CN207405064U - A kind of interim disposal system of dredged sediment - Google Patents

A kind of interim disposal system of dredged sediment Download PDF

Info

Publication number
CN207405064U
CN207405064U CN201720715017.4U CN201720715017U CN207405064U CN 207405064 U CN207405064 U CN 207405064U CN 201720715017 U CN201720715017 U CN 201720715017U CN 207405064 U CN207405064 U CN 207405064U
Authority
CN
China
Prior art keywords
air
dehydrating
sludge
air film
disposal system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720715017.4U
Other languages
Chinese (zh)
Inventor
吴龙
郝以党
岳昌盛
彭犇
胡天麒
刘永蓓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central Research Institute of Building and Construction Co Ltd MCC Group
China Jingye Engineering Corp Ltd
MCC Energy Saving and Environmental Protection Co Ltd
Original Assignee
Central Research Institute of Building and Construction Co Ltd MCC Group
China Jingye Engineering Corp Ltd
MCC Energy Saving and Environmental Protection Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central Research Institute of Building and Construction Co Ltd MCC Group, China Jingye Engineering Corp Ltd, MCC Energy Saving and Environmental Protection Co Ltd filed Critical Central Research Institute of Building and Construction Co Ltd MCC Group
Priority to CN201720715017.4U priority Critical patent/CN207405064U/en
Application granted granted Critical
Publication of CN207405064U publication Critical patent/CN207405064U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Treatment Of Sludge (AREA)

Abstract

The utility model is related to a kind of interim disposal system of dredged sediment, dredged sediment transport is poured in storage mud groove, and dehydrating agent, which is proportionally added into tank diameter, in sludge and dehydrating agent feed bin is stirred mixing;Sludge after stirring and evenly mixing is delivered to transfer tank, then is delivered to through coiled pipe in dehydrating tube;Dehydrating tube overlays closed in air film canopy seal up for safekeeping;It is blown using air blower out of a lateral air film canopy, bulging air is discharged from air film canopy opposite side, and outer air-discharging carries out deodourizing through gas purification tower;Dehydrating tube is placed on air film canopy inner cushion layer, and percolate is collected to water treatment trough through bed course and carries out purified treatment in dehydrating tube.The advantages that the utility model is economical good, and construction is fast, and environmental emission is up to standard, disclosure satisfy that the short time standardization of high-volume sludge centrally disposes, it is expected to reduce sludge and abandon the environmental pollution generated and security risk.

