CN207526189U - Stereo garage steel construction - Google Patents

Stereo garage steel construction Download PDF

Info

Publication number
CN207526189U
CN207526189U CN201721601211.6U CN201721601211U CN207526189U CN 207526189 U CN207526189 U CN 207526189U CN 201721601211 U CN201721601211 U CN 201721601211U CN 207526189 U CN207526189 U CN 207526189U
Authority
CN
China
Prior art keywords
garage
section
column
support column
steel construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721601211.6U
Other languages
Chinese (zh)
Inventor
叶峰
张高圣
陈新华
凡东生
颜国辉
孔德振
许英
许一英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUZHOU XINFENG HENG FU TECHNOLOGY Co Ltd
Zigong Innovation Center of Zhejiang University
Original Assignee
SUZHOU XINFENG HENG FU TECHNOLOGY Co Ltd
Zigong Innovation Center of Zhejiang University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUZHOU XINFENG HENG FU TECHNOLOGY Co Ltd, Zigong Innovation Center of Zhejiang University filed Critical SUZHOU XINFENG HENG FU TECHNOLOGY Co Ltd
Priority to CN201721601211.6U priority Critical patent/CN207526189U/en
Application granted granted Critical
Publication of CN207526189U publication Critical patent/CN207526189U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model is related to a kind of stereo garage steel constructions, stereo garage includes multistoried garage, several parking stalls for including several run-ins of longitudinal arrangement per layer garage and laterally arranging, stereo garage steel construction includes vertically arranged support column and lateral, longitudinally disposed supporting beam, support column includes outer support column, main support column and secondary support column, and supporting beam includes main support beam and time supporting beam;Main support column includes bottom principal post section, middle level principal post section and high-rise secondary principal post section, and outer support column and time support column respectively include bottom time shell of column, middle-level shell of column and high-rise inferior-defective shell of column;Main support beam includes bottom girder section, middle level girder section and high-rise secondary girder section, and secondary supporting beam includes bottom time beam section, middle-level beam section and high-rise inferior-defective beam section.The utility model has the characteristics that save material, reduces garage construction cost.

Description

Stereo garage steel construction
Technical field
The utility model belongs to stereo garage technical field, more particularly to a kind of stereo garage steel construction.
Background technology
Steel construction is widely used in modern stereo garage construction.In general stereo garage steel construction, including branch Dagger and supporting beam.Support column and supporting beam are designed according to the load requirement in garage.It is set in existing stereo garage the library steel construction In meter technology, using material model, specification, support column of the same size and material model, specification, branch of the same size Support beam, there is no according to support column or supporting beam the loads change of stereo garage different location require come designing material model, Specification, the support column of cause not of uniform size or supporting beam, thus be easy to cause stereo garage master-plan is unreasonable and material On waste, so as to cause stereo garage construction cost increase.
Utility model content
The technical problem to be solved by the utility model is to, provide it is a kind of design more rationally, using flexible, stereoscopic vehicle Library steel construction.
The utility model is realized in this way providing a kind of stereo garage steel construction, the stereo garage includes multilayer vehicle Library, several run-ins that longitudinal arrangement is included per layer garage and several parking stalls laterally arranged, it is described vertical Body garage steel construction includes vertically arranged support column and lateral, longitudinally disposed supporting beam, and the support column includes being arranged on Outer support column at left and right sides of stereo garage is arranged on the main support column of run-in both sides and is positioned close to adjacent The secondary support column of parking stall side, two neighboring secondary support column are fixed together.The supporting beam includes what is connect with support column Main support beam and the secondary supporting beam being connect respectively with outer support column and time support column;The main support column is included the use of in vehicle The bottom in library and by the steel construction of near-bottom bottom principal post section, use the middle level principal post in the steel construction of garage middle layer Section and using the secondary principal post section of high level in the top of garage or in the top steel construction, the outer support column and Secondary support column respectively include using garage bottom and by the steel construction of near-bottom bottom time shell of column, using in garage Middle-level shell of column and use in the steel construction of interbed is in the top of garage or the high level in top steel construction Inferior-defective shell of column;The main support beam include the use of garage bottom and by the steel construction of near-bottom bottom girder section, make Middle level girder section and use in the steel construction of garage middle layer is in the top of garage or close to top steel knot The secondary girder section of high level in structure, the secondary supporting beam are included the use of in the bottom in garage and by the bottom in the steel construction of near-bottom Secondary beam section, using the middle-level beam section in the steel construction of garage middle layer and using in the top of garage or close to most High-rise inferior-defective beam section in high-rise steel construction;The outer support column is made of H profile steel material, and the main support column uses square steel Tubing is made, and the secondary support column is made of channel steel material, and H profile steel material system is respectively adopted in the main support beam and time supporting beam Into.
Further, the stereo garage is provided with two layer garages, the bottom principal post section, bottom time shell of column, bottom master Beam section and bottom time beam section are arranged in the steel construction of garage first layer, the high-rise secondary principal post section, high-rise inferior-defective shell of column, height The secondary girder of layer and high-rise inferior-defective beam section are arranged in the steel construction of the garage second layer.
Further, the stereo garage is provided with three layer garages, the bottom principal post section, bottom time shell of column, bottom master Beam section and bottom time beam section are arranged in the steel construction of garage first layer and the second layer, the high-rise secondary principal post section, high level Inferior-defective shell of column, high-rise secondary girder and high-rise inferior-defective beam section are arranged in the steel construction of third layer.
Further, the stereo garage is provided with four layer garages, the bottom principal post section, bottom time shell of column, bottom master Beam section and bottom time beam section are arranged in the steel construction of garage first layer and the second layer, the middle level principal post section, middle-level Shell of column, middle level girder section and middle-level beam section are arranged in the steel construction of garage third layer, the high-rise secondary principal post section, high level Inferior-defective shell of column, high-rise secondary girder and high-rise inferior-defective beam section are arranged in the steel construction in the 4th layer of garage.
Further, the stereo garage is provided with five layer garages, the bottom principal post section, bottom time shell of column, bottom master Beam section and bottom time beam section are arranged in the steel construction of garage first layer and the second layer, the middle level principal post section, middle-level Shell of column, middle level girder section and middle-level beam section are arranged in garage third layer and the 4th layer of steel construction, described high-rise secondary main Shell of column, high-rise inferior-defective shell of column, high-rise secondary girder and high-rise inferior-defective beam section are arranged in the steel construction of garage layer 5.
Further, the bottom principal post section of the main support column uses specification to be made of the square steel tubing of 200*200*10, The middle level principal post section of the main support column uses specification to be made of the square steel tubing of 200*200*8, the high level of the main support column Secondary principal post section uses specification to be made of the square steel tubing of 200*200*6.
Further, the bottom time shell of column of the outer support column uses specification to be made of the H profile steel material of 200*200*8*12, The middle-level shell of column of the outer support column uses specification to be made of the H profile steel material of 200*150*6*9, the high level of the outer support column Inferior-defective shell of column uses specification to be made of the H profile steel material of 200*100*5.5*8.
Further, the bottom time shell of column of the secondary support column uses specification to be made of the groove profile steel of C20B, described time The middle-level shell of column of support column uses specification to be made of the groove profile steel of C20A, and the high-rise inferior-defective shell of column of the secondary support column uses Specification is made of the groove profile steel of C20A.
Further, the bottom girder section of the main support beam uses specification to be made of the H profile steel material of 200*200*8*12, The middle level girder section of the main support beam uses specification to be made of the H profile steel material of 200*150*6*9, the high level of the main support beam Secondary girder section uses specification to be made of the H profile steel material of 200*100*5.5*8.
Further, the bottom time beam section of the secondary supporting beam uses specification to be made of the H profile steel material of 200*200*8*12, The middle-level beam section of the secondary supporting beam uses specification to be made of the H profile steel material of 200*150*6*9, the high level of the secondary supporting beam Inferior-defective beam section uses specification to be made of the H profile steel material of 200*100*5.5*8.
Compared with prior art, the stereo garage steel construction of the utility model has following main feature:
1) designs are more reasonable;
2) reduces stereo garage steel usage amount, reduces stereo garage the library building materials cost;
3) reduces stereo garage foundation of civil work load requirement, reduces stereo garage foundation pit civil engineering construction cost.
Description of the drawings
Fig. 1 is the support column horizontal layout schematic diagram of the stereo garage steel construction of the utility model;
Fig. 2 is the installation condition signal of the main support column and main support beam in the stereo garage steel construction of the utility model Figure;
Fig. 3 is the installation condition signal of the secondary support column and time supporting beam in the stereo garage steel construction of the utility model Figure.
Specific embodiment
In order to which technical problem to be solved in the utility model, technical solution and advantageous effect is more clearly understood, with Lower combination accompanying drawings and embodiments, the present invention is further described in detail.It should be appreciated that specific reality described herein It applies example to be only used to explain the utility model, is not used to limit the utility model.
Referring to shown in Fig. 1, Fig. 2 and Fig. 3, the preferred embodiment of the utility model stereo garage steel construction, institute It states stereo garage and includes multistoried garage, laterally several run-in A that longitudinal arrangement is included per layer garage and row Several parking stall B of cloth.Vehicle middle arrow direction in-and-out stereo garage as illustrated.The stereo garage steel construction includes vertical The support column 1 of setting and the supporting beam 2 laterally set.Support column 1 is fixed on one with supporting beam 2 by connecting end plate and bolt It rises.
The support column 1 includes being arranged on outer support column 11 at left and right sides of stereo garage, is arranged on run-in The main support column 12 of both sides and the secondary support column 13 for being positioned close to adjacent firmly parking stall side, two neighboring secondary support column 13 are solid It is scheduled on together.The supporting beam 2 include the main support beam 21 that connect with support column and respectively with outer support column and secondary support column The secondary supporting beam 22 of connection.
The main support column 12 is included the use of in the bottom in garage and by the bottom principal post section in the steel construction of near-bottom 121st, using the middle level principal post section 122 in the steel construction of garage middle layer and using in the top of garage or close to most The secondary principal post section 123 of high level in high-rise steel construction.The outer support column 11 and time support column 13 respectively include use in garage Bottom and by the steel construction of near-bottom bottom time shell of column 14, use the middle-level column in the steel construction of garage middle layer Section 15 and use are in the top of garage or the high-rise inferior-defective shell of column 16 in top steel construction.
The main support beam 21 is included the use of in the bottom in garage and by the bottom girder section in the steel construction of near-bottom 211st, using the middle level girder section 212 in the steel construction of garage middle layer and using in the top of garage or close to most The secondary girder section 213 of high level in high-rise steel construction.The secondary supporting beam 22 is included the use of in the bottom in garage and by near-bottom Steel construction in bottom time beam section 221, use the middle-level beam section 222 in the steel construction of garage middle layer and use In the top of garage or the high-rise inferior-defective beam section 223 in top steel construction.
The outer support column 11 is made of H profile steel material, and the main support column 12 is made of square steel tubing, described branch Dagger 13 is made of channel steel material, and the main support beam 21 and time supporting beam 22 are respectively adopted H profile steel material and are made.
As one embodiment of the utility model, the stereo garage is provided with two layer garages, the bottom principal post Section, bottom time shell of column, bottom girder section and bottom time beam section are arranged in the steel construction of garage first layer, described high-rise secondary main Shell of column, high-rise inferior-defective shell of column, high-rise secondary girder and high-rise inferior-defective beam section are arranged in the steel construction of the garage second layer.
As second embodiment of the utility model, the stereo garage is provided with three layer garages, the bottom principal post Section, bottom time shell of column, bottom girder section and bottom time beam section are arranged in the steel construction of garage first layer and the second layer, institute High-rise secondary principal post section, high-rise inferior-defective shell of column, high-rise secondary girder and high-rise inferior-defective beam section is stated to be arranged in the steel construction of third layer.
As the third embodiment of the utility model, the stereo garage is provided with four layer garages, the bottom principal post Section, bottom time shell of column, bottom girder section and bottom time beam section are arranged in the steel construction of garage first layer and the second layer, institute It states middle level principal post section, middle-level shell of column, middle level girder section and middle-level beam section to be arranged in the steel construction of garage third layer, institute State the steel knot that high-rise secondary principal post section, high-rise inferior-defective shell of column, high-rise secondary girder and high-rise inferior-defective beam section are arranged on the 4th layer of garage In structure.
As the 4th embodiment of the utility model, the stereo garage is provided with five layer garages, the bottom principal post Section, bottom time shell of column, bottom girder section and bottom time beam section are arranged in the steel construction of garage first layer and the second layer, institute It states middle level principal post section, middle-level shell of column, middle level girder section and middle-level beam section and is arranged on garage third layer and the 4th layer of steel In structure, the high-rise secondary principal post section, high-rise inferior-defective shell of column, high-rise secondary girder and high-rise inferior-defective beam section are arranged on garage the 5th In the steel construction of layer.
It is appreciated that for stereo garage on the middle and senior level, according to the mentality of designing of the utility model, to stereo garage steel construction Used material model specification can also bottom, middle level and the high level in garage distinguish, under conditions of its intensity is ensured, It saves material, reduce cost.
The bottom principal post section 121 of the main support column 12 uses specification to be made of the square steel tubing of 200*200*10, described The middle level principal post section 122 of main support column 12 uses specification to be made of the square steel tubing of 200*200*8, the height of the main support column 12 The secondary principal post section 123 of layer uses specification to be made of the square steel tubing of 200*200*6.
The bottom time shell of column 14 of the outer support column 11 uses specification to be made of the H profile steel material of 200*200*8*12, described The middle-level shell of column 15 of outer support column 11 uses specification to be made of the H profile steel material of 200*150*6*9, the height of the outer support column 11 Layer inferior-defective shell of column 16 uses specification to be made of the H profile steel material of 200*100*5.5*8.When applied to other higher number of plies garage designs When each section of support column size can be designed according to garage load requirement.
The bottom time shell of column 14 of the secondary support column 13 uses specification to be made of the groove profile steel of C20B, the secondary support column 13 middle-level shell of column 15 uses specification to be made of the groove profile steel of C20A, and the high-rise inferior-defective shell of column 16 of the secondary support column 13 is adopted It is made with specification of the groove profile steel of C20A.The size of each section of support column can root when applied to other higher number of plies garage designs It is designed according to garage load requirement.
The bottom girder section 211 of the main support beam 21 uses specification to be made of the H profile steel material of 200*200*8*12, described The middle level girder section 212 of main support beam 21 uses specification to be made of the H profile steel material of 200*150*6*9, the main support beam 21 High-rise pair girder section 213 uses specification to be made of the H profile steel material of 200*100*5.5*8.When applied to other higher number of plies garages The size of each section of support column can be designed according to garage load requirement during design.
The bottom time beam section 221 of the secondary supporting beam 22 uses specification to be made of the H profile steel material of 200*200*8*12, described The middle-level beam section 222 of secondary supporting beam 22 uses specification to be made of the H profile steel material of 200*150*6*9, the secondary supporting beam 22 High-rise inferior-defective beam section 223 uses specification to be made of the H profile steel material of 200*100*5.5*8.When applied to other higher number of plies garages The size of each section of supporting beam can be designed according to garage load requirement during design.
In the stereo garage steel construction of the utility model, steel construction mainly includes support column and supporting beam.Support column It is designed with the size of supporting beam according to garage load requirement, the support column and system of unified specification is used unlike the prior art One specification supporting beam.The utility model is calculated by precise art analysis, by support column by it in stereo garage different location Load requirement, design as main support column, secondary support column.To same root, main support column presses its load requirement in different height, It is divided into bottom principal post section, middle level principal post section, high-rise secondary principal post section of main support column etc..And similar differentiation is also done to secondary support column. Similarly, also to by its load requirement in stereo garage different location, supporting beam is designed as main support beam, secondary supporting beam, and Also it is bottom section, middle interval, high interval etc. according to the different instructions of garage level to main support beam, secondary supporting beam.By science Different shape or different-diameter, the material of different-thickness is respectively adopted in system arrangement, support column and supporting beam to each level, from And form both reasonable designs, meet the requirements, completely new stereo garage steel structures coating, reach and save material, reduce and build The purpose of cost.
The above is only the preferred embodiment of the utility model only, is not intended to limit the utility model, all at this All any modification, equivalent and improvement made within the spirit and principle of utility model etc., should be included in the utility model Protection domain within.

Claims (10)

1. a kind of stereo garage steel construction, the stereo garage includes multistoried garage, described to include longitudinal arrangement per layer garage Several run-ins and several parking stalls laterally arranged, the stereo garage steel construction include vertically arranged support Column and lateral, longitudinally disposed supporting beam, which is characterized in that the support column includes being arranged on outer at left and right sides of stereo garage Support column, the main support column for being arranged on run-in both sides and the secondary support for being positioned close to adjacent stalls side Column, two neighboring secondary support column are fixed together;The supporting beam include the main support beam that is connect with support column and respectively with The secondary supporting beam that outer support column is connected with time support column;The main support column is included the use of in the bottom in garage and by near-bottom Bottom principal post section in steel construction, using the middle level principal post section in the steel construction of garage middle layer and using in garage The secondary principal post section of top or in top steel construction high level;The outer support column and time support column respectively include using Garage bottom and by the steel construction of near-bottom bottom time shell of column, use the middle level in the steel construction of garage middle layer Secondary shell of column and use are in the top of garage or the high-rise inferior-defective shell of column in top steel construction;The main support Beam include the use of garage bottom and by the steel construction of near-bottom bottom girder section, using the steel knot in garage middle layer The secondary girder section of high level of middle level girder section and use in the top of garage or close top steel construction in structure, The secondary supporting beam include the use of garage bottom and by the steel construction of near-bottom bottom time beam section, using in garage Middle-level beam section and use in the steel construction of interbed is in the top of garage or the high level in top steel construction Inferior-defective beam section;The outer support column is made of H profile steel material, and the main support column is made of square steel tubing, described support Column is made of channel steel material, and the main support beam and time supporting beam are respectively adopted H profile steel material and are made.
2. stereo garage steel construction as described in claim 1, which is characterized in that the stereo garage is provided with two layer garages, The bottom principal post section, bottom time shell of column, bottom girder section and bottom time beam section are arranged in the steel construction of garage first layer, The high-rise secondary principal post section, high-rise inferior-defective shell of column, high-rise secondary girder and high-rise inferior-defective beam section are arranged on the steel of the garage second layer In structure.
3. stereo garage steel construction as described in claim 1, which is characterized in that the stereo garage is provided with three layer garages, The bottom principal post section, bottom time shell of column, bottom girder section and bottom time beam section are arranged on garage first layer and the second layer Steel construction in, the high-rise secondary principal post section, high-rise inferior-defective shell of column, high-rise secondary girder and high-rise inferior-defective beam section are arranged on third In the steel construction of layer.
4. stereo garage steel construction as described in claim 1, which is characterized in that the stereo garage is provided with four layer garages, The bottom principal post section, bottom time shell of column, bottom girder section and bottom time beam section are arranged on garage first layer and the second layer Steel construction in, the middle level principal post section, middle-level shell of column, middle level girder section and middle-level beam section are arranged on garage third layer Steel construction in, the high-rise secondary principal post section, high-rise inferior-defective shell of column, high-rise secondary girder and high-rise inferior-defective beam section are arranged on garage In 4th layer of steel construction.
5. stereo garage steel construction as described in claim 1, which is characterized in that the stereo garage is provided with five layer garages, The bottom principal post section, bottom time shell of column, bottom girder section and bottom time beam section are arranged on garage first layer and the second layer Steel construction in, the middle level principal post section, middle-level shell of column, middle level girder section and middle-level beam section are arranged on garage third layer In the 4th layer of steel construction, the high-rise secondary principal post section, high-rise inferior-defective shell of column, high-rise secondary girder and high-rise inferior-defective beam section are set It puts in the steel construction of garage layer 5.
6. the stereo garage steel construction as described in any one in claim 1 to 5, which is characterized in that the main support column Bottom principal post section uses specification to be made of the square steel tubing of 200*200*10, and the middle level principal post section of the main support column uses specification It is made of the square steel tubing of 200*200*8, the secondary principal post section of high level of the main support column uses square steel of the specification for 200*200*6 Tubing is made.
7. the stereo garage steel construction as described in any one in claim 1 to 5, which is characterized in that the outer support column Bottom time shell of column uses specification to be made of the H profile steel material of 200*200*8*12, and the middle-level shell of column of the outer support column is using rule Lattice are made of the H profile steel material of 200*150*6*9, and the high-rise inferior-defective shell of column of the outer support column uses specification as 200*100*5.5* 8 H profile steel material is made.
8. the stereo garage steel construction as described in any one in claim 1 to 5, which is characterized in that the secondary support column Bottom time shell of column uses specification to be made of the groove profile steel of C20B, and the middle-level shell of column of the secondary support column uses specification as C20A Groove profile steel be made, the high-rise inferior-defective shell of column of the secondary support column uses specification to be made of the groove profile steel of C20A.
9. the stereo garage steel construction as described in any one in claim 1 to 5, which is characterized in that the main support beam Bottom girder section uses specification to be made of the H profile steel material of 200*200*8*12, and the middle level girder section of the main support beam is using rule Lattice are made of the H profile steel material of 200*150*6*9, and the secondary girder section of high level of the main support beam uses specification as 200*100*5.5* 8 H profile steel material is made.
10. the stereo garage steel construction as described in any one in claim 1 to 5, which is characterized in that the secondary supporting beam Bottom time beam section uses specification to be made of the H profile steel material of 200*200*8*12, and the middle-level beam section of the secondary supporting beam is using rule Lattice are made of the H profile steel material of 200*150*6*9, and the high-rise inferior-defective beam section of the secondary supporting beam uses specification as 200*100*5.5* 8 H profile steel material is made.
CN201721601211.6U 2017-11-24 2017-11-24 Stereo garage steel construction Expired - Fee Related CN207526189U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721601211.6U CN207526189U (en) 2017-11-24 2017-11-24 Stereo garage steel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721601211.6U CN207526189U (en) 2017-11-24 2017-11-24 Stereo garage steel construction

Publications (1)

Publication Number Publication Date
CN207526189U true CN207526189U (en) 2018-06-22

Family

ID=62580782

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721601211.6U Expired - Fee Related CN207526189U (en) 2017-11-24 2017-11-24 Stereo garage steel construction

Country Status (1)

Country Link
CN (1) CN207526189U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107939115A (en) * 2017-11-24 2018-04-20 浙江大学自贡创新中心 Multi-storied garage steel construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107939115A (en) * 2017-11-24 2018-04-20 浙江大学自贡创新中心 Multi-storied garage steel construction

Similar Documents

Publication Publication Date Title
CN1995571B (en) Built-in steel truss concrete combined huge size beam column frame and its manufacture method
CN205663076U (en) Can reduce steel and concrete composite roof beam of cross -sectional height
CN108374326A (en) A kind of combined rigid structure steel plate girder bridge pier consolidation construction
CN103603434B (en) A kind of concrete filled steel tube coupled column is to the transition node of reinforced column
CN207526189U (en) Stereo garage steel construction
CN203034599U (en) Unequal-height chord member open web overhanging steel truss structural system
CN205475731U (en) Integrated house combination mosaic structure's building node
CN105625567B (en) High-rise and superelevation layer concrete orthogonal-diagonal lattice space lattice boxlike tube-in-tube structure
CN104264897B (en) Alternate tooth must superimposed beam and plate
CN105625559A (en) High-rise and super high-rise concrete orthogonal-spatial space lattice box type cylinder-in-cylinder structure and manufacturing method
CN204876252U (en) Prefabricated assembled steel node concrete slab post structure
CN210117857U (en) Conversion structure of Y-shaped column top supporting steel truss
CN205000463U (en) Long cantilever disjunctor structure of large -span
CN103352579B (en) Adopt strengthening reconstruction masonry structure and the construction method of additional shelter bridge and additional elevator
CN107939115A (en) Multi-storied garage steel construction
CN203175092U (en) Processing shed capable of being assembled with hanging structure
CN206034264U (en) Novel steel construction shelter bridge foundation structure
CN201016187Y (en) Built-in steel truss concrete combined giant-scale beam-column framework
CN204475698U (en) A kind of steel structure frame of parapet
CN203394094U (en) Reinforced and reconstructed masonry structure using external gallery bridge and external elevator
CN208137134U (en) Assembly concrete-filled steel tube beam column goes along with sb. to guard him integrated system
CN209637111U (en) A kind of concrete-filled double skin steel tube colossal column
CN108265866B (en) Column cap radiation cross Liang Xinxing floor system
CN102767294A (en) Reinforcement method for improving seismic capacity of masonry structure by wall surface steel supports
CN206245483U (en) Superelevation steel construction band support frame core wall structure system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180622

CF01 Termination of patent right due to non-payment of annual fee