CN207314891U - A kind of steel construction high-rise working safety belt safety rope branch hang device - Google Patents

A kind of steel construction high-rise working safety belt safety rope branch hang device Download PDF

Info

Publication number
CN207314891U
CN207314891U CN201720744661.4U CN201720744661U CN207314891U CN 207314891 U CN207314891 U CN 207314891U CN 201720744661 U CN201720744661 U CN 201720744661U CN 207314891 U CN207314891 U CN 207314891U
Authority
CN
China
Prior art keywords
rope
safety belt
safety
steel
rise working
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720744661.4U
Other languages
Chinese (zh)
Inventor
曹早来
郭伟东
张磊
袁博
许仕达
张加强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201720744661.4U priority Critical patent/CN207314891U/en
Application granted granted Critical
Publication of CN207314891U publication Critical patent/CN207314891U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model belongs to building engineering construction technical field of safety protection, discloses a kind of steel construction high-rise working safety belt safety rope branch hang device, including movable support, rope end connector, horizontal hanging cable;On the spaced homonymy flange plate installed in structural steel beam of multiple movable supports, its top is used for support level hanging cable;Rope end connector is located at the outside of end movable support, is also mounted on the homonymy flange plate of structural steel beam, for fixing horizontal hanging cable end;Horizontal hanging cable is used for the safety rope for hanging safety belt, and the safe sling of safety belt hangs in the horizontal hanging cable and can slide along.The utility model neither damages steel construction, and can be fixedly mounted on steel construction, meets that the safe sling of safety belt is hung and requires, prevents high-rise working personnel from falling;Safety rope can be free to slide on it at the same time, realizes and is protected in mobile construction;The device have the characteristics that it is safe and reliable, simple in structure, be convenient to mount and dismount, can be used in turn, cost it is low.

Description

A kind of steel construction high-rise working safety belt safety rope branch hang device
Technical field
The utility model belongs to building engineering construction technical field of safety protection, is to be related to a kind of steel construction specifically High-rise working safety guard.
Background technology
Aloft in job execution, to prevent fall injury accident, it is desirable to which operating personnel's wear safety belt (falls outstanding Hanging safety belt).Safety belt is mainly made of safety rope, buffer, frenulum, and the buckle of safety rope upper end is hooked on by when use On hanging point device in fixation construct.Once falling, safety rope is caught by hanging point device, prevention continues to drop, from And provide safeguard protection for operating personnel.In Construction of Steel Structure, largely there are high-rise working.But since steel construction does not allow to weld Connect or drill and be bolted installation hanging point device, therefore have to take and tie up to safe rope end bundle on neighbouring structural member.Due to Generally non-lifting professional operation, it is difficult to reach tying specification, firmly, once fall, under gravitational thrusts, safely Rope is likely to come off, and can not ensure safe and reliable.And when periphery can be utilized without other rod pieces, and have to safety rope being bound in On the component of underfooting, using maximum low extension mode is threatened human body, then further increase dangerous;In addition hanging point limitation is fixed Job area, need to often replace hanging point position, very inconvenient, greatly influence work efficiency and construction speed;At the same time not The probability that security risk occurs is also increased during disconnected replacement hanging point.
As it can be seen that high-rise working falls, suspension safety belt is in use, hanging point is the most key as the support section of whole system. It must assure that it has higher intensity and sets first to consolidate, meet load shock of a fall load requirement, to ensure to reach peace Full guard effect.In view of steel construction does not allow to weld or drill to be bolted installation hanging point device, how to solve and ensure above-mentioned It is required that becoming problem, solution path need to be separately warded off.In addition steel construction high-rise working feature is that the more workloads of often locating of point are small, is needed in construction It is on the move, therefore the hanging point device researched and developed should also meet mobile requirement of shelter in high-rise working personnel's plane.
Utility model content
To be solved in the utility model is to set in safety rope hanging point and high-rise working construction personnel plane to move on steel construction The technical problem of dynamic protection, and a kind of steel construction high-rise working safety belt safety rope branch hang device is provided, it neither damages steel knot Structure, and can be fixedly mounted on steel construction, meet that the safe sling of safety belt is hung and require, prevent high-rise working personnel from falling;Together When safety rope can be free to slide on it, realize and protected in mobile construction;The device has safe and reliable, simple in structure, assembly and disassembly Facilitate, can be used in turn, the features such as cost is low.
In order to solve the above-mentioned technical problem, the utility model is achieved by following technical solution:
A kind of steel construction high-rise working safety belt safety rope branch hang device, including movable support, rope end connector, horizontal extension Rope;On multiple spaced homonymy flange plates installed in structural steel beam of the movable support, its top is used for described in stent Horizontal hanging cable;The rope end connector is located at the outside of two movable supports in end, is also mounted at the homonymy of structural steel beam On flange plate, for fixing the horizontal hanging cable end;The horizontal hanging cable is used for the safety rope for hanging safety belt, safety belt Safe sling hangs in the horizontal hanging cable and can slide along.
Multiple movable supports are arranged at intervals with the spacing of 6-8m.
The movable support is made of U-shaped deck, upright bar, reinforcing angle, wire rope handling ear, jackscrew;The U-shaped deck by it is upper, Lower supporting plate is formed with plate-side plate welding, its lower supporting plate is drilled with two bolts hole and welding equipment has nut, the bolt hole and institute Nut is stated to be used to jackscrew be installed so that the U-shaped deck to be fixedly installed in the flange plate of structural steel beam;The upright bar is welded in institute State the upper backup pad top surface of U-shaped deck;Two reinforcing angles are installed at left and right sides of the bottom of upright rod, with the upright bar There is welding with the upper backup pad of the U-shaped deck;Wire rope handling ear equipped with cord hole is vertically welded in the upright bar top outer, institute There is the wire rope handling ear of the movable support towards the homonymy of the U-shaped deck.
The movable support of the rope end connector apart from end is not less than 500mm.
The rope end connector is made of U-shaped deck, rope ear, jackscrew;The U-shaped deck is by upper and lower support plate and side Plate is formed by welding, its lower supporting plate is drilled with two bolts hole and welding equipment has nut, and the bolt hole and the nut are used to pacify Jackscrew is filled so that the U-shaped deck to be fixedly installed in the flange plate of structural steel beam;The rope ear vertical welding equipped with cord hole In the upper backup pad top surface of the U-shaped deck.
The horizontal hanging cable includes steel wire rope and rope clamp, and the steel wire rope sequentially passes through the described of all movable supports Wire rope handling ear, the both ends of the steel wire rope are fixed on the rope ear of the rope end connector by the rope clamp;Safety belt Safety rope hangs over the hooking point of formation activity on the steel wire rope by snap ring button.
The beneficial effects of the utility model are:
The steel construction high-rise working safety belt safety rope branch hang device of the utility model, solves steel construction and sets safety belt The problem of mobile protection in safety rope hanging point and high-rise working personnel's plane.Using the device as safety rope hanging point, do not damage Steel construction, it is solid and reliable, fully meet load shock of a fall load requirement, it is ensured that high-rise working personnel safety.Due to button The safety belt safety rope hung on the device horizontal wire rope can move horizontally, and work is expanded in the case of hanging point is changed without Face, substantially increases construction efficiency, accelerates construction speed.The device low manufacture cost, can be used in turn, and install, dismantle just Victory, economic benefit is obvious, and saving of labor, laborsaving, time saving.
Brief description of the drawings
Fig. 1 be steel construction high-rise working safety belt safety rope branch hang device provided by the utility model overall structure and Schematic view of the mounting position;
Fig. 2 is the partial enlarged view of A nodes in Fig. 1;
Fig. 3 is the partial enlarged view of B node in Fig. 1;
Fig. 4 is the partial enlarged view of C nodes in Fig. 1;
Fig. 5 is the front-view schematic diagram of movable support provided by the utility model;
Fig. 6 is the left view schematic diagram of movable support provided by the utility model.
In above-mentioned figure:1st, movable support, the 11, first U-shaped deck, 12, upright bar, 13, reinforcing angle, 14, wire rope handling ear, 15, First jackscrew;16th, the first nut;2nd, rope end connector, the 21, second U-shaped deck, 22, rope ear, 3, horizontal hanging cable, 31, steel wire Rope, 32, rope clamp;4th, structural steel beam.
Embodiment
For that can further appreciate that the content of the utility model, feature and effect, the following examples are hereby given, and coordinates attached drawing Describe in detail as follows:
As shown in Figures 1 to 4, a kind of steel construction high-rise working safety belt safety rope branch hang device is present embodiments provided, Mainly include movable support 1, rope end connector 2, horizontal hanging cable 3.Some movable supports 1 are installed on 4 same flank of structural steel beam On listrium, and it is arranged at intervals with the spacing of 6-8m, its top is used for the steel wire rope 31 of support level hanging cable 3.Rope end connector 2 The outside of two movable supports 1 in end is arranged in, and is installed on apart from end movable support 1 not less than the structural steel at 500mm On 4 the same side flange plate of beam, for fixing 31 end of steel wire rope of horizontal hanging cable 3.Horizontal hanging cable 3 is pushed up installed in movable support 1 Portion, for hanging the safety rope of safety belt.
With reference to shown in Fig. 5 and Fig. 6, movable support 1 by the first U-shaped deck 11, upright bar 12, reinforcing angle 13, wire rope handling ear 14, First jackscrew 15 is formed.
First U-shaped deck 11 is made of with plate-side plate welding upper and lower support plate, is horizontally disposed with using the processing of 10mm steel plates Upper and lower support plate be parallel to each other, the side of upper and lower support plate is connected by the side plate being vertically arranged, and it is U to be combined into section The clamping structure of font.The length dimension of upper and lower support plate and side plate is about 160mm;Width dimensions are actual according to installation position Situation determines;4 edge of a wing maximum gauge+5mm of spacing=installation position structural steel beam between upper and lower support plate.Lower supporting plate is pressed It is laterally centered to be drilled with two bolts hole, 15 diameter+4mm of bolt hole aperture=first jackscrew, separately at lower supporting plate bottom along longitudinal direction Portion's spiro keyhole position welding equipment has the first nut 16, and the screw thread specification of the first nut 16 is matched with the first jackscrew 15, for installing first Jackscrew 15.First U-shaped deck 11 is located at 1 bottom of movable support, by being caught in structure in the gap on it, between lower supporting plate 4 edge of a wing of girder steel is simultaneously spacing with side plate, the first U-shaped deck 11 is conveniently installed on structural steel beam 4, so that as work The Steady base support of dynamic stent 1.First jackscrew 15 uses M12 hexagon-headed bolts, and spiro rod length is about 50mm;Single Pin activities branch Frame 1 is furnished with two.Two first jackscrews 15 are threaded onto in two bolts hole of 11 lower supporting plate of the first U-shaped deck and with respectively One nut 16 is tightened, and the first U-shaped deck 11 for being installed on structural steel beam 4 is fixed.
Upright bar 12 is highly 500mm or so, with specific reference to the actual feelings in installation position using the processing of 40mm × 4mm square steel tubes Condition determines.12 erecting and welding placed in the middle of upright bar is in 11 upper backup pad top surface of the first U-shaped deck.
Reinforcing angle 13 arranges two on single Pin movable supports 1, is processed using the angle steel of L40 × 4;Length is 40mm.Add Gu angle steel 13 is installed at left and right sides of 12 bottom of upright bar, its two blocks of flange plates are upper with 12 and first U-shaped deck 11 of upright bar respectively Support plate is welded, and is reinforced for connecting node.
Using the processing of the angle steel of L75 × 50 × 10, length 70mm, is stayed a diameter of wire rope handling ear 14 among 75mm wide width wing edge The cord hole of 30mm, cord hole bore edges blunt angle.Wire rope handling ear 14 is vertically mounted on 12 top outer of upright bar with its 75mm wide width wing edge, with Its 50mm wide width wings edge is welded with upright bar 12.
Rope end connector 2 is installed on external distance end movable support 1 not less than on 4 flange plate of structural steel beam at 500mm, is used for The steel cord ends of fixed horizontal hanging cable 3.As shown in figure 4, rope end connector 2 is by the second U-shaped deck 21, rope ear 22, second Jackscrew is formed.The concrete structure and production method of second U-shaped deck 21 are the same as the first U-shaped deck 11;The concrete structure of rope ear 22 With production method with wire rope handling ear 14;The concrete structure and production method of second jackscrew are the same as the first jackscrew 15.Second U-shaped deck 21 In 2 bottom of rope end connector, structural steel beam 4 can be conveniently installed on;Two second jackscrews are threaded onto the second U-shaped respectively Tightened in two bolts hole of 21 lower supporting plate of deck and with the second nut, the second U-shaped deck of structural steel beam 4 will be installed on 21 is fixed.Rope ear 22 with its vertical welding equipment of 75mm wide width wing edge 21 upper backup pad of the second U-shaped deck crown center, with Its 50mm wide width wings edge and 21 upper backup pad of the second U-shaped deck weld.
Horizontal hanging cable 3 is horizontally arranged at the top of movable support 1, for hanging the safety rope of safety belt.Horizontal hanging cable 3 includes Steel wire rope 31, rope clamp 32,31 diameter of steel wire rope are not less than 12mm, and rope clamp 32 is fixed for 31 rope end of steel wire rope, specification and steel wire The matching of rope 31,32 quantity of rope clamp of 31 connecting pin of steel wire rope are no less than 3, and spacing is not less than 75mm.
The steel construction high-rise working safety belt safety rope branch hang device of the present embodiment when in use, first by movable support 1 Second U-shaped deck 21 of the first U-shaped deck 11 and rope end connector 1 is sleeved on 4 edge of a wing of structural steel beam, and the top of fastening first respectively 15 and second jackscrew of silk is fixed;Steel wire rope 31 sequentially passes through to the cord hole on the wire rope handling ear 14 of each movable support 1, and by two End is fixed on the rope ear 22 of rope end connector 2 by rope clamp 32.Safety belt safety rope is hung over into steel wire rope by snap ring button On 31, the hooking point of formation activity, operating personnel can move horizontally, while can prevent vertical drop.
The steel construction high-rise working safety belt safety rope branch hang device of the present embodiment, its Specific construction process are as follows:
1) preparation
(1) technique preparation
It is designed, checks, determines material specification.
(2) material prepares
Steel plate, the specification of shaped steel should meet design requirement, must there is certification of fitness prescribed paper and Delivery Inspection Report, mechanics Performance indicator must meet related standard regulation.Steel plate thickness, shaped steel specification and tolerance should meet its product standard It is required that.
Specification, the model of steel wire rope 31 should meet design requirement, and no dog leg, corrosion, loose stock, fracture of wire and hemp core grease dry up Phenomenon, must there is certification of fitness prescribed paper and Delivery Inspection Report, its mechanical performance index must meet related standard regulation.
Specification, the quantity of rope clamp 32 should meet design, code requirement, and holder must not have reduction intensity and significantly damage outer The defects of sight (such as stomata, crackle, loose, burning into sand, casting scar, a phosphorus, mould shift).
2) parts and components processing, buying
(1) movable support 1 is processed:By design size, requirement processing, assembly.Bolt on first U-shaped deck, 11 lower supporting plate Hole site should be correct.First nut 16 is buying, and specification matches with the first jackscrew 15, and when installation should be with hole central alignment.Wire rope handling 14 cord hole edge blunt angle of ear.First by 14 welding equipment of wire rope handling ear in upright bar 12, then upright bar 12 and the first U-shaped deck 11 assembled, Last 12 bottom reinforcing angle 13 of welding equipment upright bar.Install and pay attention to wire rope handling ear 14 during each upright bar 13 towards the first U-shaped deck 11 Side plate homonymy.Upright bar 12 should be vertical with the upper backup pad of the first U-shaped deck 11.Weld seam is full weld, it is desirable to firm welding.
(2) rope end connector 2 is processed:By design size, requirement processing, assembly.Second U-shaped deck 21, rope ear 22 add First U-shaped deck 11, wire rope handling ear 14 of the work requirement with movable support 1.22 vertical welding equipment of rope ear is in the upper of the second U-shaped deck 21 Support plate face.Weld seam is full weld, it is desirable to firm welding.
(3) first jackscrews 15 and the second jackscrew:M12 is used, the hexagon-headed bolt that length is about 50mm, for buying, is pressed 《Hexagon-headed bolt》Standard test.
(4) 31 blanking of steel wire rope:The steel wire rope 31 of 31 cutting length of steel wire rope=be connected between both sides rope end connector 2 Length+connecting pin steel wire rope 31 unrolls length × 2.Connecting pin steel wire rope 31 unroll length should meet install rope clamp 32 requirement (31 connecting pin rope clamp of steel wire rope, 32 quantity is no less than 3, and spacing is not less than 75mm).
(5) rope clamp 32:For buying.Specification is matched with steel wire rope 31, and each connecting pin sets quantity to be no less than 3.Rope clamp 32 holders must not have the defects of reducing intensity and significantly damaging appearance (such as stomata, crackle, loose, burning into sand, casting scar, a phosphorus, mistake Case etc.), U bolt surface, which is not allow for burning crackle, indenture, scabbing, streak, oxide skin and floating embroidery, thread surface, to be had Damage, burr, double cusps, cut and screw thread it is imperfect.
3) device is installed
(1) movable support 1 is installed:Movable support 1 is installed in the same side of structural steel beam 4, both ends and middle every 6-8m If one.The first U-shaped deck 11 opening upward, is inserted in 4 edge of a wing of structural steel beam, reclined structural steel to side plate by upright bar 12 during installation 4 edge of a wing side of beam, removes son with hand and screws the first jackscrew 15 on the first U-shaped deck lower supporting plate and it is held out against 4 wing of structural steel beam Edge bottom surface.
(2) rope end connector 2 is installed:External distance end movable support 1 is arranged on not less than at 500mm, rope ear during installation 22 upward, and the second U-shaped deck 21 opening is inserted in 4 edge of a wing of structural steel beam, reclines 4 edge of a wing side of structural steel beam to side plate, uses hand Removing the jackscrew that son is screwed on 21 lower supporting plate of the second U-shaped deck makes it hold out against 4 edge of a wing bottom surface of structural steel beam.
(3) horizontal hanging cable 3 is installed:Steel wire rope 31 is sequentially passed through to the wire rope handling ear 14 of each movable support 1 from one end to another end On cord hole, first 31 one end of steel wire rope is fastened on the side rope end connector 2;Steel wire rope 31 is tightened using jack, Then 31 another end of steel wire rope is connected fixation with another side rope end connector 2.Steel wire rope 31 is with 2 connection method of rope end connector: Steel wire rope 31 is unrolled through the cord hole on the rope ear 22 of rope end connector 2, is fixed fag end and steel wire rope 31 with rope clamp 32. Rope clamp 32 is no less than 3, and spacing is not less than 75mm.
(4) to ensure the safety of installation process, the installation of the device should lift preceding progress in steel structure girder 4, install Lifted afterwards with steel structure girder 4.
4) device uses
The safety rope of safety belt is hung on the steel wire rope 31 of horizontal hanging cable 3 by snap ring button, safety rope can be along steel wire rope 31 slide, and construction personnel is carried out to move protection.
Could be aware that in summary, the steel construction high-rise working safety belt safety rope branch hang device of the utility model have with Lower advantage:
1) movable support 1 and rope end connector 2 are used, is directly installed in structural steel beam 4, without welding or in steel Structure drilling is bolted, and avoids damage to structure.
2) horizontal hanging cable 3 is set between movable support 1, and the safety rope to safety belt provides adjustable hook hanging point;Safety rope Can be free to slide along hanging cable steel wire rope 31, reaching prevents vertical drop and moves horizontally construction double effects.
3) rope end connector 32 can make the Impact direction of movable support 1 be changed into downward from level, so as to greatly increase work The stability of dynamic stent 1.
4) reinforcing angle 13 is set in 12 root of upright bar of movable support 1, is greatly improved the energy of 12 resistance to deformation of upright bar Power.
5) simple in structure, materials facility, processes, is easy to use, can have enough to meet the need.
Although the preferred embodiment of the utility model is described above in conjunction with attached drawing, the utility model is not Above-mentioned embodiment is confined to, above-mentioned embodiment is only schematical, is not restricted, ability The those of ordinary skill in domain is not departing from invention objective and scope of the claimed protection feelings under the enlightenment of the utility model Under condition, the specific conversion of many forms can also be made, these are belonged within the scope of protection of the utility model.

Claims (8)

1. a kind of steel construction high-rise working safety belt safety rope branch hang device, it is characterised in that connected including movable support, rope end Device, horizontal hanging cable;On multiple spaced homonymy flange plates installed in structural steel beam of the movable support, its top is used for Horizontal hanging cable described in stent;The rope end connector is located at the outside of two movable supports in end, is also mounted at structural steel On the homonymy flange plate of beam, for fixing the horizontal hanging cable end;The horizontal hanging cable is used for the safety rope for hanging safety belt, The safe sling of safety belt hangs in the horizontal hanging cable and can slide along.
2. a kind of steel construction high-rise working safety belt safety rope branch hang device according to claim 1, it is characterised in that more A movable support is arranged at intervals with the spacing of 6-8m.
A kind of 3. steel construction high-rise working safety belt safety rope branch hang device according to claim 1, it is characterised in that institute Movable support is stated to be made of U-shaped deck, upright bar, reinforcing angle, wire rope handling ear, jackscrew;The U-shaped deck by upper and lower support plate with Plate-side plate welding is formed, its lower supporting plate is drilled with two bolts hole and welding equipment has nut, and the bolt hole and the nut are used for Jackscrew is installed so that the U-shaped deck to be fixedly installed in the flange plate of structural steel beam;The upright bar is welded in the U-shaped deck Upper backup pad top surface;Two reinforcing angles are installed at left and right sides of the bottom of upright rod, with the upright bar and the U-shaped card The upper backup pad of seat has welding;Wire rope handling ear equipped with cord hole is vertically welded in the upright bar top outer, all activities Homonymy of the wire rope handling ear of stent towards the U-shaped deck.
A kind of 4. steel construction high-rise working safety belt safety rope branch hang device according to claim 3, it is characterised in that institute Stating horizontal hanging cable includes steel wire rope and rope clamp, and the steel wire rope sequentially passes through the wire rope handling ear of all movable supports.
A kind of 5. steel construction high-rise working safety belt safety rope branch hang device according to claim 1, it is characterised in that institute State the movable support of the rope end connector apart from end and be not less than 500mm.
A kind of 6. steel construction high-rise working safety belt safety rope branch hang device according to claim 1, it is characterised in that institute Rope end connector is stated to be made of U-shaped deck, rope ear, jackscrew;The U-shaped deck is made of upper and lower support plate with plate-side plate welding, Its lower supporting plate is drilled with two bolts hole and welding equipment has a nut, and the bolt hole and the nut are used to installing jackscrew with by institute State the flange plate that U-shaped deck is fixedly installed in structural steel beam;The rope ear-lobe equipped with cord hole is directly welded in the U-shaped deck Upper backup pad top surface.
A kind of 7. steel construction high-rise working safety belt safety rope branch hang device according to claim 6, it is characterised in that institute Stating horizontal hanging cable includes steel wire rope and rope clamp, and the both ends of the steel wire rope are fixed on the rope end connector by the rope clamp The rope ear.
8. a kind of steel construction high-rise working safety belt safety rope branch hang device according to claim 4 or 7, its feature exist In the safety rope of the safety belt hangs over the hooking point of formation activity on the steel wire rope by snap ring button.
CN201720744661.4U 2017-06-24 2017-06-24 A kind of steel construction high-rise working safety belt safety rope branch hang device Active CN207314891U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720744661.4U CN207314891U (en) 2017-06-24 2017-06-24 A kind of steel construction high-rise working safety belt safety rope branch hang device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720744661.4U CN207314891U (en) 2017-06-24 2017-06-24 A kind of steel construction high-rise working safety belt safety rope branch hang device

Publications (1)

Publication Number Publication Date
CN207314891U true CN207314891U (en) 2018-05-04

Family

ID=62436425

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720744661.4U Active CN207314891U (en) 2017-06-24 2017-06-24 A kind of steel construction high-rise working safety belt safety rope branch hang device

Country Status (1)

Country Link
CN (1) CN207314891U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107190997A (en) * 2017-06-24 2017-09-22 中国建筑第六工程局有限公司 A kind of steel construction high-rise working safety belt safety rope branch hang device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107190997A (en) * 2017-06-24 2017-09-22 中国建筑第六工程局有限公司 A kind of steel construction high-rise working safety belt safety rope branch hang device

Similar Documents

Publication Publication Date Title
CN107190997A (en) A kind of steel construction high-rise working safety belt safety rope branch hang device
CN201730338U (en) Strut for supporting polyphenyl foam formwork walls
CN207314891U (en) A kind of steel construction high-rise working safety belt safety rope branch hang device
CN204552054U (en) A kind of telescopic work high above the ground hanger bracket
CN204752026U (en) Tower crane escape way
CN212053859U (en) Horizontal overhanging flexible protective net for construction of main structure of building
CN206971689U (en) Support operating platform that is detachable and recycling
CN211689948U (en) Suspension operation platform device for construction of suspension cable at tower part of cable-stayed bridge
CN102182324A (en) Anti-falling safety net
CN205908004U (en) Special hoist and mount fixing device of hanging flower basket
CN211173007U (en) Novel tripod of encorbelmenting
CN210798250U (en) Electric power iron tower overhauls uses portable operation platform
CN209308433U (en) A kind of multi-functional trolley of Cast-in-situ Beam steel reinforcement cage binding installation
CN105888269A (en) Suspended cable type safety protection device for building construction overhead operation, and construction method of suspended cable type safety protection device
CN212789487U (en) Safety protection device for transverse operation of power transmission tower
CN107217912A (en) It is a kind of to be used for the superelevation physical isolation construction method of neighbouring high ferro Business Line construction
CN204038917U (en) Dismountable external hanging service platform
CN206928683U (en) A kind of lifeline standing rigging
CN216949609U (en) Anti-tearing woven safety net
CN207296350U (en) Detachable operating platform for steel pipe column
CN205713183U (en) A kind of cooling tower perimeter security preventer
CN202263317U (en) Safety belt
CN203855337U (en) Safety protection device for operation of tower crane suspension arm
CN211572655U (en) Building outer wall super-high large cantilever lifting structure
CN209261249U (en) A kind of staircase protective device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant