CN102425188B - Method for adjusting height-adjustable tower foundation - Google Patents

Method for adjusting height-adjustable tower foundation Download PDF

Info

Publication number
CN102425188B
CN102425188B CN201110262996.XA CN201110262996A CN102425188B CN 102425188 B CN102425188 B CN 102425188B CN 201110262996 A CN201110262996 A CN 201110262996A CN 102425188 B CN102425188 B CN 102425188B
Authority
CN
China
Prior art keywords
crossbeam
foundation
tower
base plate
pad
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110262996.XA
Other languages
Chinese (zh)
Other versions
CN102425188A (en
Inventor
苏荣臻
鲁先龙
丁士君
冯自霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Electric Power Research Institute Co Ltd CEPRI
State Grid Corp of China SGCC
Original Assignee
China Electric Power Research Institute Co Ltd CEPRI
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=45959214&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=CN102425188(B) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by China Electric Power Research Institute Co Ltd CEPRI, State Grid Corp of China SGCC filed Critical China Electric Power Research Institute Co Ltd CEPRI
Priority to CN201110262996.XA priority Critical patent/CN102425188B/en
Publication of CN102425188A publication Critical patent/CN102425188A/en
Application granted granted Critical
Publication of CN102425188B publication Critical patent/CN102425188B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

本发明属于输电线路的基础工程领域,具体涉及一种可调高度型杆塔基础及其调节方法。该杆塔基础主要包括立柱、横梁I、竖梁、横梁II、竖撑、底板和地脚螺栓,该杆塔基础将用于支撑杆塔塔腿的各立柱联结为一体式结构,该结构不易发生不均匀沉降,当地基不均匀沉降造成杆塔基础发生倾斜时,通过本发明的调节方法,可以调节杆塔基础四角的高度,使用于支撑杆塔塔腿的各立柱顶面重新保持水平,以保证上部杆塔的稳定性要求。该杆塔基础具有结构简单、稳定可靠等优点,能够满足上部杆塔的稳定性要求;该调节方法具有操作简单、可靠性高等优点。

The invention belongs to the field of foundation engineering of power transmission lines, and in particular relates to a height-adjustable pole tower foundation and an adjustment method thereof. The tower foundation mainly includes columns, beams I, vertical beams, beams II, vertical braces, bottom plates and anchor bolts. The tower foundation connects the columns used to support the tower legs into an integrated structure, which is not prone to unevenness. Settlement, when the uneven settlement of the ground causes the tower foundation to tilt, the adjustment method of the present invention can adjust the height of the four corners of the tower foundation, so that the top surfaces of the columns supporting the tower legs can be kept horizontal again to ensure the stability of the upper tower sexual demands. The pole tower foundation has the advantages of simple structure, stability and reliability, etc., and can meet the stability requirements of the upper pole tower; the adjustment method has the advantages of simple operation, high reliability, and the like.

Description

一种可调高度型杆塔基础的调节方法A method for adjusting the height-adjustable tower foundation

技术领域technical field

本发明属于输电线路的基础工程领域,具体涉及一种可调高度型杆塔基础发生倾斜时的调节方法。The invention belongs to the field of foundation engineering of power transmission lines, and in particular relates to a method for adjusting height-adjustable tower foundations when they are tilted.

背景技术Background technique

按照结构形式,输电线路分为架空输电线路和电缆线路,架空输电线路通常由杆塔、导线、绝缘子、线路金具、拉线、杆塔基础、接地装置等构成,并架设于地面之上。现有的杆塔基础一般采用独立式基础,如图1所示,杆塔11具有四个塔腿12,每个塔腿均由一个独立式基础进行支撑,独立式基础包括上部立柱13和下部阶梯式底板14。为了避免对人体的伤害,输电线路通常建设在偏僻或人烟稀少的地区,有些输电线路也架设于环境恶劣地区,例如山上或煤矿附近,当输电线路经过煤矿采空区等可能引起地基不均匀沉降区域时,会造成地基不均匀沉降,以致于杆塔的塔腿沉降不均,当沉降不均超过一定程度时,必然导致上部杆塔结构遭到破坏,从而影响输电线路的运行安全。According to the structural form, transmission lines are divided into overhead transmission lines and cable lines. Overhead transmission lines are usually composed of towers, wires, insulators, line fittings, guy wires, tower foundations, grounding devices, etc., and are erected on the ground. Existing tower foundations generally adopt independent foundations. As shown in Figure 1, the tower 11 has four tower legs 12, and each tower leg is supported by an independent foundation. The independent foundation includes upper columns 13 and lower stepped Bottom plate 14. In order to avoid harm to the human body, transmission lines are usually built in remote or sparsely populated areas, and some transmission lines are also erected in areas with harsh environments, such as mountains or near coal mines. When the transmission line passes through coal mine goafs, it may cause uneven subsidence of the foundation. When the settlement is uneven, it will cause uneven settlement of the foundation, so that the settlement of the tower legs of the tower is uneven. When the uneven settlement exceeds a certain level, it will inevitably lead to damage to the upper tower structure, thereby affecting the operation safety of the transmission line.

因此,迫切的需要本领域技术人员开发出一款在杆塔的塔腿产生不均匀沉降时,可以满足上部杆塔结构稳定性要求的可调高度型杆塔基础及其发生倾斜时的调节方法。Therefore, there is an urgent need for those skilled in the art to develop a height-adjustable tower foundation that can meet the structural stability requirements of the upper tower when uneven settlement occurs on the tower legs of the tower and its adjustment method when tilting occurs.

发明内容Contents of the invention

为了克服现有技术的上述缺陷,本发明的目的之一在于提出一种可以满足杆塔结构稳定性要求的可调高度型杆塔基础的调节方法。In order to overcome the above-mentioned defects of the prior art, one of the purposes of the present invention is to propose a height-adjustable tower foundation adjustment method that can meet the structural stability requirements of the tower.

本发明是通过以下技术方案来实现的:The present invention is achieved through the following technical solutions:

一种可调高度型杆塔基础的调节方法,该杆塔基础包括立柱、横梁I、竖梁、横梁II、竖撑、底板和地脚螺栓,用于支撑杆塔塔腿的各立柱通过横梁I和竖梁连成基本结构,该基本结构的两侧分别对称设有两根横梁II,每一侧的两根横梁II之间通过竖撑相连接,在每两根通过竖撑相连的横梁II下端设有一底板,各地脚螺栓均埋设于底板中,并且其顶端依次穿过横梁II和竖撑上相对应的通孔后由垫片和螺母进行紧固;所述垫片呈上、下端面均为水平面的圆环结构;当该杆塔基础发生倾斜时,将垫片更换为垫片,所述垫片呈下端面为水平状、上端面为倾斜面的环状结构;A method for adjusting the height-adjustable tower foundation. The tower foundation includes columns, beams I, vertical beams, beams II, vertical braces, bottom plates and anchor bolts. The columns used to support the tower legs pass through the beams I and vertical Beams are connected to form a basic structure, and two beams II are symmetrically arranged on both sides of the basic structure, and the two beams II on each side are connected by vertical braces, and a bottom plate is provided at the lower end of every two beams II connected by vertical braces , all the anchor bolts are buried in the bottom plate, and the tops of them pass through the corresponding through holes on the beam II and the vertical support in turn, and then are fastened by gaskets and nuts; the upper and lower end surfaces of the gaskets are both horizontal. Ring structure; when the foundation of the pole tower is inclined, the gasket is replaced with a gasket, and the gasket has a ring structure with a horizontal lower end surface and an inclined upper end surface;

该调节方法包括如下步骤:The adjustment method includes the following steps:

A)当地基不均匀沉降造成该杆塔基础发生倾斜时,先旋松固定地脚螺栓的螺母,取下垫片和螺母;再挖开竖撑与底板之间的空间,用工具将竖撑较低一侧顶起,调整竖撑的顶面至水平状态;A) When the uneven settlement of the ground causes the foundation of the tower to tilt, first unscrew the nuts fixing the anchor bolts, remove the gasket and nuts; then dig out the space between the vertical brace and the bottom plate, and use tools to tighten the vertical brace Lift up the lower side, and adjust the top surface of the vertical support to a horizontal state;

B)如果经步骤A调整后,地基不均匀沉降已结束,则先采用混凝土或水泥砂浆将横梁II和竖撑上的通孔以及横梁II与底板间的空间浇注成一体式结构;再将垫片套设于地脚螺栓上,并通过螺母对地脚螺栓进行固定;最后取出顶起竖撑较低一侧的工具,采用混凝土或水泥砂浆将竖撑与底板间的空间浇注成一体式结构;B) If after the adjustment in step A, the uneven settlement of the foundation has ended, first use concrete or cement mortar to pour the through holes on the beam II and the vertical brace and the space between the beam II and the bottom plate to form an integrated structure; The sheet is set on the anchor bolts, and the anchor bolts are fixed by nuts; finally, the tool for jacking up the lower side of the vertical brace is taken out, and the space between the vertical brace and the bottom plate is poured into an integrated structure with concrete or cement mortar ;

C)如果经步骤A调整后,预测到地基不均匀沉降会再次产生,则用与通孔同径的护管护住横梁II与底板间的那段地脚螺栓,并采用混凝土或水泥砂浆将横梁II与底板间的空间浇注成一体式结构;当二次地基不均匀沉降已结束,则用工具重新调整竖撑的顶面至水平状态后,重复步骤B;如预测到地基不均匀沉降会继续产生,则重复步骤C;C) If after the adjustment in step A, it is predicted that the uneven settlement of the foundation will occur again, use a protective pipe with the same diameter as the through hole to protect the section of anchor bolts between the beam II and the bottom plate, and use concrete or cement mortar to The space between the beam II and the bottom plate is poured into an integrated structure; when the secondary uneven settlement of the foundation is over, use tools to readjust the top surface of the vertical brace to a horizontal state, and then repeat step B; if it is predicted that the uneven settlement of the foundation will Continue to generate, then repeat step C;

所述步骤A中的垫片呈上、下端面均为水平面的圆环结构,所述步骤B中的垫片呈下端面为水平状、上端面为倾斜面的环状结构。The gasket in the step A has a ring structure with both upper and lower end surfaces being horizontal, and the gasket in the step B has a ring structure with a horizontal lower end surface and an inclined upper end surface.

其中,所述横梁II和竖撑上通孔的孔径不小于地脚螺栓直径的2倍。Wherein, the diameter of the through hole on the beam II and the vertical support is not less than twice the diameter of the anchor bolt.

其中,所述横梁I、竖梁和横梁II的底面均与立柱的底面平齐,所述横梁I、竖梁和横梁II的顶面均低于立柱的顶面。Wherein, the bottom surfaces of the beam I, the vertical beam and the beam II are all flush with the bottom surface of the column, and the top surfaces of the beam I, the vertical beam and the beam II are all lower than the top surface of the column.

其中,所述立柱、横梁I、竖梁、横梁II、竖撑连成一体式结构。Wherein, the column, the beam I, the vertical beam, the beam II, and the vertical brace are connected into an integrated structure.

其中,所述立柱的数量为四根,四根立柱按照矩形进行分布。Wherein, the number of the columns is four, and the four columns are distributed according to a rectangle.

其中,所述步骤B中,在用混凝土或水泥砂浆将横梁II与底板间的空间以及竖撑与底板间的空间浇注成一体式结构前,在横梁II与底板间的空间以及竖撑与底板间的空间设置钢筋网片。Wherein, in the step B, before using concrete or cement mortar to pour the space between the beam II and the bottom plate and the space between the vertical brace and the bottom plate into an integrated structure, the space between the beam II and the bottom plate and the space between the vertical brace and the bottom plate Set the steel mesh sheet in the space between.

其中,将竖撑较低一侧顶起,调整竖撑的顶面至水平状态的工具为千斤顶。Wherein, the lower side of the vertical support is jacked up, and the tool for adjusting the top surface of the vertical support to a horizontal state is a jack.

本发明的有益效果在于:The beneficial effects of the present invention are:

1)本发明的杆塔基础将用于支撑杆塔塔腿的各立柱通过横梁I和竖梁连接为一体式结构,这种杆塔基础形式不易发生不均匀沉降,当地基不均匀沉降时,本发明的杆塔基础结构完全可以满足上部杆塔的稳定性要求;该杆塔基础具有结构简单,稳定可靠等优点。1) The pole tower foundation of the present invention connects each upright column that is used to support the tower legs of the pole tower through the crossbeam I and the vertical beam into an integrated structure. This form of pole tower foundation is not prone to uneven settlement. When the foundation is unevenly settled, the present invention The tower foundation structure can fully meet the stability requirements of the upper tower; the tower foundation has the advantages of simple structure, stability and reliability.

2)当地基不均匀沉降造成杆塔基础发生倾斜时,通过本发明的调节方法,可以调节杆塔基础四角的高度,使立柱顶面重新保持水平,以保证上部杆塔的稳定性要求;该调节方法具有操作简单、可靠性高等优点。2) When the uneven settlement of the ground causes the tower foundation to tilt, the adjustment method of the present invention can adjust the height of the four corners of the tower foundation, so that the top surface of the column can be kept horizontal again to ensure the stability requirements of the upper tower; the adjustment method has It has the advantages of simple operation and high reliability.

附图说明Description of drawings

图1是现有独立式基础的结构示意图,其中,11-杆塔,12-塔腿,13-立柱,14-底板;Fig. 1 is the structural schematic diagram of existing free-standing foundation, wherein, 11-pole tower, 12-tower leg, 13-column, 14-base plate;

图2是本发明可调高度型杆塔基础的结构示意图;Fig. 2 is a schematic structural view of the height-adjustable pole tower foundation of the present invention;

图3是图2的A-A剖视图;Fig. 3 is the A-A sectional view of Fig. 2;

图4是图2的B-B剖视图;Fig. 4 is the B-B sectional view of Fig. 2;

图5是通过本发明调节方法调整后、杆塔基础的状态示意图;Fig. 5 is a schematic diagram of the state of the tower foundation after being adjusted by the adjustment method of the present invention;

图6是图5中I部的放大示意图Fig. 6 is the enlarged schematic view of part I in Fig. 5

其中,21-立柱,22-横梁I,23-竖梁,24-横梁II,25-竖撑,26-底板,27-地脚螺栓,28、28′-垫片,29-螺母,210-通孔,211-护管,212-千斤顶,213-水泥砂浆或混凝土。Among them, 21-column, 22-beam I, 23-vertical beam, 24-beam II, 25-vertical support, 26-bottom plate, 27-anchor bolt, 28, 28'-washer, 29-nut, 210- Through hole, 211-protective pipe, 212-jack, 213-cement mortar or concrete.

具体实施方式Detailed ways

下面结合附图对本发明的可调高度型杆塔基础及其发生倾斜时的调节方法做进一步详细的说明。The height-adjustable pole tower foundation of the present invention and its adjustment method when tilted will be described in further detail below in conjunction with the accompanying drawings.

如图2-4所示,本例中的可调高度型杆塔基础主要包括用于支撑杆塔塔腿12的立柱21,横梁I 22,竖梁23,横梁II 24,竖撑25,底板26和地脚螺栓27;立柱21、横梁I 22、竖梁23、横梁II 24、竖撑25连成一体式结构。四根立柱21之间通过两根对称设置的横梁I 22和两根对称设置的竖梁23连成基本结构,该基本结构的横截面为矩形,四根立柱21分别设置在四角上,每根立柱21的外侧分别连接有一根横梁II,其中两根横梁II与立柱之间的一根横梁I同轴设置、另外两根横梁II与立柱之间对称设置的另一根横梁I同轴设置,并且每两根相对的横梁II上端通过一根竖撑25相连接,在这两根通过竖撑相连的横梁II的下端固设有一预埋四根地脚螺栓27的底板26,每根横梁II 24和竖撑25上均设有供相应的地脚螺栓穿过的通孔210,每根地脚螺栓27的顶端依次穿过横梁II24和竖撑25上的通孔210后,分别由垫片28和螺母29进行紧固。横梁I 22、竖梁23和横梁II 24的底面均与立柱21的底面平齐,横梁I、竖梁和横梁II的顶面均低于立柱的顶面。立柱21、横梁I 22、竖梁23、横梁II 24、竖撑25和底板26均由钢筋骨架和混凝土一体浇注成型。As shown in Figure 2-4, the height-adjustable tower foundation in this example mainly includes the column 21 for supporting the tower leg 12, the beam I 22, the vertical beam 23, the beam II 24, the vertical brace 25, the bottom plate 26 and Anchor bolt 27; Column 21, crossbeam I 22, vertical beam 23, crossbeam II 24, vertical brace 25 are connected into an integrated structure. Between the four columns 21, two symmetrically arranged beams 122 and two symmetrically arranged vertical beams 23 are connected to form a basic structure. The cross section of the basic structure is a rectangle. The outer sides of the column 21 are respectively connected with a beam II, wherein two beams II are arranged coaxially with a beam I between the column, and the other two beams II are arranged coaxially with the other beam I symmetrically arranged between the column, And the upper ends of every two opposite beams II are connected by a vertical brace 25, and a bottom plate 26 with four anchor bolts 27 is fixed at the lower ends of the two beams II connected by vertical braces, and each beam II 24 and vertical brace 25 are all provided with through holes 210 for corresponding anchor bolts to pass through. 28 and nut 29 for fastening. The bottom surface of crossbeam I 22, vertical beam 23 and crossbeam II 24 is all flush with the bottom surface of column 21, and the top surface of crossbeam I, vertical beam and crossbeam II is all lower than the top surface of column. Column 21, crossbeam I 22, vertical beam 23, crossbeam II 24, vertical brace 25 and base plate 26 are all integrally casted by steel skeleton and concrete.

为了使杆塔基础倾斜时调整方便,最好使横梁II 24和竖撑25上通孔210的孔径不小于地脚螺栓27直径的2倍。In order to make the adjustment convenient when the tower foundation is inclined, it is preferable to make the aperture of the through hole 210 on the beam II 24 and the vertical brace 25 not less than 2 times of the anchor bolt 27 diameters.

初始构建的该杆塔基础的垫片28为圆环状,其底面与顶面均为水平面;当发生地基不均匀沉降造成杆塔基础倾斜时,根据各立柱的沉降高度,将垫片28拆下替换成新垫片28′,新垫片28′呈底面为水平面、顶面为倾斜面的环状结构,新垫片28′可以满足其底面与竖撑25的顶面相贴紧,而顶面与调整后的地脚螺栓27的轴线相垂直,从而保证螺母29、垫片28′与地脚螺栓27相配合该杆塔基础的各部件进行紧固连接。The gasket 28 of the initially constructed tower foundation is in the shape of a ring, and its bottom and top surfaces are both horizontal; when the uneven settlement of the foundation causes the tower foundation to tilt, the gasket 28 is removed and replaced according to the settlement height of each column into a new pad 28', the new pad 28' is a ring-shaped structure whose bottom surface is a horizontal plane and the top surface is an inclined surface. The axes of the adjusted anchor bolts 27 are perpendicular to each other to ensure that the nuts 29, washers 28' and the anchor bolts 27 cooperate with each part of the tower foundation for fastening and connection.

当地基不均匀沉降造成该杆塔基础发生倾斜时,可通过如下调节方法对杆塔基础进行调节,具体步骤包括:When the uneven settlement of the foundation causes the tower foundation to tilt, the tower foundation can be adjusted through the following adjustment methods. The specific steps include:

A)当地基不均匀沉降造成该杆塔基础发生倾斜时,先旋松固定地脚螺栓的螺母29,取下垫片28和螺母29;再挖开竖撑25与底板26之间的空间,将千斤顶212置于沉降较大的一端,将竖撑25较低一侧顶起,调整竖撑的顶面至水平状态;A) When the uneven settlement of the ground causes the tower foundation to incline, first unscrew the nut 29 of the anchor bolt, take off the gasket 28 and the nut 29; then dig the space between the vertical brace 25 and the base plate 26, and place The jack 212 is placed at the end with larger settlement, and the lower side of the vertical brace 25 is lifted up, and the top surface of the vertical brace is adjusted to a horizontal state;

B)如果经步骤A调整后,通过沉降监测仪器预测到地基不均匀沉降已基本结束,则先采用混凝土或水泥砂浆将横梁II和竖撑上的通孔210以及横梁II 24与底板26间的空间浇注成一体式结构;再将垫片28′套设于地脚螺栓27上,确保该新垫片28′的底面与竖撑25的顶面相贴紧、顶面与地脚螺栓27的轴线方向相垂直;然后通过螺母29对地脚螺栓进行固定;固定好后,取出千斤顶212,用混凝土或水泥砂浆将竖撑25与底板26间的空间浇注成一体式结构,经过该调节方法调整后的杆塔基础图5所示;B) If after step A is adjusted, the settlement monitoring instrument predicts that the uneven settlement of the foundation has basically ended, then first use concrete or cement mortar to seal the through holes 210 on the beam II and the vertical brace and the gap between the beam II 24 and the base plate 26 The space is poured into an integrated structure; then the gasket 28' is sleeved on the anchor bolt 27 to ensure that the bottom surface of the new gasket 28' is closely attached to the top surface of the vertical support 25, and the axis of the top surface and the anchor bolt 27 The direction is vertical; then the anchor bolts are fixed by nuts 29; after fixing, take out the jack 212, and use concrete or cement mortar to pour the space between the vertical brace 25 and the bottom plate 26 into an integrated structure, after adjustment by this adjustment method The tower foundation shown in Figure 5;

C)如果经步骤A调整后,通过沉降监测仪器预测到地基不均匀沉降会再次产生,则用与通孔210同径的护管211(同径即为:通孔的孔径与护管的外径相等,)护住横梁II 24与底板26间的那段地脚螺栓27,并用混凝土或水泥砂浆213将横梁II 24与底板26间的空间浇注成一体式结构,护管211可以采用钢管;通过护管211可以确保对横梁II 24与底板26间的空间进行浇注时,混凝土或水泥砂浆213不会灌入到通孔210中,以保证再次发生沉降时,还可以对杆塔基础进行调整;当通过沉降监测仪器预测到二次地基不均匀沉降已结束并且不会发生再次沉降时,则用千斤顶212重新调整竖撑25的顶面至水平状态后,重复步骤B;如沉降监测仪器预测到地基不均匀沉降会继续产生,则重复步骤C。C) If after the adjustment in step A, it is predicted by the settlement monitoring instrument that the uneven settlement of the foundation will occur again, then use the protective pipe 211 with the same diameter as the through hole 210 (the same diameter is: the aperture of the through hole and the outer surface of the protective pipe) diameter is equal,) protect that section of anchor bolt 27 between beam II 24 and base plate 26, and pour the space between beam II 24 and base plate 26 into an integrated structure with concrete or cement mortar 213, and protective pipe 211 can adopt steel pipe; When the space between the beam II 24 and the base plate 26 can be guaranteed to be poured through the protective pipe 211, concrete or cement mortar 213 will not be poured into the through hole 210, so that when the settlement occurs again, the tower foundation can also be adjusted; When it is predicted by the settlement monitoring instrument that the secondary uneven settlement of the foundation has ended and no further settlement will occur, then use the jack 212 to readjust the top surface of the vertical brace 25 to a horizontal state, and then repeat step B; if the settlement monitoring instrument predicts that If uneven settlement of foundation will continue to occur, repeat step C.

为了提高杆塔基础的稳定性,在用混凝土或水泥砂浆213将横梁II 24与底板26间的空间以及竖撑25与底板26间的空间浇注成一体式结构之前,最好在横梁II 24与底板26间的空间以及竖撑25与底板26间的空间均加设有钢筋网片。In order to improve the stability of the tower foundation, before the space between the beam II 24 and the base plate 26 and the space between the vertical brace 25 and the base plate 26 are poured into an integrated structure with concrete or cement mortar 213, it is best to place the beam II 24 and the base plate The space between 26 and the space between the vertical support 25 and the base plate 26 are all provided with reinforced mesh sheets.

初始构建的该杆塔基础的垫片28为圆环状,其底面与顶面均为水平面;当发生地基不均匀沉降造成杆塔基础倾斜时,根据各立柱沉降的高度,再需要对地脚螺栓27进行紧固前,将新垫片28′套设于地脚螺栓27上,由于该垫片28′呈底面为水平面、顶面为倾斜面的环状结构(垫片28′的顶面与底面之间的夹角0°<θ<90°),所以可以满足如图6所示的垫片28′的底面与竖撑25的顶面相贴紧,而顶面与调整后的地脚螺栓27的轴线相垂直,可以保证螺母与地脚螺栓的紧固连接,使调整后的杆塔基础更加安全可靠。The gasket 28 of the initially constructed tower foundation is circular, and its bottom and top surfaces are both horizontal; when uneven settlement of the foundation causes the tower foundation to tilt, according to the height of the settlement of each column, it is necessary to adjust the anchor bolts 27 Before fastening, the new gasket 28' is sleeved on the anchor bolt 27. Since the gasket 28' is a ring-shaped structure with the bottom surface as a horizontal plane and the top surface as an inclined surface (the top surface and the bottom surface of the gasket 28' The angle between them is 0°<θ<90°), so it can be satisfied that the bottom surface of the gasket 28' as shown in Fig. The axes are perpendicular to each other, which can ensure the tight connection between the nut and the anchor bolt, making the adjusted tower foundation safer and more reliable.

当地基不均匀沉降造成杆塔基础发生倾斜时,通过该调节方法,可以调节杆塔基础四角的高度,使用于支撑杆塔塔腿的各立柱顶面重新保持水平,以保证上部杆塔的稳定性要求。When the uneven settlement of the foundation causes the tower foundation to tilt, the height of the four corners of the tower foundation can be adjusted through this adjustment method, so that the top surfaces of the columns supporting the tower legs can be kept horizontal again to ensure the stability requirements of the upper tower.

最后应当说明的是:以上实施例仅用以说明本发明的技术方案而非对其限制,尽管参照上述实施例对本发明进行了详细的说明,所属领域的普通技术人员应当理解:依然可以对本发明的具体实施方式进行修改或者等同替换,而未脱离本发明精神和范围的任何修改或者等同替换,其均应涵盖在本发明的权利要求范围当中。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and not to limit them. Although the present invention has been described in detail with reference to the above embodiments, those of ordinary skill in the art should understand that: the present invention can still be Any modification or equivalent replacement that does not depart from the spirit and scope of the present invention shall be covered by the scope of the claims of the present invention.

Claims (7)

1. the control method of an adjustable height type pole and tower foundation, described pole and tower foundation comprises column (21), crossbeam I (22), vertical beam (23), crossbeam II (24), perpendicular support (25), base plate (26) and foundation bolt (27), it is characterized in that: each column (21) for supporting shaft tower tower leg is linked to be basic structure by crossbeam I (22) and vertical beam (23), the both sides of this basic structure are arranged with two crossbeam II (24) respectively, be connected by perpendicular support (25) between two crossbeam II of every side, a base plate (26) is provided with in every two crossbeam II lower ends be connected by perpendicular support, each foundation bolt (27) is all embedded in base plate (26), and its top is successively through being undertaken fastening by pad (28) and nut (29) after crossbeam II (24) and the upper corresponding through hole (210) of perpendicular support (25), described pad (28) goes to upper and lower the circular ring structure that end face is horizontal plane, when this pole and tower foundation run-off the straight, pad (28) is replaced by pad (28 '), described pad (28 ') is horizontal, upper surface in lower surface is the circulus of inclined plane,
The control method of described adjustable height type pole and tower foundation comprises the steps:
A) when uneven settlement of foundation causes this pole and tower foundation run-off the straight, first unscrew the nut (29) of foot bolt regularly, take off pad (28) and nut (29); Excavate the space between perpendicular support (25) and base plate (26) again, will erect support (25) lower side jack-up with instrument, the end face of the perpendicular support of adjustment is to level;
B) if after steps A adjustment, uneven settlement of foundation terminates, then first adopt concrete or cement mortar crossbeam II and the perpendicular through hole (210) that supports and the space between crossbeam II (24) and base plate (26) to be poured into an integrated entity formula structure; Again pad (28 ') is sheathed on foundation bolt (27), and by nut (29), foundation bolt is fixed; Finally take out jack-up and erect the instrument of the lower side of support, adopt concrete or cement mortar to be poured into an integrated entity in the space of erecting between support (25) and base plate (26) formula structure;
C) if after steps A adjustment, predict uneven settlement of foundation can again produce, then protect that section of foundation bolt (27) between crossbeam II (24) and base plate (26) with through hole (210) with the pillar (211) in footpath, and adopt concrete or cement mortar to be poured into an integrated entity in the space between crossbeam II (24) and base plate (26) formula structure; When secondary uneven settlement of foundation terminates, then readjust the end face of perpendicular support to level with instrument, repeat step B; Can continue to produce as predicted uneven settlement of foundation, then repeat step C;
Described steps A) in pad (28) go to upper and lower the circular ring structure that end face is horizontal plane, the pad (28 ') in described step B is horizontal, upper surface in lower surface is the circulus of inclined plane.
2. control method as claimed in claim 1, is characterized in that: the aperture of described crossbeam II (24) and the upper through hole (210) of perpendicular support (25) is not less than 2 times of foundation bolt (27) diameter.
3. control method as claimed in claim 1, it is characterized in that: described crossbeam I (22), vertical beam (23) are all concordant with the bottom surface of column (21) with the bottom surface of crossbeam II (24), and the end face of described crossbeam I, vertical beam and crossbeam II is all lower than the end face of column.
4. control method as claimed in claim 1, is characterized in that: described column (21), crossbeam I (22), vertical beam (23), crossbeam II (24), perpendicular support (25) are connected formula structure.
5. control method as claimed in claim 1, is characterized in that: the quantity of described column (21) is four, and four root posts distribute according to rectangle.
6. control method as claimed in claim 1, it is characterized in that: in described step B, before the formula structure that the space between crossbeam II (24) and base plate (26) and perpendicular space of support between (25) and base plate (26) poured into an integrated entity by concrete or cement mortar, the space between crossbeam II (24) and base plate (26) and erect the spatial placement reinforced mesh supportted between (25) and base plate (26).
7. the control method as described in claim 1 or 6, is characterized in that: will erect support (25) lower side jack-up, and the perpendicular end face supportted of adjustment is jack (212) to the instrument of level.
CN201110262996.XA 2011-09-07 2011-09-07 Method for adjusting height-adjustable tower foundation Active CN102425188B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110262996.XA CN102425188B (en) 2011-09-07 2011-09-07 Method for adjusting height-adjustable tower foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110262996.XA CN102425188B (en) 2011-09-07 2011-09-07 Method for adjusting height-adjustable tower foundation

Publications (2)

Publication Number Publication Date
CN102425188A CN102425188A (en) 2012-04-25
CN102425188B true CN102425188B (en) 2015-03-25

Family

ID=45959214

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110262996.XA Active CN102425188B (en) 2011-09-07 2011-09-07 Method for adjusting height-adjustable tower foundation

Country Status (1)

Country Link
CN (1) CN102425188B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836942B (en) * 2016-12-14 2019-03-19 李家树 A kind of pylon Anti-inclining pedestal
CN109594579A (en) * 2018-02-11 2019-04-09 乌鲁木齐智源易通智能科技有限公司 Transmission line tower foundation and its reinforcement means
CN111368411B (en) * 2020-02-27 2020-11-27 国网山西省电力公司晋城供电公司 A balanced pole tower foundation and its design method and design device
CN114525806A (en) * 2022-03-31 2022-05-24 四川电力设计咨询有限责任公司 Iron tower single-pile combined foundation and construction method thereof
CN115435183A (en) * 2022-09-13 2022-12-06 上海船舶电子设备研究所(中国船舶集团有限公司第七二六研究所) Underwater attitude adjustment construction operation device and method for underwater equipment
CN116988507B (en) * 2023-08-15 2025-12-02 中国电建集团西北勘测设计研究院有限公司 Self-adjusting foundation device and tower modification method for power transmission and transformation engineering towers
CN118187133A (en) * 2024-04-30 2024-06-14 四川翔晖路桥工程有限公司 A method for preventing bridge pile foundation from settling
CN119754621B (en) * 2025-03-06 2025-05-13 甘肃电通电力工程设计咨询有限公司 Power transmission line tower foundation height adjusting device

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101187268A (en) * 2007-08-08 2008-05-28 安徽省电力公司淮北供电公司 Uniform settlement and height-adjustable transmission towers
CN101250952A (en) * 2008-04-02 2008-08-27 大连理工大学 Adjustable real-time self-balancing transmission tower with cable-stayed slanted columns
CN201817817U (en) * 2010-10-15 2011-05-04 汤跃超 Integral continuously-adjustable foundation for power transmission and transformation tower (pole)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8272181B2 (en) * 2009-03-03 2012-09-25 Tooman Norman L Grout sleeve for foundation anchor bolts and method for protection of anchor bolts for a vertical structure, including wind turbines

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101187268A (en) * 2007-08-08 2008-05-28 安徽省电力公司淮北供电公司 Uniform settlement and height-adjustable transmission towers
CN101250952A (en) * 2008-04-02 2008-08-27 大连理工大学 Adjustable real-time self-balancing transmission tower with cable-stayed slanted columns
CN201817817U (en) * 2010-10-15 2011-05-04 汤跃超 Integral continuously-adjustable foundation for power transmission and transformation tower (pole)

Also Published As

Publication number Publication date
CN102425188A (en) 2012-04-25

Similar Documents

Publication Publication Date Title
CN102425188B (en) Method for adjusting height-adjustable tower foundation
CN202273244U (en) Height-adjustable tower leg connecting device of pole tower
CN103132766B (en) Truss for lifting power transmission line tower connecting leg and erection method
JP2013112926A (en) Foundation structure for photovoltaic generation device, and construction method for the same
CN110565676A (en) Cantilever type tower crane foundation structure and construction method thereof
CN112878354A (en) Beam-slab assembled prestressed concrete foundation for onshore wind turbine generator
CN107326816A (en) A kind of method for improving of prefabricated pinner and bridge
CN101691813B (en) Device and method for elevation synchronous compensation for super-high structure construction
CN111119222A (en) An assembly device for towers of UHVDC transmission lines in alpine regions
CN117005739A (en) A bottom support system for shallow round silo roof construction and its construction method
CN202273243U (en) Adjustable height type pole and tower foundation
CN102277900A (en) Sectional-stacking jacking mounting method of vase-shaped space steel structure
CN221760464U (en) Construction structure for anchoring No. 0 blocks and pier beams of small-size bearing platform pier body
CN219586774U (en) Prefabricated retaining wall suitable for crown beam top
TWI814472B (en) Wind power generation tower and construction method of wind power generation tower
CN210714048U (en) Self-supporting iron tower base deviation correcting device
CN216555980U (en) Suspension protection device for large-span pipeline
CN204112827U (en) A kind of communications tower
CN211713706U (en) A large cantilever prefabricated cover beam installation lattice support device
CN212026321U (en) Underwater steel structure tower crane foundation
CN215053064U (en) Lattice column verticality correction device
CN212927216U (en) Assembled steel structure foundation of prefabricated cabin transformer substation
CN216948301U (en) Supporting structure of foundation pit
CN108547312A (en) The blower foundation of steel truss structure
CN212359287U (en) Steep slope iron tower leg heightening structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Effective date: 20130520

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20130520

Address after: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15

Applicant after: China Electric Power Research Institute

Applicant after: State Grid Corporation of China

Address before: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15

Applicant before: China Electric Power Research Institute

C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15

Patentee after: CHINA ELECTRIC POWER RESEARCH INSTITUTE Co.,Ltd.

Patentee after: STATE GRID CORPORATION OF CHINA

Address before: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15

Patentee before: China Electric Power Research Institute

Patentee before: State Grid Corporation of China