CN207499383U CN201721335806.1U CN201721335806U CN207499383U CN 207499383 U CN207499383 U CN 207499383U CN 201721335806 U CN201721335806 U CN 201721335806U CN 207499383 U CN207499383 U CN 207499383U
Authority
CN
China
Prior art keywords
height
platform
adjustable
operation platform
hoistway operation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721335806.1U
Other languages
Chinese (zh)
Inventor
隋沿辉
李兆祥
朱永柏
薛建房
王加
张英龙
崔海鹤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201721335806.1U priority Critical patent/CN207499383U/en
Application granted granted Critical
Publication of CN207499383U publication Critical patent/CN207499383U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to a kind of height-adjustable hoistway operation platform, including:It is fastened transversely to the support base of the borehole wall of elevator;First platform structure, on support base;Height-adjustable adjusting bracket, branch are set on the first platform structure;Set on the top of adjusting bracket, the distance between the first platform structure and the second platform structure are adjusted by adjusting the height of adjusting bracket for second platform structure.That is the height of the second platform structure is adjusted.The height-adjustable of hoistway operation platform is achieved.Height constantly variation non-standard layers can be met and set up requirement and whole promotion, can be used in turn, improve construction efficiency.

Description

Height-adjustable hoistway operation platform
Technical field
The utility model is related to the realm of building construction, espespecially a kind of height-adjustable hoistway operation platform.
Background technology
In high-rise, Super High Core Walls Structure in construction of lift well, operating platform need to be set up.
Traditional erection method uses steel tube fastener scaffold, and scaffold board is completely spread on scaffold.But it such sets up Height it is unadjustable, it is impossible to adaptation layer High variation it is more non-standard layers construction.The process of setting up takes time and effort, cost of labor and Labor intensity is big, and can not be used in turn.The narrow space of elevator, operation is inconvenient, and there are security risks.
Utility model content
The purpose of the utility model is to overcome the defects of the prior art, provide a kind of height-adjustable hoistway operation Platform solves the problems, such as that operating platform of the prior art cannot adjust height.
Realizing the technical solution of above-mentioned purpose is:
The utility model provides a kind of height-adjustable hoistway operation platform, including:
It is fastened transversely to the support base of the borehole wall of elevator;
First platform structure, on the support base;
Height-adjustable adjusting bracket, branch are set on first platform structure;
Second platform structure set on the top of the adjusting bracket, is adjusted by adjusting the height of the adjusting bracket Save the distance between first platform structure and second platform structure.
The advantageous effect of the height-adjustable hoistway operation platform of the utility model:
The height-adjustable hoistway operation platform of the utility model is by using a height-adjustable adjusting bracket branch It supports between the first platform structure and the second platform structure, described first is adjusted by adjusting the height of the adjusting bracket The distance between platform structure and second platform structure, that is to say, that adjust the height of second platform structure.In this way Realize the height-adjustable of hoistway operation platform.Can meet height constantly variation non-standard layers set up requirement and Ensure whole promotion, can be used in turn, improve construction efficiency.
The height-adjustable hoistway operation platform of the utility model further improvement lies in that, the adjusting bracket packet It includes:
Spaced upright bar, the upright bar are equipped at intervals with the first adjustment hole;
The adjusting rod that can be moved up and down in the upright bar and along the upright bar is inserted in, the adjusting rod is equipped at intervals with Second adjustment hole is worn first adjustment hole and corresponding second adjustment hole by bolt and is screwed togather using nut solid It is fixed.
The height-adjustable hoistway operation platform of the utility model further improvement lies in that, the adjusting bracket is also wrapped Include the connecting rod being laterally connected between the upright bar.
The height-adjustable hoistway operation platform of the utility model further improvement lies in that, the support base is laterally It is arranged in multiple supporting rods of the borehole wall of the elevator.
The height-adjustable hoistway operation platform of the utility model further improvement lies in that, first platform structure Including:
First framework;And
It is fixed on the first bottom plate of first framework.
The height-adjustable hoistway operation platform of the utility model further improvement lies in that, first platform structure Further include the first hanging ring set on first bottom plate.
The height-adjustable hoistway operation platform of utility model further improvement lies in that, the second platform structure packet It includes:
Second framework;And
The second bottom plate of the second framework is fixed on, outlet is offered on second bottom plate, the outlet cap is equipped with Removable cover.
The height-adjustable hoistway operation platform of utility model further improvement lies in that, the removable cover passes through conjunction Page is articulated with second bottom plate, and the removable cover is equipped with handle.
The height-adjustable hoistway operation platform of utility model further improvement lies in that, second platform structure is also The second hanging ring including being set on second bottom plate.
The height-adjustable hoistway operation platform of utility model further improvement lies in that, second platform structure is also Foot guard plate including being erected on second bottom edge.
Description of the drawings
Fig. 1 is the structure diagram of the height-adjustable hoistway operation platform of the utility model.
Fig. 2 is the structure diagram of the adjusting bracket of the height-adjustable hoistway operation platform of the utility model.
Fig. 3 is the schematic diagram of the first platform structure of the height-adjustable hoistway operation platform of the utility model.
Fig. 4 is the vertical view of Fig. 3.
Fig. 5 is the schematic diagram of the second platform structure of the height-adjustable hoistway operation platform of the utility model.
Fig. 6 is the vertical view of Fig. 5.
Specific embodiment
The utility model is described in further detail in the following with reference to the drawings and specific embodiments.
Refering to Fig. 1, it is shown that the structure diagram of the height-adjustable hoistway operation platform of the utility model.Such as Fig. 1 Shown, the height-adjustable hoistway operation platform of the utility model includes:It is fastened transversely to the support of the borehole wall 10 of elevator Seat 20;First platform structure 30, on support base 20;Height-adjustable adjusting bracket 40, branch are set on the first platform structure On 30;Set on the top of adjusting bracket 40, first is adjusted by adjusting the height of adjusting bracket 40 for second platform structure 50 The distance between 30 and second platform structure 50 of platform structure.The height-adjustable hoistway operation platform of the utility model passes through It is supported between the first platform structure and the second platform structure using a height-adjustable adjusting bracket, by adjusting branch The height of frame is so as to adjust the distance between the first platform structure and the second platform structure, that is to say, that adjusts the second platform structure Height.The height-adjustable of hoistway operation platform is achieved.Height constantly variation non-standard layers can be met to set up and make With requiring, and can guarantee whole promotion, it can be used in turn, improve construction efficiency.
Referring to Fig.2, show that the structure of the adjusting bracket of the height-adjustable hoistway operation platform of the utility model is shown It is intended to.With reference to shown in Fig. 1 and Fig. 2, adjusting bracket 40 includes:Spaced upright bar 41, upright bar 41 are equipped at intervals with the first adjusting Hole;The adjusting rod 42 that can be moved up and down in upright bar 41 and along upright bar 41 is inserted in, adjusting rod 42 is equipped at intervals with the second adjusting Hole wears the first adjustment hole and corresponding second adjustment hole by bolt 43 and screws togather fixation using nut.
In the present embodiment, multiple upright bars 41 are erected on the first platform structure 30, and use 43 lateral connection of connecting rod So as to carry out lateral drawknot connection between upright bar 41, to ensure the stability of the structure of entire adjusting bracket 40, enhancing support Power.
In the construction process, after this layer construction finishes, bolt 43 is taken out, upwardly or downwardly adjusts adjusting rod 42 To at the appropriate position of upright bar 41, to reach at the construction location of the second platform structure 50,43 secured adjusted of bolt is recycled Bar 42 and the position of upright bar 41, so as to ensure the stability of total.
One better embodiment of the hoistway operation platform height-adjustable as the utility model, support base 20 are horizontal stroke To the multiple supporting rods for the borehole wall 10 for being arranged in elevator.In the present embodiment, multiple supporting rods are laterally embedded in elevator in advance The borehole wall 10 bottom.
One better embodiment of the hoistway operation platform height-adjustable as the utility model, refering to Fig. 3, display The schematic diagram of first platform structure of the height-adjustable hoistway operation platform of the utility model.Refering to Fig. 4, it is shown that figure 3 vertical view.With reference to shown in Fig. 1 to Fig. 4, the first platform structure 30 includes:First framework 31;And it is fixed on the first framework 31 The first bottom plate 32.First platform structure 30 further includes the first hanging ring 33 set on the first bottom plate 32.In the present embodiment, it uses Channel steel welds to form rectangle frame, and welds multiple channel steels as the first framework 31 in rectangle frame.First bottom plate 32 is covered solid Due in the first framework 31.
One better embodiment of the hoistway operation platform height-adjustable as the utility model, refering to Fig. 5, display The schematic diagram of second platform structure of the height-adjustable hoistway operation platform of the utility model.Refering to Fig. 6, it is shown that figure 5 vertical view.With reference to shown in Fig. 1 to Fig. 6, the second platform structure 50 includes:Second framework 51;And it is fixed on second framework 51 The second bottom plate 52.Second platform structure 50 further includes the second hanging ring 53 set on the second bottom plate 52.In the present embodiment, it uses Channel steel welds to form rectangle frame, and welds multiple channel steels as second framework 51 in rectangle frame.Second bottom plate 52 is covered solid Due in second framework 51.Outlet is offered on second bottom plate 52, outlet cap is equipped with removable cover 54.Removable cover 54 is opened, Construction operation can be facilitated from the second platform structure 50 downwardly on the first platform structure 30.
One better embodiment of the hoistway operation platform height-adjustable as the utility model, removable cover 54 are logical It crosses hinge 540 and is articulated with the second bottom plate 52, removable cover 54 is equipped with handle 541.
One better embodiment of the hoistway operation platform height-adjustable as the utility model, the second platform structure 50 further include the foot guard plate 55 for being erected on 52 edge of the second bottom plate, to ensure the safety of construction.
The height-adjustable hoistway operation platform of the utility model has the beneficial effect that:
The height-adjustable hoistway operation platform of the utility model is by using a height-adjustable adjusting bracket branch It supports between the first platform structure and the second platform structure, the first platform structure is adjusted by adjusting the height of adjusting bracket The distance between second platform structure, that is to say, that adjust the height of the second platform structure.Hoistway operation is achieved to put down Platform it is height-adjustable.Height constantly variation non-standard layers can be met and set up requirement and whole promotion, it can week Turn to use, improve construction efficiency.
The utility model is described in detail above in association with attached drawing embodiment, those skilled in the art can root Many variations example is made to the utility model according to above description.Thus, certain details in embodiment should not be formed to this practicality Novel restriction, the utility model will be using the ranges that the appended claims define as the scope of protection of the utility model.

Claims (10)

1. a kind of height-adjustable hoistway operation platform, which is characterized in that including:
It is fastened transversely to the support base of the borehole wall of elevator;
First platform structure, on the support base;
Height-adjustable adjusting bracket, branch are set on first platform structure;
Second platform structure, set on the top of the adjusting bracket, by adjusting the height of the adjusting bracket so as to adjust State the distance between the first platform structure and second platform structure.
2. height-adjustable hoistway operation platform as described in claim 1, which is characterized in that the adjusting bracket packet It includes:
Spaced upright bar, the upright bar are equipped at intervals with the first adjustment hole;
The adjusting rod that can be moved up and down in the upright bar and along the upright bar is inserted in, the adjusting rod is equipped at intervals with second Adjustment hole wears first adjustment hole and corresponding second adjustment hole by bolt and screws togather fixation using nut.
3. height-adjustable hoistway operation platform as claimed in claim 2, which is characterized in that the adjusting bracket is also wrapped Include the connecting rod being laterally connected between the upright bar.
4. height-adjustable hoistway operation platform as described in claim 1, which is characterized in that the support base is laterally It is arranged in multiple supporting rods of the borehole wall of the elevator.
5. height-adjustable hoistway operation platform as described in claim 1, which is characterized in that first platform structure Including:
First framework;And
It is fixed on the first bottom plate of first framework.
6. height-adjustable hoistway operation platform as claimed in claim 5, which is characterized in that first platform structure Further include the first hanging ring set on first bottom plate.
7. height-adjustable hoistway operation platform as described in claim 1, which is characterized in that second platform structure Including:
Second framework;And
The second bottom plate of the second framework is fixed on, outlet is offered on second bottom plate, the outlet cap is equipped with activity Cover board.
8. height-adjustable hoistway operation platform as claimed in claim 7, which is characterized in that the removable cover passes through Hinge is articulated with second bottom plate, and the removable cover is equipped with handle.
9. height-adjustable hoistway operation platform as claimed in claim 7, which is characterized in that second platform structure Further include the second hanging ring set on second bottom plate.
10. height-adjustable hoistway operation platform as claimed in claim 7, which is characterized in that the second platform knot Structure further includes the foot guard plate for being erected on second bottom edge.
CN201721335806.1U 2017-10-17 2017-10-17 Height-adjustable hoistway operation platform Expired - Fee Related CN207499383U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721335806.1U CN207499383U (en) 2017-10-17 2017-10-17 Height-adjustable hoistway operation platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721335806.1U CN207499383U (en) 2017-10-17 2017-10-17 Height-adjustable hoistway operation platform

Publications (1)

Publication Number Publication Date
CN207499383U true CN207499383U (en) 2018-06-15

Family

ID=62500562

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721335806.1U Expired - Fee Related CN207499383U (en) 2017-10-17 2017-10-17 Height-adjustable hoistway operation platform

Country Status (1)

Country Link
CN (1) CN207499383U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110284699A (en) * 2019-07-29 2019-09-27 福建省惠东建筑工程有限公司 A kind of elevator job platform of energy flexible modulation lifting

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110284699A (en) * 2019-07-29 2019-09-27 福建省惠东建筑工程有限公司 A kind of elevator job platform of energy flexible modulation lifting

Similar Documents

Publication Publication Date Title
CN205688774U (en) A kind of electric bridge scaffold
CN205743670U (en) A kind of Telescopic herringbone ladder
CN207499383U (en) Height-adjustable hoistway operation platform
CN207003870U (en) A kind of combined type balcony solar energy guardrail support brace structure
CN206205308U (en) A kind of balcony guard rail
CN213710299U (en) Modular two-layer elevartor shaft integral lifting bracing operation platform
CN205713096U (en) A kind of roofing cantilevered structure form bracing system
CN208502316U (en) The external cantilevered structure of tripod built construction
CN206941390U (en) Collison fence for bridge reinforcing bar three-dimensional localization frame
CN206158146U (en) Novel building section of thick bamboo well construction operation platform
CN208105835U (en) A kind of safe construction frame of construction
CN205259555U (en) Device of adjustment reinforcing bar net piece height
CN206189829U (en) Auto -lock lifting foot hand rack
CN206903246U (en) A kind of structure with oblique member for building
CN206903204U (en) A kind of gantry type fence structure
CN207079953U (en) Edge protection rail structure
CN207110421U (en) One kind is used to protect frame system outside the working regularization of assembled architecture
CN219261563U (en) But height-adjusting's roofing railing device
CN107461029B (en) Lower hanging beam pouring forming device based on hydraulic climbing formwork system setting
CN205907999U (en) Drawer type operation platform is taken out to box transformer
CN201292656Y (en) Inner formwork construction support of shaft
CN217782800U (en) Take daylighting well of vertical protection to lean on steel platform to one side
CN205531267U (en) Integrated configuration support body convenient to building is draped over one's shoulders eaves and is decorated construction
CN105464359B (en) A kind of scaffold board of scaffold
CN209323936U (en) A kind of civil engineering work construction bracket

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180615