Description

A kind of interim disposal system of dredged sediment
Technical field
The utility model is related to a kind of interim disposal systems of dredged sediment.
Background technology
China is populous nation, and the urbanization process in China has obtained development at full speed since 2000, and in future Longer period is among Process of Urbanization Construction.With the development of urbanization process, many urban issueses are also brought.In recent years Come, the urban issueses such as city black and odorous water, urban sewage piping lane impeded drainage emerge in an endless stream.Current governmental is to urban water-body environment And drainage problem pay attention to day by day, the relevant items such as black and odorous water dredging and the transformation of city piping lane are increasing.Black and odorous water is clear In the work progress of silt and city piping lane transformation project, substantial amounts of black foul sewage mud will be generated in the short period of time.It is a large amount of black smelly Sludge concentrates generation in the short period of time, and how quickly, safe, economic the disposal for completing the black foul sewage mud of high-volume is one Problem.
The processing of sludge at present generally requires dehydration, desiccation minimizing processing, minimizing treated sludge with low moisture content It burned, filled again, cement mixes the final processing or disposal such as burning.Above-mentioned black smelly moisture percentage in sewage sludge often more than 80%, Sludge treatment capacity is chiefly used in meeting the processing that itself generates sludge in sewage treatment plant in general city, lacks the production of dredging process The processing capacity of primary sludge;But more than 80% sludge of moisture content can not also carry out landfill disposal.Sludge reduction processing is carried out to set It applies or the construction of the conventional sludge treatment facility such as landfill yard can not also be completed within a short period of time, and lack economic feasibility.
The dredged sediment generated in current country's associated construction project lacks effective processing approach, and substantial amounts of sludge " is changed Whole is zero ", is often discarded in isolated area by all means by construction party, and there are larger safety and environmental hazards.
Using sludge is quenched, is pumped to after mixing in sludge dewatering pipe, sludge dewatering pipe has certain the utility model Bearing capacity can stack;Sludge dewatering pipe is deposited on the bed course of special designing, on the one hand prevents percolate from passing through osmosis pollution Underground water, while can also meet the collection of percolate in sludge, is conducive in interim disposal process that sludge oozes in geotechnological cloth bag The discharge in a organized way and centralized processing of filtrate;It banks up and sets air film canopy closed outside the sludge dewatering pipe of completion, prevent black foul sewage The foul gas uncontrollable discharge that mud generates;Air film canopy is supported and taken a breath by air blast, efflux gas carries out in a organized way Fume treatment.
Dredged sediment is disposed temporarily by this way, economical good, it is excellent that construction is fast, and environmental emission is up to standard etc. Point disclosure satisfy that the standardization for the short time high-volume sludge that the dredgings engineering project such as black and odorous water and piping lane transformation is related to is concentrated Disposal, it is therefore prevented that related arbitrarily heap abandons the appearance of phenomenon, it is expected to reduce sludge environmental pollution and security risk.
Utility model content
The utility model is intended to solve one of above-mentioned technical problem to a certain extent.The utility model aim is proposition one The kind interim disposal system of dredged sediment.The technical solution of the utility model is as follows:
A kind of interim disposal system of dredged sediment, including storage mud groove, dehydrating agent feed bin, tank diameter, transfer tank, snakelike Pipe, dehydrating tube, air film canopy, air blower, gas purification tower, bed course and water treatment trough;Wherein, mud groove and dehydrating agent feed bin difference are stored up It is connected with tank diameter, is carried out for the dehydrating agent in the sludge and dehydrating agent feed bin that store up in mud groove to be proportionally added into tank diameter It stirs and evenly mixs;Tank diameter is connected with transfer tank, for the sludge after stirring and evenly mixing to be delivered to transfer tank, transfer tank and coiled pipe Connection, coiled pipe is connected with dehydrating tube, and for sludge to be delivered to through coiled pipe in dehydrating tube, dehydrating tube is overlayed in air film canopy Bed course on it is closed seal up for safekeeping, the one side of air film canopy sets air blower, and the opposite side of air film canopy sets gas purification tower, and bed course is set In air film canopy bottom, water treatment trough is connected with bed course, and percolate is collected to water treatment trough through bed course and carries out at purification in dehydrating tube Reason.
Wherein, dredged sediment moisture content is 75%~90%.It is preferred that dehydrating agent main component is polyacrylamide (PAM), Polyacrylamide (PAM) proportion is higher than 90%, and dehydrating agent additive amount is 0.2 ‰~the 0.4 ‰ of sludge weight;It is preferred that sludge is stirring It is 20~40 minutes to mix mixing time in slot.It is preferred that steel pipe, PE pipes or pvc pipe can be used in the coiled pipe.It is preferred that dehydrating tube (6) the long bag of tubulose that stereochemical structure yarn is used to be formed for raw material sewing, dehydrating tube maximum packed height are 2.5m, and maximum is held Product is 900m3, and possess good tensile strength, abrasion resistance, anti-uv-ray and water permeability.
