CN207526144U - A kind of docking structure of the electrical set aside pre-embedded pipeline of assembled - Google Patents
A kind of docking structure of the electrical set aside pre-embedded pipeline of assembled Download PDFInfo
- Publication number
- CN207526144U CN207526144U CN201721610558.7U CN201721610558U CN207526144U CN 207526144 U CN207526144 U CN 207526144U CN 201721610558 U CN201721610558 U CN 201721610558U CN 207526144 U CN207526144 U CN 207526144U
- Authority
- CN
- China
- Prior art keywords
- pipe
- built
- assembled
- docking
- set aside
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model discloses a kind of docking structure of the electrical set aside pre-embedded pipeline of assembled, including prefabricated components, site concrete, the first built-in pipe and the second built-in pipe, prefabricated components are arranged on site concrete side, docking groove is provided on the prefabricated components, first built-in pipe and the second built-in pipe are separately positioned in prefabricated components and site concrete, and are stretched into docking groove and be connected by connector.The docking structure is used for assembled architecture construction field, can effectively prevent the installation because of prefabricated components and pre-buried error, and the phenomenon that preheating embedding line can not dock occurs, and can effectively improve the docking speed of live pipeline.
Description
Technical field
The utility model is related to reserved pipeline installation docking, more particularly, to a kind of electrical set aside pre-embedded pipeline of assembled
Docking structure.
Background technology
In overall assembled construction, dry wall is lifted to floor, needing will be pre- in dry wall and floor
Buried pipeline is docked, because prefabricated components are in design, production and construction, by the precision and machining accuracy of production mould
It influencing, deviation can also occur accordingly in preheating embedding line, and the position deviation of preheating embedding line can cause the docking at seam more intractable,
Conventional method is to use directly to be docked, but because the modular nature of industrialized building construction, causes in actual installation
Easily there are deviations for future insufficiency docking, can cause larger constructional difficulties to the docking of later stage pipeline, expend a large amount of people
Work.
Invention content
The technical problems to be solved in the utility model is:It is electrically pre- to overcome the deficiencies of the prior art and provide a kind of assembled
The docking structure of preheating embedding line is stayed, which is used for assembled architecture construction field, can effectively prevent because of prefabricated components
Installation and pre-buried error, and there is the phenomenon that preheating embedding line can not dock, and pair of live pipeline can be effectively improved
Connect speed.
Technical solution is used by the utility model solves its technical problem:A kind of assembled wall electric set aside pre-embedded
Pipeline docking structure is arranged on cast-in-place including prefabricated components, site concrete, the first built-in pipe and the second built-in pipe, prefabricated components
Component side is provided with docking groove on the prefabricated components, and first built-in pipe and the second built-in pipe are separately positioned on prefabricated
In component and site concrete, and stretch into docking groove and be connected by connector.
In said program, after docking groove is set, to reserve adjustment space when the first built-in pipe of docking and the second built-in pipe,
Can effectively prevent causing both threads pipe that can not dock because of deviation, and set after connector can so that when installation be directed to
The adjusting range bigger of deviation.
Further, the docking groove is arranged on the side that prefabricated components lean on site concrete side.Docking groove is exposed cast-in-place
Component, it is convenient that docking construction is carried out to the first built-in pipe and the second built-in pipe.
Further, opening area of the docking groove in prefabricated components side is 2 ~ 5 times of the first built-in pipe sectional area.It closes
The opening area of reason setting docking groove can not only meet adjustment demand during spool docking, and will not lead to that opening is too big and
Influence structural strength and beauty.
Further, the connector is flexible connecting member.Setting flexible connecting member can be improved when there is error, to first
The adjustment capability of built-in pipe and the second built-in pipe.
Further, the flexible connecting member is entirely or partially fabricated from a flexible material.Flexible material can ensure to connect
The adjustment of part and bending ability, the length of connector is longer made of flexible material, and flexible angle and range are also bigger.
Further, it is provided with locking member on the connector and the junction of the first built-in pipe and/or the second built-in pipe.
Specifically, locking member is clip, metal binding wire or binding strap, setting locking member can further prevent connecting
Part is detached from from the first built-in pipe and the second built-in pipe.
Further, it is provided with bulge loop on first built-in pipe and the second built-in pipe.One circle of setting or a few bulge loops, can
After preventing installation connecting element, connector is detached from from the first built-in pipe and the second built-in pipe.
Further, the connector is provided at both ends with articulation.Articulation is provided on connector, in the first built-in pipe
Respective threaded is set on the second built-in pipe, only needs swivelling union when mounted, you can by connector and the first built-in pipe and
Second built-in pipe is connected.
Further, the prefabricated components and site concrete are split installation structure.
Further, the prefabricated components are dry wall, precast beam, prefabricated post or prefabricated board.
Further, the site concrete is cast-in-place wall, Cast-in-situ Beam, Bars In Poured Concrete Slab or cast-in-place column.
A kind of advantageous effect of the docking structure of the electrical set aside pre-embedded pipeline of assembled of the utility model:This docking structure is used
In assembled architecture construction field, the installation because of prefabricated components and pre-buried error can be effectively prevent, and preheating embedding line occurs
The phenomenon that can not docking, and the docking speed of live pipeline can be effectively improved.
Description of the drawings
The structure diagram of the docking structure of the electrical set aside pre-embedded pipeline of assembled in Fig. 1-embodiment 1;
The structure diagram of the docking structure of the electrical set aside pre-embedded pipeline of assembled in Fig. 2-embodiment 2;
The close-up schematic view of A is identified in Fig. 3-Fig. 2;
First built-in pipe and the connection diagram of the second built-in pipe and connector in Fig. 4-embodiment 2;
First built-in pipe and the connection diagram of the second built-in pipe and connector in Fig. 5-embodiment 2;
In figure:1-site concrete, the 2-the second built-in pipe, 3-prefabricated components, the 4-the first built-in pipe, 5-connector,
6-docking groove, 7-bulge loop, 8-locking member, 9-articulation.
Specific embodiment
The utility model is described in further detail with reference to the accompanying drawings and embodiments.
Embodiment 1
With reference to Fig. 1:In the present embodiment,
A kind of assembled wall electric set aside pre-embedded pipeline docking structure, it is pre- including prefabricated components 3, site concrete 1, first
Pipe laying and the second built-in pipe, prefabricated components 3 are arranged on 1 side of site concrete, docking groove 6, institute are provided on the prefabricated components 3
It states the first built-in pipe and the second built-in pipe is separately positioned in prefabricated components 3 and site concrete 1, and stretch into docking groove 6 and lead to
Connector 5 is crossed to be connected.
It is empty to reserve adjustment when the first built-in pipe 4 of docking and the second built-in pipe 2 after docking groove 6 is set in said program
Between, it can effectively prevent causing both threads pipe that can not dock because of deviation.
The docking groove 6 is arranged on the side that prefabricated components 3 lean on 1 side of site concrete.Docking groove 6 is exposed into site concrete
1, it is convenient that docking construction is carried out to the first built-in pipe 4 and the second built-in pipe 2.
Opening area of the docking groove 6 in 3 side of prefabricated components is 2 times of the first built-in pipe sectional area.Rationally setting
The opening area of docking groove 6 can not only meet adjustment demand during spool docking, but also opening will not be caused to influence greatly very much
Structural strength and beauty.
First built-in pipe and the second built-in pipe are connected by connector 5.Setting connector 5, which can improve, there is error
When, to the adjustment capability of the first built-in pipe 4 and the second built-in pipe 2.
The prefabricated components 3 and site concrete 1 are split installation structure, and the prefabricated components 3 and site concrete 1 are distinguished
For dry wall and cast-in-place wall.
In the present embodiment, the docking connection in docking groove 6 by the first built-in pipe 4 and the second built-in pipe 2, and be provided with
Fixed connector 5 will be connected, can effectively prevent causing both threads pipe that can not dock because of deviation.
Embodiment 2:
Compared with Example 1, there are following for a kind of docking structure of the electrical set aside pre-embedded pipeline of assembled of the present embodiment
It is different:
The connector 5 is using integral type flexible connecting member made of soft material, when the first built-in pipe 4 and second is pre-
When the error of pipe laying 2 is larger, integral type connector 5 made of soft material has larger bending ability and adjustment capability.
As shown in figure 3, being provided with bulge loop 7 on the first built-in pipe 4 and the second built-in pipe 2, it can equally prevent installation from connecting
After fitting 5, connector 5 is detached from from the first built-in pipe 4 and the second built-in pipe 2.
It, can as shown in Figure 4 in order to further strengthen the bonding strength of 5 and first built-in pipe 4 of connector and the second built-in pipe 2
To set locking member 8 in junction, locking member 8 can be the common locking tools such as clip, metal binding wire or binding strap.
As shown in figure 5, in order to improve installation speed, articulation 9 is provided at both ends in connector 5, in 4 He of the first built-in pipe
Respective threaded is set on second built-in pipe 2, only needs swivelling union 9 when mounted, you can by 5 and first built-in pipe 4 of connector
It is connected with the second built-in pipe 2.
Above-mentioned all embodiments are only the technical concepts and features for illustrating the utility model, and its object is to allow be familiar with this
The personage of technology can understand the content of the utility model and be implemented, and the protection model of the utility model can not be limited with this
It encloses, all equivalent change or modifications substantially made according to the spirit of the present invention should all cover the protection model in the utility model
Within enclosing.
Claims (10)
1. a kind of docking structure of the electrical set aside pre-embedded pipeline of assembled, including prefabricated components, site concrete, the first built-in pipe and
Second built-in pipe, prefabricated components are arranged on site concrete side, it is characterised in that:Docking groove is provided on the prefabricated components,
First built-in pipe and the second built-in pipe are separately positioned in prefabricated components and site concrete, and stretch into docking groove and pass through
Connector is connected.
2. the docking structure of the electrical set aside pre-embedded pipeline of assembled as described in claim 1, it is characterised in that:The docking groove is set
Put the side that site concrete side is leaned in prefabricated components.
3. the docking structure of the electrical set aside pre-embedded pipeline of assembled as claimed in claim 2, it is characterised in that:The docking groove exists
The opening area of prefabricated components side is 2 ~ 5 times of the first built-in pipe sectional area.
4. the docking structure of the electrical set aside pre-embedded pipeline of the assembled as described in claim 1 ~ 3 any one, it is characterised in that:Institute
Connector is stated as flexible connecting member.
5. the docking structure of the electrical set aside pre-embedded pipeline of assembled as claimed in claim 4, it is characterised in that:The flexible connection
Part is entirely or partially fabricated from a flexible material.
6. the docking structure of the electrical set aside pre-embedded pipeline of assembled as claimed in claim 4, it is characterised in that:The connector with
Locking member is provided on the junction of first built-in pipe and/or the second built-in pipe.
7. the docking structure of the electrical set aside pre-embedded pipeline of assembled as claimed in claim 4, it is characterised in that:Described first is pre-buried
Bulge loop is provided on pipe and the second built-in pipe.
8. the docking structure of the electrical set aside pre-embedded pipeline of assembled as claimed in claim 4, it is characterised in that:The connector two
End is provided with articulation.
9. the docking structure of the electrical set aside pre-embedded pipeline of the assembled as described in claim 1 ~ 3 any one, it is characterised in that:Institute
It is split installation structure to state prefabricated components and site concrete.
10. the docking structure of the electrical set aside pre-embedded pipeline of assembled as claimed in claim 9, it is characterised in that:The prefabricated structure
Part is dry wall, precast beam, prefabricated post or prefabricated board;The site concrete is cast-in-place wall, Cast-in-situ Beam, Bars In Poured Concrete Slab or cast-in-place
Column.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721610558.7U CN207526144U (en) | 2017-11-28 | 2017-11-28 | A kind of docking structure of the electrical set aside pre-embedded pipeline of assembled |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721610558.7U CN207526144U (en) | 2017-11-28 | 2017-11-28 | A kind of docking structure of the electrical set aside pre-embedded pipeline of assembled |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207526144U true CN207526144U (en) | 2018-06-22 |
Family
ID=62580476
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721610558.7U Active CN207526144U (en) | 2017-11-28 | 2017-11-28 | A kind of docking structure of the electrical set aside pre-embedded pipeline of assembled |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207526144U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110359580A (en) * | 2019-08-19 | 2019-10-22 | 常州工程职业技术学院 | Prefabricated assembled composite steel concrete column component node connection structure and method for protecting support |
-
2017
- 2017-11-28 CN CN201721610558.7U patent/CN207526144U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110359580A (en) * | 2019-08-19 | 2019-10-22 | 常州工程职业技术学院 | Prefabricated assembled composite steel concrete column component node connection structure and method for protecting support |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205444613U (en) | Be applied to prefabricated coincide floor connecting piece of assembled steel construction building | |
CN207526144U (en) | A kind of docking structure of the electrical set aside pre-embedded pipeline of assembled | |
CN107044177A (en) | A kind of assembly concrete shear wall fractionation, assembled attachment structure and connection method | |
CN201794164U (en) | Reinforced guy rope intersecting joint | |
CN110424529B (en) | Prefabricated cantilever beam balcony and construction method | |
CN101892708A (en) | Inserting plate type welding through node | |
CN105317168A (en) | Split-type steel bar sleeve full-grouting joint | |
CN105089182B (en) | A kind of concrete partition system and its construction method for steel construction | |
CN207063180U (en) | A kind of installation steel bar connecting joints of overall assembled balcony component | |
CN111456233B (en) | Prefabricated assembled concrete beam column joint structure and construction method thereof | |
CN103741801B (en) | A kind of balcony slab and the attachment structure of composite beam | |
CN104005476B (en) | Be easy to fabrication and installation precast frame system and construction method | |
CN205822451U (en) | A kind of prefabricated assembled concrete composite beam docking connecting structure | |
CN109441016A (en) | Prefabricated concrete structure column steel pipe socket shell ring point and preparation method thereof | |
CN207121999U (en) | A kind of precast concrete connector | |
CN103924687A (en) | Connection method of steel plate-concrete composite shear wall and concrete shear wall | |
CN208650281U (en) | Combined type connector | |
CN205857403U (en) | Building wall board connects and piece structure | |
CN109555232B (en) | Precast beam mortise and tenon joint connects | |
CN209742091U (en) | PC component node connection structure | |
CN208122059U (en) | A kind of prefabricated whole slab assembly dark pipe laying system of building and its prefabricated whole slab | |
CN205840006U (en) | A kind of shingle nail with cantilevered plate and the attachment structure of floorboard | |
CN205276692U (en) | Grout cover tubular construction is connected to disconnect -type | |
CN209179285U (en) | A kind of full prefabricated PC concrete two-way slab structure | |
CN215211553U (en) | Assembled prefabricated component combination |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20210305 Address after: 410000 Junction of Lusong Road and Dongfanghong Road, Changsha High-tech Development Zone, Changsha City, Hunan Province Patentee after: CHANGSHA BROAD HOMES INDUSTRIAL GROUP Co.,Ltd. Address before: 271000 north of Xingye street, east of Tai'an, Daiyue, Shandong. Patentee before: TAIAN LIANQIANG YUANDA RESIDENTIAL INDUSTRY Co.,Ltd. Patentee before: CHANGSHA BROAD HOMES INDUSTRIAL GROUP Co.,Ltd. |