CN207458116U - A kind of construction machinery managing device based on BIM technology - Google Patents

A kind of construction machinery managing device based on BIM technology Download PDF

Info

Publication number
CN207458116U
CN207458116U CN201820119961.8U CN201820119961U CN207458116U CN 207458116 U CN207458116 U CN 207458116U CN 201820119961 U CN201820119961 U CN 201820119961U CN 207458116 U CN207458116 U CN 207458116U
Authority
CN
China
Prior art keywords
construction machinery
construction
sensor
locator
direction board
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820119961.8U
Other languages
Chinese (zh)
Inventor
翟东
李佳益
张旗旗
苗晔敏
洪子锐
温迪·德玛万
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University ZJU
Original Assignee
Zhejiang University ZJU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University ZJU filed Critical Zhejiang University ZJU
Priority to CN201820119961.8U priority Critical patent/CN207458116U/en
Application granted granted Critical
Publication of CN207458116U publication Critical patent/CN207458116U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The utility model discloses a kind of construction machinery managing device based on BIM technology, which includes electronic direction board, sensor side, locator, network service end and background server;Electronic direction board dispersed placement is fixed in construction site, sensor side and locator on construction machinery;Electronic direction board is used to send the geographic coordinate values of designated position to locator;Sensor side is used to obtain construction machinery working condition and safe state data;Network service end is for the data interaction between sensor side, locator and background server;The utility model is by the way that BIM technology is applied in construction site machine management, the site operation machinery essential information of management needed for being recorded in BIM models, with reference to technologies such as sensor, Internet of Things, real-time tracking and information record are carried out to the use process of construction machinery, be conducive to administrative staff and understand the real-time status that construction machinery uses, improve construction machinery service efficiency.

Description

A kind of construction machinery managing device based on BIM technology
Technical field
The utility model is related to construction machinery management domains, and in particular, to a kind of construction machinery pipe based on BIM technology Manage device.
Background technology
With the rapid development of the national economy, country makes an investment in increasing to building trade.One side architectural engineering just with Unprecedented high speed, high quality are pushed ahead, and another aspect building engineering construction mechanization degree is higher and higher.In order to add Fast project progress, it is ensured that construction quality acquires broader living space for enterprise, and each construction department has purchased large quantities of elder generations one after another Into engineering machinery facility.Construction machinery facilities control device based on BIM can assist administrative staff carry out scientifically management, Rationalize ground organizing construction machinery, comprehensive visualized management is carried out to existing machinery facility.BIM and technology of Internet of things draw Enter to contribute to overcome region, time domain limitation, realize the intercommunication of mechanical equipment information, realize the optimization of mechanical facility management, into And reaching the maximizing the benefits of various construction machinery facilities, this is the key that complete building engineering construction.BIM and Internet of Things skill Art as the emerging information technology that architectural engineering is concerned at this stage, can provide efficiently, efficiently for construction machinery management Management approach.1st, BIM technology introduction
Building Information Model (Building Information Modeling), i.e. BIM briefly just refer to be based on Identical standard can be integrated from building design stage until with building work in the lifecycle process of operation and maintenance stage The relevant information model of journey project.BIM models be using every relevant information data of construction-engineering project as the basis of model, The foundation of buildings model is carried out, and then realizes the new ant algorithms effectively managed.It refers to build by digital information analogue simulation Real information possessed by object, herein, the intension of information are not only the visual information of geometry description, also comprising a large amount of Non-geometry information, such as the cost of the heat transfer coefficient of the fire resistance rating of material, material, component, procurement information.In fact, BIM Be exactly by digitizing technique, establish a Virtual Building in a computer, provide one it is single, complete it is consistent, patrol The architecture information storehouse collected.
2nd, traditional construction machine management there are the problem of
Current Building ' engineering construction mechanical facility is managed mostly using static management pattern, this is unfavorable for construction machinery Efficiently use.There are the following problems for construction machinery management under static management pattern:
(1) construction machinery facility macro-management wretched insufficiency
The development advanced by leaps and bounds with architectural engineering, the requirement to the quality and progress of architectural engineering is also higher and higher, applies Work organization unit becomes the important finger of construction team's competitive bidding qualification using facility strength as one of construction ability of construction team Mark.However, its attention is only merely machinery itself, and " mechanical facility management " is ignored, this is objectively only paying attention to machinery " mechanical facility " this hardware in facilities management, and ignore " management " this crucial component.
(2) construction machinery facility blindly configures, renewal of facility hysteresis
Because investment subject is higher level department, subordinate unit often without considering actual needs, blindly strives investment, strives facility. Since unit in charge of construction lacks technology, the economic analysis of science when purchasing facility, although some facilities are leaving unused, still constantly draw Into more advanced facility, so as to which more new facility be caused to lack of capital.
(3) acts and efforts for expediency " used again, light management, gently maintenance " are serious
Due to the disposable feature of project under construction, item manager branch often considers from this project economic interests, to pursue matter Amount, progress and benefit, the nature that uses to facility is that expense is more low more reasonable;In order to surpass the duration, rob progress, simply risk one's life and use Machinery, and the maintenance of facility is ignored, it is reluctant to take out fund maintenance facility, facility is caused to be operating only haltingly.The result is that item Mesh completes, and facility is also in the flue, and next project under construction is made to have to take much time and fund recovery facility, influences enterprise Sustainable development and overall efficiency, facility price for repairing is also made to misplace, Project Financial Analysis is untrue.
(4) construction machinery facility utilization rate is low, supply-demand imbalance
The machine management of each construction department is fought separately, and is had a style of one's own, can not be carried out unified allotment, construction machinery facility By engineering cannot coordinate, overall arrangement uses, thus mechanical facility is difficult to comprehensively put into engineering.
(5) construction machinery facility archives disperse confusion
Since the ownership level of facility ownership in building engineering construction enterprise is different so that facility archives are also dispersed within not The facilities management department of same level.Since the outfit of each level facilities management departmental staff is not quite similar, management intensity difference is very Greatly, indivedual departments or base are equipped with even without facilities management personnel or only part-time staff, cause facility unattended or management Strength deficiency so that the damage of some facilities is lost and but be nobody shows any interest in, and causes the unknown loss of assets.
3rd, effects of the BIM in construction machinery management is solved
For existing construction machinery management domain there are the problem of, building engineering construction has the characteristics that multi-point and wide-ranging, work Work flowing is scattered, production unit is numerous and diverse, and the mechanical facility possessed is often allocated mutually, is continually moved due to mobile operational process Position, this just brings certain difficulty to management and accounting.Original static management pattern is relied solely on, is set by single posting Card, acquires account, card, object and is consistent, be not suitable with the needs of market economic development.The application of BIM can realize mechanical facility Dynamic management provides information system management approach, type selecting for machinery, purchase, install, use, guarantee, transformation, update is until scrap Overall process information-based management measure is provided, to prolonged mechanical facility service life, improve mechanical integrated efficiency help be provided.
(1) BIM applications can strengthen the centralized management of mechanical facility
Among the data inputs three-dimensional building information model such as the requirement of business facility situation and each project under construction to facility, According to distribute rationally, dynamic management principle allotment facility, relation of plane of coordinating all quarters concerned.
(2) mechanical facility, the information system management of part centralized purchasing are carried out in BIM models
It is rational to choose the important step that mechanical facility is mechanical facility dynamic management, not only to have in mind when purchasing facility More to consider the repair and update that have facility in the performance of facility.Mechanical facility specialty accessory can be supplied in BIM models Business's information is answered to be integrated, purchasing demand is realized during choosing with efficiently quickly being matched between facilities information compared with, The quality and price for making construction machinery facility can realize optimization.It is necessarily required to carry out during the use of construction machinery facility It repairs and updates, perfect construction machinery facility accessory information can be that construction machinery uses with supplier information in BIM models Process provides accurate facilities information.
(3) BIM models can make construction machinery facility technology archives with no paper, strengthen facilities information management
Mechanical facility dynamic management requirement to every mechanical facility will establishing techniques archives, main contents should include repair Manage record, record of relieving, maintaining record and the projects such as maintenance and repair schedule.Construction machinery shelves under traditional mode Case management is all paper-based form, it is easy to occur mechanical archive information update not in time, information is lost and damage etc., cause to construct Mechanical facility difficult management is heavy.Construction machinery facilities management based on BIM can realize the with no paper of technology files so that apply Update, calling, the inquiry of work mechanical facility information are more convenient.
(4) regulation and control of facility dynamic management are strengthened
Construction machinery facilities management based on BIM can realize construction machinery facility position in three-dimensional building information model It puts, the real-time management of the information such as use state, danger early warning.
The content of the invention
For existing construction machinery management domain there are the problem of, the utility model provides a kind of applying based on BIM technology Work machine management device.
The purpose of this utility model is achieved through the following technical solutions:A kind of construction machinery based on BIM technology Managing device, the device include electronic direction board, sensor side, locator, network service end and background server;The electronics Direction board dispersed placement is fixed in construction site, the sensor side and locator on construction machinery;
The electronic direction board is made of RFID chip and coordinate direction board;The RFID chip is used for construction machinery Locator send designated position geographic coordinate values;The coordinate direction board refers to for fixing RFID chip and mark electronics Show the number of board;
The sensor side is made of sensor chip, first processor, the first signal projector and the first package casing; The sensor chip is fixed on construction machinery designated position, and first processor is connected to by conducting wire;The first processor by First AD conversion chip and the first singlechip group are into the first AD conversion chip is used for the AD conversion of sensor signal, the first monolithic Machine is used to the transducing signal received being converted into the wireless signal that can be received by network service end and transmitting;First signal Transmitter sends sensor signal for sensor side to network service end;With sensor side on first package casing Mark coding, first processor and the first signal projector are located in the first package casing;
The locator is made of RFID reader, second processor, secondary signal transmitter and the second package casing;Institute It states RFID reader and is used for the radiofrequency signal receive, identify, the RFID chip of amplification electron direction board emits;The second processing Device is made of the second AD conversion chip and second singlechip, and the second AD conversion chip is used for the AD conversion of radiofrequency signal, and second is single The radiofrequency signal received is converted into the wireless signal that can be received by network service end and transmitting by piece machine;The secondary signal hair Emitter sends radiofrequency signal for locator to network service end;The outside upper mark coding with locator of second encapsulation, Second processor and secondary signal transmitter are located in the second package casing;
The network service end, for the data interaction between sensor side, locator and background server, including sensing Device end to the data transmission of background server, data transmission from locator to background server;
The background server is made of logical server and storage server;The logical server is used for BIM models Processing, the position display of construction machinery, the working condition of construction machinery show;The storage server is used to store BIM moulds Type, sensing data, construction machinery information, construction machinery status data.
Further, the electronic direction board disperses to be evenly distributed at the construction field (site), and construction site signal can be covered entirely Lid, and do not influence being normally carried out for construction, do not hinder construction machinery into appearance.
Further, the RFID chip uses 2.4GHz active RFID chips, the coordinate direction board alloy steel Make.
Further, the sensor chip includes mechanics sensor, temperature sensor, displacement sensor, oil mass sensing Device, first package casing use steel alloy material.
Further, the RFID reader uses 2.4G active RFID readers, and second package casing is using conjunction Golden steel material.
Further, the construction machinery includes referring to crane, excavator, crane.
The beneficial effects of the utility model are:The utility model by BIM technology by applying to construction site machinery In management, recorded in BIM models needed for management site operation machinery essential information, with reference to technologies such as sensor, Internet of Things, Real-time tracking and information record are carried out to the use process of construction machinery, is conducive to administrative staff and understands the reality that construction machinery uses When state, improve construction machinery service efficiency, can also may be occurred according to the virtual condition look-ahead construction machinery of equipment Failure, strengthen effectively safeguard, reduce construction machinery maintenance cost.It specifically includes:
1. the utility model uses sensor technology, signal is sent to background server by network service end, is realized To comprehensive, the real time monitoring of mechanical equipment;
2., can be according to different mechanical equipments due to the flexibility of sensor arrangement, different sensings is arranged in difference requirement Device, therefore, the utility model have great flexibility, can adapt to the requirement of modern construction mechanization very well;
3. the quantified management of the data such as pair mechanical oil consumption, power consumption, working condition is easier;
4. pair construction machinery carries out automation positioning, field management is facilitated, is conducive to construction manager and carries out scene Planning;
5. since the present apparatus numbers locator, electronic signs, be conducive to docking for scene and project management department, have It disconnects beneficial to solving the problems, such as to manage in conventional method with scene;
6. by the combinations such as BIM technology and sensor technology, technology of Internet of things, the number of construction machinery data archival is realized Change, paperless management, realize record and the update of construction machinery real time data.
Description of the drawings
Fig. 1 is the overall structure diagram of the utility model device;
Fig. 2 is the detail of construction of the utility model device;
Fig. 3 is the layout drawing of electronic direction board at the construction field (site);
Fig. 4 is the detail of construction of construction machinery;
In figure, construction machinery 1, electronic direction board 2, background server 3, locator 4, sensor side 5, sensor chip 6, First package casing 7, network service end 8, RFID chip 9, coordinate direction board 10, first processor 11, the first signal projector 12nd, the second package casing 13, RFID reader 14, second processor 15, secondary signal transmitter 16, signal receiving-transmitting device 17, letter Number amplifier 18, interchanger 19, logical server 20, storage server 21.
Specific embodiment
The utility model is described in further detail in the following with reference to the drawings and specific embodiments.
As shown in Figure 1, a kind of construction machinery managing device based on BIM technology provided by the utility model, the device bag Include electronic direction board 2, sensor side 5, locator 4, network service end 8 and background server 3;As shown in figure 3, the electronics refers to Show that board point 2 is spread and be placed in construction site, as shown in figure 4, the sensor side 5 and locator 4 are fixed on construction machinery 1;Institute State network service end 8 and background server 3 be positioned over project management department, receive the signal from construction site, and to construction site into Row control;The construction machinery 1 refers mainly to the common large scale equipment in the construction sites such as crane, excavator, crane;
The electronic direction board 2 is for the geographic coordinate values of 1 transmission of locator 4 designated position on construction machinery, association Locator 4 is helped to carry out the real-time positioning of site operation machinery;
The sensor side 5 is fixed on for collecting acquired in the sensor chip 6 of specific position on construction machinery 1 1 working condition of construction machinery and safe state data;
The locator 4, for receiving, identifying geographical coordinate radiofrequency signal that electronic direction board 2 is sent, and by information Transcoding and encryption are carried out, the real-time geographic of construction machinery 1 at the construction field (site) can be accurately positioned by multiple electronic direction boards 2 Coordinate information;It is required that easy to disassemble to replace power supply, when construction machinery 1 moves, locator 4 is fixed on construction machinery 1 simultaneously It moves with construction machinery, is positioned in real time with the position to construction machinery 1;
The network service end 8, for the data interaction between sensor side 5, locator 4 and background server 3, including Sensor side 5 to the data transmission of background server 3, data transmission from locator 4 to background server 3;
The background server 3, is made of logical server 20 and storage server 21;The logical server 20 uses Power PC, the position display of processing, construction machinery, the working condition of construction machinery for BIM models are shown;The storage Server 21 is used to store BIM models, sensing data, construction machinery information, construction machinery status data;The finger of construction site Determine construction machinery to correspond with the virtual three-dimensional mechanical model in BIM models, the construction machinery relevant information of collection in worksite will Can be obtained in BIM models in real time, intuitively show;The actual geographic coordinate of construction site and the three-dimensional coordinate in BIM models System is unified, and the virtual three-dimensional mechanical model in BIM models can be according to the construction site information being collected into, to construction machinery Operating status carry out real-time display.
The processing of the BIM models mainly includes the conversion of BIM models and BIM model lightweights, is specially:BIM is soft The BIM models that part is established switch to IFC formatted files, then the geological information by IFC resolver extraction models;By model geometric Information imports professional Web page image lightweight engine, regenerates physical model;To physical model addition construction site place, apply The relevant information of work machinery generates construction site placement model.The emphasis of the utility model and the tool for not lying in BIM model treatments Body method, the conversion and the lightweight of BIM models of BIM models can be realized by the prior art.
It is carried between the sensor side 5, locator 4, network service end 8, background server 3 using wireless Internet technologies For the upload and download of real time data.
As shown in Fig. 2, the electronic direction board 2 is made of RFID chip 9 and coordinate direction board 10;Electronic direction board 2 divides Distribution is placed in construction site, and position can specifically be set by construction site situation, it is desirable that is evenly distributed, construction site can be believed Number all standing, and do not influence being normally carried out for construction, do not hinder construction machinery 1 into appearance;
The RFID chip 9 uses 2.4GHz active RFID chips, for emitting specified point position geographic coordinate data;
The coordinate direction board 10 makes of steel alloy, for fixing RFID chip 9 and indicating the volume of electronic direction board 2 Number.
As shown in Fig. 2, the sensor side 5 is by sensor chip 6, first processor 11,12 and of the first signal projector First package casing 7 forms;
The sensor chip 6 includes mechanics sensor, temperature sensor, displacement sensor, fuel-quantity transducer etc., different The sensor chip 6 of function is according to needing to be individually fixed in specific position, to detect the use state of construction machinery 1, institute in real time It states sensor chip 6 and first processor 11 is connected to by conducting wire, for collecting the information such as construction machinery mechanics, temperature, displacement;
The first processor 11 is by AD conversion chip with singlechip group into wherein AD conversion chip is used for sensor signal AD conversion, microcontroller use 80C51 microcontrollers, for the processing and encryption of sensor signal, the biography that microcontroller will receive Sense signal is converted into the wireless signal that can be received by network service end 8 and transmitting;
First signal projector 12 sends sensor signal for sensor side 5 to network service end 8;
First package casing 7 uses steel alloy material, and the mark on the first package casing 7 with sensor side 5 is compiled Code, 11 and first signal projector 12 of first processor are located in the first package casing 7, are protected by the first package casing 7.
As shown in Fig. 2, the locator 4 is by RFID reader 14, second processor 15, secondary signal transmitter 16 and Two package casings 13 form;
The RFID reader 14 uses 2.4G active RFID readers, for receiving, identifying, amplifying the active of 2.4GHz The radiofrequency signal that RFID chip 9 emits;
The second processor 15 is by AD conversion chip with singlechip group into wherein AD conversion chip is for radiofrequency signal AD conversion, microcontroller use 80C51 microcontrollers, and for the processing and encryption of radiofrequency signal, microcontroller believes the radio frequency received Number be converted into can be received by network service end 8 wireless signal and transmitting;
The secondary signal transmitter 16 sends radiofrequency signal for locator 4 to network service end 8;
Second package casing 13 uses steel alloy material, and the mark on the second package casing 13 with locator 4 is compiled Code, 15 secondary signal transmitters 16 of second processor are located in the second package casing 13, are protected by the second package casing 13.
The network service end 8 is made of signal receiving-transmitting device 17, signal amplifier 18 and interchanger 19, for sensor side 5th, the data interaction between locator 4 and background server 3, including sensor side 5 to the data transmission, fixed of background server 3 Position data transmission from device 4 to background server 3.
Above-described embodiment is a preferred embodiment of the utility model, is to the utility model content and its application It further illustrates, should not be construed as the utility model and be only applicable to above-described embodiment.It is all to be based on the utility model principle and practicality The technology that new content is realized belongs to the scope of the utility model.

Claims (6)

1. a kind of construction machinery managing device based on BIM technology, which is characterized in that the device includes electronic direction board, sensing Device end, locator, network service end and background server;The electronic direction board dispersed placement is in construction site, the sensing Device end and locator are fixed on construction machinery;
The electronic direction board is made of RFID chip and coordinate direction board;The RFID chip is used to determine on construction machinery Position device sends the geographic coordinate values of designated position;The coordinate direction board is used to fix RFID chip and mark electronic direction board Number;
The sensor side is made of sensor chip, first processor, the first signal projector and the first package casing;It is described Sensor chip is fixed on construction machinery designated position, and first processor is connected to by conducting wire;The first processor is by first AD conversion chip and the first singlechip group are into the first AD conversion chip is used for the AD conversion of sensor signal, and the first microcontroller is used It can be by the wireless signal of network service end reception and transmitting in the transducing signal received is converted into;The first signal transmitting Device sends sensor signal for sensor side to network service end;There is the mark of sensor side on first package casing Coding, first processor and the first signal projector are located in the first package casing;
The locator is made of RFID reader, second processor, secondary signal transmitter and the second package casing;It is described RFID reader is used for the radiofrequency signal receive, identify, the RFID chip of amplification electron direction board emits;The second processor It is made of the second AD conversion chip and second singlechip, the second AD conversion chip is used for the AD conversion of radiofrequency signal, the second monolithic The radiofrequency signal received is converted into the wireless signal that can be received by network service end and transmitting by machine;The secondary signal transmitting Device sends radiofrequency signal for locator to network service end;The outside upper mark coding with locator of second encapsulation, the Two processors and secondary signal transmitter are located in the second package casing;
The network service end, for the data interaction between sensor side, locator and background server, including sensor side Data transmission, locator to background server are to the data transmission of background server;
The background server is made of logical server and storage server;The logical server is used for the place of BIM models Reason, the position display of construction machinery, the working condition of construction machinery are shown;The storage server is used to store BIM models, pass Sensor data, construction machinery information, construction machinery status data.
A kind of 2. construction machinery managing device based on BIM technology according to claim 1, which is characterized in that the electricity Sub- direction board disperses to be evenly distributed at the construction field (site), can be to construction site signal all standing, and does not influence the normal of construction Carry out, do not hinder construction machinery into appearance.
3. a kind of construction machinery managing device based on BIM technology according to claim 1, which is characterized in that described RFID chip uses 2.4GHz active RFID chips, and the coordinate direction board makes of steel alloy.
A kind of 4. construction machinery managing device based on BIM technology according to claim 1, which is characterized in that the biography Sensor chip includes mechanics sensor, temperature sensor, displacement sensor, fuel-quantity transducer, and first package casing uses Steel alloy material.
5. a kind of construction machinery managing device based on BIM technology according to claim 1, which is characterized in that described RFID reader uses 2.4G active RFID readers, and second package casing uses steel alloy material.
6. a kind of construction machinery managing device based on BIM technology according to claim 1, which is characterized in that described to apply Work machinery includes referring to crane, excavator, crane.
CN201820119961.8U 2018-01-24 2018-01-24 A kind of construction machinery managing device based on BIM technology Active CN207458116U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820119961.8U CN207458116U (en) 2018-01-24 2018-01-24 A kind of construction machinery managing device based on BIM technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820119961.8U CN207458116U (en) 2018-01-24 2018-01-24 A kind of construction machinery managing device based on BIM technology

Publications (1)

Publication Number Publication Date
CN207458116U true CN207458116U (en) 2018-06-05

Family

ID=62275948

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820119961.8U Active CN207458116U (en) 2018-01-24 2018-01-24 A kind of construction machinery managing device based on BIM technology

Country Status (1)

Country Link
CN (1) CN207458116U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110160491A (en) * 2019-05-27 2019-08-23 施甸县保施高速公路投资开发有限公司 It is a kind of that technology and system are calculated based on sensor technology and the side slope construction progress indicator of 3D laser scanner technique
CN110659317A (en) * 2019-08-14 2020-01-07 珠海市规划设计研究院 BIM data lightweight method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110160491A (en) * 2019-05-27 2019-08-23 施甸县保施高速公路投资开发有限公司 It is a kind of that technology and system are calculated based on sensor technology and the side slope construction progress indicator of 3D laser scanner technique
CN110659317A (en) * 2019-08-14 2020-01-07 珠海市规划设计研究院 BIM data lightweight method

Similar Documents

Publication Publication Date Title
You et al. A framework for data-driven informatization of the construction company
Hu et al. BIM-based integrated delivery technologies for intelligent MEP management in the operation and maintenance phase
Motamedi et al. Extending IFC to incorporate information of RFID tags attached to building elements
Li et al. SWOT analysis and Internet of Things-enabled platform for prefabrication housing production in Hong Kong
CN108364123A (en) A kind of construction machinery managing device based on BIM technology
US20040225676A1 (en) Site epuipment survey tool
Suprabhas et al. Integration of BIM and utility sensor data for facilities management
CN109345168A (en) A kind of petrochemical plant mounting material storage management method and system
Scheer et al. Managing of process key performance indicators as part of the aris methodology
CN106384189A (en) Enterprise management system based on sale management
CN207458116U (en) A kind of construction machinery managing device based on BIM technology
CN105160477A (en) RFID-based geographical position simulation positioning method and asset equipment management system using the method
Zhong et al. RFID-enabled real-time manufacturing execution system for discrete manufacturing: Software design and implementation
CN109636156A (en) A kind of digital management system and method for multi-code unification
Evjen et al. Enterprise BIM: A holistic approach to the future of smart buildings
CN106487799A (en) Facility information storage system based on cloud platform
Motamedi et al. RFID-assisted lifecycle management of building components using BIM data
CN111708827A (en) Real estate unit coding system
Sharma et al. Location-based highway construction planning using geographic information systems
CN114970792A (en) Novel digital management label of power grid physical equipment
Sinha et al. Complete it solution for Enterprise Asset Management (EAM) in Indian power Utility business
Jing et al. Development of BIM-Sensor integrated platform for MEP piping maintenance
Dumitrascu et al. Actual state of knowledge in the field of Supply Chain Management
CN111833453A (en) Space code positioning method and device
CN108805515A (en) Enterprise's nursery resource online management method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant