CN207484507U - A kind of bridge pier foundation pile precast construction - Google Patents
A kind of bridge pier foundation pile precast construction Download PDFInfo
- Publication number
- CN207484507U CN207484507U CN201721598749.6U CN201721598749U CN207484507U CN 207484507 U CN207484507 U CN 207484507U CN 201721598749 U CN201721598749 U CN 201721598749U CN 207484507 U CN207484507 U CN 207484507U
- Authority
- CN
- China
- Prior art keywords
- foundation pile
- pier
- hole
- foundation
- ontology
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model is related to the bridge pier foundation pile fields of bridge construction, it is intended to provide a kind of bridge pier foundation pile precast construction of generation that can reduce security risk, its key points of the technical solution are that including foundation pile ontology, foundation pile ontology is arranged in foundation pit, supporting table is equipped in foundation pit, foundation pile ontology is equipped with several fixed steel bars close to foundation pit side, fixed steel bars are equipped with " V " shape reinforcing bar away from one end of foundation pile ontology, fixed steel bars pass through supporting table, and foundation pile ontology contradicts supporting table, cement has been poured in gap between supporting table table top and bottom of foundation ditch, cement has been poured in gap between foundation pile ontology and foundation pit side-wall.By using above-mentioned technical proposal, cement between supporting table and foundation pit limits fixed steel bars and " V " shape reinforcing bar, the gap around foundation pile ontology is filled by cement again, and it is filled out below supporting table and is filled with cement, so as to improve the stability of fixed foundation pile, and then the stability of precast pier is improved, reduce the generation of security risk.
Description
Technical field
The utility model is related to the bridge pier foundation pile field of bridge construction, more particularly to a kind of bridge pier foundation pile precast construction.
Background technology
Bridge pier be in bridge more than holes and holes in addition to the abutment that both ends are connected with embankment remaining intermediate supports
Structure is usually arranged at the solid ground of subsurface by bridge pier foundation pile below bridge pier.
At present, the Chinese patent of Publication No. CN205224078U discloses a kind of bridge pier foundation pile structure, it includes support
Arch, support stake, foundation pile, the supporting arch are made of two arch bridge intersections, and there are four be respectively provided at two for the support stake
Four bridge pier lower parts of arch bridge, the foundation pile are located at supporting arch top, and bridge pier is located on foundation pile.
Although this bridge pier foundation pile structure can carry and fixed abutment, since the supporting arch of foundation pile lower part connection is
Arch, and the middle section of supporting arch does not support, if foundation pile carries bridge pier for a long time, easily generates the supporting arch in foundation pit
Deformation, foundation pile, which easily sinks, either to be tilted so as to cause pier sinking or inclination, brings security risk.
Utility model content
The purpose of this utility model is to provide a kind of bridge pier foundation pile precast construction, can make the stability of foundation pile enhance, and carries
High stability between bridge pier and foundation pile, reduces the generation of security risk.
A kind of bridge pier foundation pile precast construction, including foundation pile ontology, in the foundation pit of the foundation pile ontology setting on the ground, institute
Foundation pile ontology is stated equipped with pier hole, the pier hole is equipped with supporting table, and the support for placing precast pier in the foundation pit
The table top of platform is equipped with gap, and the foundation pile ontology is equipped with several fixed steel bars close to foundation pit side, and the fixed steel bars deviate from
One end of foundation pile ontology is equipped with " V " shape reinforcing bar, and the point of the " V " shape reinforcing bar is away from foundation pile ontology, the fixed steel bars
Across supporting table, and foundation pile ontology contradicts supporting table, and the footprint of the supporting table is more than the floor space of foundation pile ontology, described
Cement is poured in gap between supporting table table top and bottom of foundation ditch, in the gap between the foundation pile ontology and foundation pit side-wall
Cement is poured.
By using above-mentioned technical proposal, first foundation pile ontology is mounted in supporting table, makes the fixation with " V " shape reinforcing bar
Reinforcing bar passes through supporting table, supporting table and foundation pit is fixed together by cement, the cement between supporting table and foundation pit is to fixation
Reinforcing bar and " V " shape reinforcing bar are limited, so as to fulfill the limiting to foundation pile ontology in the vertical direction, then by cement by foundation pile
Gap filling around ontology, limits foundation pile ontology by cement, in the horizontal direction since foundation pile ontology is in level
Direction and vertical direction are limited, and are filled out below supporting table and be filled with cement, so as to improve the stability of fixed foundation pile, into
And the stability of precast pier is improved, reduce the generation of security risk.
Further setting:The first reinforced hole to match with the first reinforcing bar of precast pier end is set in the pier hole.
By using above-mentioned technical proposal, the first reinforcing bar is plugged in the first reinforced hole, realize to precast pier into
One step limits, and so as to improve the stability between foundation pile ontology and precast pier, reduces the generation of security risk.
Further setting:The marginal portion in the pier hole is equipped with slope.
By using above-mentioned technical proposal, the convenient gap between foundation pile ontology and precast pier of setting on slope pours
Cement makes cement uniformly be filled in gap, improves the stability between foundation pile ontology and precast pier, so as to make foundation pile
It is more stable between ontology and precast pier, reduce the generation of security risk.
Further setting:Gusset is additionally provided on the foundation pile ontology, the gusset is arranged on the surrounding in pier hole.
By using above-mentioned technical proposal, the setting of gusset further limits the precast pier being mounted in pier hole
Position, makes the stability between precast pier and foundation pile ontology more secure, further reduces the generation of security risk.
Further setting:The profile and the outer profile of precast pier that the gusset of pier hole surrounding surrounds match.
By using above-mentioned technical proposal, profile and the outer profile of precast pier that gusset surrounds match, and can make muscle
Plate contradicts precast pier, improves limit effect of the gusset to precast pier, so as to improve precast pier and foundation pile ontology it
Between stability, make security risk occur probability reduce.
Further setting:Screwed pipe is equipped in the gusset, is equipped with and the screw thread phase in screwed pipe in the screwed pipe
The threaded rod matched, the threaded rod are equipped with push plate close to pier hole direction.
By using above-mentioned technical proposal, threaded rod rotates in screwed pipe, can change between push plate and precast pier
Distance, after precast pier is mounted on foundation pile ontology, by rotating threaded rod, push plate is made to contradict precast pier, to pre-
Bridge pier processed is limited in the horizontal direction, is improved the stability between precast pier and foundation pile ontology, is reduced security risk
Occur.
Further setting:The threaded rod is equipped with nut, and the nut is placed in the both sides of gusset.
By using above-mentioned technical proposal, by rotation of the nut on threaded rod, threaded rod can be limited, kept away
Exempt from push plate causes threaded rod to be subjected to displacement when by external force.
Further setting:The edge in the pier bottom hole portion is equipped with the second reinforcing bar, and the precast pier is equipped with the second steel
Muscle hole, and the internal diameter of second reinforced hole is more than the diameter of the second reinforcing bar, and the L-shaped setting of the second reinforced hole, the
Two reinforced holes run through precast pier perpendicular to the part of the second reinforcing bar.
By using above-mentioned technical proposal, after the second reinforcing bar is inserted into the second reinforced hole, hung down by the second reinforced hole of " L " shape
Directly cement is injected in the second reinforced hole in the part of the second reinforcing bar, makes the gap in the second reinforced hole around the second reinforcing bar by water
Mud is filled, and by realizing the limiting between foundation pile ontology and precast pier to the limiting of the second reinforcing bar, improves foundation pile ontology
Stability between precast pier reduces the generation of security risk.
In conclusion the utility model has the advantages that:
1st, be equipped with supporting table below foundation pile ontology, and filled with cement between supporting table and foundation pit, around foundation pile ontology with
Gap between foundation pit is also filled by cement, so as to improve the stability of foundation pile ontology, since the stability of foundation pile ontology carries
Height so as to which the stability between precast pier and foundation pile ontology be caused to improve, reduces the generation of security risk;
2nd, the setting of gusset further limits the precast pier being mounted in pier hole, and precast pier inclination is avoided to lead
Cause the generation of security risk;
3rd, the cooperation of the cooperation of the first reinforcing bar and the first reinforced hole, the second reinforcing bar and the second reinforced hole can make foundation pile ontology
It is mutually limited between precast pier, improves the stability between precast pier and foundation pile ontology, reduce security risk
Occur.
Description of the drawings
Fig. 1 is the structure diagram for being used to embody the utility model in embodiment 1;
Fig. 2 is the A portions schematic enlarged-scale view for being used to embody position relationship between slope and pier hole in Fig. 1;
Fig. 3 is the structure diagram for being used to embody position relationship between supporting table and foundation pile ontology in embodiment 1;
Fig. 4 is the structure diagram for being used to embody position relationship between precast pier and push plate in embodiment 2;
Fig. 5 is the B portions schematic enlarged-scale view for being used to embody position relationship between gusset and screwed pipe in Fig. 4.
In figure, 1, foundation pile ontology;2nd, foundation pit;3rd, pier hole;4th, supporting table;5th, fixed steel bars;6th, " V " shape reinforcing bar;7th, first
Reinforced hole;8th, the first reinforcing bar;9th, gusset;10th, screwed pipe;11st, threaded rod;12nd, push plate;13rd, nut;14th, the second reinforcing bar;15、
Second reinforced hole;16th, slope;17th, precast pier.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment 1:A kind of bridge pier foundation pile precast construction, as shown in Figure 1, the foundation pile ontology 1 including carrying pier hole 3, pier hole 3
For placing precast pier 17, foundation pile ontology 1 is set in foundation pit 2 on the ground, and the edge of 3 bottom of pier hole is equipped with the second reinforcing bar
14, precast pier 17 is equipped with the second reinforced hole of " L " shape 15, and the internal diameter of the second reinforced hole 15 is more than the diameter of the second reinforcing bar 14,
For second reinforced hole 15 perpendicular to the part of the second reinforcing bar 14 through precast pier 17, the end of precast pier 17 is equipped with the first reinforcing bar
8, pier hole 3 is interior to be equipped with the first reinforced hole 7 to match with the first reinforcing bar 8.
As depicted in figs. 1 and 2, the marginal portion in pier hole 3 is equipped with slope 16, and gusset 9, gusset 9 are additionally provided on foundation pile ontology 1
The surrounding in pier hole 3 is arranged on, the outer profile of profile and precast pier 17 that the gusset 9 of 3 surrounding of pier hole surrounds matches.
As shown in figure 3, foundation pile ontology 1 is equipped with several fixed steel bars 5, and each fixed steel bars 5 close to 2 bottom side of foundation pit
" V " shape reinforcing bar 6 is equipped with away from one end of foundation pile ontology 1, the setting of " V " shape reinforcing bar 6 enhances the stability of fixed steel bars 5,
When fixed steel bars 5 loosen, " V " shape reinforcing bar 6 limits fixed steel bars 5, and fixed steel bars 5 is avoided to face away from 6 side of " V " shape reinforcing bar
To movement, it is free to be additionally provided with band away from foundation pile ontology 1 between 2 bottom of foundation pile ontology 1 and foundation pit for the point of " V " shape reinforcing bar 6
The supporting table 4 of gap, the area of 4 table top of supporting table are more than the floor space of foundation pile ontology 1, and the fixed steel bars 5 on foundation pile ontology 1 pass through
Supporting table 4, foundation pile ontology 1 contact at supporting table 4, and water has been poured in the gap between 2 bottom of 4 table top of supporting table and foundation pit
Mud has poured cement in the gap between 2 side wall of foundation pile ontology 1 and foundation pit.
Implementation process:Supporting table 4 is mounted in foundation pit 2, then foundation pile ontology 1 is placed in supporting table 4, makes foundation pile sheet
Fixed steel bars 5 and " V " shape reinforcing bar 6 on body 1 pass through the gap in supporting table 4, since the area of 4 table top of supporting table is more than foundation pile
Cement is injected into 4 table top of supporting table in the following, by pouring water by the floor space of ontology 1 by the gap around 4 table top of supporting table
Mud connects supporting table 4 and foundation pit 2, meanwhile, cement in foundation pit 2 is by the fixed steel bars 5 and " V " shape on foundation pile ontology 1
Reinforcing bar 6 is fixed, and by being fixed to fixed steel bars 5 and " V " shape reinforcing bar 6, realizes the limiting in the vertical direction to foundation pile ontology 1.
After joints cement below 4 table top of supporting table, by the gap between 2 side wall of foundation pile ontology 1 and foundation pit, by water
Mud is cast in gap, and by the joints cement in gap, foundation pile ontology 1 and foundation pit 2 are connected, foundation pile ontology 1 is made to exist
It is limited in horizontal direction.
After foundation pile ontology 1 is limited in the horizontal direction with vertical direction, precast pier 17 is placed on foundation pile ontology 1
In pier hole 3, when installing precast pier 17, the first reinforcing bar 8 is made to be inserted into the first reinforced hole 7, the second reinforcing bar 14 is inserted into second
In reinforced hole 15, precast pier 17 is limited, cement is cast between precast pier 17 and pier hole 3 by slope 16
In gap, then by the second reinforced hole 15 cement is cast in the second reinforced hole 15 through one end of precast pier 17, so as to
Second reinforced hole 15 is tightened together with the second reinforcing bar 14, due to the outer profile of the profile that gusset 9 forms and precast pier 17
Match, gusset 9 is put into one end limiting to precast pier 17 close to foundation pile ontology 1, avoids its inclination.
Embodiment 2:A kind of bridge pier foundation pile precast construction, with embodiment 1 the difference lies in, as shown in Figure 4 and Figure 5,
The screwed pipe 10 for being parallel to foundation pile ontology 1 is equipped in gusset 9, threaded rod 11, threaded rod 11 and screwed pipe are equipped in screwed pipe 10
10 matchings, threaded rod 11 are equipped with nut 13, and nut 13 is placed in the both sides of gusset 9, and the one end in threaded rod 11 towards pier hole 3 is set
There is push plate 12.
Implementation process:After precast pier 17 is mounted in pier hole 3, rotating nuts 13 make nut 13 to away from gusset 9
Direction is transported, and threaded rod 11 is enable to have the range of activity, threaded rod 11 is rotated further by, threaded rod 11 is made to pass through 10 direction of screwed pipe
17 direction of precast pier moves, until the push plate 12 on threaded rod 11 contradicts precast pier 17, rotating nuts 13, make nut again
13 move towards 9 direction of gusset, until nut 13 contradicts gusset 9, stop rotating nut 13, and nut 13 limits threaded rod 11
Position, avoids push plate 12 that threaded rod 11 is caused to be subjected to displacement in the case where being acted on by external force.
The above embodiments are only explanation to the utility model, are not the limitation to the utility model, ability
Field technique personnel can as needed make the present embodiment the modification of no creative contribution after this specification is read, but
As long as it is all protected in the right of the utility model by Patent Law.
Claims (8)
1. a kind of bridge pier foundation pile precast construction, including foundation pile ontology (1), the foundation pit of foundation pile ontology (1) setting on the ground
(2) in, the foundation pile ontology (1) is equipped with pier hole (3), and for placing precast pier (17), feature exists the pier hole (3)
In:Supporting table (4) is equipped in the foundation pit (2), and the table top of the supporting table (4) is equipped with gap, the foundation pile ontology (1)
Several fixed steel bars (5) are equipped with close to foundation pit (2) side, the fixed steel bars (5) are equipped with away from one end of foundation pile ontology (1)
" V " shape reinforcing bar (6), and the point of the " V " shape reinforcing bar (6) is away from foundation pile ontology (1), the fixed steel bars (5) are across branch
Platform (4) is supportted, and foundation pile ontology (1) contradicts supporting table (4), the footprint of the supporting table (4) is more than the bottom of foundation pile ontology (1)
Area has poured cement, the foundation pile ontology (1) and base in the gap between supporting table (4) table top and foundation pit (2) bottom
Cement has been poured in gap between (2) side wall of hole.
2. a kind of bridge pier foundation pile precast construction according to claim 1, it is characterised in that:Set in the pier hole (3) in advance
The first reinforced hole (7) that the first reinforcing bar (8) of bridge pier (17) end processed matches.
3. a kind of bridge pier foundation pile precast construction according to claim 2, it is characterised in that:The edge part of the pier hole (3)
It is arranged with slope (16).
4. a kind of bridge pier foundation pile precast construction according to claim 3, it is characterised in that:On the foundation pile ontology (1) also
Equipped with gusset (9), the gusset (9) is arranged on the surrounding of pier hole (3).
5. a kind of bridge pier foundation pile precast construction according to claim 4, it is characterised in that:The muscle of pier hole (3) surrounding
The outer profile of the profile that plate (9) surrounds and precast pier (17) matches.
6. a kind of bridge pier foundation pile precast construction according to claim 4, it is characterised in that:Spiral shell is equipped in the gusset (9)
Line pipe (10), the screwed pipe (10) is interior to be equipped with the threaded rod (11) to match with the screw thread in screwed pipe (10), the screw thread
Bar (11) is equipped with push plate (12) close to pier hole (3) direction.
7. a kind of bridge pier foundation pile precast construction according to claim 6, it is characterised in that:The threaded rod (11) is equipped with
Nut (13), and the nut (13) is placed in the both sides of gusset (9).
8. a kind of bridge pier foundation pile precast construction according to claim 5 or 7, it is characterised in that:Pier hole (3) bottom
Edge is equipped with the second reinforcing bar (14), and the precast pier (17) is equipped with the second reinforced hole (15), and second reinforced hole
(15) internal diameter is more than the diameter of the second reinforcing bar (14), and second reinforced hole (15) L-shaped setting, the second reinforced hole
(15) run through precast pier (17) perpendicular to the part of the second reinforcing bar (14).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721598749.6U CN207484507U (en) | 2017-11-24 | 2017-11-24 | A kind of bridge pier foundation pile precast construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721598749.6U CN207484507U (en) | 2017-11-24 | 2017-11-24 | A kind of bridge pier foundation pile precast construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207484507U true CN207484507U (en) | 2018-06-12 |
Family
ID=62471547
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721598749.6U Active CN207484507U (en) | 2017-11-24 | 2017-11-24 | A kind of bridge pier foundation pile precast construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207484507U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111535310A (en) * | 2020-05-11 | 2020-08-14 | 安徽建大交通科技有限公司 | Combined foundation pile for civil engineering |
-
2017
- 2017-11-24 CN CN201721598749.6U patent/CN207484507U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111535310A (en) * | 2020-05-11 | 2020-08-14 | 安徽建大交通科技有限公司 | Combined foundation pile for civil engineering |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106836463A (en) | The constructing device and construction method of cushion cap and ground girder construction | |
CN107429496A (en) | Wind energy plant ground and wind energy plant | |
CN207776485U (en) | A kind of novel work people construction wall bracing means | |
CN207063522U (en) | A kind of frame column high-supported formwork | |
CN207484507U (en) | A kind of bridge pier foundation pile precast construction | |
CN205676882U (en) | A kind of novel supporting construction | |
JP5635048B2 (en) | Basics for installing solar panels | |
CN104060585B (en) | Floating-plug bulkhead gate | |
JP2005090116A (en) | Method for erecting steel frame column and positioning frame body used for it | |
CN202595758U (en) | Batter post foundation structure for overhead transmission line | |
CN106968241A (en) | Continuous underground wall structure and retaining design construction method | |
CN102425188B (en) | Method for adjusting height-adjustable tower foundation | |
US4232491A (en) | Swimming pool deck | |
CN103669976A (en) | Ancient pagoda correction | |
CN206529881U (en) | The constructing device of cushion cap and ground girder construction | |
CN206800371U (en) | Continuous underground wall structure and retaining design | |
CN206752675U (en) | A kind of concrete frame node | |
CN206887980U (en) | A kind of integrated bracket basis of antifreeze pile | |
CN201809974U (en) | Glass steel cylindrical formwork device | |
CN206829786U (en) | Construction, which is enclosed, covers | |
CN209555866U (en) | A kind of unrestrained device of gear | |
CN202273243U (en) | Adjustable height type pole and tower foundation | |
CN203222808U (en) | Foundation processing structure for floating sluice | |
CN207062981U (en) | A kind of Retaining Wall | |
CN207277848U (en) | Metro Station Structure side wall punching block ruggedized construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |