CN207499793U - Transformer high-voltage bushing upkeep operation frame - Google Patents

Transformer high-voltage bushing upkeep operation frame Download PDF

Info

Publication number
CN207499793U
CN207499793U CN201721459780.1U CN201721459780U CN207499793U CN 207499793 U CN207499793 U CN 207499793U CN 201721459780 U CN201721459780 U CN 201721459780U CN 207499793 U CN207499793 U CN 207499793U
Authority
CN
China
Prior art keywords
bushing
transformer high
body panel
operation frame
voltage bushing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721459780.1U
Other languages
Chinese (zh)
Inventor
沈心江
高琦
周晶
张瀚文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
Suzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd filed Critical Suzhou Power Supply Co of State Grid Jiangsu Electric Power Co Ltd
Priority to CN201721459780.1U priority Critical patent/CN207499793U/en
Application granted granted Critical
Publication of CN207499793U publication Critical patent/CN207499793U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Insulators (AREA)

Abstract

The utility model is related to a kind of transformer high-voltage bushing upkeep operation framves, including multiple supporting legs, it is arranged in a one-to-one correspondence in each supporting leg bottom and multiple wheels on working face, it is arranged in a one-to-one correspondence in each supporting leg bottom and positioned at multiple adjustable support feet of wheel side, it is set at the top of each supporting leg to fix the operation body panel of bushing, the cat ladder being set between operation body panel and working face, the corresponding first positioning hole of screw hole on multiple spacer flangers with bushing is offered on operation body panel, bushing is connected by the first bolt to match with screw hole and first positioning hole with operation body panel.Transformer high-voltage bushing upkeep operation frame further includes the retainer plate for selection that several internal diameters match from the spacer flanger of different bushings.The support transformer high-voltage bushing that the utility model can consolidate makes it keep vertical state, simple in structure, easy to use so as to which maintenance, the experiment for transformer high-voltage bushing provide safeguard.

Description

Transformer high-voltage bushing upkeep operation frame
Technical field
The utility model belongs to electric power apparatus examination field, and in particular to is examined with a kind of bushing to transformer The operation frame used when repairing.
Background technology
Bushing shell for transformer is the primary insulation device outside transformer tank, and the lead-out wire of transformer winding has to pass through insulation sleeve Pipe makes to insulate, while bushing shell for transformer also plays the work of fixed lead-out wire between lead-out wire and between lead-out wire and transformer case With.Transformer high-voltage bushing refers to 110kV, 220kV, 500kV casing, at present predominantly condenser-type terminal.Inside pipe casing constructs: The multi-layer cylindrical capacitor core formed using cable paper and aluminium foil screening electrodes is major insulation, and porcelain piece is as external insulation and transformer The container of oil;Casing is all-sealed structure, and internal transformer oil is absolute construction, with atmospheric isolation;Casing integrated connection uses Brute spring mechanical fasteners not only ensure to seal, but also compensation each section length caused by temperature change changes.Jacket exterior Structure:Top is terminal plate, pigtail splice, rain cover, oil meter, plug cock, conservator, upper insulator;Middle part is end shield, hanging ring, takes oil Valve, nameplate, air relief cock, central flange etc.;Lower part is lower insulator voltage equalizing ball.
At workshop and scene, to the bushing of transformer overhaul, test when, casing must be vertically disposed in specially With on operation frame.And the existing full fixed structure of operation frame generally use, and generally require to match double ladder or trolley etc. Device, use are very inconvenient.
Invention content
The purpose of this utility model is to provide a kind of transformer high-voltage bushing upkeep operation simple in structure, easy to use Frame.
In order to achieve the above objectives, the technical solution adopted in the utility model is:
A kind of transformer high-voltage bushing upkeep operation frame is used to vertically put when the bushing to transformer overhauls The bushing is put, the transformer high-voltage bushing upkeep operation frame includes multiple supporting legs, is arranged in a one-to-one correspondence Yu Gesuo It states supporting leg bottom and multiple wheels on the working face, be arranged in a one-to-one correspondence in each supporting leg bottom and positioned at described Multiple adjustable support feet of wheel side are set at the top of each supporting leg and are put down with the operation frame of the fixation bushing Platform, the cat ladder being set between the operation body panel and the working face offer multiple and institute on the operation body panel State the corresponding first positioning hole of screw hole on the spacer flanger of bushing, the bushing by with the screw hole and institute It states the first bolt that first positioning hole matches and is connected with the operation body panel.
Preferably, the transformer high-voltage bushing upkeep operation frame further includes several internal diameters and the different bushings Spacer flanger match for the retainer plate selected, the outer ring edge of the retainer plate has and the first positioning hole phase Matched second location hole, the inner ring edge of the retainer plate have that several are corresponding with the screw hole on the spacer flanger Third location hole, the retainer plate by the second bolt for matching with the first positioning hole and second location hole and It is connected with the operation body panel, the bushing passes through the third that matches with the screw hole and the third location hole Bolt and be connected with the retainer plate.
Preferably, the adjustable support foot includes mutually being fixedly connected and offering with the supporting leg adjusting threaded hole Support chip, the carrying bolt being set in the adjusting threaded hole, the supporting block for being set to the carrying bolt bottom.
Preferably, the operation body panel includes being sequentially connected end to end in turn the frame for connecing and forming by plurality of rods part.
Preferably, the rod piece for forming the frame includes what an at least both ends were detachably connected with other described rod pieces Motion bar.
Preferably, the cat ladder includes fixed ladder, and the fixed ladder includes two first support bars and several first cross bars, The top of the first support bar is mutually fixedly connected with the operation body panel, and the bottom of the first support bar is located at the work Make on face, first cross bar is connected between two first support bars.
Preferably, the cat ladder further includes ramp, and the ramp includes two second support bars and several second horizontal strokes Bar, second cross bar are connected between two second support bars;It is described solid when the cat ladder includes the ramp Whole first cross bar of fixed ladder is respectively positioned below the support midleg.
Preferably, it is provided between the ramp and the operation body panel and the ramp is fixed on upper limit position Locking device.
Preferably, the locking device includes the first crosspiece being connected with two second support bars, fixed setting In the second crosspiece of the operation frame platform sides, correspondence offers connecting hole on first crosspiece and second crosspiece, First crosspiece is connected with second crosspiece by the connection bolt to match with the connecting hole.
Preferably, each supporting leg is obliquely installed, and the bottom of each supporting leg disperses compared with its top.
Since above-mentioned technical proposal is used, the utility model has following advantages compared with prior art:The utility model The support transformer high-voltage bushing that can be consolidated makes it keep vertical state, so as to maintenance, the experiment for transformer high-voltage bushing It provides safeguard, it is simple in structure, easy to use.
Description of the drawings
Schematic front view of the attached drawing 1 for the transformer high-voltage bushing upkeep operation frame of the utility model.
Schematic side view of the attached drawing 2 for the transformer high-voltage bushing upkeep operation frame of the utility model.
Attached drawing 3 is vertical view signal of the transformer high-voltage bushing upkeep operation frame of the utility model when not installing retainer plate Figure.
Attached drawing 4 is vertical view signal of the transformer high-voltage bushing upkeep operation frame of the utility model when being equipped with retainer plate Figure.
In the figures above:1st, supporting leg;2nd, wheel;3rd, adjustable support foot;4th, operation body panel;5th, cat ladder;6th, strengthen Bar;7th, support chip;8th, carrying bolt;9th, supporting block;10th, motion bar;11st, installation bolt;12nd, first positioning hole;13rd, it is fixed Ladder;14th, first support bar;15th, the first cross bar;16th, ramp;17th, second support bar;18th, the second cross bar;19th, the first crosspiece; 20th, the second crosspiece;21st, connecting hole;22nd, positioning plate;23rd, locating slot;24th, retainer plate;25th, the second location hole;26th, third positions Hole.
Specific embodiment
The invention will be further described for shown embodiment below in conjunction with the accompanying drawings.
Embodiment one:What a kind of bushing to transformer used when overhauling for being disposed vertically bushing Transformer high-voltage bushing upkeep operation frame, is positioned over working face, on ground.The transformer high-voltage bushing upkeep operation frame packet Include multiple supporting legs 1, multiple wheels 2, multiple adjustable support feet 3, operation body panel 4 and cat ladder 5.
Supporting leg 1 is made of rod piece, such as angle steel, and usual transformer high-voltage bushing upkeep operation frame includes four branch Support leg 1, each 1 four corners that are non-coplanar and being distributed in quadrangle of supporting leg.Each supporting leg 1 is obliquely installed, and 1 bottom of each supporting leg Portion disperses compared with its top, so that four supporting legs 1 substantially form pyramid shape.The bottom of each supporting leg 1 can also increase more Root bracing piece 6 connects adjacent supporting leg 1 respectively.
Wheel 2 is arranged in a one-to-one correspondence in the bottom of a supporting leg 1, and wheel 2 is located on working face and can be on working face It rolls.
Adjustable support foot 3 is arranged in a one-to-one correspondence in the bottom of a supporting leg 1 and positioned at the side of wheel 2, adjustable branch Spike includes mutually being fixedly connected and offering with supporting leg adjusting the support chip 7 of threaded hole, being set to the branch adjusted in threaded hole Staybolt 8, the supporting block 9 for being set to 8 bottom of carrying bolt.When rotating carrying bolt 8, but supporting block 9 connects with working face It touches and forms support or make somebody a mere figurehead on working face.
For operation body panel 4 for fixing bushing, it is set to each 1 top of supporting leg.Operation body panel 4 is included by more Root rod piece is sequentially connected end to end in turn the frame for connecing and forming.By being provided with four supporting legs 1 in this present embodiment, industry body panel is pretended 4 frame is made of four rod pieces, and the both ends of rod piece are connected between the top of two supporting legs 1.In general, frame can be with each Support leg 1 welds together, and in order to preferably lift transformer high-voltage bushing, the rod piece of composition frame can be made to include at least The motion bar 10 that piece both ends are detachably connected with other rod pieces, the both ends of the motion bar 10 can utilize installation bolt 11 and and its He is connected rod piece.The screw hole offered on the frame of operation body panel 4 on multiple spacer flangers with bushing is corresponding First positioning hole 12, such as open up a first positioning hole 12 respectively on every rod piece, bushing by with in-between method The first bolt that screw hole and first positioning hole 12 on orchid match and be connected with operation body panel 4, hang down so as to fulfill it Straight installation.
Cat ladder 5 is set between operation body panel 4 and working face.Cat ladder 5 generally comprises fixed ladder 13, and fixed ladder 13 includes The first support bar 14 of two fore-and-aft tilts setting and several horizontally disposed first cross bars 15, the top of first support bar 14 with 4 phase of operation body panel is fixedly connected, and the bottom of first support bar 14 is located on working face, and the first cross bar 15 is connected to two first Between supporting rod 14.Cat ladder 5 can also further include ramp 16 on the basis of fixed ladder 13.Ramp 16 includes two second Supporting rod 17 and several second cross bars 18, the second cross bar 18 are connected between two second support bars 17.When cat ladder 5 includes movement When terraced, all the first cross bars 15 of fixed ladder 13 are respectively positioned below the middle part of supporting leg 1.So that ramp 16 is located at The top of fixed ladder 13 and form complete cat ladder 5.It is provided between ramp and operation body panel 4 and is fixed on ramp The locking device of extreme position.Locking device includes the first crosspiece 19 being connected with two second support bars 17, is fixedly installed on Corresponding on second crosspiece 20 of 4 side of operation body panel, the first crosspiece 19 and the second crosspiece 20 to offer connecting hole 21, first is horizontal Shelves 19 are connected with the second crosspiece 20 by the connection bolt to match with connecting hole 21.It additionally can be in operation body panel 4 Side setting positioning plate 22, offer the locating slot 23 to match with the second support bar of ramp 16 17 on positioning plate 22. After mobile above-mentioned ramp 16 to its upper limit position, ramp and operation body panel 4 are connected by connecting bolt, at this time second Supporting rod 17 is inserted into locating slot 23, and its bottom is connected with fixed ladder 13, so as to fixed ramp 16.Ramp 16 may be used also It is connected in a manner of using sliding rail with the first support bar 14 of fixed ladder 13.It can respectively be set in the both sides of operation body panel 4 Put cat ladder 5.
In order to adapt to the transformer high-voltage bushing of different model, which is also equipped with Multiple retainer plates 24 for selecting.Retainer plate 24 is annular in shape, so as to the outer ring edge with outer ring and inner ring, outer ring have with The second location hole 25 that first positioning hole 12 on operation body panel 4 matches, so as to retainer plate 24 by with first positioning hole 12 and second the second bolt that matches of location hole 25 and be connected with operation body panel 4.24 internal diameter of retainer plate is used to match height The spacer flanger of pressing sleeve pipe, then different retainer plates 24 are with different internal diameters, so as to the intermediate method from different bushings Orchid matches.The inner ring edge of retainer plate 24 has several and the corresponding third location hole of screw hole on spacer flanger 26, so as to bushing by the third bolt that matches with the screw hole on in-between flange and third location hole 26 and with fixation Circle 24 is connected.The spacer flanger of general high voltage casing can at least be connected there are four screw hole with third location hole 26.
Above-mentioned transformer high-voltage bushing upkeep operation frame can be by the wheel 2 that each 1 bottom of supporting leg is installed and easily It is mobile.When needing mobile, the adjustable support foot 3 on 2 side of wheel, which need to be rotated to its supporting block 9, leaves working face(Ground), So as to operation frame can individually or drive transformer high-voltage bushing move.After reaching appointed place, adjustable support foot 3 is screwed off Carrying bolt 8 and make supporting block 9 and working face(Ground)Rigid contact, firmness total and that entire operation frame can be increased, It places operation frame to alter shifting or topple over, protects the bushing on operation frame and the work people for being overhauled, being tested on operation frame Member.
When middle part, the lower part to bushing are overhauled and during test connection, fixed ladder 13 can be utilized without making With ramp 16.And when the top to bushing is needed to be overhauled and during test connection, ramp 16 is risen with manpower, is made In the locating slot 23 for obtaining 17 embedded operation body panel of second support bar, 4 side, and pass through the first crosspiece 19, the second crosspiece 20 and connect Connecting bolt and fix ramp 16, be allowed to be fixedly connected with 4 phase of operation body panel, and without gap is shaken, at this time i.e. using solid Fixed ladder 13 and ramp 16.After ramp 16, which rises, to be fixed, enough safe distances are kept with the insulator of bushing, until Ramp 16 will not encounter insulator during rising, and avoid damage insulator.Staff is upward from fixed ladder 13 and ramp 16, Its security insurance band can be fixed on the second cross bar 18 of ramp 16(After mobile and arrival job position), made with increasing The safety of industry(State Grid Corporation of China electric power safety working regulation 15.1.8 provides that the hook or rope of safety belt should hang over knot On real firm component or aim on the steel wire rope of hanging safety belt.Forbid hanging on mobile or unstable object).It is above-mentioned to climb The design of ladder 5, strengthens the security reliability of staff and improves service work efficiency, avoid portion on high voltage bushings During maintenance, the inconvenience and security risk that are worked using overlength double ladder are limited using the place of trolley or installation scaffold It is cumbersome with it is inefficient.In cat ladder 5, connection bolt may be used M12 galvanized bolts, shearing resistance at least in more than 37000N, It is fully able to bear the weight of staff and tool materials(The weight is no more than 100kg).
Operation body panel 4 is matched with partial high pressure casing spacer flanger, and casing can be directly lifted on operation body panel 4, Four 16mm first positioning holes 12 screw hole corresponding with bushing spacer flanger of operation body panel 4 is bolted.In addition Design can be selected sequentially with major vendor, the matched several retainer plates 24 of model bushing shell for transformer spacer flanger.
To fix, rod piece made of a face right angle iron bar can be dismantled in operation body panel 4 three face(Dismantle two, both sides 12mm It is bolted), such bushing can be lifted on operation body panel 4 from side, it is in place after removal and installation again right angle iron bar Rod piece(Partial high pressure casing does not need to retainer plate 24 can be directly in place;Need the casing of retainer plate 24 can be before in place, solid Surely circle 24 is mounted on the spacer flanger lower part of bushing, is connected with, then in place).4 three face of operation body panel is fixed, Dismountable design on one side had not only improved bushing slinging work efficiency, but also increased the safety during bushing lifting (Conventional high-tension sleeve hoisting method is bushing vertical rise and fall, this operating experience and casing to driving or hoistman Vertically bind it is more demanding, casing sling after slightly tilt rise and fall difficulty and safety is just significantly greatly increased).
Above-described embodiment is only the technical concepts and features for illustrating the utility model, and its object is to allow be familiar with technique Personage can understand the content of the utility model and implement according to this, can not the scope of protection of the utility model be limited with this. It is all according to the spirit of the present invention substantially equivalent change or modification for being made, should all cover the scope of protection of the utility model it It is interior.

Claims (10)

1. a kind of transformer high-voltage bushing upkeep operation frame is used to be disposed vertically when the bushing to transformer overhauls The bushing, it is characterised in that:The transformer high-voltage bushing upkeep operation frame includes multiple supporting legs, one-to-one correspondence is set It is placed in each supporting leg bottom and multiple wheels on the working face, is arranged in a one-to-one correspondence in each supporting leg bottom simultaneously Multiple adjustable support feet positioned at the wheel side are set at the top of each supporting leg with the fixation bushing Operation body panel, the cat ladder being set between the operation body panel and the working face are offered on the operation body panel The corresponding first positioning hole of screw hole on multiple spacer flangers with the bushing, the bushing by with it is described The first bolt that screw hole and the first positioning hole match and be connected with the operation body panel.
2. transformer high-voltage bushing upkeep operation frame according to claim 1, it is characterised in that:The transformer high-voltage set Pipe upkeep operation frame further includes the fixation for selection that several internal diameters match from the spacer flanger of the different bushings Circle, the outer ring edge of the retainer plate have the second location hole to match with the first positioning hole, the retainer plate Inner ring edge has several and the corresponding third location hole of screw hole on the spacer flanger, the retainer plate by with The second bolt that the first positioning hole and second location hole match and be connected with the operation body panel, the height Pressing sleeve pipe is connected by the third bolt to match with the screw hole and the third location hole with the retainer plate.
3. transformer high-voltage bushing upkeep operation frame according to claim 1 or 2, it is characterised in that:The adjustable branch Spike includes mutually being fixedly connected and offering with the supporting leg adjusting the support chip of threaded hole, being set to the adjusting threaded hole In carrying bolt, be set to the supporting block of the carrying bolt bottom.
4. transformer high-voltage bushing upkeep operation frame according to claim 1 or 2, it is characterised in that:The operation frame is put down Platform includes being sequentially connected end to end in turn the frame for connecing and forming by plurality of rods part.
5. transformer high-voltage bushing upkeep operation frame according to claim 4, it is characterised in that:Form the bar of the frame Part includes the motion bar that at least a both ends are detachably connected with other described rod pieces.
6. transformer high-voltage bushing upkeep operation frame according to claim 1 or 2, it is characterised in that:The cat ladder includes Fixed ladder, the fixed ladder include two first support bars and several first cross bars, the top of the first support bar with it is described Operation body panel is mutually fixedly connected, and the bottom of the first support bar is located on the working face, and first cross bar is connected to Between two first support bars.
7. transformer high-voltage bushing upkeep operation frame according to claim 6, it is characterised in that:The cat ladder further includes shifting Dynamic ladder, the ramp include two second support bars and several second cross bars, and second cross bar is connected to two described the Between two supporting rods;When the cat ladder includes the ramp, whole first cross bar of the fixed ladder is respectively positioned on institute It states below support midleg.
8. transformer high-voltage bushing upkeep operation frame according to claim 7, it is characterised in that:The ramp with it is described The locking device that the ramp is fixed on to upper limit position is provided between operation body panel.
9. transformer high-voltage bushing upkeep operation frame according to claim 8, it is characterised in that:The locking device includes The first crosspiece for being connected with two second support bars, the second crosspiece for being fixedly installed on the operation frame platform sides, It is corresponding on first crosspiece and second crosspiece to offer connecting hole, first crosspiece and second crosspiece by with The connection bolt that the connecting hole matches is connected.
10. transformer high-voltage bushing upkeep operation frame according to claim 1 or 2, it is characterised in that:Each supporting leg It is obliquely installed, and the bottom of each supporting leg disperses compared with its top.
CN201721459780.1U 2017-11-06 2017-11-06 Transformer high-voltage bushing upkeep operation frame Active CN207499793U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721459780.1U CN207499793U (en) 2017-11-06 2017-11-06 Transformer high-voltage bushing upkeep operation frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721459780.1U CN207499793U (en) 2017-11-06 2017-11-06 Transformer high-voltage bushing upkeep operation frame

Publications (1)

Publication Number Publication Date
CN207499793U true CN207499793U (en) 2018-06-15

Family

ID=62502933

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721459780.1U Active CN207499793U (en) 2017-11-06 2017-11-06 Transformer high-voltage bushing upkeep operation frame

Country Status (1)

Country Link
CN (1) CN207499793U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110303459A (en) * 2019-03-28 2019-10-08 江苏核电有限公司 A kind of packaged type overhaul working platform for the maintenance of nuclear power station hydraulic damper
CN113059896A (en) * 2021-03-31 2021-07-02 魏新 Small-size screen printing machine

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110303459A (en) * 2019-03-28 2019-10-08 江苏核电有限公司 A kind of packaged type overhaul working platform for the maintenance of nuclear power station hydraulic damper
CN113059896A (en) * 2021-03-31 2021-07-02 魏新 Small-size screen printing machine

Similar Documents

Publication Publication Date Title
CN103175998B (en) A kind of portable test shaft tower detected for transmission circuit insulator string high-voltage performance
CN104035014B (en) Method for alternating-current voltage withstand testing of 220 kV and 330 kV insulated tools and instruments
CN203850679U (en) Elevating disassembly and assembly platform with limiting support for current transformer in high-voltage switchgear
CN207499793U (en) Transformer high-voltage bushing upkeep operation frame
CN104020400B (en) 750kV insulating tool segmentation ac voltage withstanding test method
CN201817223U (en) Suspension device for on-load tapping switches of transformers
CN204643719U (en) A kind of jacking system for changing 10kV middle-placed switch cabinet current transformer
CN109818284B (en) 1000kV extra-high voltage transformer low-voltage lead dismounting platform
CN207033023U (en) A kind of adhesion type is from lifting pole
CN104882267B (en) Method for adding angle ring to transformer coil assembly
CN206301662U (en) A kind of transformer rack
CN104953471A (en) Mobile lightning rod
CN101908731B (en) Hoisting device for on-load tap changers of transformers
CN209488063U (en) A kind of electric automatization control cable laying apparatus
CN107742850A (en) The oil-gas casing assembly and disassembly methods of connection exchange 500kV oil-immersed type transformers and GIS tube type bus
CN110485792A (en) A kind of vertical safe construction method of iron tower of power transmission line group
CN103293452B (en) Insulating ladder Withstand test device
CN207966568U (en) A kind of cable production wire installation
CN110593546A (en) Chimney heat preservation construction auxiliary device
CN210659898U (en) Insulating platform of live-line maintenance work of transformer substation
CN206298298U (en) A kind of transformer carrier of four motor-driven jacks of band
CN106629455A (en) Mutual inductor carrying vehicle with four electric jacks
CN211473325U (en) Chimney heat preservation construction auxiliary device
CN207069293U (en) One kind uses distribution framework made of composite insulating material
CN206278853U (en) A kind of transformer carrier with single motor-driven jack

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant