CN207469740U - For the hanging seat of climbing type scaffold - Google Patents

For the hanging seat of climbing type scaffold Download PDF

Info

Publication number
CN207469740U
CN207469740U CN201721621897.5U CN201721621897U CN207469740U CN 207469740 U CN207469740 U CN 207469740U CN 201721621897 U CN201721621897 U CN 201721621897U CN 207469740 U CN207469740 U CN 207469740U
Authority
CN
China
Prior art keywords
hanging seat
plate
fixing piece
installing plate
hanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721621897.5U
Other languages
Chinese (zh)
Inventor
张荣华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Pioneer Mould Frame Technology Co., Ltd.
Original Assignee
张荣华
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 张荣华 filed Critical 张荣华
Priority to CN201721621897.5U priority Critical patent/CN207469740U/en
Application granted granted Critical
Publication of CN207469740U publication Critical patent/CN207469740U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model provides a kind of hanging seat for climbing type scaffold, it is related to building engineering construction apparatus field, including upper hanging seat and lower hanging seat, upper hanging seat is located at the upper end of lower hanging seat, lower hanging seat is connect with scaffold, it is connected between upper hanging seat and lower hanging seat by lifting device, upper hanging seat includes the first fixing piece and the first installed part, first fixing piece is connect with major structure of construction, first installed part is fixedly connected with the first fixing piece, first installed part is provided with the first rib close to one end of the first fixing piece, and the first rib is embedded in the first fixing piece.This hanging seat can very easily carry out the operation that moves up of scaffold, and hanging seat and lower hanging seat on this, rational in infrastructure, stablize and can save a large amount of material, and manufacture cost is made to be well controlled.

Description

For the hanging seat of climbing type scaffold
Technical field
The utility model relates generally to building engineering construction apparatus field, and climbing type foot is used in particular to one kind The hanging seat of hand cradle.
Background technology
At present, Climbing frame for outer-wall uses raise scaffold more in Tall Reinforced Concrete Buildings construction, but is made at present Lifting scaffold device is such as big for installing the consumption of materials of scaffold all there are some shortcomings, hanging seat itself it is strong Degree needs a large amount of reinforcement structure to maintain, and its stability Shortcomings.
Utility model content
The purpose of this utility model is to provide a kind of hanging seats for climbing type scaffold, are there is the problem of above-mentioned Effect improves.
The utility model is realized in this way:
Based on above-mentioned purpose, the embodiment of the utility model provides a kind of hanging seat for climbing type scaffold, including Upper hanging seat and lower hanging seat, the upper hanging seat are located at the upper end of the lower hanging seat, and the lower hanging seat is connect with the scaffold, described It being connected between upper hanging seat and the lower hanging seat by lifting device, the upper hanging seat includes the first fixing piece and the first installed part, First fixing piece is connect with major structure of construction, and first installed part is fixedly connected with first fixing piece, described First installed part is provided with the first rib close to one end of first fixing piece, and first rib is embedded at described In first fixing piece.
In the alternative embodiment of the utility model, first fixing piece includes at least two first horizontal strokes arranged side by side The first longeron that beam and Duo Gen are arranged side by side, more first longerons are connected between two first crossbeams, and described One installed part includes at least two pieces the first installing plates arranged side by side, hanging plate, the first tie-beam and at least two piece of first securing plate, First installing plate is vertically set, and the side of first tie-beam is consolidated with one of first installing plate Fixed, the opposite side of first tie-beam is fixed with another piece of first installing plate, and first tie-beam is positioned at described The centre position of first installing plate, the hanging plate are set to the top of first installing plate, and the hanging plate is located at described the One end far from the first crossbeam of one installing plate, the centre position of the hanging plate offers hanging hole, first securing plate Horizontally disposed, one of first securing plate is located at the top of first installing plate, another piece described first Securing plate is located at the bottom of first installing plate, and first securing plate is fixed with the first crossbeam, and described first adds Strong portion is located between two first crossbeams.
In the alternative embodiment of the utility model, one side that the first crossbeam is connect with first securing plate is the One mounting surface, the distance between first mounting surface and the one side far from the hanging plate of first rib add for first Strong distance, described first strengthens distance between 1.5cm-3cm.
In the alternative embodiment of the utility model, described first strengthens distance as 2cm.
In the alternative embodiment of the utility model, the lower hanging seat includes the second fixing piece and the second installed part, described Second fixing piece is connect with the scaffold, and second installed part is fixedly connected with second fixing piece, second peace Piece installing is provided with the second rib close to one end of second fixing piece, and it is solid that second rib is embedded at described second Determine in part.
In the alternative embodiment of the utility model, second fixing piece includes at least two second horizontal strokes arranged side by side The second longeron that beam and Duo Gen are arranged side by side, more second longerons are connected between two second cross beams, and described Two installed parts include at least two pieces the second installing plates arranged side by side, the second tie-beam, at least two piece of second securing plate and extremely Few two reinforcing beams, second installing plate are vertically set, and the separate second cross beam of second installing plate One end offer through-hole, the side of second tie-beam is fixed with one of second installing plate, it is described second connect The opposite side and another piece of second installing plate for connecing beam are fixed, and second tie-beam is located in second installing plate Between position, second securing plate is horizontally disposed, and one of second securing plate is located at second installing plate Top, another piece of second securing plate be located at the bottom of second installing plate, and second securing plate and described the Two crossbeams are fixed, and two reinforcing beams are individually fixed in the side far from second installing plate of second securing plate, And the reinforcing beam is fixed with the second cross beam, second rib is located between two second cross beams.
In the alternative embodiment of the utility model, one side that the second cross beam is connect with second securing plate is the Two mounting surfaces, the distance between second mounting surface and the one side far from the through-hole of second rib add for second Strong distance, described second strengthens distance between 1.5cm-3cm.
In the alternative embodiment of the utility model, described second strengthens distance as 2cm.
Compared with prior art, the beneficial effects of the utility model are:
The hanging seat for the climbing type scaffold that the embodiment of the utility model provides, can be with there is provided upper hanging seat and lower hanging seat Very easily carry out scaffold moves up operation, and hanging seat and lower hanging seat on this, rational in infrastructure, stablize and can save greatly The material of amount makes manufacture cost be well controlled.
Description of the drawings
It, below will be to required in embodiment in order to illustrate more clearly of the technical solution of the utility model embodiment The attached drawing used is briefly described, it should be understood that the following drawings illustrates only some embodiments of the utility model, therefore not The restriction to range is should be considered as, for those of ordinary skill in the art, without creative efforts, It can also be obtained according to these attached drawings other relevant attached drawings.
Fig. 1 is the structure diagram for the upper hanging seat that the utility model embodiment provides;
Fig. 2 is the enlarged diagram at the A of Fig. 1;
Fig. 3 is the structure diagram for the lower hanging seat that the utility model embodiment provides.
Fig. 4 is the enlarged diagram at the B of Fig. 3.
Icon:The upper hanging seats of 10-;The first installed parts of 11-;The first installing plates of 110-;111- hanging plates;1110- hanging holes;112- One tie-beam;The first securing plates of 113-;The first fixing pieces of 12-;120- first crossbeams;The first longerons of 121-;13- first strengthens Portion;130- first strengthens distance;Hanging seat under 20-;The second fixing pieces of 21-;210- second cross beams;The second longerons of 211-;22- second Installed part;The second installing plates of 220-;2200- through-holes;The second tie-beams of 221-;The second securing plates of 222-;223- reinforcing beams;23- Second rib;230- second strengthens distance.
Specific embodiment
Purpose, technical scheme and advantage to make the utility model embodiment are clearer, new below in conjunction with this practicality Attached drawing in type embodiment, the technical scheme in the utility model embodiment is clearly and completely described, it is clear that is retouched The embodiment stated is the utility model part of the embodiment, instead of all the embodiments.Usually here described in attached drawing and The component of the utility model embodiment shown can be configured to arrange and design with a variety of different.Therefore, below to attached The detailed description of the embodiment of the utility model provided in figure is not intended to limit claimed the scope of the utility model, But it is merely representative of the selected embodiment of the utility model.
Embodiment
It please refers to shown in Fig. 1 and Fig. 3, the embodiment of the utility model provides a kind of extension for climbing type scaffold Seat, including upper hanging seat 10 and lower hanging seat 20, upper hanging seat 10 is located at the upper end of lower hanging seat 20, and lower hanging seat 20 is connect with scaffold, on It is connected between hanging seat 10 and lower hanging seat 20 by lifting device, lifting device here is electronic promotion cucurbit or hand It is dynamic to promote cucurbit.Upper hanging seat 10 includes the first fixing piece 12 and the first installed part 11, the first fixing piece 12 and major structure of construction Connection, the first installed part 11 are fixedly connected with the first fixing piece 12, one end of close first fixing piece 12 of the first installed part 11 The first rib 13 is provided with, the first rib 13 is embedded in the first fixing piece 12.
It should be noted that under the cooperation of upper hanging seat 10, lower hanging seat 20 and lifting device, entire scaffold can be very Easily climb.
In the present embodiment, the first fixing piece 12 includes at least two first crossbeams 120 and Duo Gen arranged side by side side by side First longeron 121 of setting, more first longerons 121 are connected between two first crossbeams 120, and the first installed part 11 is included extremely Few two pieces of first installing plates 110 arranged side by side, hanging plate 111, the first tie-beam 112 and at least two piece of first securing plate 113, the One installing plate 110 is vertically set, and the side of the first tie-beam 112 is fixed with one of first installing plate 110, and first The opposite side of tie-beam 112 is fixed with another piece of the first installing plate 110, and the first tie-beam 112 is located at the first installing plate 110 Centre position, hanging plate 111 are set to the top of the first installing plate 110, and hanging plate 111 be located at the first installing plate 110 far from the One end of one crossbeam 120, the centre position of hanging plate 111 offer hanging hole 1110, and hanging hole 1110 here is used for and lifting device The hook on top is connected, and the first securing plate 113 is horizontally disposed, and one of first securing plate 113 is located at the first installation The top of plate 110, another piece of the first securing plate 113 are located at the bottom of the first installing plate 110, and the first securing plate 113 and first Crossbeam 120 is fixed, and the first rib 13 is located between two first crossbeams 120.
First rib 13 is embedded between two first crossbeams 120, and the first crossbeam 120 positioned at upper end is allow to push down the One rib 13 is more secured so as to make to connect between the first installing plate 110 and first crossbeam 120.
It please refers to shown in Fig. 2, in the present embodiment, the one side that first crossbeam 120 is connect with the first securing plate 113 is first The distance between one side of separate hanging plate 111 of mounting surface, the first mounting surface and the first rib 13 strengthens distance for first 130, first strengthens distance 130 between 1.5cm-3cm, it is preferable that the first reinforcement distance 130 is set as 2cm.This away from From, can allow hanging seat 10 have enough intensity support the pulling force of electric block, and structural material can be saved.
It please refers to shown in Fig. 3, in the alternative embodiment of the utility model, lower hanging seat 20 includes the second fixing piece 21 and the Two installed parts 22, the second fixing piece 21 are connect with scaffold, and the second installed part 22 is fixedly connected with the second fixing piece 21, the second peace Piece installing 22 is provided with the second rib 23 close to one end of the second fixing piece 21, and the second rib 23 is embedded at the second fixing piece In 21.
In the present embodiment, the second fixing piece 21 includes at least two second cross beams 210 and Duo Gen arranged side by side side by side Second longeron 211 of setting, more second longerons 211 are connected between two second cross beams 210, and the second installed part 22 is included extremely Few two pieces of second installing plates 220 arranged side by side, the second tie-beam 221, at least two piece of second securing plate 222 and at least two Reinforcing beam 223, the second installing plate 220 are vertically set, and one end of the separate second cross beam 210 of the second installing plate 220 Through-hole 2200 is offered, through-hole 2200 here is used to be connected with the hook of lifting device lower part.The side of second tie-beam 221 It is fixed with one of second installing plate 220, the opposite side of the second tie-beam 221 is fixed with another piece of the second installing plate 220, and Second tie-beam 221 is located at the centre position of the second installing plate 220, and the second securing plate 222 is horizontally disposed, one of Second securing plate 222 is located at the top of the second installing plate 220, and another piece of the second securing plate 222 is located at the bottom of the second installing plate 220 Portion, and the second securing plate 222 is fixed with second cross beam 210, two reinforcing beams 223 are individually fixed in the remote of the second securing plate 222 Side from the second installing plate 220, and reinforcing beam 223 is fixed with second cross beam 210, the second rib 23 is located at two second horizontal strokes Between beam 210.
It should be noted that the second rib 23 here is embedded between two second cross beams 210, make the positioned at upper end Two crossbeams 210 can push down the second rib 23, so as to make to be connected more between the second installing plate 220 and second cross beam 210 It is secured.
It please refers to shown in Fig. 4, in the present embodiment, the one side that second cross beam 210 is connect with the second securing plate 222 is second The distance between one side of separate through-hole 2200 of mounting surface, the second mounting surface and the second rib 23 strengthens distance for second 230, second strengthens distance 230 between 1.5cm-3cm, it is preferable that the second reinforcement distance 230 is set as 2cm.This away from From can make lower hanging seat 20 that there is enough intensity with the gravity of support scaffolding, and structural material can be saved
The above descriptions are merely preferred embodiments of the present invention, is not intended to limit the utility model, for this For the technical staff in field, various modifications and changes may be made to the present invention.It is all in the spirit and principles of the utility model Within, any modification, equivalent replacement, improvement and so on should be included within the scope of protection of this utility model.

Claims (8)

1. a kind of hanging seat for climbing type scaffold, which is characterized in that including upper hanging seat and lower hanging seat, the upper hanging seat is located at The upper end of the lower hanging seat, the lower hanging seat are connect with the scaffold, by carrying between the upper hanging seat and the lower hanging seat Device connection is risen, the upper hanging seat includes the first fixing piece and the first installed part, first fixing piece and major structure of construction Connection, first installed part are fixedly connected with first fixing piece, and first installed part is fixed close to described first One end of part is provided with the first rib, and first rib is embedded in first fixing piece.
2. the hanging seat according to claim 1 for climbing type scaffold, which is characterized in that first fixing piece includes The first longeron that at least two first crossbeams and Duo Gen arranged side by side are arranged side by side, more first longerons are connected to two Between the first crossbeam, first installed part includes at least two pieces the first installing plates arranged side by side, hanging plate, the first connection Beam and at least two piece of first securing plate, first installing plate are vertically set, the side of first tie-beam and its In one piece of first installing plate fix, the opposite side of first tie-beam is fixed with another piece of first installing plate, and First tie-beam is located at the centre position of first installing plate, and the hanging plate is set to the top of first installing plate Portion, and the hanging plate is located at one end far from the first crossbeam of first installing plate, the centre position of the hanging plate is opened Equipped with hanging hole, first securing plate is horizontally disposed, and one of first securing plate is located at the described first installation The top of plate, another piece of first securing plate are located at the bottom of first installing plate, and first securing plate with it is described First crossbeam is fixed, and first rib is located between two first crossbeams.
3. the hanging seat according to claim 2 for climbing type scaffold, which is characterized in that the first crossbeam with it is described The one side of first securing plate connection is the first mounting surface, and first mounting surface is with first rib far from the hanging plate The distance between one side strengthen distance for first, described first strengthens distance between 1.5cm-3cm.
4. the hanging seat according to claim 3 for climbing type scaffold, which is characterized in that described first, which strengthens distance, is 2cm。
5. the hanging seat according to claim 1 for climbing type scaffold, which is characterized in that the lower hanging seat includes second Fixing piece and the second installed part, second fixing piece are connect with the scaffold, and second installed part is solid with described second To determine part to be fixedly connected, second installed part is provided with the second rib close to one end of second fixing piece, and described the Two ribs are embedded in second fixing piece.
6. the hanging seat according to claim 5 for climbing type scaffold, which is characterized in that second fixing piece includes The second longeron that at least two second cross beams and Duo Gen arranged side by side are arranged side by side, more second longerons are connected to two Between the second cross beam, second installed part includes at least two pieces the second installing plates arranged side by side, the second tie-beam, extremely Few two piece of second securing plate and at least two reinforcing beams, second installing plate are vertically set, and second peace One end far from the second cross beam of loading board offers through-hole, the side of second tie-beam and one of described second Installing plate is fixed, and the opposite side of second tie-beam is fixed with another piece of second installing plate, and second tie-beam Positioned at the centre position of second installing plate, second securing plate is horizontally disposed, and one of described second adds Solid plate is located at the top of second installing plate, and another piece of second securing plate is located at the bottom of second installing plate, and Second securing plate is fixed with the second cross beam, and two reinforcing beams are individually fixed in the separate of second securing plate The side of second installing plate, and the reinforcing beam is fixed with the second cross beam, second rib is located at two institutes It states between second cross beam.
7. the hanging seat according to claim 6 for climbing type scaffold, which is characterized in that the second cross beam with it is described The one side of second securing plate connection is the second mounting surface, and second mounting surface is with second rib far from the through-hole The distance between one side strengthen distance for second, described second strengthens distance between 1.5cm-3cm.
8. the hanging seat according to claim 7 for climbing type scaffold, which is characterized in that described second, which strengthens distance, is 2cm。
CN201721621897.5U 2017-11-28 2017-11-28 For the hanging seat of climbing type scaffold Active CN207469740U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721621897.5U CN207469740U (en) 2017-11-28 2017-11-28 For the hanging seat of climbing type scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721621897.5U CN207469740U (en) 2017-11-28 2017-11-28 For the hanging seat of climbing type scaffold

Publications (1)

Publication Number Publication Date
CN207469740U true CN207469740U (en) 2018-06-08

Family

ID=62259029

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721621897.5U Active CN207469740U (en) 2017-11-28 2017-11-28 For the hanging seat of climbing type scaffold

Country Status (1)

Country Link
CN (1) CN207469740U (en)

Similar Documents

Publication Publication Date Title
CN101878341B (en) Frame structure for installation of wall panel of building, and wall panel installation device and wall panel installation method using same
CN207469740U (en) For the hanging seat of climbing type scaffold
CN210659232U (en) Top-hung type horizontal formwork system
CN205857040U (en) A kind of for the device to temporary support precompressed
CN2916596Y (en) Improvement of electronic platform scale structure
CN212317547U (en) Novel shear force wall reinforcing and supporting system
CN209891597U (en) Cast-in-situ plate type stair with sliding support at high-end ladder beam supporting position
CN211313485U (en) Building is strutted with strengthening rib
CN207847092U (en) Creeping formwork, which floats, deepens component at plate
CN202108249U (en) Bench die carriage
CN206829587U (en) A kind of hydraulic climbing formwork wall-attached frame
CN210342416U (en) Prefabricated wall panel
CN103993673A (en) Shear wall panel with supporting frames and connecting structure and construction method for shear wall panel and composite floor slab
CN209572298U (en) Profile rack and electronic equipment
CN206118244U (en) Rack
CN210659366U (en) Old building outer wall reinforced structure
CN209179475U (en) A kind of quick assembly and disassembly type building template
CN209065240U (en) Bucket elevator middle casing
CN220318517U (en) Unilateral formwork structure of wallboard
CN215055245U (en) Novel building template component
CN218323888U (en) Platform template bearing structure that encorbelments outward of bay window building
CN209384579U (en) A kind of elevator shaft preventing deformation
CN207245132U (en) A kind of finishing can automatic controlled height scaffold
CN211078102U (en) Reinforced cover plate for car roof
CN215052128U (en) Platform in tower column shaft

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20181207

Address after: 529725 Block F, No. 38, Jianxi Road, Taoyuan Town, Heshan City, Jiangmen City, Guangdong Province

Patentee after: Guangdong Pioneer Mould Frame Technology Co., Ltd.

Address before: 516000 Jindi Xingyuan, 110 Eling South Road, Huicheng District, Huizhou City, Guangdong Province, 117 Jinhe Pavilion, Unit 1, 705

Patentee before: Zhang Ronghua

TR01 Transfer of patent right