Wherein, it is in a pile that dehydrating tube, which stacks height to be no more than 10m, and more pile dehydrating tubes can be placed on bed course.
Wherein, air film canopy uses building film material to be anchored for shell using wirerope, is formed by air blower air-supply inflation closed Space, in air film canopy air pressure be higher by 200~300Pa than external pressure.It is preferred that air-discharging uses gas purification inside and outside air film canopy Tower processing, so as to the acid foul gas such as hydrogen sulfide in air-discharging except going.
Wherein, bed course is made of top guide layer and lower part impervious barrier, and top guide layer has spinning filtering geotechnique by top Cloth tiling layer and the boulder bed composition of bottom;Wherein there is spinning filtering geotextiles tiling layer to there is spinning to filter geotextiles for 250g/m2 Tile layer, and boulder bed is that the cobble tiling thickness that grain size is 20~40mm sizes is more than the boulder bed of 300mm, and perforation high density is gathered Dilute (HDPE) pipe of second is embedded in the water conservancy diversion that boulder bed bottom carries out percolate;Lower part impervious barrier is by top non-woven geotextile, intermediate height The bentonite liner three parts of density polyethylene (HDPE) geomembrane and bottom form;Top non-woven geotextile is 600g/m2 Non-woven geotextile, intermediate high-density polyethylene (HDPE) geomembrane are high-density polyethylene (HDPE) soil not less than 1.5mm thickness Work film, the bentonite liner of bottom are not less than 4800g/m2 bentonite liners using dosage.
Description of the drawings
A kind of interim disposal system structure diagram of dredged sediment of Fig. 1 the utility model.
Note:1 storage mud groove, 2 dehydrating agent feed bins, 3 tank diameters, 4 transfer tanks, 5 coiled pipes, 6 dehydrating tubes, 7 air film canopies, 8 air blast Machine, 9 gas purification towers, 10 bed courses, 11 water treatment troughs
Specific embodiment
The embodiment of the utility model is described below in detail, the example of the embodiment is shown in the drawings, wherein from beginning Same or similar element is represented to same or similar label eventually or there is same or like element.Below by ginseng The embodiment for examining attached drawing description is exemplary, and is only used for explaining that the utility model is used, and it is not intended that the utility model Limitation.
As shown in Figure 1, a kind of method that dredged sediment is disposed temporarily, the dredged sediment transport of moisture content 75%~90% is inclined It is poured in storage mud groove 1.Dehydrating agent adds in tank diameter 3 according to 0.2 ‰~the 0.4 ‰ of sludge quality in sludge and dehydrating agent feed bin 2 In be stirred mixing, stir and evenly mix the time 20~40 minutes;It is preferred that dehydrating agent main component is polyacrylamide (PAM), gather Acrylamide (PAM) proportion is higher than 90%;Sludge after stirring and evenly mixing is delivered to transfer tank 4, then is delivered to dehydration through coiled pipe 5 In pipe 6;It is preferred that steel pipe, PE pipes or pvc pipe can be used in 5 grade conveyance conduits of coiled pipe;It is preferred that dehydrating tube 6 uses stereochemical structure yarn It is sewed for raw material;Empty dehydrating tube 6 is lain on the bed course 10 under air film canopy 7 covers in work progress, then by transfer tank 4 In sludge be delivered to through coiled pipe 5 in dehydrating tube 6, dehydrating tube 6 has been filled can place empty dehydration after sludge again at the top of it Pipe 6 fills sludge, so stacks dehydrating tube 6 successively and fills sludge, dehydrating tube 6 stacks height and is no more than 10m in a pile, bed course 10 On can place the air-supply out of a lateral air film canopy 7 using air blowers 8 of more pile dehydrating tubes 6 as needed, bulging air is from air film canopy 7 Opposite side is discharged, and outer air-discharging carries out deodourizing through gas purification tower 9;It is preferred that air film canopy 7 uses building film material to make for shell Anchored with wirerope, closed space formed by the air-supply inflation of air blower 8, in air film canopy 7 air pressure be higher by 200 than external pressure~ 300Pa;It is preferred that gas purification tower 9 carries out washing neutralization, oxidation using sodium hydroxide, sodium hypochlorite, and carried out using ultraviolet light Catalysis oxidation, so as to remove the acidity such as hydrogen sulfide foul gas in efflux gas;Dehydrating tube 6 is placed on 7 inner cushion layer 10 of air film canopy On, dehydrating tube 6 is stackable, and superposition height is no more than 10m;Bed course 10 is made of top guide layer and lower part impervious barrier.Guide layer By top 250g/m2Have a spinning filtering geotextiles tiling layer, the cobble tiling thickness of bottom 20~40mm sizes is more than 300mm Boulder bed forms, and perforation high-density polyethylene (HDPE) pipe is embedded in boulder bed bottom and carries out water conservancy diversion;Lower part impervious barrier is by top 600g/m2Non-woven geotextile, centre are not less than the HDPE geomembranes of 1.5mm thickness, and bottom is not less than 4800g/m using dosage2Swelling Soil pad three parts composition.Dehydrating tube 6 is placed on 7 inner cushion layer 10 of air film canopy, and percolate is collected to through bed course 10 in dehydrating tube Water treatment trough 11 carries out purified treatment.

Claims (8)

1. a kind of interim disposal system of dredged sediment, including storage mud groove (1), dehydrating agent feed bin (2), tank diameter (3), transfer tank (4), coiled pipe (5), dehydrating tube (6), air film canopy (7), air blower (8), gas purification tower (9), bed course (10) and water treatment trough (11);Wherein, store up mud groove (1) and dehydrating agent feed bin (2) is connected respectively with tank diameter (3), for the sludge in mud groove (1) will to be stored up It is proportionally added into the dehydrating agent in dehydrating agent feed bin (2) in tank diameter (3) and is stirred mixing;Tank diameter (3) and transfer tank (4) connect, for the sludge after stirring and evenly mixing to be delivered to transfer tank (4), transfer tank (4) is connected with coiled pipe (5), coiled pipe (5) it is connected with dehydrating tube (6), for sludge to be delivered to through coiled pipe (5) in dehydrating tube (6), dehydrating tube (6) overlays air film Closed on bed course (10) in canopy (7) to seal up for safekeeping, the one side of air film canopy (7) sets air blower (8), the opposite side of air film canopy (7) with Air blower is corresponding to set gas purification tower (9), and bed course (10) is arranged on air film canopy (7) bottom, water treatment trough (11) and bed course (10) connect, dehydrating tube (6) interior percolate is collected to water treatment trough (11) through bed course (10) and carries out purified treatment.
2. the interim disposal system of dredged sediment according to claim 1, which is characterized in that the coiled pipe (5) uses steel Pipe, PE pipes or pvc pipe.
3. the interim disposal system of dredged sediment according to claim 1 or 2, which is characterized in that dehydrating tube (6) is using three-dimensional The long bag of tubulose that structure yarn forms for raw material sewing, dehydrating tube (6) maximum packed height is 2.5m, and maximum volume is 900m3, and possess good tensile strength, abrasion resistance, anti-uv-ray and water permeability.
4. the interim disposal system of dredged sediment according to claim 1 or 2, which is characterized in that dehydrating tube (6) stacks height It is in a pile no more than 10m, more pile dehydrating tubes (6) is placed on bed course (10).
5. the interim disposal system of dredged sediment according to claim 1 or 2, which is characterized in that air film canopy (7) is using building Membrane material is shell, is anchored using wirerope, and closed space, the interior air pressure ratio of air film canopy (7) are formed by air blower (8) air-supply inflation External pressure is higher by 200~300Pa.
6. the interim disposal system of dredged sediment according to claim 5, which is characterized in that air-discharging inside and outside air film canopy (7) It is handled using gas purification tower (9), so as to acid foul gas in air-discharging except going.
7. the interim disposal system of dredged sediment according to claim 6, which is characterized in that acid foul gas is vulcanization Hydrogen.
8. the interim disposal system of dredged sediment according to claim 1 or 2, which is characterized in that bed course (10) is by upper guide Fluid layer and lower part impervious barrier composition, top guide layer have the boulder bed group for spinning filtering geotextiles tiling layer and bottom by top Into;It is 250g/m wherein to have spinning filtering geotextiles tiling layer2Have a spinning filtering geotextiles tiling layer, boulder bed is grain size for 20~ The cobble tiling thickness of 40mm sizes is more than the boulder bed of 300mm, and perforation high-density polyethylene (HDPE) pipe is embedded in boulder bed bottom Portion carries out the water conservancy diversion of percolate;Lower part impervious barrier by top non-woven geotextile, intermediate high-density polyethylene (HDPE) geomembrane with And the bentonite liner three parts composition of bottom;Top non-woven geotextile is 600g/m2Non-woven geotextile, intermediate high-density polyethylene Dilute (HDPE) geomembrane is high-density polyethylene (HDPE) geomembrane not less than 1.5mm thickness, and the bentonite liner of bottom uses Dosage is not less than 4800g/m2Bentonite liner.
CN201720715017.4U 2017-06-19 2017-06-19 A kind of interim disposal system of dredged sediment Active CN207405064U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720715017.4U CN207405064U (en) 2017-06-19 2017-06-19 A kind of interim disposal system of dredged sediment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720715017.4U CN207405064U (en) 2017-06-19 2017-06-19 A kind of interim disposal system of dredged sediment

Publications (1)

Publication Number Publication Date
CN207405064U true CN207405064U (en) 2018-05-25

Family

ID=62322303

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720715017.4U Active CN207405064U (en) 2017-06-19 2017-06-19 A kind of interim disposal system of dredged sediment

Country Status (1)

Country Link
CN (1) CN207405064U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107098569A (en) * 2017-06-19 2017-08-29 中冶节能环保有限责任公司 The method and system that a kind of dredged sediment is disposed temporarily

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107098569A (en) * 2017-06-19 2017-08-29 中冶节能环保有限责任公司 The method and system that a kind of dredged sediment is disposed temporarily
CN107098569B (en) * 2017-06-19 2023-05-05 中冶节能环保有限责任公司 Method and system for temporarily disposing dredging sludge

Similar Documents

Publication Publication Date Title
CN105731743A (en) Comprehensive treatment system for urban lake pollution sludge
CN102583950A (en) Mobile contaminated bottom mud bag pocket dewatering and volume reduction treatment method
CN106284429B (en) A kind of domestic refuse incineration ash landfill yard and its good antiscale property processing method
CN102493397A (en) In-situ landfill and island creation method for recycling polluted bed-mud dehydrated by geotextile tubes
CN201358205Y (en) Dehydrated mud burying device
CN207405064U (en) A kind of interim disposal system of dredged sediment
CN205473290U (en) A comprehensive control system for urban lake pollution silt
CN111014226A (en) Ton package and landfill of soluble waste salt
CN105780784B (en) A kind of method for being suitable to carry out fine tailings by level land or massif in dry heap
CN204897690U (en) Drying bed that bed mud was dealt with is dredged in river course or lake
CN212612660U (en) Hazardous waste landfill system
CN212452804U (en) Simple industrial solid waste storage place pollution blocking system
CN107098569A (en) The method and system that a kind of dredged sediment is disposed temporarily
CN111570467B (en) Ectopic aerobic reinforced stabilization system and method for stored household garbage
CN101486526B (en) Dewatered sludge landfill method
CN102010066A (en) Method for purifying sewage in vertical-flow artificial wetland
CN102060337B (en) Recirculation unit and method for waste leachate or concentrate thereof
CN102261082B (en) Method for controlling seepage by laying membrane for slag field in high water level area, membrane laying slag field and use method thereof
CN114804553A (en) Drying, toxicity reducing and harm reducing equipment and method for black and odorous water body dredging sediment
CN110303022B (en) Anti-seepage pollution household garbage landfill system and method
CN111335362B (en) Structural arrangement mode of common industrial solid waste storage place
CN207013434U (en) The dehydration of industry and mining particulate form solid waste and safety stockpiling integral system
JP2004237260A (en) Processing method of biodegradable organic waste and methane collection apparatus
CN217665328U (en) Ecological restoration device for refuse landfill
CN111285580A (en) Method for dehydrating and continuously repairing reinforced sludge geotechnical pipe bag

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant