural column 2, overhanging rack 3, the first connecting plate 4, the second connecting plate 5, third connecting plate 6,7 and of the first steel wire rope
Second steel wire rope 8, first connecting plate 4 are set on 1 lateral surface of n-th layer structural column, and second connecting plate 5 and third connect
Fishplate bar 6 is respectively arranged on lateral surface in the N+1 layers of structural column 2, and the bottom end of the overhanging rack 3 is set on first connecting plate
4,7 and second steel wire rope 8 of the first steel wire rope connects second connecting plate 5 and third connecting plate 6 and overhanging rack 3 respectively
Top.
Preferably, as shown in Fig. 2, the overhanging rack 3 includes steel pipe framework 31, steel fabric sheet 32 and the close mesh peace of flame retardant type
The whole network 33, the steel fabric sheet 32 are layed in 31 surface of steel pipe framework, and the close mesh safety net 33 of flame retardant type is layed in institute
State 32 surface of steel fabric sheet.
Preferably, the steel fabric sheet 32 is three layers, and the aperture of compound steel silk netting 32 from top to bottom is descending.
Preferably, between 7 and second steel wire rope 8 of the first steel wire rope and second connecting plate 5 and third connecting plate 6
It is connected using shape of a hoof wire line shoe.
This protection network, when falling from high altitude occurs for worker or object, is provided by installing overhanging rack on the outside of steel construction
One of safeguard ensures high-altitude and ground staff's life security, and avoid falling object bounces it is secondary fall, be suitable for
High-rise, super high steel structure construction.Wherein overhanging rack appearance and size can be configured according to corresponding demand, overhanging rack by
Steel pipe skeleton, and using the refinement of steel wire rope lattice as a whole.Overhang rack and drawknot, steel wire are carried out by steel wire rope and connecting plate
Rope diameter need to meet estimated force request, and both ends need to use shape of a hoof wire line shoe to provide requirement fastening according to specification, avoid
It loosens.
Claims (4)
1. a kind of safety guard net of super high steel structure construction, including n-th layer structural column and N+1 layers of structural column, feature
It is:Overhanging rack, the first connecting plate, the second connecting plate, third connecting plate, the first steel wire rope and the second steel wire rope are further included,
First connecting plate is set on the n-th layer structural column lateral surface, and second connecting plate and third connecting plate are respectively arranged on institute
State lateral surface in N+1 layers of structural column, the bottom end of the overhanging rack is set on first connecting plate, first steel wire rope and
Second steel wire rope connects the top of second connecting plate and third connecting plate and overhanging rack respectively.
2. the safety guard net of super high steel structure construction according to claim 1, it is characterised in that:The overhanging rack
The steel pipe framework surface, institute are layed in including steel pipe framework, steel fabric sheet and the close mesh safety net of flame retardant type, the steel fabric sheet
It states the close mesh safety net of flame retardant type and is layed in the steel fabric sheet surface.
3. the safety guard net of super high steel structure construction according to claim 2, it is characterised in that:The steel fabric sheet
It it is three layers, and the aperture of compound steel silk netting from top to bottom is descending.
4. the safety guard net of the super high steel structure construction according to claim 1,2 or 3, it is characterised in that:Described
It is connected between one steel wire rope and the second steel wire rope and second connecting plate and third connecting plate using shape of a hoof wire line shoe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721538477.0U CN207568221U (en) | 2017-11-17 | 2017-11-17 | The safety guard net of super high steel structure construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721538477.0U CN207568221U (en) | 2017-11-17 | 2017-11-17 | The safety guard net of super high steel structure construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207568221U true CN207568221U (en) | 2018-07-03 |
Family
ID=62690540
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721538477.0U Active CN207568221U (en) | 2017-11-17 | 2017-11-17 | The safety guard net of super high steel structure construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207568221U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109577213A (en) * | 2019-01-24 | 2019-04-05 | 宝丰县农村公路管理所 | A kind of road and bridge construction protective device |
CN110206329A (en) * | 2019-05-17 | 2019-09-06 | 陕西理工大学 | A kind of civil engineering construction protection device |
-
2017
- 2017-11-17 CN CN201721538477.0U patent/CN207568221U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109577213A (en) * | 2019-01-24 | 2019-04-05 | 宝丰县农村公路管理所 | A kind of road and bridge construction protective device |
CN110206329A (en) * | 2019-05-17 | 2019-09-06 | 陕西理工大学 | A kind of civil engineering construction protection device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205421984U (en) | Net is weighed down in high air defence with cushioning effect | |
CN207568221U (en) | The safety guard net of super high steel structure construction | |
US9649517B2 (en) | Fall arrester having damping, and damping elements for a fall protection device | |
TW201202523A (en) | Fall-off avoiding system, plural-rings member, ''8'' shaped ring member, four-holes member, method of operating on roof, method for setting primary rope, bucket of fall-off avoiding system and hook for bucket | |
CN107190997A (en) | A kind of steel construction high-rise working safety belt safety rope branch hang device | |
CN206256704U (en) | A kind of umbrella shape high-altitude protection safety net | |
CN203783171U (en) | Assembled type overhanging protective shed for high-rise building construction | |
CN206144180U (en) | Protection network for construction | |
CN106013187A (en) | Active protection system | |
CN205296888U (en) | Safety device for building | |
CN105888269A (en) | Suspended cable type safety protection device for building construction overhead operation, and construction method of suspended cable type safety protection device | |
CN205713178U (en) | A kind of construction work high above the ground suspension safety device | |
CN204876616U (en) | Novel fire -retardant construction safety net | |
CN206634949U (en) | A kind of building tower crane cat ladder and safeguard | |
CN214402848U (en) | Safe plain net convenient to it is fixed | |
CN201535061U (en) | Light scaffold with protective shed | |
CN201953297U (en) | Modular anti-tear mesh ladder | |
CN207314891U (en) | A kind of steel construction high-rise working safety belt safety rope branch hang device | |
CN206715062U (en) | Escape bag and escape pack assembly | |
CN204311718U (en) | A kind of outer overhanging type steel scaffold with horizontal protective function | |
CN214807968U (en) | Anti-falling flame-retardant safe flat net | |
CN219344120U (en) | Building outer wall protection structure | |
CN205822758U (en) | A kind of high-building construction safety guard net | |
CN217631452U (en) | Chemical fiber safety protection net with good protection performance | |
CN203857884U (en) | Nearby protection device used in demolition blasting process of beam column type steel structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |