CN207392164U - A kind of plugging structure of hanging vertical shaft - Google Patents
A kind of plugging structure of hanging vertical shaft Download PDFInfo
- Publication number
- CN207392164U CN207392164U CN201721197477.9U CN201721197477U CN207392164U CN 207392164 U CN207392164 U CN 207392164U CN 201721197477 U CN201721197477 U CN 201721197477U CN 207392164 U CN207392164 U CN 207392164U
- Authority
- CN
- China
- Prior art keywords
- vertical shaft
- hanging vertical
- hanging
- tunnel
- anchor pole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Abstract
The utility model is related to a kind of plugging structures of hanging vertical shaft.The purpose of this utility model is to provide a kind of plugging structure simple in structure, easy for construction, safe and reliable, the smaller hanging vertical shaft of interference.The technical solution of the utility model is:A kind of plugging structure of hanging vertical shaft, for blocking the hanging vertical shaft excavated in advance at the top of tunnel, it is characterised in that:At the top of tunnel, around hanging Shaft bank anchor pole is penetrated equipped with several, this penetrates anchor pole and arranges and expose in hanging vertical shaft obliquely at the top of tunnel, the template being equipped in the hanging vertical shaft in silo bottom has poured blocking concrete, and exposing section of the anchor pole in hanging vertical shaft is penetrated described in blocking concrete package.The utility model is suitable for the underground engineering fields such as water power water conservancy.
Description
Technical field
The utility model is related to a kind of plugging structures of hanging vertical shaft.Suitable for underground engineering fields such as water power water conservancies.
Background technology
In modern water power hydraulic engineering, the subterranean tunnels such as generating system by piloting water are huge, many for ventilation requirement
Engineering can excavate Temporary Ventilation vertical shaft in advance at the top of tunnel, and the high tens of rice of the short person of these vertical shafts are had up to a hundred or so rice, adopted more
It is bored and constructed with anti-well, do not take supporting measure substantially.After the completion of tunnel, air shaft bottom terrain clearance up to more than 20 rice,
How even more high becomes a no small problem to vertical shaft closure.
Such vertical shaft tradition closure scheme is that scaffold is set up in tunnel until at the top of tunnel, then sets concrete bottom
Mould is blocked, and steel bar stress can not be set in concrete.There is the construction time is long, security risk is high, shadow for traditional scheme
It rings in tunnel and passes through, influences the construction of other positions, tie up the unfavorable factors such as duration.
The content of the invention
The technical problems to be solved in the utility model is:In view of the above problems, a kind of simple in structure, construction is provided
Convenient, safe and reliable, the smaller hanging vertical shaft of interference plugging structure.
Technical solution is used by the utility model:A kind of plugging structure of hanging vertical shaft, for blocking at the top of tunnel
The hanging vertical shaft excavated in advance, it is characterised in that:Anchor pole is penetrated equipped with several at the top of tunnel, around hanging Shaft bank, it should
It penetrates anchor pole to arrange and expose in hanging vertical shaft obliquely at the top of tunnel, be equipped in the hanging vertical shaft in vertical shaft bottom
The template in portion has poured blocking concrete, and exposing section of the anchor pole in hanging vertical shaft is penetrated described in blocking concrete package.
The shuttering supporting is on formwork support structure, and formwork support structure is fixed on through fixing anchor bar at the top of tunnel, institute
State that fixing anchor bar is fixed at the top of tunnel and its lower end is exposed, fixing anchor bar exposed junction is welded and fixed with formwork support structure.
The anchor pole that penetrates is evenly arranged at the top of tunnel using hanging Shaft bank center on several circles in the center of circle, to wear
Vertical shaft axis is directed toward in oblique top to saturating anchor pole at an angle.
The anchor pole that penetrates is directed toward vertical shaft axis in the oblique top of 45° angle.
The anchor pole that penetrates is evenly arranged at the top of tunnel using hanging Shaft bank center as on two circles in the center of circle, two
The distance of circle and hanging Shaft bank is respectively 1.5m and 2.5m.
The fixing anchor bar be arranged in around hanging Shaft bank, it is parallel with hanging vertical shaft axis.
The formwork support structure is made of several main support dowels being criss-cross arranged and auxiliary support dowel,
Main and auxiliary support dowel both ends are weldingly connected with the corresponding fixing anchor bar.
The beneficial effects of the utility model are:Anchor pole is penetrated in the utility model reversely to apply to hanging vertical shaft out of tunnel
Work can not dispose main reinforcement in the joint bar that solves the problems, such as can not to construct in hanging vertical shaft, concrete, make blocking concrete with enclosing
Rock is combined together, and improves the safety coefficient of blocking concrete.
Fixing anchor bar lower part is exposed in the utility model, simple in structure, easy for construction as the fulcrum of fixed form, solution
The fixation problem for silo bottom template of having determined.
The utility model arrangement and method for construction is simple and practicable, can be pre-buried in early period, also can in equipment constructions such as later-stage utilization cranes,
And short construction period, other positions are disturbed small.
Description of the drawings
Fig. 1 is the diagrammatic cross-section of embodiment.
Fig. 2 is the arrangement schematic diagram that anchor pole is penetrated in embodiment.
Fig. 3 is the scheme of installation of formwork support structure in embodiment.
Specific embodiment
As shown in Figure 1, the present embodiment is a kind of plugging structure of hanging vertical shaft, excavated in advance for blocking 2 top of tunnel
Hanging vertical shaft 1, hanging 1 diameter 3.5m of vertical shaft is advance by certain layout rules around the top of tunnel 2,1 well head of hanging vertical shaft
Anchor pole 5 and fixing anchor bar 3 are penetrated equipped with several, you can it is pre-buried early period in 1 stage excavation of tunnel, it can also be stepped on using crane etc. in the later stage
High equipment is implemented.
Anchor pole 5 is penetrated in the present embodiment in tunnel to implement, it is circumferentially disposed along hanging 1 periphery of vertical shaft, it is evenly arranged in tunnel
2 top of hole is enclosed using hanging 1 well head of vertical shaft as the two of the center of circle on circle.The distance of two circles and hanging 1 well head of vertical shaft is respectively 1.5m
And 2.5m, the axis (see Fig. 2) that anchor pole 5 is directed toward hanging vertical shaft 1 in the oblique top of 45° angle is penetrated, anchor pole 5 is penetrated on same circle circle
Spacing 1m or so, penetrates 5 length 4.5m of anchor pole, and its upper part penetrates hanging 1 borehole wall of vertical shaft and exposed.
This example sets to block the template 6 of hanging Shaft bank below hanging vertical shaft 1, and template 6 is supported in template branch
On support structure 4, formwork support structure 4 is fixed on 2 top of tunnel through fixing anchor bar 3.As shown in figure 3, formwork support structure 4 is by indulging
3 of horizontal interlaced arrangement main support dowels 41 and 1 auxiliary support dowel 42 form, main and auxiliary support dowel both ends with
Corresponding fixing anchor bar 3 is weldingly connected.Fixing anchor bar 3 is implemented in tunnel in this example, is arranged on hanging 1 periphery of vertical shaft, length
3m is constructed upwards by 2 crown of tunnel, and parallel with hanging 1 axis of vertical shaft, appear 20cm for lower part, and section is exposed in the lower part of fixing anchor bar 3
It is weldingly connected with formwork support structure 4.
Blocking concrete is poured using the template 6 below hanging vertical shaft 1 in hanging vertical shaft 1, blocking concrete package is worn
Saturating exposing section of the anchor pole 5 in hanging vertical shaft.It penetrates anchor pole 5 and can be used as blocking concrete steel bar stress, but also as country rock
Joint bar links together blocking concrete and hanging 1 country rock of vertical shaft.
The construction method of the present embodiment is as follows:
The first step in 2 stage excavation early period of tunnel, in the case of hanging 1 terrain clearance of vertical shaft is smaller, is pressed in tunnel 2
Certain rule penetrates anchor pole 5 and fixing anchor bar 3 to the construction of hanging 1 periphery of vertical shaft, also can according to circumstances be utilized after the completion of tunnel 1
Crane etc. ascend a height equipment implementation.
Second step, hanging vertical shaft 1 are appeared using the equipment of ascending a height such as loop wheel machine in 3 lower part of fixing anchor bar using after the completion of function
The main and auxiliary support dowel 41,42 of section welding, the formwork support structure 4 of the corresponding hanging vertical shaft 1 of composition.
Template 6 is inserted between 2 crown of formwork support structure 4 and tunnel in interspacing in advance, and is securely connected by the 3rd step, seals
Closed cycle side gap.
4th step pours downwards blocking concrete from hanging 1 top of vertical shaft.
5th step, form removal after blocking concrete solidification, completes closure.
Certainly, above description is not limitation of the utility model, and the utility model is also not limited to the example above, this skill
The those of ordinary skill in art field, in the scope of the utility model, variation, addition or the replacement made should all belong to this reality
With new protection domain.
Claims (7)
1. a kind of plugging structure of hanging vertical shaft, for blocking the hanging vertical shaft (1) excavated in advance at the top of tunnel (2), feature
It is:Anchor pole (5) is penetrated equipped with several at the top of tunnel (2), around hanging vertical shaft (1) well head, this penetrates anchor pole from tunnel (2)
Top is implemented and is exposed in hanging vertical shaft (1) obliquely, and the template in silo bottom is equipped in the hanging vertical shaft (1)
(6) blocking concrete has been poured, exposing section of the anchor pole (5) in hanging vertical shaft (1) is penetrated described in blocking concrete package.
2. the plugging structure of hanging vertical shaft according to claim 1, it is characterised in that:The template (6) is supported in template
In support construction (4), formwork support structure (4) is fixed on through fixing anchor bar (3) at the top of tunnel (2), and the fixing anchor bar (3) is solid
At the top of tunnel (2) and its lower end is exposed, and fixing anchor bar (3) exposed junction is welded and fixed with formwork support structure (4).
3. the plugging structure of hanging vertical shaft according to claim 1 or 2, it is characterised in that:It is described to penetrate anchor pole (5) uniformly
It is in certain angle to be arranged at the top of tunnel (2) using hanging vertical shaft (1) well head center as anchor pole (5) on several circles in the center of circle, is penetrated
It spends oblique top and is directed toward vertical shaft axis.
4. the plugging structure of hanging vertical shaft according to claim 3, it is characterised in that:The anchor pole (5) that penetrates is in 45° angle
It is directed toward vertical shaft axis in oblique top.
5. the plugging structure of hanging vertical shaft according to claim 4, it is characterised in that:It is described to penetrate anchor pole (5) uniform cloth
It is two circles and hanging vertical shaft (1) well head on two circles in the center of circle to be placed at the top of tunnel (2) using hanging vertical shaft (1) well head center
Distance be respectively 1.5m and 2.5m.
6. the plugging structure of hanging vertical shaft according to claim 2, it is characterised in that:The fixing anchor bar (3) is arranged in
It is parallel with hanging vertical shaft (1) axis around hanging vertical shaft (1) well head.
7. the plugging structure of hanging vertical shaft according to claim 2, it is characterised in that:The formwork support structure (4) by
Several main support dowels (41) being criss-cross arranged and auxiliary support dowel composition (42), main and auxiliary support dowel both ends
It is weldingly connected with the corresponding fixing anchor bar (3).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721197477.9U CN207392164U (en) | 2017-09-18 | 2017-09-18 | A kind of plugging structure of hanging vertical shaft |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721197477.9U CN207392164U (en) | 2017-09-18 | 2017-09-18 | A kind of plugging structure of hanging vertical shaft |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207392164U true CN207392164U (en) | 2018-05-22 |
Family
ID=62404405
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721197477.9U Active CN207392164U (en) | 2017-09-18 | 2017-09-18 | A kind of plugging structure of hanging vertical shaft |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207392164U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109611138A (en) * | 2019-01-17 | 2019-04-12 | 平顶山平煤设计院有限公司 | A kind of distinguished and admirable partition method of mine shaft |
-
2017
- 2017-09-18 CN CN201721197477.9U patent/CN207392164U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109611138A (en) * | 2019-01-17 | 2019-04-12 | 平顶山平煤设计院有限公司 | A kind of distinguished and admirable partition method of mine shaft |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107060840B (en) | A kind of construction method of large cross-section tunnel V grades of country rock excavation supportings | |
CN101614125B (en) | Construction method of V-level surrounding rock tunnel | |
CN105201532B (en) | The Ring Cutting construction method of underground Long span spherical crown shape dome under weak surrounding rock | |
CN104806252B (en) | Underground dome excavation construction arrangement and excavation method | |
CN103628885A (en) | Tunnel exit cover-excavation construction method of Ultra-shadow buried tunnel | |
CN105350973A (en) | Construction method for large-span section loess tunnel under-crossing highway | |
CN102606162A (en) | Quick construction method for weak surrounding rock shallowly-buried easily-collapsed area of tunnel | |
CN104612713B (en) | Buried section of method for tunnel construction of an ultra shallow | |
CN109707399B (en) | Tunnel exit supporting structure and construction method thereof | |
CN102226398A (en) | Soft rock four-line large-span tunnel compound double-side wall bracing cable conversion excavation construction method | |
CN105041333A (en) | Method for treating tunnel collapse through dugand covered method | |
CN103195076A (en) | Method for constructing silt deep foundation pit tower crane foundation | |
CN108166989A (en) | The asymmetric twin-arch tunnel interval wall construction method of water rich strata " OC " shape | |
CN105114098A (en) | Method for treating unfavorable geology segment of diversion tunnel and major-diameter diversion tunnel structure | |
CN109930609A (en) | A kind of campshed composite supporting construction and its construction method for upper-soft lower-hard ground | |
CN107965341A (en) | A kind of large-section underground pipe canopy pipe network concrete support method | |
CN103114595A (en) | Support method and device of support pile preformed core-soil double-buttress inclined inner-strut foundation ditch | |
CN106968139A (en) | The construction method of railway bed supporting in undercrossing tunnel jacking framed bridge jack-in process | |
CN104405411A (en) | Oversized variable cross section tunnel supporting structure | |
CN107575237A (en) | A kind of subsurface excavation method is combined the construction method of construction subway station with shield method | |
CN104141500A (en) | Hardened sand gravel stratum cavern construction method | |
CN207392164U (en) | A kind of plugging structure of hanging vertical shaft | |
CN204716253U (en) | Circular major diameter diversion tunnel structure | |
CN109518722A (en) | The short underpass structure and its construction method of newly-built basement and existing subway station | |
CN206530341U (en) | A kind of underground cavern crown structure and its underground chamber |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |