CN109441016A - Prefabricated concrete structure column steel pipe socket shell ring point and preparation method thereof - Google Patents

Prefabricated concrete structure column steel pipe socket shell ring point and preparation method thereof Download PDF

Info

Publication number
CN109441016A
CN109441016A CN201811563804.7A CN201811563804A CN109441016A CN 109441016 A CN109441016 A CN 109441016A CN 201811563804 A CN201811563804 A CN 201811563804A CN 109441016 A CN109441016 A CN 109441016A
Authority
CN
China
Prior art keywords
column
base plate
reserved
upper column
substrate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811563804.7A
Other languages
Chinese (zh)
Other versions
CN109441016B (en
Inventor
黄振宇
范时勇
周英武
隋莉莉
邢锋
张昊
邓伟雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen University
Original Assignee
Shenzhen University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen University filed Critical Shenzhen University
Priority to CN201811563804.7A priority Critical patent/CN109441016B/en
Publication of CN109441016A publication Critical patent/CN109441016A/en
Application granted granted Critical
Publication of CN109441016B publication Critical patent/CN109441016B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements
    • E04C5/163Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

本发明公开了一种装配式混凝土结构柱钢管套筒节点及其制作方法,节点的下柱连接组件包括下基板和下柱连接管,下柱连接管的下端连接于下基板的上表面,下基板的下表面承载于下柱的上表面,下柱预留的纵筋穿过下基板的纵筋孔;上柱连接组件包括上基板、上柱外管及嵌合在上柱外管内部的上柱内管,上基板的上表面连接上柱的下表面,上柱预留的纵筋穿过上基板的纵筋孔,上柱外管的上端连接于上柱基板的下表面,上柱外管的外轮廓呈适应下基板的外轮廓设计,上柱外管的下端连接于下基板的上表面边缘处,且下柱连接管进入上柱内管的内部空间,上柱连接组件的侧面可注入超高性能混凝土浆料以形成节点。本发明安装方便迅速,能大大降低施工时间和操作难度。

The invention discloses an assembled concrete structure column steel pipe sleeve joint and a manufacturing method thereof. The lower surface of the base plate is carried on the upper surface of the lower column, and the longitudinal ribs reserved for the lower column pass through the longitudinal rib holes of the lower base plate; The inner tube of the upper column, the upper surface of the upper base plate is connected to the lower surface of the upper column, the longitudinal ribs reserved for the upper column pass through the longitudinal rib holes of the upper base plate, the upper end of the outer tube of the upper column is connected to the lower surface of the upper column base plate, the upper column The outer contour of the outer tube is designed to adapt to the outer contour of the lower base plate, the lower end of the outer tube of the upper column is connected to the edge of the upper surface of the lower base plate, and the lower column connecting tube enters the inner space of the inner tube of the upper column, and the side surface of the upper column connecting assembly Ultra high performance concrete grout can be injected to form nodes. The invention is convenient and quick to install, and can greatly reduce construction time and operation difficulty.

Description

Prefabricated concrete structure column steel pipe socket shell ring point and preparation method thereof
Technical field
The invention patent belongs to prefabricated concrete structure field in civil engineering, is related to a kind of easy for installation rapid, energy The construction time is substantially reduced, prefabricated concrete structure column steel pipe socket shell ring point of efficiency of construction and preparation method thereof is improved.
Background technique
Assembled architecture has the function of design diversity, modernization, technicalization, production (production) industrialization, construction assembly The advantages that change, time optimization, systematization, the more personalized and cost of design and efficiency are optimised, develops assembled architecture It is the important channel for realizing building industrialization, is the direction of China's future architecture industry development, and the heat currently studied both at home and abroad One of point problem, and the switching performance of prefabricated components intermediate node is the key that influence integrality performance of the structure.
China " prefabricated concrete structure technical regulation " (JGJ1-2014) (referred to as " regulation ") suggestion vertical member (wall, Column) connection type mainly have reinforcing bar grouting connection and reinforcing bar slurry anchor overlap joint connection etc. modes.Overhanging steel is also reserved in engineering Muscle forms the concrete joint of assembled integral by rear pouring concrete.
Reinforcing bar grouting connection and reinforcing bar slurry anchor overlap joint connection need in advance to reserve the reinforcing bar of column both ends or one end one section with Just it docks, however this method is higher to required precision, it is desirable that two end bars or the necessary centering of reinforcing bar and reserving hole, especially When overlap joint number of steel bars is numerous, grouting connection and reinforcing bar are anchored quality and are difficult to ensure.
The shortcomings that overcome the above technology, the present invention propose the node between a kind of Novel steel telescoping column and column, this section The square steel sleeve of column one end need to be only inserted into the sleeve of another styletable by point, then be filled out with high-strength grout, in connecting node The effect of the mutual mechanical snap of concrete and the protrusion being welded in sleeve (shear connector) can guarantee the enough shearing resistance carryings of node Power.It avoids traditional reinforcing bar grout sleeve connection from needing the process of a large amount of apertures and check and correction hole, decreases the wave of construction auxiliary material Take.
Summary of the invention
It is easy for installation rapidly that the object of the present invention is to provide one kind, can substantially reduce construction time and operation difficulty, raising Prefabricated concrete structure column steel pipe socket shell ring point of efficiency of construction and preparation method thereof.
To achieve the goals above, technical solution provided by the invention are as follows: the invention discloses a kind of assembly concretes Structural column steel pipe socket shell ring point, the node include:
Lower prop connection component, the lower prop connection component include lower substrate and lower column connecting pipe, the lower column connecting pipe Lower end is connected at the upper face center of the lower substrate, and the lower surface of the lower substrate is carried on the upper surface of lower prop, described The reserved vertical muscle of lower prop passes through the vertical muscle hole of the lower substrate;
Upper prop connection component, the upper prop connection component include upper substrate, upper prop outer tube and are entrenched in the upper prop outer tube Internal upper prop inner tube, the lower surface of the upper surface connection upper prop of the upper substrate, the reserved vertical muscle of the upper prop passes through described The vertical muscle hole of upper substrate, the upper end of the upper prop outer tube are connected to the lower surface of the upper prop substrate, the upper prop outer tube it is outer For profile in the outer profile design for adapting to the lower substrate, the lower end of the upper prop outer tube is connected to the upper surface side of the lower substrate At edge, and the lower column connecting pipe enters the inner space of the upper prop inner tube, and the side of the upper prop connection component can be injected Ultra-high performance concrete slurry is to form the node.
Fluted, the lower end insertion of the upper prop connection component is opened up around the circle of upper surface outer edge one of the lower substrate It is attached in the groove.
The vertical muscle that the reserved vertical muscle of the upper prop and lower prop are reserved is equipped with external screw thread, and is every reserved vertical muscle configuration two A stop nut, and the upper substrate and lower substrate are limited by the stop nut respectively.
Several first lateral projections are equably laid with along the lower column connecting pipe outer wall longitudinal gap, and described first is horizontal To protrusion in being arranged for outer wall one week around the lower column connecting pipe.
Several second lateral projections are equably laid with along the upper prop inner tube wall longitudinal gap, and described second is lateral Protrusion in being arranged around the upper prop inner tube for inner wall one week.
The side lower end of the upper prop outer tube is equipped with injected hole, and upper end is equipped with slurry outlet.
To achieve the goals above, the invention also discloses a kind of systems of prefabricated concrete structure column steel pipe socket shell ring point Make method, includes the following steps:
The lower surface of the lower substrate of the lower prop connection component is carried on the upper surface of lower prop, and passed through by step 1 The lower surface of the lower substrate is connected to the lower prop by the vertical muscle hole that the reserved vertical muscle of the lower prop passes through the lower substrate Upper surface;
Step 2, the lower surface that the upper surface of the upper substrate of the upper prop connection component is connected to the upper prop, it is described on The lower end of column outer tube is connected at the top surface edge of the lower substrate, and the lower column connecting pipe enters the upper prop inner tube Inner space, the upper prop connection component are injected laterally ultra-high performance concrete slurry to form the node.
In step 1, further includes: the vertical muscle for reserving the lower prop makes external screw thread, and the reserved vertical muscle of the lower prop passes through When the vertical muscle hole of the lower substrate, by configuring stop nut on the vertical muscle that the lower prop is reserved, and pass through the limit spiral shell Mother limits the lower substrate;
In step 2, further includes: the vertical muscle for reserving the upper prop makes external screw thread, and the reserved vertical muscle of the upper prop passes through When the vertical muscle hole of the upper substrate, by configuring stop nut on the vertical muscle that the upper prop is reserved, and pass through the limit spiral shell Mother limits the upper substrate.
Beneficial effects of the present invention:
Node connection of the present invention is easy, then upper prop connection component need to be only aligned in splicing by scene with lower prop connection component Inject grouting material.Reduce a large amount of reinforcing bar reserving hole and steel reinforcement abutting joints process, thus reinforced hole when solving anchor slurry connector Hole misalignment and bring construction is inconvenient and safety problem.
The present invention inherits the advantages of assembled architecture, precast concrete column pour and the production of steel bushing node is all It is completed in factory, scene only need to carry out a small amount of construction operation, and it is time saving and energy saving, avoid live welding for steel structure, bolt connects The process connect.
Steel bushing pipe node can substitute permanent template of the wooden form as rear pouring concrete in the present invention, reduce construction Expense and difficulty of construction avoid the waste to construction auxiliary material.
Steel bushing pipe node can be referred to as " Qiang Jiedian ", meet Qiang Jiedian in engineering compared with concrete in the present invention, The earthquake-resistant structure requirement of " weak component ".
Through the following description and in conjunction with the attached drawings, the present invention will become more fully apparent, these attached drawings are used to explain the present invention Embodiment.
Detailed description of the invention
Fig. 1 show the schematic diagram of the lower prop connection component of prefabricated concrete structure column steel pipe socket shell ring point of the present invention.
Fig. 2 show the schematic diagram of the upper prop connection component of prefabricated concrete structure column steel pipe socket shell ring point of the present invention.
Fig. 3 show the schematic diagram of the section structure of prefabricated concrete structure column steel pipe socket shell ring point of the present invention.
Specific embodiment
The embodiment of the present invention described referring now to the drawings, similar element numbers represent similar element in attached drawing.Such as Upper described, with reference to 1,2,3, the embodiment of the invention discloses a kind of prefabricated concrete structure column steel pipe socket shell ring point, the sections It puts and includes:
Lower prop connection component 10, the lower prop connection component 10 include lower substrate 1 and lower column connecting pipe 2, and the lower prop connects The lower end of adapter tube 2 is connected at the upper face center of the lower substrate 1, and the lower surface of the lower substrate 1 is carried on the upper of lower prop 3 Surface, and be equipped with vertical muscle hole (not showing on figure) through the upper surface and the lower surface of the lower substrate 1, the reserved vertical muscle of the lower prop 4 pass through the vertical muscle hole of the lower substrate 1;The lower column connecting pipe 2 of the lower prop connection component 10 as shown in Figure 1 is steel Structural tube, the lower substrate 1 is equally steel baseplate, and the lower column connecting pipe 2 is welded on the lower substrate 1, and described The position that the corresponding vertical muscle of lower substrate 1 stretches out opens up the vertical muscle hole of the lower substrate 1, to allow the vertical muscle to pass through institute The vertical muscle hole of lower substrate 1 is stated, so that the lower substrate 1 is well secured to the upper surface of the lower prop 3.
Upper prop connection component 20, the upper prop connection component 20 include upper substrate 15, upper prop outer tube 5 and are entrenched on described Upper prop inner tube 6 inside column outer tube 5, the lower surface of the upper surface connection upper prop 16 of the upper substrate 15, what the upper prop was reserved Vertical muscle 17 passes through the vertical muscle hole of the upper substrate 15, and the upper end of the upper prop outer tube 5 is connected to the following table of the upper prop substrate 15 Face, the outer profile of the upper prop outer tube 5 is in the outer profile design for adapting to the lower substrate 1, the lower end connection of the upper prop outer tube 5 At the top surface edge of the lower substrate 1, and the lower column connecting pipe 2 enters the inner space of the upper prop inner tube 6, described The side of upper prop connection component 20 can inject ultra-high performance concrete slurry to form the node.It is as shown in Figure 2 it is described on Column connection component 20, the upper prop outer tube 5 and upper prop inner tube 6 are steel structure pipes, and the upper prop inner tube 6 is welded on described It is attached at the inner wall of column outer tube 5.Since the outer profile of the upper prop outer tube 5 is set in the outer profile for adapting to the lower substrate 1 Meter, therefore, when the lower end of the upper prop outer tube 5 is connected at the top surface edge of the lower substrate 1, the lower prop connection component 10 and upper prop connection component 20 connect after, the effect of adaptability transition can be played.
With reference to Fig. 1, the circle of upper surface outer edge one around the lower substrate 1 opens up fluted 7, the upper prop connection component 20 lower end is inserted into the groove 7 and is attached.The shape of the groove 7 is in the outer profile with the upper prop connection component 20 The adaptable setting of shape.The groove 7, which is arranged, can greatly facilitate the fixed and positioned of the upper prop connection component 20, and Also it can be improved the connection concertedness between the upper prop connection component 20 and the lower prop connection component 10.Specifically, described The lower end of the upper prop outer tube 5 of upper prop connection component 20 is inserted into the groove 7 and is attached, and the shape of the groove 7 is in It is adapted with the outer contour shape of the upper prop outer tube 5.So set, the upper prop connection component 20 is enabled to be lifted on institute When stating on lower prop connection component 10, can be realized it is quick, accurate, position securely, in next step operate, get ready.
With reference to Fig. 1, the vertical muscle 4 that the reserved vertical muscle 17 of the upper prop and lower prop are reserved is equipped with external screw thread, and pre- for every It stays vertical muscle to configure two stop nuts 8, and the upper substrate 15 and lower substrate 1 is limited by the stop nut 8 respectively Position.Specifically, the reserved vertical muscle 17 of the upper prop is equipped with external screw thread, and the reserved vertical muscle 17 of the upper prop passes through the upper substrate 1 Vertical muscle hole when, by the lower prop reserve vertical muscle 4 on configuration two stop nuts 8 lower substrate 15 is consolidated Fixed, the lower substrate 15 is limited between two stop nuts 8.It should be noted that the vertical muscle 17 that the upper prop is reserved End be arranged external screw thread, to be threadedly coupled between two stop nuts 8, and the upper substrate 15 is limited in institute It states between two stop nuts 8.It so can greatly reinforce connecting between the upper prop connection component 20 and upper prop 16 Concertedness, it is ensured that the phenomenon that node accurate positioning during the installation process is not in displacement.
Similarly, the reserved vertical muscle 4 of the lower prop is equipped with external screw thread, and the reserved vertical muscle 4 of the lower prop passes through the lower substrate 1 Vertical muscle hole when, by the lower prop reserve vertical muscle 4 on configuration two stop nuts 8 lower substrate 1 is fixed, The lower substrate 1 is limited between two stop nuts 8.It should be noted that the end for the vertical muscle 4 that the lower prop is reserved External screw thread is set, to be threadedly coupled between two stop nuts 8, and the lower substrate 1 is limited in described two Between stop nut 8.It so can greatly reinforce the concertedness connecting between the lower prop connection component 10 and lower prop 3, The phenomenon that ensuring node accurate positioning during the installation process, being not in displacement.
With reference to Fig. 1 and Fig. 3, it is laterally convex that several first are equably laid with along the lower 2 outer wall longitudinal gap of column connecting pipe 12 are played, and first lateral projection 12 is in being arranged for outer wall one week around the lower column connecting pipe 2.It should be noted that described The section of lower column connecting pipe 2 can be round or rectangle, and therefore, the shape of first lateral projection 12 should will adapt to institute The shape setting of lower column connecting pipe 2 is stated, and material can be regular reinforcement, and be welded on the outer wall of the lower column connecting pipe 2 On.
With reference to Fig. 2 and 3, several second lateral projections 11 are equably laid with along the 6 inner wall longitudinal gap of upper prop inner tube, And second lateral projection 11 is in being arranged for inner wall one week around the upper prop inner tube 6.It should be noted that the upper prop inner tube 6 interior shape can be round or rectangle, and therefore, the shape of second lateral projection 11 should will adapt to the upper prop The shape of inner tube 6 is arranged, and material can be regular reinforcement, and be welded on the inner wall of the upper prop inner tube 6.
It should be noted that by be arranged on the outer wall of the lower column connecting pipe 2 first lateral projection 12 and it is described on Second lateral projection 11 is set on the inner wall of column inner tube 6, and first lateral projection 12 and second lateral projection 11 are equal It can be welded in advance in factory, therefore after cement slurry pours into the node and conserves molding, can greatly improve node Longitudinal draw knot force, be particularly suitable in the pipeline of ocean engineering or the pillar of high-rise, because of two kinds of applied fields Pillar in conjunction may due to wave or wind-force effect and by biggish load, and in skyscraper, top post It may be similarly subjected to great pulling force at node, therefore need since wind-force or seismic factors are by by great pulling force Want can the great node of tensile strength, can guarantee the safety of node, and node of the invention is due to being provided with described One lateral projection 12 and the second lateral projection 11 when being used cooperatively with super high strength concrete, act on energy by mutual mechanical snap Biggish tensile bearing capacity is enough provided, to guarantee that improving node has enough intensity.
It should be noted that the section of first lateral projection 12 and the second lateral projection 11 may each be it is round or Rectangular protrusion can be welded on the outer wall of the lower column connecting pipe 2 by reinforcing bar coiling into shape is adapted to, And it is welded on the inner wall of the upper prop inner tube 6.
In one embodiment, as shown in Fig. 2, the side lower end of the upper prop outer tube 5 is equipped with injected hole 13, upper end is equipped with Starch hole 14.When to intra-node slip casting, ultra-high performance concrete slurry is injected from the injected hole 13, it is ensured that the high property of injection Energy concrete slurry can fill the entire space of full node, then come out from the slurry outlet 14, can stop slip casting.
To achieve the goals above, the embodiment of the invention also discloses a kind of prefabricated concrete structure column steel pipe socket shell rings The production method of point, includes the following steps:
Step 1, the lower column connecting pipe that outer wall is equably laid with to first lateral projection be welded in it is described under On substrate, and open up on the lower substrate the vertical muscle of the lower substrate of the upper surface and the lower surface through the lower substrate The lower surface of the lower substrate, is carried on the upper surface of lower prop by hole, and by the vertical muscle that the lower prop is reserved pass through it is described under The lower substrate is bolted in the upper surface of the lower prop by the vertical muscle hole of substrate;It should be noted that described first is lateral Protrusion is regular reinforcement, and is welded on the outer wall of the lower column connecting pipe, and above each step can be made in advance in factory Make, and transported after factory makes to construction site, the vertical muscle that the lower prop is reserved passes through the vertical muscle of the lower substrate The lower surface of the lower substrate is connected to the upper surface of the lower prop by hole, so, it is understood that the lower prop connection group The in-site installation of part is very simple and efficient, significantly reduces field operation difficulty and labor intensity, and the scene of substantially increasing is The efficiency of confession.
Step 2, the lower surface that the upper surface of the upper substrate of the upper prop connection component is connected to the upper prop, it is described on The lower end of column outer tube is connected at the top surface edge of the lower substrate, and the lower column connecting pipe enters the upper prop inner tube Inner space, the upper prop connection component are injected laterally ultra-high performance concrete slurry to form the node.
It should be noted that the upper prop inner tube welds the second lateral projection, second lateral projection is regular reinforcement, And it is welded at the inside of the upper prop inner tube, above each step can be made in factory's pre-production in factory It is transported later to construction site, is directly lifted on upper prop on the lower prop connection component together with the upper prop connection component, and And it is fluted due to being arranged on the lower substrate, it is convenient for fixed and connects.
It should be noted that the upper prop connection component includes upper prop inner tube and upper prop outer tube, the upper prop inner tube be Factory is welded in the upper prop outer tube in advance.
Connected it should be noted that the lower end of the upper prop outer tube of the upper prop connection component is inserted into the groove It connects, the shape of the groove is in be adapted with the outer contour shape of the upper prop outer tube.So set, enabling to the upper prop When connection component is lifted on the lower prop connection component, can be realized it is quick, accurate, position securely, in next step operate, It gets ready.
It should be noted that the vertical muscle that can in advance reserve the lower prop makes external screw thread, the lower prop is reserved to be indulged When muscle passes through the vertical muscle hole of the lower substrate, by the vertical muscle that the lower prop is reserved two stop nuts of configuration under described Substrate is fixed, and the lower substrate is limited between described two stop nuts.Similarly, the upper prop is reserved in advance Vertical muscle makes external screw thread, when the reserved vertical muscle of the upper prop passes through the vertical muscle hole of the upper substrate, by reserved in the upper prop Vertical muscle on configuration two stop nuts the upper substrate is fixed, the upper substrate is limited in described two limit spiral shells Between mother.
It should be noted that by the way that the first lateral projection and the upper prop is arranged on the outer wall of the lower column connecting pipe Second lateral projection is set on the inner wall of inner tube, and first lateral projection and second lateral projection can exist in advance Factory's welding, therefore after cement slurry pours into the node and conserves molding, it can greatly improve longitudinal drawknot of node Power is particularly suitable in the pipeline of ocean engineering or the pillar of high-rise, because of the pillar in two kinds of applications May due to wave or wind-force effect and by biggish load, and in skyscraper, top post may be due to Wind-force or seismic factors are similarly subjected to great pulling force at node, it is therefore desirable to being capable of tension by by great pulling force The node of intensity maximum can guarantee the safety of node, and node of the invention is due to being provided with first lateral projection With the second lateral projection, when being used cooperatively with super high strength concrete, it is capable of providing by the effect of mutual mechanical snap biggish anti- Bearing capacity is drawn, to guarantee that improving node has enough intensity.
It should be noted that the section of first lateral projection and the second lateral projection may each be round or rectangular Protrusion, can directly be by reinforcing bar coiling into adapt to shape, be welded on the outer wall of the lower column connecting pipe, and weldering It connects on the inner wall of the upper prop inner tube.
In the production method of prefabricated concrete structure column steel pipe socket shell ring point provided by the invention, significantly reduces and apply Expenses of labour is used and difficulty of construction, substantially increases construction efficiency, simultaneously because upper prop connection outer tube through the invention is under Column connects inner tube and forms the cooperation of the protrusion in cavity, also avoids avoiding using outer wooden template to construction auxiliary material Waste.
The above disclosure is only a preferred embodiment of the invention, cannot limit the right of the present invention with this certainly Range, therefore according to equivalent variations made by scope of the present invention patent, it is still within the scope of the present invention.

Claims (8)

1.一种装配式混凝土结构柱钢管套筒节点,其特征在于,所述节点包括:1. an assembled concrete structure column steel pipe sleeve joint, is characterized in that, described joint comprises: 下柱连接组件,所述下柱连接组件包括下基板和下柱连接管,所述下柱连接管的下端连接于所述下基板的上表面中央处,所述下基板的下表面承载于下柱的上表面,所述下柱预留的纵筋穿过所述下基板的纵筋孔;A lower column connection assembly, the lower column connection assembly includes a lower base plate and a lower column connection pipe, the lower end of the lower column connection pipe is connected to the center of the upper surface of the lower base plate, and the lower surface of the lower base plate is carried on the lower the upper surface of the column, the longitudinal ribs reserved by the lower column pass through the longitudinal rib holes of the lower base plate; 上柱连接组件,所述上柱连接组件包括上基板、上柱外管及嵌合在所述上柱外管内部的上柱内管,所述上基板的上表面连接上柱的下表面,所述上柱预留的纵筋穿过所述上基板的纵筋孔,所述上柱外管的上端连接于所述上柱基板的下表面,所述上柱外管的外轮廓呈适应所述下基板的外轮廓设计,所述上柱外管的下端连接于所述下基板的上表面边缘处,且所述下柱连接管进入所述上柱内管的内部空间,所述上柱连接组件的侧面可注入超高性能混凝土浆料以形成所述节点。an upper column connection assembly, the upper column connection assembly includes an upper substrate, an upper column outer tube and an upper column inner tube embedded in the upper column outer tube, the upper surface of the upper substrate is connected to the lower surface of the upper column, The longitudinal ribs reserved for the upper column pass through the longitudinal rib holes of the upper base plate, the upper end of the upper column outer tube is connected to the lower surface of the upper column base plate, and the outer contour of the upper column outer tube is adapted to The outer contour of the lower base plate is designed, the lower end of the upper column outer tube is connected to the edge of the upper surface of the lower base plate, and the lower column connecting tube enters the inner space of the upper column inner tube, and the upper column The sides of the column connection assemblies may be injected with ultra high performance concrete grout to form the nodes. 2.如权利要求1所述的装配式混凝土结构柱钢管套筒节点,其特征在于,绕所述下基板的上表面外边缘处一圈开设有凹槽,所述上柱连接组件的下端插入所述凹槽内进行连接。2. The prefabricated concrete structural column steel pipe sleeve joint according to claim 1, wherein a groove is formed around the outer edge of the upper surface of the lower base plate, and the lower end of the upper column connecting component is inserted into The connection is made in the groove. 3.如权利要求1所述的装配式混凝土结构柱钢管套筒节点,其特征在于,所述上柱预留的纵筋及下柱预留的纵筋均设有外螺纹,并为每根预留纵筋配置两个限位螺母,并分别通过所述限位螺母对所述上基板及下基板进行限位。3. The prefabricated concrete structural column steel pipe sleeve joint of claim 1, wherein the longitudinal bars reserved for the upper column and the longitudinal bars reserved for the lower column are provided with external threads, and each The reserved longitudinal ribs are configured with two limit nuts, and the upper substrate and the lower substrate are respectively limited by the limit nuts. 4.如权利要求1所述的装配式混凝土结构柱钢管套筒节点,其特征在于,沿所述下柱连接管外壁纵向间隔均匀地布设有若干第一横向凸起,且所述第一横向凸起呈绕所述下柱连接管的外壁一周设置。4 . The fabricated concrete structural column steel pipe sleeve joint according to claim 1 , wherein a plurality of first lateral protrusions are evenly spaced longitudinally along the outer wall of the lower column connecting pipe, and the first lateral The protrusions are arranged around the outer wall of the lower column connecting pipe. 5.如权利要求4所述的装配式混凝土结构柱钢管套筒节点,其特征在于,沿所述上柱内管内壁纵向间隔均匀地布设有若干第二横向凸起,且所述第二横向凸起呈绕所述上柱内管的内壁一周设置。5 . The fabricated concrete structural column steel pipe sleeve joint according to claim 4 , wherein a plurality of second transverse protrusions are evenly spaced along the inner wall of the upper column inner pipe, and the second transverse The protrusions are arranged around the inner wall of the inner tube of the upper column. 6.如权利要求5所述的装配式混凝土结构柱钢管套筒节点,其特征在于,所述上柱外管的侧面下端设有注浆孔,上端设有出浆孔。6 . The fabricated concrete structural column steel pipe sleeve joint according to claim 5 , wherein the lower end of the side surface of the upper column outer tube is provided with a grouting hole, and the upper end is provided with a grouting hole. 7 . 7.一种如权利要求6所述的装配式混凝土结构柱钢管套筒节点的制作方法,其特征在于,包括如下步骤:7. A method for making a fabricated concrete structural column steel pipe sleeve joint as claimed in claim 6, characterized in that, comprising the steps: 步骤1、将所述下柱连接组件的所述下基板的下表面承载于下柱的上表面,且通过所述下柱预留的纵筋穿过所述下基板的纵筋孔将所述下基板的下表面连接于所述下柱的上表面;Step 1. The lower surface of the lower base plate of the lower column connecting assembly is supported on the upper surface of the lower column, and the longitudinal rib reserved for the lower column passes through the longitudinal rib hole of the lower base plate to connect the the lower surface of the lower substrate is connected to the upper surface of the lower column; 步骤2、将所述上柱连接组件的上基板的上表面连接于所述上柱的下表面,所述上柱外管的下端连接于所述下基板的上表面边缘处,且所述下柱连接管进入所述上柱内管的内部空间,所述上柱连接组件的侧面注入超高性能混凝土浆料以形成所述节点。Step 2. Connect the upper surface of the upper substrate of the upper column connecting assembly to the lower surface of the upper column, the lower end of the outer tube of the upper column is connected to the edge of the upper surface of the lower substrate, and the lower The column connection pipe enters the inner space of the upper column inner pipe, and the side surface of the upper column connection assembly is injected with ultra-high performance concrete slurry to form the node. 8.如权利要求7所述的制作方法,其特征在于,8. The manufacturing method according to claim 7, characterized in that, 步骤1中,还包括:将所述下柱预留的纵筋制作外螺纹,所述下柱预留的纵筋穿过所述下基板的纵筋孔时,通过在所述下柱预留的纵筋上配置限位螺母,并通过所述限位螺母对所述下基板进行限位;In step 1, it also includes: making the longitudinal ribs reserved for the lower column into external threads, and when the longitudinal ribs reserved for the lower column pass through the longitudinal rib holes of the lower base plate, through the reserved longitudinal ribs on the lower column. A limit nut is arranged on the longitudinal rib, and the lower base plate is limited by the limit nut; 步骤2中,还包括:将所述上柱预留的纵筋制作外螺纹,所述上柱预留的纵筋穿过所述上基板的纵筋孔时,通过在所述上柱预留的纵筋上配置限位螺母,并通过所述限位螺母对所述上基板进行限位。In step 2, it also includes: making the longitudinal ribs reserved on the upper column into external threads, and when the longitudinal ribs reserved on the upper column pass through the longitudinal rib holes of the upper base plate, the vertical ribs reserved on the upper column A limit nut is arranged on the longitudinal rib, and the upper substrate is limited by the limit nut.
CN201811563804.7A 2018-12-20 2018-12-20 Assembled concrete structure column steel tube sleeve joint and manufacturing method thereof Active CN109441016B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811563804.7A CN109441016B (en) 2018-12-20 2018-12-20 Assembled concrete structure column steel tube sleeve joint and manufacturing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811563804.7A CN109441016B (en) 2018-12-20 2018-12-20 Assembled concrete structure column steel tube sleeve joint and manufacturing method thereof

Publications (2)

Publication Number Publication Date
CN109441016A true CN109441016A (en) 2019-03-08
CN109441016B CN109441016B (en) 2024-03-22

Family

ID=65559358

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811563804.7A Active CN109441016B (en) 2018-12-20 2018-12-20 Assembled concrete structure column steel tube sleeve joint and manufacturing method thereof

Country Status (1)

Country Link
CN (1) CN109441016B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113737945A (en) * 2021-09-17 2021-12-03 上海大学 Prefabricated assembled column connection node with hoop steel sleeve plate
CN114319980A (en) * 2021-11-23 2022-04-12 中国能源建设集团安徽省电力设计院有限公司 A concrete-filled steel tube and steel tube conversion node suitable for large-scale transmission towers
CN114658097A (en) * 2022-03-31 2022-06-24 上海市机械施工集团有限公司 Combined structure and construction method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU62622U1 (en) * 2005-07-19 2007-04-27 Открытое Акционерное Общество "Ленстройдеталь" REINFORCED REINFORCED CONCRETE STRUCTURE OF A MULTI-STOREY BUILDING, FRAMEWORK CONSTRUCTION OF A FRAME, INTERIOR ELEMENT
CN205134738U (en) * 2015-11-02 2016-04-06 上海市机械施工集团有限公司 Precast concrete post
CN106381926A (en) * 2016-10-28 2017-02-08 湖南大学 Detachable assembly type splicing node for reinforced concrete columns
CN106760054A (en) * 2017-03-01 2017-05-31 同济大学 Precast reinforced concrete shear wall
CN107327020A (en) * 2017-07-06 2017-11-07 能诚集团有限公司 A kind of concrete component attachment structure
CN206646642U (en) * 2016-12-27 2017-11-17 北京智慧云建科技有限公司 A kind of assembled architecture post and column connected node
CN206769051U (en) * 2017-04-14 2017-12-19 陈思萍 A kind of assembled integral column connected node
CN107989186A (en) * 2017-11-29 2018-05-04 厦门合立道工程设计集团股份有限公司 A kind of prefabricated concrete structure primary steel feather joint node and its construction method
CN209227902U (en) * 2018-12-20 2019-08-09 深圳大学 Steel pipe sleeve joints of prefabricated concrete structural columns

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU62622U1 (en) * 2005-07-19 2007-04-27 Открытое Акционерное Общество "Ленстройдеталь" REINFORCED REINFORCED CONCRETE STRUCTURE OF A MULTI-STOREY BUILDING, FRAMEWORK CONSTRUCTION OF A FRAME, INTERIOR ELEMENT
CN205134738U (en) * 2015-11-02 2016-04-06 上海市机械施工集团有限公司 Precast concrete post
CN106381926A (en) * 2016-10-28 2017-02-08 湖南大学 Detachable assembly type splicing node for reinforced concrete columns
CN206646642U (en) * 2016-12-27 2017-11-17 北京智慧云建科技有限公司 A kind of assembled architecture post and column connected node
CN106760054A (en) * 2017-03-01 2017-05-31 同济大学 Precast reinforced concrete shear wall
CN206769051U (en) * 2017-04-14 2017-12-19 陈思萍 A kind of assembled integral column connected node
CN107327020A (en) * 2017-07-06 2017-11-07 能诚集团有限公司 A kind of concrete component attachment structure
CN107989186A (en) * 2017-11-29 2018-05-04 厦门合立道工程设计集团股份有限公司 A kind of prefabricated concrete structure primary steel feather joint node and its construction method
CN209227902U (en) * 2018-12-20 2019-08-09 深圳大学 Steel pipe sleeve joints of prefabricated concrete structural columns

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113737945A (en) * 2021-09-17 2021-12-03 上海大学 Prefabricated assembled column connection node with hoop steel sleeve plate
CN114319980A (en) * 2021-11-23 2022-04-12 中国能源建设集团安徽省电力设计院有限公司 A concrete-filled steel tube and steel tube conversion node suitable for large-scale transmission towers
CN114658097A (en) * 2022-03-31 2022-06-24 上海市机械施工集团有限公司 Combined structure and construction method thereof

Also Published As

Publication number Publication date
CN109441016B (en) 2024-03-22

Similar Documents

Publication Publication Date Title
CN108678218B (en) Assembly type concrete shear wall based on multipurpose thin-wall steel pipe and construction method thereof
CN108560544B (en) Sleeve connection assembled pile foundation and construction method thereof
CN202391019U (en) End part thickened grouting connector of steel bar
CN108951847B (en) UHPC-based precast concrete frame structure system and construction method thereof
CN107254937B (en) A prefabricated energy-dissipating beam joint with built-in X-shaped low-yield point steel connectors
CN109025064A (en) Method for manufacturing and installing prefabricated concrete column and column assembly type connecting node
CN206279628U (en) A kind of precast concrete reinforcing bar grouting connecting structure
CN102116075B (en) Novel joint prepared from cement grout and steel bars
CN205206033U (en) Frame post connected node suitable for prefabricated assembly building
CN109441016A (en) Prefabricated concrete structure column steel pipe socket shell ring point and preparation method thereof
CN109235781B (en) Self-centering structure and method for connecting prefabricated part steel bars through grouting sleeve
CN106760054B (en) Prefabricated reinforced concrete shear walls
CN107059911A (en) A kind of prefabricated assembled basis and its assemble method
WO2017096644A1 (en) Expanded-foot tubular pile having unfolding blade and piling method thereof
CN103075013A (en) Building construction steel bar connection structure and connection method
CN110593303B (en) Prefabricated reinforced concrete fixed buttress for thermal pipeline and construction method
CN108678287A (en) A kind of bar connecting full grout sleeve of slurry pin bank conjunction
CN113513015A (en) A kind of semi-prefabricated concrete reinforced cage underground continuous wall and construction method
CN209260897U (en) Combined connection node of fabricated concrete beam-column sleeve
CN207063226U (en) Precast reinforced concrete shear wall
CN102561600A (en) Steel bar splicing sleeve
CN108677731B (en) Rotary splicing structure and splicing method of cover beam and bridge pier
CN106149878A (en) Attachment structure at concrete frame structure prefabricated post and beam slab node and method
CN209227902U (en) Steel pipe sleeve joints of prefabricated concrete structural columns
CN109057031A (en) Assembly concrete-filled steel tube superposed column-girder construction system of built-in more steel pipes

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant