CN207568163U - Prefabricated Climbing frame for outer-wall hole mounting structure - Google Patents

Prefabricated Climbing frame for outer-wall hole mounting structure Download PDF

Info

Publication number
CN207568163U
CN207568163U CN201721620511.9U CN201721620511U CN207568163U CN 207568163 U CN207568163 U CN 207568163U CN 201721620511 U CN201721620511 U CN 201721620511U CN 207568163 U CN207568163 U CN 207568163U
Authority
CN
China
Prior art keywords
wall
hole
reinforcing plate
climbing frame
mounting structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721620511.9U
Other languages
Chinese (zh)
Inventor
徐敏
迟毅
张晓峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201721620511.9U priority Critical patent/CN207568163U/en
Application granted granted Critical
Publication of CN207568163U publication Critical patent/CN207568163U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a kind of prefabricated Climbing frame for outer-wall hole mounting structure, stud including passing through hole, and stud both ends are installed on for locking the nut of stud position, further include metal sleeve, reinforcing plate, the hole mold installed when metal sleeve is poured for wall, the outer end of blade of metal sleeve is welded with reinforcing plate, reinforcing plate is close to outer leaf surface, the mounting structure of wall hole climbing frame provided by the utility model, casing rigidity is strong, it is hardly damaged, hole portion sets reinforced structure, ensure that wall can bear larger pressure, installation is avoided to destroy, reduce later stage repairing.

Description

Prefabricated Climbing frame for outer-wall hole mounting structure
Technical field
The utility model belongs to prefabricated wall climbing frame technical field of construction, and in particular to climbing frame wall hole is installed Structure.
Background technology
In traditional assembled architecture work progress, it is related to the installation of climbing frame, in order to easy for construction, is making prefabricated cut In the operation of power wall, corresponding drawing swashes the position of frame installation hole, by pre-buried pvc pipe to climbing frame on corresponding shear wall Hole is reserved, and in this way convenient for the installation of later stage climbing frame and is improved the precision installed, is reduced and punch to the shear wall later stage Labour cost is saved in the destruction of wall body structure caused by and.
But above-mentioned form of construction work there are it is certain the defects of, first, causing material using pre-buried can not be used in turn of pvc pipe It is poor that waste and later stage block water proofing property.Second, since precast shear wall is made of, and its outer leaf thickness siphonal lobe, heat preservation, internal lobe It is smaller, in climbing frame installation process, reinforce bolt and reinforced across reserved opening, easily the siphonal lobe of wall and heat preservation are carried out It destroys, leads to the decline of wall appearance deformation and wall integral strength, increase later stage renewal expense.
Utility model content
The purpose of this utility model is solved in the prior art with pvc pipe reserved opening, 1) fragile, material is managed during construction Consume the shortcomings that big;2) pvc pipe hole and periphery rigidity are inadequate, and climbing frame installation is caused to damage wall siphonal lobe.
In order to solve the above technical problems, the utility model provide it is a kind of be hardly damaged and the hole of reinforcement siphonal lobe installation knot Structure, specific technical solution are:
A kind of prefabricated Climbing frame for outer-wall hole mounting structure, including passing through the stud at hole and being installed on Stud both ends are used to lock the nut of stud position, further include metal sleeve, reinforcing plate, metal sleeve is poured for wall The hole mold installed when building, the outer end of blade of metal sleeve are welded with reinforcing plate, and reinforcing plate is close to outer leaf surface.
The utility model provides a kind of mounting structure of wall hole climbing frame, and casing rigidity is strong, is hardly damaged, and hole portion is set Reinforced structure ensures that wall can bear larger pressure, installation is avoided to destroy, and reduces later stage repairing.
Description of the drawings
Fig. 1 is casing overall structure figure;
Fig. 2 is casing side view angle figure one;
Fig. 3 is casing side view angle figure two;
Fig. 4 is the utility model integral installation combination figure;
Fig. 5 is the utility model usage state diagram.
In figure, tube body 1, reinforcing plate 2, stud 3, nut 4, climbing frame 5.
Specific embodiment
The utility model is illustrated below in conjunction with the accompanying drawings:A kind of prefabricated Climbing frame for outer-wall as shown in Figs. 1-5 Hole mounting structure includes tube body 1, reinforcing plate 2, stud 3, nut 4.Wherein reinforcing plate 2 is fixed in 1 one end of tube body, Reinforcing plate 2 and tube body 1 are all preferred metal materials, and the two is welded, becomes metal sleeve.When metal sleeve is poured for wall Installation hole mold, reinforcing plate 2 is located at siphonal lobe side, is tightly attached to the outer leaf surface for pouring completion.Stud 3 is installed on metal In casing, metal sleeve is stretched out at both ends, and with 4 locked position of nut.
Reinforcing plate 2 described in the utility model can be round or rectangular.
The metal sleeve of the utility model can be it is made of iron, can also steel and the strong construction material of other rigidity.
The mounting structure of the utility model, climbing frame 5 are fixed between reinforcing plate 2 and nut 4.
The utility model concrete operation method follows these steps to carry out:
1) during precast wall body, the mold of wall siphonal lobe is assembled.
2) reinforced mesh and cushion block are placed, while metal sleeve is embedded into siphonal lobe, it is made to be fixed on reinforcing bar with silk is tied up In mesh sheet.
3) concreting is carried out to siphonal lobe.
4) insulating layer, assembling internal lobe mold, while assembling reinforcement and casting concrete are laid with,
5) the steam-cured making for completing precast shear wall, while by inserting or withdrawing sleeves.
6) wall is transported to scene to install.
7) stud 3 is passed through into tube body 1,5 bearing of climbing frame is fixed on precast wall body and is reinforced with nut 4, completed The fixed installation of climbing frame 5.
By the stress of bracing means when the utility model is reinforced, therefore wall siphonal lobe and heat preservation will not be damaged.Casing Rigidity is strong, is hardly damaged, and hole portion sets reinforced structure, ensures that wall can bear larger pressure, installation is avoided to destroy, reduce the later stage Repairing.

Claims (2)

1. a kind of prefabricated Climbing frame for outer-wall hole mounting structure, including passing through the stud at hole and being installed on double Hook bolt both ends are used to lock the nut of stud position, it is characterised in that:Further include metal sleeve, reinforcing plate, metallic sheath The hole mold installed when being poured for wall is managed, the outer end of blade of metal sleeve is welded with reinforcing plate, and reinforcing plate is close to outer leaf surface.
2. prefabricated Climbing frame for outer-wall hole as described in claim 1 mounting structure, it is characterised in that:The reinforcing plate is round Shape is rectangular.
CN201721620511.9U 2017-11-28 2017-11-28 Prefabricated Climbing frame for outer-wall hole mounting structure Active CN207568163U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721620511.9U CN207568163U (en) 2017-11-28 2017-11-28 Prefabricated Climbing frame for outer-wall hole mounting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721620511.9U CN207568163U (en) 2017-11-28 2017-11-28 Prefabricated Climbing frame for outer-wall hole mounting structure

Publications (1)

Publication Number Publication Date
CN207568163U true CN207568163U (en) 2018-07-03

Family

ID=62688508

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721620511.9U Active CN207568163U (en) 2017-11-28 2017-11-28 Prefabricated Climbing frame for outer-wall hole mounting structure

Country Status (1)

Country Link
CN (1) CN207568163U (en)

Similar Documents

Publication Publication Date Title
CN105569224A (en) Concrete-filled steel tube edge restraint overlapping integrated shear wall and preparing and installation methods thereof
CN104790569A (en) Formwork-free shear wall and construction method thereof
CN103422674A (en) Cast-in-place section concrete construction method of assembling-type concrete structure
JP2022506916A (en) Ultra-high performance concrete prefabricated permanent template and its applications
CN109736499B (en) Prefabricating process of prefabricated laminated slab
CN106638697A (en) Method for rapidly constructing light formwork of reinforced-concrete-cast-in-place circular draining inspection well
CN107119901A (en) The cast-in-place system of formwork structure and shear wall and construction method of shear wall angle node
CN111734018A (en) Formwork structure, disassembly-free mold and concrete wall construction method
CN110630011A (en) Template reinforcing system for double shear walls at deformation joint and construction method thereof
CN211007659U (en) Device for controlling forming of embedded steel plate in concrete column on column surface
CN104727552A (en) Construction method for reserving water feed pipe grooves in prefabricated shear wall
CN215760469U (en) Building structure movement joint position shear force wall aluminum mould board location reinforcement device
CN107905424A (en) Full prefabricated band splicing groove unidirectional harden structure, making and assembly method
CN207568163U (en) Prefabricated Climbing frame for outer-wall hole mounting structure
CN106337530B (en) A kind of construction of frame beam seams stifled construction method
CN205712565U (en) A kind of prefabricated two-sided wall
CN209874483U (en) Detachable fixing die for reserved air conditioner hole of shear wall
CN106836559A (en) A kind of reinforced concrete wall structure and its construction method for preventing from ftractureing
CN104878756B (en) Sand-filling hollow structure based cast-in-place special-shaped pile construction method
CN216609427U (en) Mould for manufacturing concrete hollow column
CN212506913U (en) Integrated wall structure of external wall heat-insulation decorative plate
CN108867890A (en) The integral prefabricated node of beam column of the junction with rigid template bracket and its construction method
CN111456254B (en) Connecting device convenient for aluminum die reinforcement of heat insulation plate and construction method
CN210082045U (en) Superimposed floor slab side formwork
CN208235803U (en) A kind of non-dismantling formwork system chooses part

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant