CN209990022U - Construction steel bar connecting piece - Google Patents

Construction steel bar connecting piece Download PDF

Info

Publication number
CN209990022U
CN209990022U CN201920200835.XU CN201920200835U CN209990022U CN 209990022 U CN209990022 U CN 209990022U CN 201920200835 U CN201920200835 U CN 201920200835U CN 209990022 U CN209990022 U CN 209990022U
Authority
CN
China
Prior art keywords
loop bar
bar
connecting loop
thread
steel bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920200835.XU
Other languages
Chinese (zh)
Inventor
黄传明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Fuxin Construction Management Co Ltd
Original Assignee
Guangdong Fuxin Construction Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Fuxin Construction Management Co Ltd filed Critical Guangdong Fuxin Construction Management Co Ltd
Priority to CN201920200835.XU priority Critical patent/CN209990022U/en
Application granted granted Critical
Publication of CN209990022U publication Critical patent/CN209990022U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The utility model discloses a construction steel bar connecting piece, including first reinforcing bar, second reinforcing bar, first connecting loop bar and second connecting loop bar, first reinforcing bar surface is provided with first external screw thread, first internal thread with first external screw thread assorted is seted up to first connecting loop bar inner wall, first reinforcing bar connects soon through the first internal thread of first external screw thread with first connecting loop bar inner wall, second reinforcing bar surface is provided with the second external screw thread. The utility model discloses a first internal thread in the first connecting loop bar and the second internal thread in the second connecting loop bar, conveniently connect first reinforcing bar and second reinforcing bar to connect soon respectively and fix in first connecting loop bar and second connecting loop bar, and through solid fixed ring, can fix first connecting loop bar and second connecting loop bar, traditional manual welding has been replaced, staff's working strength has been reduced, and joint strength is high, moreover, the steam generator is simple in structure, and convenient for operation, therefore, the steam generator is relatively practical, and is suitable for wide popularization and use.

Description

Construction steel bar connecting piece
Technical Field
The utility model relates to a construction steel bar connection technical field, in particular to construction steel bar connecting piece.
Background
Reinforcing steel is an important component in the modern building industry due to its good fire and shock resistance. The types, specifications, and types of reinforcing bars vary and play a different role in the construction. In addition, with the rapid development of national building foundations, cement prefabricated parts are used in large quantities in the building construction process. At present, the connection of prefabricated parts is generally to adopt the welded connection mode with the exposed end of the reinforcing bar in the prefabricated part, then pour the junction with cement, this kind of mode is inefficient, and solder joint intensity is difficult to guarantee, has brought the hidden danger for the security of building, and job site operating condition is abominable simultaneously, especially in hot summer. Therefore, we propose a construction rebar connector.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a main aim at provides a construction steel bar connecting piece, through the first internal thread in the first connecting loop bar and the second internal thread in the second connecting loop bar, conveniently connect first reinforcing bar and second reinforcing bar to fix in first connecting loop bar and second connecting loop bar respectively soon, and through solid fixed ring, can fix first connecting loop bar and second connecting loop bar, traditional manual welding has been replaced, staff's working strength has been reduced, and joint strength is high, moreover, the steam generator is simple in structure, and convenient for operation, through the solid fixed ring of first connecting loop bar left end and second connecting loop bar right-hand member and the cooperation of fixed screw use, can press from both sides tightly fixedly to further going on of first reinforcing bar and second reinforcing bar, avoid first reinforcing bar and second reinforcing bar atress to drop, therefore, the steam generator is comparatively practical, can effectively solve the problem in the background art.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
a construction steel bar connecting piece comprises a first steel bar, a second steel bar, a first connecting loop bar and a second connecting loop bar, the outer surface of the first steel bar is provided with a first external thread, the inner wall of the first connecting loop bar is provided with a first internal thread matched with the first external thread, the first steel bar is screwed with the first internal thread on the inner wall of the first connecting loop bar through the first external thread, the outer surface of the second steel bar is provided with a second external thread, the inner wall of the second connecting sleeve rod is provided with a second internal thread matched with the second external thread, the second steel bar is screwed with a second internal thread on the inner wall of the second connecting sleeve rod through a second external thread, the left end of the first connecting sleeve rod and the right end of the second connecting sleeve rod are fixedly provided with fixing rings, the middle parts of the upper surface and the lower surface of each fixing ring are vertically provided with screw holes, and fixing screws are screwed in the screw holes.
Furthermore, a thread B is arranged on the left side of the outer surface of the second connecting sleeve rod, and a fixing nut is screwed on the thread B.
Furthermore, a limiting ring is fixedly installed at the position, which is slightly to the right, of the middle of the outer surface of the first connecting sleeve rod.
Furthermore, the right side of the outer surface of the first connecting sleeve rod is provided with a thread A, the thread A is located on the right side of the limiting ring, and the thread A is matched with the thread B.
Furthermore, the first connecting sleeve rod and the second connecting sleeve rod are fixedly connected through a fixing nut, and the diameters of the first connecting sleeve rod and the second connecting sleeve rod are the same.
Compared with the prior art, the utility model discloses following beneficial effect has:
1. the utility model discloses a construction steel bar connecting piece, through the first internal thread in the first connecting loop bar and the second internal thread in the second connecting loop bar, conveniently connect first reinforcing bar and second reinforcing bar to connect respectively soon and fix in first connecting loop bar and second connecting loop bar, and through solid fixed ring, can fix first connecting loop bar and second connecting loop bar, traditional manual welding has been replaced, staff's working strength has been reduced, and joint strength is high, moreover, the steam generator is simple in structure, and convenient for operation.
2. The utility model discloses a construction steel bar connection spare uses through the solid fixed ring of first connecting sleeve pole left end and second connecting sleeve pole right-hand member and the cooperation of fixed screw, can press from both sides tightly fixedly to the further going on of first reinforcing bar and second reinforcing bar, avoids first reinforcing bar and second reinforcing bar atress to drop, and is comparatively practical.
Drawings
Fig. 1 is a schematic view of the whole structure of the construction steel bar connecting piece of the utility model;
fig. 2 is a schematic view of the connection structure of the first steel bar and the first connecting loop bar of the construction steel bar connecting piece of the present invention;
fig. 3 is a schematic view of the connection structure between the second steel bar and the second connecting sleeve of the construction steel bar connector of the present invention;
fig. 4 is the utility model discloses construction steel bar connection's solid fixed ring structure schematic diagram.
In the figure: 1. a first reinforcing bar; 2. a first external thread; 3. a fixing ring; 4. fastening screws; 5. A first connecting loop bar; 6. a limiting ring; 7. fixing a nut; 8. a second connecting loop bar; 9. a second external thread; 10. a second reinforcing bar; 11. a thread A; 12. a thread B; 13. a first internal thread; 14. a second internal thread; 15. and a screw hole.
Detailed Description
In order to make the technical means, creation features, achievement purposes and functions of the present invention easy to understand, the present invention is further described below with reference to the following embodiments.
As shown in fig. 1-4, a construction steel bar connecting member comprises a first steel bar 1, a second steel bar 10, a first connecting loop bar 5 and a second connecting loop bar 8, wherein the outer surface of the first steel bar 1 is provided with a first external thread 2, the inner wall of the first connecting loop bar 5 is provided with a first internal thread 13 matched with the first external thread 2, the first steel bar 1 is screwed with the first internal thread 13 on the inner wall of the first connecting loop bar 5 through the first external thread 2, the outer surface of the second steel bar 10 is provided with a second external thread 9, the inner wall of the second connecting loop bar 8 is provided with a second internal thread 14 matched with the second external thread 9, the second steel bar 10 is screwed with the second internal thread 14 on the inner wall of the second connecting loop bar 8 through the second external thread 9, the left end of the first connecting loop bar 5 and the right end of the second connecting loop bar 8 are both fixedly provided with a fixing ring 3, the middle parts of the upper surface and the lower surface of the fixing ring 3 are both vertically provided with screw holes 15, and fixing screws 4 are screwed in the screw holes 15.
In this embodiment as shown in fig. 1, fig. 2 and fig. 3, through the first internal thread 13 in the first connecting loop bar 5 and the second internal thread 14 in the second connecting loop bar 8, conveniently connect first reinforcing bar 1 and second reinforcing bar 10 soon respectively and fix in first connecting loop bar 5 and second connecting loop bar 8, and use through the cooperation of solid fixed ring 3 and set screw 4, can further fix first reinforcing bar 1 and second reinforcing bar 10, avoid first reinforcing bar 1 and second reinforcing bar 10 atress to drop, and is comparatively practical.
And a thread B12 is arranged on the left side of the outer surface of the second connecting loop bar 8, and a fixing nut 7 is screwed on the thread B12.
In this embodiment, as shown in fig. 1 and 3, the joint of the first connecting loop bar 5 and the second connecting loop bar 8 is conveniently fixed by the fixing nut 7.
Wherein, a limiting ring 6 is fixedly arranged at the right part of the middle part of the outer surface of the first connecting loop bar 5.
In the embodiment, as shown in fig. 1 and 2, a limiting ring 6 is fixedly installed at the right part of the middle part of the outer surface of the first connecting loop bar 5. Can play a limiting role for the fixing nut 7.
Wherein, the right side of the outer surface of the first connecting sleeve rod 5 is provided with a thread A11, the thread A11 is positioned on the right side of the limit ring 6, and the thread A11 is matched with the thread B12.
In this embodiment, as shown in fig. 1 and fig. 2, the screw thread a11 is matched with the screw thread B12, so that the fixing nut 7 can be adjusted conveniently to fix the joint of the first connecting loop bar 5 and the second connecting loop bar 8.
The first connecting loop bar 5 and the second connecting loop bar 8 are fixedly connected through a fixing nut 7, and the diameters of the first connecting loop bar 5 and the second connecting loop bar 8 are the same.
The working principle is as follows: when in use, the first reinforcing steel bar 1 is screwed into the first internal thread 13 in the first connecting loop bar 5 through the first external thread 2, the second reinforcing steel bar 10 is screwed into the second internal thread 14 in the second connecting loop bar 8 through the second external thread 9, then the fastening screw 4 is rotated to respectively clamp and fix the first steel bar 1 and the second steel bar 10, the first steel bar 1 and the second steel bar 10 are prevented from falling off under stress, the right end of the first connecting loop bar 5 is horizontally butted with the left end of the second connecting loop bar 8, then the fixing nut 7 is rotated to be in contact with the limiting ring 6 from the thread B, fix first connecting loop bar 5 and the 8 junctions of second connecting loop bar, accomplish the connection to first reinforcing bar 1 and second reinforcing bar 10, replaced traditional manual welding, alleviateed staff's working strength, convenient operation, it is comparatively practical.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (5)

1. The utility model provides a construction steel bar connecting piece, includes first reinforcing bar (1), second reinforcing bar (10), first connecting loop bar (5) and second connecting loop bar (8), its characterized in that: the outer surface of the first reinforcing steel bar (1) is provided with a first external thread (2), the inner wall of the first connecting sleeve rod (5) is provided with a first internal thread (13) matched with the first external thread (2), the first reinforcing steel bar (1) is connected with the first internal thread (13) on the inner wall of the first connecting sleeve rod (5) through the first external thread (2) in a screwing way, the outer surface of the second reinforcing steel bar (10) is provided with a second external thread (9), the inner wall of the second connecting sleeve rod (8) is provided with a second internal thread (14) matched with the second external thread (9), the second reinforcing steel bar (10) is connected with the second internal thread (14) on the inner wall of the second connecting sleeve rod (8) through the second external thread (9) in a screwing way, the left end of the first connecting sleeve rod (5) and the right end of the second connecting sleeve rod (8) are both fixedly provided with a fixing ring (3), the middle part of the upper surface of the fixing ring (3) is provided with a screw hole, and fixing screws (4) are screwed in the screw holes (15).
2. The construction rebar connector of claim 1, wherein: and a thread B (12) is arranged on the left side of the outer surface of the second connecting loop bar (8), and a fixing nut (7) is screwed on the thread B (12).
3. The construction rebar connector of claim 1, wherein: and a limiting ring (6) is fixedly arranged at the right part of the middle part of the outer surface of the first connecting sleeve rod (5).
4. The construction rebar connector of claim 1, wherein: the right side of the outer surface of the first connecting sleeve rod (5) is provided with a thread A (11), the thread A (11) is located on the right side of the limiting ring (6), and the thread A (11) is matched with the thread B (12).
5. The construction rebar connector of claim 1, wherein: the first connecting loop bar (5) and the second connecting loop bar (8) are fixedly connected through a fixing nut (7), and the diameters of the first connecting loop bar (5) and the second connecting loop bar (8) are the same.
CN201920200835.XU 2019-02-15 2019-02-15 Construction steel bar connecting piece Active CN209990022U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920200835.XU CN209990022U (en) 2019-02-15 2019-02-15 Construction steel bar connecting piece

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920200835.XU CN209990022U (en) 2019-02-15 2019-02-15 Construction steel bar connecting piece

Publications (1)

Publication Number Publication Date
CN209990022U true CN209990022U (en) 2020-01-24

Family

ID=69288503

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920200835.XU Active CN209990022U (en) 2019-02-15 2019-02-15 Construction steel bar connecting piece

Country Status (1)

Country Link
CN (1) CN209990022U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112095591A (en) * 2020-08-07 2020-12-18 四川建筑职业技术学院 Pile connecting structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112095591A (en) * 2020-08-07 2020-12-18 四川建筑职业技术学院 Pile connecting structure

Similar Documents

Publication Publication Date Title
CN105442760A (en) Steel bar connection mode used for connection among prefabricated reinforced concrete members
CN209990022U (en) Construction steel bar connecting piece
CN104358405B (en) The full hall pattern board supporting system of a kind of heavy duty
CN208329155U (en) A kind of assembled hollow hub node applied to grid shell
CN210342642U (en) Scaffold wall connecting piece and scaffold
CN214995260U (en) Positioning steel bar position controller
CN108505620A (en) A kind of steel construction clamp device
CN212388966U (en) External scaffold tool type wall connecting piece for cast-in-place concrete outer wall
CN209855214U (en) Scissor-bracing steel pipe connector
CN211690768U (en) Novel net rack rod piece
CN202187482U (en) Reinforcing steel bar connecting device
CN206769213U (en) A kind of reinforcing steel bar connecting device being used in precast concrete
CN202031315U (en) A vertical rod of a fastener type steel pipe scaffold
CN206581502U (en) A kind of reinforcing bar couples fastener
CN201779107U (en) Special fixture for temporarily fixing steel pipe connection
CN207021930U (en) A kind of photovoltaic solar installation work high above the ground support and system
CN220704743U (en) Self-locking circular steel tube concrete column joint
CN204754224U (en) Wear wall fastening bolt
CN206289875U (en) A kind of reinforcing bar cylinder button coupling arrangement
CN204784005U (en) Interior threaded fastener
CN216341065U (en) Adjustable pre-buried rigid sleeve clamp
CN104481127A (en) Rigidly-connected and high-strength die plate supporting system
CN219713341U (en) Novel in-furnace hanging screen of circulating fluidized bed boiler
CN215442729U (en) Welding sleeve for connecting reinforcing steel bar and building component
CN214272406U (en) Energy-saving steel structure unit

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant