CN207452898U - A kind of clip pile device of municipal road construction vibratory piling machine - Google Patents

A kind of clip pile device of municipal road construction vibratory piling machine Download PDF

Info

Publication number
CN207452898U
CN207452898U CN201721472493.4U CN201721472493U CN207452898U CN 207452898 U CN207452898 U CN 207452898U CN 201721472493 U CN201721472493 U CN 201721472493U CN 207452898 U CN207452898 U CN 207452898U
Authority
CN
China
Prior art keywords
sleeve
strut
directional vibrator
lantern ring
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721472493.4U
Other languages
Chinese (zh)
Inventor
郑旭辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201721472493.4U priority Critical patent/CN207452898U/en
Application granted granted Critical
Publication of CN207452898U publication Critical patent/CN207452898U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model discloses a kind of clip pile devices of municipal road construction vibratory piling machine, including directional vibrator mounting bracket and pile sinking prefabricated pipe, the upper end of the directional vibrator mounting bracket is connected with mechanical arm, directional vibrator is installed on the inside of the directional vibrator mounting bracket, the lower end of the directional vibrator output shaft is installed with hydraulic cylinder, and the upper end for pressing sleeve is fixedly connected with the output terminal of hydraulic cylinder.The utility model is related to vibratory piling machine clip pile device, it is used for the clamp structure of stake, by inside and outside clamping, it can cause more preferable to the clamping effect of stake, so that stake is not easy to clamping device disengaging, and the clamp structure can cause after the completion of pile sinking works, and easily be dismantled, time and labour are saved, is improved work efficiency;The vibratory piling machine can be caused to be not susceptible to rock and deviate in pile driving process, add its stability, it is highly practical, beneficial to popularization.

Description

A kind of clip pile device of municipal road construction vibratory piling machine
Technical field
The utility model is related to vibratory piling machine technical fields, are specially a kind of municipal road construction vibratory piling machine Clip pile device.
Background technology
, it is necessary to use vibratory piling machine in span bridge construction engineering, vibratory piling machine groundwork device is fixed To vibrator, exciting part is paired horizontal rotating shaft, the eccentric block for having several pieces of quality identical with shape in shaft.Often The eccentric block of countershaft is arranged symmetrically, and by a pair of identical gear drive, rotating speed is identical, turns on the contrary, therefore, two axis operate When generated perturbed force in the horizontal direction mutually balance offset, prevent the horizontal swing of pile-sinking machine and stake, disturbed in vertical direction Power is overlapped mutually, and forms exciting force and pile body is promoted to vibrate.
Traditional vibratory piling machine still has following defect in actual operation:
1. the pile chuck on traditional vibratory piling machine is not enough for the clamping degree of stake, in pile sinking and the process promoted In easily there is the scene that stake and pile chuck depart from, and traditional pile chuck, after stake is clamped, dismounting is more inconvenient, thus Reduce work efficiency;
2. traditional vibratory piling machine carries out piling work, stake is because there is longer length, in pile driving process, Stake easily occurs rocking or occurring position offset, and stability is poor.
Utility model content
The purpose of this utility model is to provide a kind of clip pile device of municipal road construction vibratory piling machine, to solve The problems mentioned above in the background art.
To achieve the above object, the utility model provides following technical solution:A kind of municipal road construction pile vibrosinking The clip pile device of machine, including directional vibrator mounting bracket and pile sinking prefabricated pipe, the upper end connection of the directional vibrator mounting bracket There is mechanical arm, directional vibrator is installed on the inside of the directional vibrator mounting bracket, under the directional vibrator output shaft End is installed with hydraulic cylinder, and four ends of the directional vibrator have been fixedly connected with connecting rod, and the lower end of four connecting rods is welded with One connecting sleeve, the upper end of the pile sinking prefabricated pipe are plugged on the inside of connecting sleeve, the outer upper end of the pile sinking prefabricated pipe Fixing sleeve is equipped with fixed sleeving, and two outsides of the fixed sleeving are welded with metal sleeve, the lower end two of the connecting sleeve Side is welded with connecting screw, and the lower end of the connecting screw both passes through corresponding metal sleeve, and is located at gold on connecting screw The upper and lower ends for belonging to sleeve are arranged with stop nut, and the outer middle side part upper end of the pile sinking prefabricated pipe is arranged with the first stop collar Ring, is provided with the second /V lantern ring below the first /V lantern ring, the first /V lantern ring and the second /V lantern ring it Between fixed by the connection of more fixed links, the both ends of the connecting sleeve are hinged with the first gag lever post, first stop collar The both ends of ring are hinged with the second gag lever post, are cut with scissors between corresponding first gag lever post and the second gag lever post by the first axis pin It connects, the first spring, the inside of the pile sinking prefabricated pipe has been fixedly connected between corresponding first gag lever post and the second gag lever post Upper end is provided with interior installation disk, is set in the pile sinking prefabricated pipe with interior installation disk correspondence position there are six preformed hole, described The outside of interior installation disk is opened up there are six threaded hole corresponding with preformed hole, is inserted between corresponding preformed hole and threaded hole Equipped with a high-strength bolt, the upper center of the interior installation disk is welded with guide rod, the outside lower end of the guide rod Fixing sleeve is equipped with lower retaining collar, and the outer middle side part of the guide rod, which is slidingly connected, upper movable loop, the upper movable loop Four end of outside be hinged with the first strut, four end of outside of the lower retaining collar is hinged with the second strut, corresponding It is hinged by the second axis pin between one strut and the second strut, is fixedly connected between the upper movable loop and lower retaining collar There is second spring, and second spring is set in the outside of guide rod, the upper end movable sleeve of the guide rod, which is equipped with, presses sleeve, institute It states and presses the upper end of sleeve and be fixedly connected with the output terminal of hydraulic cylinder.
Preferably, first strut and the second strut are disposed as stainless steel supporting rod, and the first strut and the second support The diameter of bar is not less than 1.5 centimeters.
Preferably, the lower end of the directional vibrator output shaft is welded with upper junction plate, the lower end welding of the hydraulic cylinder There is lower connecting plate, fixed between the upper junction plate and lower connecting plate by fixing bolt, and the quantity of fixing bolt is no less than Four.
Preferably, the fixed sleeving is spliced by two arc steel loops, the equal external welding in both ends of two arc steel loops There is fixation steel plate, fixed between corresponding two pieces of fixation steel plates by running through the caging bolt of setting, and the head of caging bolt End is arranged with nut.
Preferably, the internal diameter for pressing sleeve is more than the internal diameter of upper movable loop, the first /V lantern ring, the second limit The position inner wall of lantern ring is not contacted with the inner wall of pile sinking prefabricated pipe.
Compared with prior art, the beneficial effects of the utility model are:The structure design of the utility model is reasonable, compared to existing For technology, the utility model is related to vibratory piling machine clip pile device, the clamp structure of stake is used for, by inside and outside pressing from both sides It holds, can cause more preferable to the clamping effect of stake so that stake is not easy to clamping device disengaging, and the clamp structure can cause After the completion of pile sinking work, easily dismantled, save time and labour, improved work efficiency;By in stake Be arranged the first /V lantern ring and the second /V lantern ring, can cause the vibratory piling machine be not susceptible to rock in pile driving process and Offset, adds its stability, highly practical, beneficial to popularization.
Description of the drawings
Fig. 1 is the utility model structure diagram;
Fig. 2 is installation disk schematic diagram in the utility model;
Fig. 3 presses sleeve schematic diagram for the utility model.
In figure:Directional vibrator mounting bracket 1, directional vibrator 2, hydraulic cylinder 3, connecting rod 4, connecting sleeve 5, fixed sleeving 6, Metal sleeve 7, connecting screw 8, stop nut 9, the first gag lever post 10, the second gag lever post 11, the first spring 12, the first stop collar It is ring 13, the second /V lantern ring 14, fixed link 15, pile sinking prefabricated pipe 16, interior installation disk 17, preformed hole 18, threaded hole 19, high-strength Degree bolt 20, lower retaining collar 21, the first strut 23, the second strut 24, second spring 25, press sleeve at upper movable loop 22 26th, guide rod 27.
Specific embodiment
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out It clearly and completely describes, it is clear that the described embodiments are only a part of the embodiments of the utility model rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are without making creative work All other embodiments obtained shall fall within the protection scope of the present invention.
- 3 are please referred to Fig.1, the utility model provides a kind of technical solution:A kind of municipal road construction vibratory piling machine Clip pile device, including directional vibrator mounting bracket 1 and pile sinking prefabricated pipe 16 (stake of the prior art), directional vibrator mounting bracket 1 upper end is connected with mechanical arm, and the inside of directional vibrator mounting bracket 1 is equipped with directional vibrator 2, and directional vibrator 2 exports The lower end of axis is welded with upper junction plate, and the lower end of hydraulic cylinder 3 is welded with lower connecting plate, passes through between upper junction plate and lower connecting plate Fixing bolt is fixed, and the quantity of fixing bolt is no less than four, and four ends of directional vibrator 2 have been fixedly connected with connecting rod 4, and four Connecting sleeve 5 that there are one the lower end welding of root connecting rod 4, the upper end of pile sinking prefabricated pipe 16 to be plugged in 5 inside of connecting sleeve, and pile sinking is pre- The outer upper end fixing sleeve of tubulation 16 is equipped with fixed sleeving 6, and fixed sleeving 6 is spliced by two arc steel loops, two arcs The equal outside weld in both ends of steel loop is connected to fixation steel plate, is consolidated between corresponding two pieces of fixation steel plates by running through the caging bolt of setting It is fixed, and the head end of caging bolt is arranged with nut, two outsides of fixed sleeving 6 are welded with metal sleeve 7, connecting sleeve 5 Lower end both sides be welded with connecting screw 8, the lower end of connecting screw 8 both passes through corresponding metal sleeve 7, and connecting screw 8 The upper upper and lower ends positioned at metal sleeve 7 are arranged with stop nut 9, and the outer middle side part upper end of pile sinking prefabricated pipe 16 is arranged with the One /V lantern ring 13, the lower section of the first /V lantern ring 13 are provided with the second /V lantern ring 14, the first /V lantern ring 13 and the second limit It is fixed between the lantern ring 14 of position by the connection of more fixed links 15, the both ends of connecting sleeve 5 are hinged with the first gag lever post 10, and first The both ends of /V lantern ring 13 are hinged with the second gag lever post 11, lead between corresponding first gag lever post, 10 and second gag lever post 11 It crosses the first axis pin to be hinged, the first spring 12 has been fixedly connected between corresponding first gag lever post, 10 and second gag lever post 11, sink The inner top side of stake prefabricated pipe 16 is provided with interior installation disk 17, is set in pile sinking prefabricated pipe 16 with interior installation 17 correspondence position of disk There are six preformed hole 18, the outside of interior installation disk 17 open up there are six with 18 corresponding threaded hole 19 of preformed hole, it is corresponding A high-strength bolt 20 is inserted between preformed hole 18 and threaded hole 19, the upper center of interior installation disk 17, which is welded with, to be led To bar 27, the outside lower end fixing sleeve of guide rod 27 is equipped with lower retaining collar 21, and the outer middle side part of guide rod 27 is slidingly connected and has Upper movable loop 22, four end of outside of upper movable loop 22 are hinged with the first strut 23, four end of outside of lower retaining collar 21 The second strut 24 is hinged with, is hinged between corresponding first strut, 23 and second strut 24 by the second axis pin, the first support 23 and second strut 24 of bar is disposed as stainless steel supporting rod, and the diameter of the first strut 23 and the second strut 24 is not less than 1.5 centimeters, second spring 25 is fixedly connected between upper movable loop 22 and lower retaining collar 21, and second spring 25 is set in The outside of guide rod 27, the upper end movable sleeve of guide rod 27, which is equipped with, presses sleeve 26, presses the upper end of sleeve 26 and hydraulic cylinder 3 Output terminal is fixedly connected, and the internal diameter for pressing sleeve 26 is more than the internal diameter of upper movable loop 22, the first /V lantern ring 13, the second /V The inner wall of lantern ring 14 is not contacted with the inner wall of pile sinking prefabricated pipe 16.By controlling hydraulic cylinder 3, the drive of hydraulic cylinder 3 presses sleeve 26 Push, press sleeve 26 and push upper movable loop 22, the first strut 23 and the second strut 24 can be caused to strut, and be against it is heavy Stake prefabricated pipe 16 inner wall on, then by outside set connecting screw 8 be connected with metal sleeve 7 so that stake can be clamped It is tighter, be not susceptible to break-off, and easy for removal and installation.
The utility model is related to vibratory piling machine clip pile device, be used for the clamp structure of stake, by inside and outside clamping, It can cause more preferable to the clamping effect of stake so that stake is not easy to clamping device disengaging, and the clamp structure can cause After the completion of pile sinking work, easily dismantled, save time and labour, improved work efficiency;By being covered in stake If the first /V lantern ring 13 and the second /V lantern ring 14, can cause the vibratory piling machine to be not susceptible to rock in pile driving process And offset.
While there has been shown and described that the embodiment of the utility model, for the ordinary skill in the art, It is appreciated that in the case where not departing from the principle of the utility model and spirit can these embodiments be carried out with a variety of variations, repaiied Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.

Claims (5)

1. a kind of clip pile device of municipal road construction vibratory piling machine, pre- including directional vibrator mounting bracket (1) and pile sinking Tubulation (16), the upper end of the directional vibrator mounting bracket (1) are connected with mechanical arm, the directional vibrator mounting bracket (1) Inside is equipped with directional vibrator (2), it is characterised in that:The lower end of directional vibrator (2) output shaft is installed with liquid Cylinder pressure (3), four ends of the directional vibrator (2) have been fixedly connected with connecting rod (4), and the lower end of four connecting rods (4) is welded with one A connecting sleeve (5), the upper end of the pile sinking prefabricated pipe (16) are plugged on the inside of connecting sleeve (5), the pile sinking prefabricated pipe (16) outer upper end fixing sleeve is equipped with fixed sleeving (6), and two outsides of the fixed sleeving (6) are welded with metal sleeve (7), the lower end both sides of the connecting sleeve (5) are welded with connecting screw (8), and the lower end of the connecting screw (8) both passes through Corresponding metal sleeve (7), and the upper and lower ends on connecting screw (8) positioned at metal sleeve (7) are arranged with stop nut (9), the outer middle side part upper end of the pile sinking prefabricated pipe (16) is arranged with the first /V lantern ring (13), the first /V lantern ring (13) the second /V lantern ring (14) is provided with below, is led between the first /V lantern ring (13) and the second /V lantern ring (14) Excessive root fixed link (15) connection is fixed, and the both ends of the connecting sleeve (5) are hinged with the first gag lever post (10), and described first The both ends of /V lantern ring (13) are hinged with the second gag lever post (11), corresponding first gag lever post (10) and the second gag lever post (11) Between be hinged by the first axis pin, has been fixedly connected between corresponding first gag lever post (10) and the second gag lever post (11) One spring (12), the inner top side of the pile sinking prefabricated pipe (16) are provided with interior installation disk (17), the pile sinking prefabricated pipe (16) set on interior installation disk (17) correspondence position there are six preformed hole (18), the outside of the interior installation disk (17) is opened If there are six threaded holes (19) corresponding with preformed hole (18), it is inserted between corresponding preformed hole (18) and threaded hole (19) A piece high-strength bolt (20), the upper center of the interior installation disk (17) are welded with guide rod (27), the guide rod (27) outside lower end fixing sleeve is equipped with lower retaining collar (21), and the outer middle side part of the guide rod (27) is slidingly connected and has upper work Dynamic lantern ring (22), four end of outside of the upper movable loop (22) is hinged with the first strut (23), the lower retaining collar (21) four end of outside is hinged with the second strut (24), passes through between corresponding first strut (23) and the second strut (24) Second axis pin is hinged, and second spring (25) is fixedly connected between the upper movable loop (22) and lower retaining collar (21), and Second spring (25) is set in the outside of guide rod (27), and the upper end movable sleeve of the guide rod (27), which is equipped with, presses sleeve (26), the upper end for pressing sleeve (26) is fixedly connected with the output terminal of hydraulic cylinder (3).
2. a kind of clip pile device of municipal road construction vibratory piling machine according to claim 1, it is characterised in that:Institute It states the first strut (23) and the second strut (24) is disposed as stainless steel supporting rod, and the first strut (23) and the second strut (24) Diameter be not less than 1.5 centimeters.
3. a kind of clip pile device of municipal road construction vibratory piling machine according to claim 1, it is characterised in that:Institute The lower end for stating directional vibrator (2) output shaft is welded with upper junction plate, and the lower end of the hydraulic cylinder (3) is welded with lower connecting plate, It is fixed between the upper junction plate and lower connecting plate by fixing bolt, and the quantity of fixing bolt is no less than four.
4. a kind of clip pile device of municipal road construction vibratory piling machine according to claim 1, it is characterised in that:Institute It states fixed sleeving (6) to be spliced by two arc steel loops, the equal outside weld in both ends of two arc steel loops is connected to fixation steel plate, corresponding Two pieces of fixation steel plates between fixed by running through the caging bolt of setting, and the head end of caging bolt is arranged with nut.
5. a kind of clip pile device of municipal road construction vibratory piling machine according to claim 1, it is characterised in that:Institute It states and presses internal diameter of the internal diameter of sleeve (26) more than upper movable loop (22), the first /V lantern ring (13), the second stop collar The inner wall of ring (14) is not contacted with the inner wall of pile sinking prefabricated pipe (16).
CN201721472493.4U 2017-11-07 2017-11-07 A kind of clip pile device of municipal road construction vibratory piling machine Expired - Fee Related CN207452898U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721472493.4U CN207452898U (en) 2017-11-07 2017-11-07 A kind of clip pile device of municipal road construction vibratory piling machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721472493.4U CN207452898U (en) 2017-11-07 2017-11-07 A kind of clip pile device of municipal road construction vibratory piling machine

Publications (1)

Publication Number Publication Date
CN207452898U true CN207452898U (en) 2018-06-05

Family

ID=62254177

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721472493.4U Expired - Fee Related CN207452898U (en) 2017-11-07 2017-11-07 A kind of clip pile device of municipal road construction vibratory piling machine

Country Status (1)

Country Link
CN (1) CN207452898U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109208598A (en) * 2018-10-31 2019-01-15 安徽科信矿山机械制造有限公司 A kind of clip pile device of mine pile-sinking machine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109208598A (en) * 2018-10-31 2019-01-15 安徽科信矿山机械制造有限公司 A kind of clip pile device of mine pile-sinking machine

Similar Documents

Publication Publication Date Title
CN205129269U (en) Fixture for welding pipelines
CN107893419A (en) A kind of clip pile device of municipal road construction vibratory piling machine
CN203795829U (en) Hoop assembly
CN207452898U (en) A kind of clip pile device of municipal road construction vibratory piling machine
CN104070603A (en) Tensioning assembly for producing prestressed concrete pile without end plate
CN205978275U (en) Bridge type ship unloaders damping cable device
CN104196023B (en) A kind of using method of the concrete precast pipe pile pile top of band mechanical connecting device
CN109550874A (en) A kind of mould for the processing of the double-deck main reinforcement steel reinforcement cage
CN216990505U (en) Welding machine negative electrode connecting device used during tubular pile welding butt joint
CN102787727A (en) Clamp and method using clamp to mount large converter engineering articulated leaning column
CN212613749U (en) Beam-penetrating sleeve for building pipeline
CN209990022U (en) Construction steel bar connecting piece
CN106695077A (en) Inner support type wedge device inflated with protective gas at the back
CN208379655U (en) A kind of static load pullout tests quick-fitting device
CN204098031U (en) A kind of concrete precast pipe pile pile top with mechanical connecting device
CN208702156U (en) A kind of construction formwork reinforcement fixture
CN211192640U (en) Sleeve welding tool
CN219195014U (en) Quick dismounting device for screw rod is tightened up to blast furnace tuyere
CN209604373U (en) Rod piece clamper, instrument
CN109500524A (en) A kind of plate difference of height regulating device
CN213135592U (en) Welding tool for machining sleeve pipe welding part
CN212471212U (en) High-stability fixing clamp for stainless steel pipe
CN215561991U (en) Bailey bridge is built and is used high performance crossbeam clamping device
CN213898899U (en) Oil pipe clamp assembly
CN208459158U (en) A kind of building bar jointing detection device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180605

Termination date: 20181107

CF01 Termination of patent right due to non-payment of annual fee